Professional Documents
Culture Documents
INTRODUCTION
Project Description
The Portion of Work for this estimate involves the redevelopment and site improvements of the existing campus athletic
fields. Scope will provide a new football field, new running track, strutural upgrades to existing concrete bleacher
structure, new aluminum bleacher seating, a new concessions building, and a new press box. Adjacent areas will be
developed to include new field events areas, and new landscape and hardscape intermixed into the existing site. Musco
lighting will also be provided to these areas. New ADA parking will be provided on the north/east side of the site.
Basis of Estimate
This statement is based on the schematic drawing plans dated June 03, 2014 and received on June 06, 2014; the basis
of design narrative dated June 03, 2014; client meeting on June 05, 2014; and verbal direction by the architect.
Construction Schedule
Costs as included herein have been based upon a construction period of 13 months. Any costs for excessive overtime
to meet accelerated schedule milestone dates are not included in this estimate. It has been assumed that the project will
commence July 2015 and completed by end July 2016.
Method of Procurement
The Estimate is based on traditional Design-Bid-Build procurement competitively bid with pre-qualified general
contractors and main subcontractors.
Design Allowances
A Design Contingency of 7.5% has been included for undeveloped design details.
INTRODUCTION
Construction Contingency
It is prudent for all program budgets to include an allowance for change orders which occur during construction. These
change orders normally increase the cost of the project. It is recommended that a 5% to 10% contingency be carried by
the Owner in this respect.
Bid Conditions
This estimate has been based upon competitive bid situations (min of 4 bidders) for all items of subcontracted work.
We recommend that the client review this statement, and that any interpretations contrary to those intended by the
design documents be fully addressed. The statement is based upon a detailed measurement of quantities, when
possible, and reasonable allowances for items not clearly defined in the documents.
The statement reflects probable construction costs obtainable in a competitive and stable bidding market. This estimate
is based upon a minimum of three competitive bids from qualified general contractors, with bids from a minimum of three
(3) subcontractors per trade. This statement is a determination of fair market value for the construction of the project and
is not intended to be a prediction of low bid. Experience indicates that a fewer number of bidders may result in a higher
bid amount, and more bidders may result in a lower bid result.
INTRODUCTION
Statement of Probable Cost
Cumming has no control over the cost of labor and materials, the general contractor’s or any subcontractor’s method of
determining prices, or competitive bidding and market conditions. This opinion of the probable cost of construction is
made on the basis of the experience, qualifications, and best judgment of a professional consultant familiar with the
construction industry. Cumming, however, cannot and does not guarantee that proposals, bids, or actual construction
costs will not vary from this or subsequent cost estimates.
Cumming has no control over the quality, completeness, intricacy, constructability, or coordination of design documents.
Cumming also has no control over the amount of funds available for the project. We, therefore, cannot be responsible
for any design revision costs incurred in the event that this estimate is in excess of the budget.
Cumming’s staff of professional cost consultants has prepared this estimate in accordance with generally accepted
principles and practices. This staff is available to discuss its contents with any interested party.
It is recommended that there are preparations of further cost estimates throughout design by Cumming to determine
overall cost changes since the preparation of this preliminary estimate. These future estimates will have detailed
breakdowns indicating materials by type, kind, and size, priced by their respective units of measure.
Davidson Field
Summary $8,413,110
4 Bleachers $1,349,500
5 Structures $2,248,720
6 Utilities $366,000
8 Softscape $282,200
Subtotal $8,917,910
General Contractor's Fee 3.5% $312,100
Subtotal $9,230,010
Contractor Bonds and Insurance 1.5% $138,500
Subtotal $9,368,510
Design Contingency 7.5% $702,600
Subtotal $10,071,110
Escalation to MOC 6.0% $601,800
Site
Fence and gates 835 lf $4.75 $3,966
Sawcut concrete 1,179 lf $4.72 $5,563
Concrete 16,034 sf $2.50 $40,013
Sawcut AC paving 1,793 lf $2.93 $5,245
AC paving 15,215 sf $0.87 $13,252
Concrete curb 495 lf $6.22 $3,079
Handrails 530 lf $7.10 $3,763
Stairs 260 sf $12.85 $3,341
Block walls 350 lf $25.00 $8,750
Planter walls 722 lf $8.50 $6,137
Landscape 10,133 sf $0.50 $5,067
Bleachers 7,507 lf $3.75 $28,151
Buildings 920 sf $10.75 $9,890
Underground utilities, allowance 326,825 sf $0.15 $49,024
Protect in place miscellaneous items, allowance 326,825 sf $0.05 $16,341
Earthwork
Over-ex and recompact, 2' entire site 24,209 cy $6.75 $163,413
Rough and fine grading 326,825 sf $0.29 $96,232
Musco Lighting
Main field, pole fixture and lamps 4 ea $71,100.00 $284,400
Installation 4 ea $6,500.00 $26,000
Feeders, 60 amp including trench and backfill 1,380 lf $45.00 $62,100
Scoreboard
Main field 1 ea $55,000.00 $55,000
Feeders, 60 amp including trench and backfill 225 lf $45.00 $10,100
Public address
Main field, includes comm boxes and backbone for special systems, 1 ls $88,250.00 $88,300
allowance
Lighting
Site, distribution and fixtures, allowance 1 ls $75,000.00 $75,000
Power
Site allowance 1 ls $75,000.00 $75,000
Miscellaneous
Lynx timing system 1 ls $18,435.00 $18,400
4 Bleachers
Bleachers
Structural upgrades to concrete bleacher base
Steel embeds, bracing, connections, and anchors 1 ls $237,322.70 $237,300
CMU shear walls, includes footing and reinforcement 1 ls $72,602.00 $72,600
Concrete beam at top of shearwalls 1 ls $27,407.41 $27,400
FRP composite shear strengthening to bottom of bleacher base 1 ls $209,625.00 $209,600
Miscellaneous concrete
Concrete slab at new ADA seating 1,528 sf $14.79 $22,600
Concrete ramps 1,828 sf $45.00 $82,300
Concrete stairs 198 lf $55.00 $10,900
5 Structures
Concessions
CMU framed 1-story structure, 186' x 40' x 20' 6,148 square feet 6,148 sf $300.00 $1,844,400
Pressbox
CMU framed 3-story structure with elevator, 46' x 16' x 30' 1444 1,444 sf $280.00 $404,320
square feet
6 Utilities
Storm drainage
Pipe, 4" dia, PVC 154 lf $41.50 $6,400
Pipe, 6" dia, PVC 180 lf $45.40 $8,200
Pipe, 8" dia, PVC 405 lf $49.60 $20,100
Pipe, 10" dia, PVC 304 lf $70.45 $21,400
Pipe, 12" dia, PVC 124 lf $83.09 $10,300
Pipe, 15" dia, PVC 20 lf $102.13 $2,000
Pipe, 18" dia, PVC 36 lf $118.08 $4,300
Storm water treatment infiltration system 1 ls $110,500.00 $110,500
Catch basin 2 ea $896.00 $1,800
Parkway culvert 1 ea $5,580.00 $5,600
Area drain 24 ea $1,350.00 $32,400
Trench drain 147 lf $56.88 $8,400
Connection to existing 2 ea $5,000.00 $10,000
Sewer drainage
Pipe, 4" dia, PVC 46 lf $46.40 $2,100
Pipe, 6" dia, PVC 280 lf $48.72 $13,600
Grease interceptor 1 ea $9,675.00 $9,700
Sewer manholes, 60" dia 1 ea $10,500.00 $10,500
Sewer cleanout 2 ea $874.95 $1,700
Connection to existing 1 ea $2,750.00 $2,800
Domestic water
Pipe, 3" dia, PVC 319 lf $40.52 $12,900
Drinking fountains, hi-lo 2 ea $3,500.00 $7,000
Pressure reducing valve, 3" dia 1 ea $2,372.50 $2,400
Reduce pressure backflow assembly, 3" 1 ea $2,350.00 $2,400
Double check backflow assembly, 3" 1 ea $5,653.03 $5,700
Connection to existing 1 ls $2,750.00 $2,800
Water meter box and piping 1 ea $4,500.00 $4,500
Water meter (supplied / installed by utility company) Excluded
Pedestrian paving
Reinforced concrete, broom finish 44,571 sf $6.45 $287,400
Enhanced sandblast finish premium 40,019 sf $1.13 $45,100
Paving
AC paving 3" over 6" prepared base 24,962 sf $3.45 $86,100
Concrete 6" vertical curb 316 lf $12.98 $4,100
Concrete mow curb 1,152 lf $10.98 $12,600
Concrete rolled curb 50 lf $15.00 $800
Road crossover, connection to existing road, repair pedestrian 1 ls $7,500.00 $7,500
sidewalk and curbs
Miscellaneous
Stall markings 7 ea $15.00 $100
Hatching 444 sf $1.15 $500
ADA symbol, post and sign 7 ea $350.00 $2,500
Wheel stop 7 ea $60.00 $400
Fencing
Tube steel fence, 4' at track 1,454 lf $82.50 $120,000
Tube steel fence, 10' perimeter 1,826 lf $154.50 $282,100
Tube steel gate, single pedestrian 1 ea $1,895.00 $1,900
Tube steel gate, double pedestrian 14 pr $3,275.00 $45,900
Tube steel gate, double vehicle 3 pr $7,595.00 $22,800
Miscellaneous
Flagpole 1 ea $5,500.00 $5,500
Decorative bollards 8 ea $675.00 $5,400
Site furnishings, allowance 1 ls $25,000.00 $25,000
Site signage, allowance 1 ls $25,000.00 $25,000
8 Softscape
Landscape
Trees
Box, 48" 22 ea $1,040.00 $22,900
Date palm, 25' 17 ea $3,500.00 $59,500
Shrubs, groundcover, and vines
Groundcover, allowance 30,549 sf $3.75 $114,600
Turf 14,065 sf $1.25 $17,600
Irrigation
Planting areas 44,614 sf $1.25 $55,800
Micellaneous
Tree grates 12 ea $984.00 $11,800
Alternates
Alternates Summary
Add Alternates
1 Skim Coat and Paint Over Bleacher Base $37,300
2 Upgrade Space Beneath Bleachers $499,716
3 Chain Link Fencing in Lieu of Tube Steel ($285,000)
4 Standard Brock Field $57,100
5 Standard Brock Field With Cement Stabilized Soil $113,500
6 Sand Volley Ball Court $21,857
7 Provide Upgraded Scoreboard $31,450
8 16th Street Parking Lot Upgrade $106,013
Subtotal $31,100
General Contractor's Fee 3.5% $1,100
Subtotal $32,200
Contractor Bonds and Insurance 1.5% $500
Subtotal $32,700
Design Contingency 7.5% $2,500
Subtotal $35,200
Escalation to MOC 6.0% $2,100
Subtotal $417,516
General Contractor's Fee 3.5% $14,600
Subtotal $432,116
Contractor Bonds and Insurance 1.5% $6,500
Subtotal $438,616
Design Contingency 7.5% $32,900
Subtotal $471,516
Escalation to MOC 6.0% $28,200
Fencing
Tube steel fence, 4' at track 1,454 lf ($82.50) ($120,000)
Chain link fence, 4' at track 1,454 lf $41.25 $60,000
Tube steel fence, 10' perimeter 1,826 lf ($154.50) ($282,100)
Chain link fence, 10' perimeter 1,826 lf $77.25 $141,100
Tube steel gate, single pedestrian 1 ea ($1,895.00) ($1,900)
Tube steel gate, single pedestrian 1 ea $1,262.07 $1,300
Tube steel gate, double pedestrian 14 pr ($3,275.00) ($45,900)
Tube steel gate, double pedestrian 14 pr $2,181.15 $30,500
Tube steel gate, double vehicle 3 pr ($7,595.00) ($22,800)
Tube steel gate, double vehicle 3 pr $5,058.27 $15,200
Subtotal -$238,100
General Contractor's Fee 3.5% -$8,300
Subtotal -$246,400
Contractor Bonds and Insurance 1.5% -$3,700
Subtotal -$250,100
Design Contingency 7.5% -$18,800
Subtotal -$268,900
Escalation to MOC 6.0% -$16,100
Field
Main field surface, 2 1/2" turf including markings 81,320 sf ($6.28) ($510,800)
Main field surface, 2 1/4" turf including markings 81,320 sf $6.09 $494,800
Brock YSR layer 81,320 sf $2.05 $166,700
Typar membrane 81,320 sf $0.25 $20,300
Class II permeable 4" base 81,320 sf ($3.35) ($272,400)
Structural rock base, 3" crusher fines 81,320 sf $1.65 $134,200
Soil Isolation fabric 81,320 sf $0.15 $12,200
Subtotal $47,700
General Contractor's Fee 3.5% $1,700
Subtotal $49,400
Contractor Bonds and Insurance 1.5% $700
Subtotal $50,100
Design Contingency 7.5% $3,800
Subtotal $53,900
Escalation to MOC 6.0% $3,200
Field
Brock YSR layer 81,320 sf $2.05 $166,700
Typar membrane 81,320 sf $0.25 $20,300
Class II permeable 4" base 81,320 sf ($3.35) ($272,400)
Structural rock base, 2" crusher fines 81,320 sf $1.45 $117,900
Stabilized soils, cemented or lime treated 81,320 sf $0.70 $56,900
Subtotal $94,800
General Contractor's Fee 3.5% $3,300
Subtotal $98,100
Contractor Bonds and Insurance 1.5% $1,500
Subtotal $99,600
Design Contingency 7.5% $7,500
Subtotal $107,100
Escalation to MOC 6.0% $6,400
Subtotal $18,357
General Contractor's Fee 3.5% $600
Subtotal $18,957
Contractor Bonds and Insurance 1.5% $300
Subtotal $19,257
Design Contingency 7.5% $1,400
Subtotal $20,657
Escalation to MOC 6.0% $1,200
Subtotal $26,250
General Contractor's Fee 3.5% $900
Subtotal $27,150
Contractor Bonds and Insurance 1.5% $400
Subtotal $27,550
Design Contingency 7.5% $2,100
Subtotal $29,650
Escalation to MOC 6.0% $1,800
Site Demolition
Paving 7,564 sf $0.75 $5,673
Demo chain link fence 25 lf $30.00 $750
Site Grading
Clear and grub site 7,564 sf $0.05 $378
Rough grading 308 cy $5.30 $1,633
Fine grading 7,564 sf $0.30 $2,269
Erosion control 7,564 sf $0.10 $756
Dust control 7,564 sf $0.05 $378
Paving
Asphalt paving at parking lot, includes striping and curbs, 1/8 of the
total parking area 7,564 sf $4.75 $35,928
Slurry seal the remaining 7/8 of the total parking area 52,946 sf $0.75 $39,710
Concrete paving 750 sf $10.50 $7,875
Subtotal $88,513
General Contractor's Fee 3.5% $3,100
Subtotal $91,613
Contractor Bonds and Insurance 1.5% $1,400
Subtotal $93,013
Design Contingency 7.5% $7,000
Subtotal $100,013
Escalation to MOC 6.0% $6,000