You are on page 1of 4

Consultants for Mining and Financial Solutions ISSUE NO.

86 — September 2007

C A L E N D A R See How They Run


○ ○ ○ ○ ○ ○ ○ ○ ○ ○ ○

(Project Cost and Schedule Overruns)



12th Brazilian Mining Congress and


EXPOSIBRAM 2007

September 24 – 27, 2007 But Mouse, you are not alone, other 90 percent run the spectrum

EXPOMINAS
In proving foresight may be vain: from close to the projected values to

Belo Horizonte, Brazil


e-mail: ibram@ibram.org.br The best laid plans of mice and men an outside limit of about double the

gang aft agley, budget and double the schedule. Is


XXVII International Mining


And leave us nought but grief and this the result of incompetence on

Congress and Exhibit 2007


October 10 – 13, 2007 pain for promised joy! the part of the estimators and

World Trade Center Veracruz


schedulers? Unequivocally, the


Veracruz, Mexico
Robert Burns answer is “No!” Why, then, does it

e-mail: reservaciones@turycon.com.mx

happen? There are, of course, other


The Geological Society of America


Here at Pincock, Allen & Holt (PAH), factors affecting estimates and

October 28 – 31, 2007


Colorado Convention Center we are occasionally asked to schedules, other than contemplative

Denver, Colorado
prognosticate on project cost and and rational deliberation,

e-mail: gsaservice@geosociety.org

schedule overruns, to give our measurement, and calculation, and



Mining the Americas opinion on how much extra the they are as follows:

October 29 – 30, 2007


projects might cost and how much

Doral Golf Resort 7 Spa


longer they may take to complete 1. Pressure from owners to minimize


Miami, Florida

e-mail: iiconf@iiconf.com
than has been estimated. One might costs and schedules. This is not

Runge North American presume that all of this has been inappropriate: where money and

Professional Development Courses thoroughly assessed by the project time are limited, people can be

estimators and schedulers, and it very innovative and, conversely,


Mining for Non Miners


probably has, but, alas, as most of us where money and time are

Denver: November 12

Calgary: November. 23 well know, Burns’ famous words too unrestricted, people have a

Dragline Mining Systems frequently ring true. tendency to be profligate.



Denver: November 13–14


Factors Contributing to Cost 2. Intentionally tight project budgets


Mining Economics

Overruns and schedules, designed to


Denver: November 15–16


Calgary: November 19–20 “pressurize” project management



For additional information or to register,


We see numerous projects at PAH in hopes of minimizing project

and there are probably fewer than costs and schedules, often

please contact Marcie Schmidt at


403-217-4981 or
10 percent that are completed accompanied by financial

mschmidt@runge.com.au

within budget and schedule. The incentives for the contractors.



Copyright 2007 by Pincock, Allen and Holt, a division of Runge Inc. All Rights Reserved.



Assessing whether estimated The Three Blind Mice cost and schedule overruns.



costs and schedules are When projects are in remote



excessively tight can, to a large Is there any way to judge the locations the efficiency of



degree, be determined by logistics, the availability of


vulnerability of a project to cost



comparison with other similar and schedule overrun and to services, and the efficiency of



projects and by comparing the construction come into play.


quantify how much more it



values with those in cost- might cost and how much Remoteness applies primarily in



estimating handbooks. the following areas:


longer it will take to complete?



There certainly seems to be a



It might also seem that the ♦ High elevation, usually

relation between overruns and



larger the project, the more the following factors, all of them accompanied by severe



likely it will overrun, but, in related to lack of knowledge or weather


reality, large projects are no


insufficient knowledge, what


more vulnerable than small might be termed the three blind ♦ Arctic, also accompanied by



projects; it is just that large mice of projects: severe weather



projects are more visible,


especially if they are massive ♦ Remoteness ♦ Third world, accompanied by



civil projects such as bridges ♦ Unconventionality poor infrastructure and



and tunnels. ♦ Earthwork political instability




Remoteness


3. Contractors that estimate It is difficult for estimators and


and bid low are more likely to schedulers to properly assess



win work; accordingly they Remoteness is certainly a factor these factors and include them


are so inclined. Still, this in making a project subject to in preparing cost estimates and


does put them under



pressure to achieve the



accepted values.

T

R

4. Lack of knowledge or

insufficient knowledge. If a H

E

project incorporates a

E

significant part or parts of it



related to lack of knowledge,


B

there is a tendency for things


L

to go awry. When the level


I

of knowledge is low,
N

determining likely overruns is D



then primarily a matter of


determining where M

knowledge is lacking and I



making allowances for it, C


E

recognizing that one unit of



uncertainty equals about two


units of vulnerability.

Remoteness

2



schedules, perhaps because incorporated they are generally There is often a considerable



they are not familiar with them. well tested and well thought amount of uncertainty associated



How much allowance should be out, but, even so, they have a with such projects and this lack of



made for remoteness? PAH tendency to go awry, often as a knowledge leads to vulnerability.



suggests adding 50 percent to result of unexpected interactions As stated in the previous



both cost and schedule for the with other well-established paragraph, projects incorporating



most extreme circumstances processes and methods. No unconventional processes usually



and ratio it down from there. mouse is an island! With proceed normally until startup;


unconventionality, engineering similarly, heap leach projects



Unconventionality and construction usually usually follow this pattern and




proceeds normally until plant then often struggle to reach



Unconventionality is certainly a startup; it is getting the project projected production rates and



factor in cost and schedule up to intended production rates efficiency. Perhaps it is more


overruns. While incorporating and efficiency that add cost and appropriate to discount projected



new processes and methods is delays. We suggest adding 50 production rates for these projects



sometimes essential to even percent to both cost and and assume increased operating



make a project viable, it does schedule in the most extreme costs, rather than add to the


increase vulnerability. This circumstances and ratio it down capital costs and schedule to



applies to those processes and from there. achieve them.



methods that have been applied



to a limited extent elsewhere, as One process that might be Earthwork



well as those that are completely considered quasi-unconventional


new. Of course, when new is heap leaching, though it is a Time and time again we see


processes or methods are fairly commonly applied process. earthwork estimates being


Unconventionality Earthwork

33
exceeded, with costs for this item percent to the earthwork estimate help. One must make allowances
often exceeding 100 percent of the of practically any project. for them so that, when plans do
estimated value. In contrast to go agley, we are not particularly
earthwork, estimating the rest of a Schedule Overruns surprised or disconsolate, as
project is not that problematical: Burns suggests we often are, in
quantities and costs for concrete, Schedule overruns are usually the final verse of his famous ode
steel, machinery, pipe, and cable closely related to cost overruns, but to the mouse:
can be closely estimated; there are this is not always the case; it seems
few unknowns in these areas. that schedule overruns occur even Still you are blest, compared
Fortunately for most projects, the where cost overruns do not occur. with me!
amount of money in the Schedules do not incorporate The present only touches thee:
earthwork account is less than 10 contingencies, they are set to But oh! I backward cast my
percent, so an increase in follow projected work sequences eye on prospects drear!
earthwork costs by 100 percent and equipment deliveries, and And forward, though I cannot
results in a total project cost including extra time for possible see, I guess and fear!
increase of 10 percent, which is upsets and delays is not rational.
not that critical. Some projects, But delays usually occur; if they are While we may yet, at times, have
however, have much more than minor it is often possible to catch reason to be fearful, healthy
10 percent of the project in the up, usually by working extra time; skepticism and anticipation of
earthwork account, especially if but just as often the cumulative possible disaster can make us,
they incorporate water-retention effect of delays is such that it is not perhaps, a little less so.
dams and/or underground possible to catch up, and most
workings. projects exceed the projected time
by about 10 percent as a matter of
It seems that, no matter how course. Such delays, unrelated to
extensive and how sophisticated specific problems related in This month’s article was provided
the geotechnical investigations, previous paragraphs, also add cost, by Dick Addison, P.E., and Princi-
surprises occur. Yet some generally about one percent of the pal Process Engineer who delights
responsibility also lies with the project total cost per month of in trapping blind mice and is ever
earthwork design and some with delay. reluctant to set them free.
the construction. Perhaps, by its dick.addison@pincock.com
very nature, it is impossible to be Conclusion
more precise; accordingly, The cartoons were drawn by
recognition of this we suggest Cutting off the tails of the three Aaron McMahon, Geologist, and
adding an overrun estimate of 100 blind mice does not seem to mouseketeer extraordinaire.

Pincock, Allen & Holt is a consulting and engineering firm serving the international mineral resource
industry. Your comments and suggestions are always welcome. Contact Pincock, Allen & Holt • 165 S.
Union Blvd., Suite 950, Lakewood, Colorado 80228 • TEL 303.986.6950 • FAX 303.987.8907 •
www.pincock.com. Pincock Perspectives is published as a free information service for friends and clients.

Consultants for Mining and Financial Solutions

You might also like