Professional Documents
Culture Documents
86 — September 2007
○ ○ ○ ○ ○ ○ ○ ○ ○ ○ ○
○
EXPOSIBRAM 2007
○
September 24 – 27, 2007 But Mouse, you are not alone, other 90 percent run the spectrum
○
○
EXPOMINAS
In proving foresight may be vain: from close to the projected values to
○
e-mail: ibram@ibram.org.br The best laid plans of mice and men an outside limit of about double the
○
○
October 10 – 13, 2007 pain for promised joy! the part of the estimators and
○
Veracruz, Mexico
Robert Burns answer is “No!” Why, then, does it
○
e-mail: reservaciones@turycon.com.mx
○
Here at Pincock, Allen & Holt (PAH), factors affecting estimates and
○
Colorado Convention Center we are occasionally asked to schedules, other than contemplative
○
Denver, Colorado
prognosticate on project cost and and rational deliberation,
○
e-mail: gsaservice@geosociety.org
○
Mining the Americas opinion on how much extra the they are as follows:
○
Miami, Florida
○
e-mail: iiconf@iiconf.com
than has been estimated. One might costs and schedules. This is not
○
○
Runge North American presume that all of this has been inappropriate: where money and
○
○
Professional Development Courses thoroughly assessed by the project time are limited, people can be
○
probably has, but, alas, as most of us where money and time are
○
Denver: November 12
○
Calgary: November. 23 well know, Burns’ famous words too unrestricted, people have a
○
○
Mining Economics
○
and there are probably fewer than costs and schedules, often
○
403-217-4981 or
10 percent that are completed accompanied by financial
○
mschmidt@runge.com.au
○
Copyright 2007 by Pincock, Allen and Holt, a division of Runge Inc. All Rights Reserved.
○
○
○
○
Assessing whether estimated The Three Blind Mice cost and schedule overruns.
○
○
○
costs and schedules are When projects are in remote
○
○
○
excessively tight can, to a large Is there any way to judge the locations the efficiency of
○
○
degree, be determined by logistics, the availability of
○
vulnerability of a project to cost
○
○
comparison with other similar and schedule overrun and to services, and the efficiency of
○
○
○
projects and by comparing the construction come into play.
○
quantify how much more it
○
○
○
values with those in cost- might cost and how much Remoteness applies primarily in
○
○
estimating handbooks. the following areas:
○
longer it will take to complete?
○
○
There certainly seems to be a
○
○
○
It might also seem that the ♦ High elevation, usually
○
relation between overruns and
○
○
○
larger the project, the more the following factors, all of them accompanied by severe
○
○
○
○
likely it will overrun, but, in related to lack of knowledge or weather
○
○
reality, large projects are no
○
○
insufficient knowledge, what
○
○
more vulnerable than small might be termed the three blind ♦ Arctic, also accompanied by
○
○
○
○
projects; it is just that large mice of projects: severe weather
○
○
○
○
projects are more visible,
○
○
○
○
○
○
○
○
○
○
○
○
○
○
○
○
Remoteness
○
3. Contractors that estimate It is difficult for estimators and
○
○
○
and bid low are more likely to schedulers to properly assess
○
○
○
○
win work; accordingly they Remoteness is certainly a factor these factors and include them
○
○
○
are so inclined. Still, this in making a project subject to in preparing cost estimates and
○
○
○
accepted values.
○
○
T
○
R
○
4. Lack of knowledge or
○
insufficient knowledge. If a H
○
E
○
project incorporates a
○
E
○
I
○
of knowledge is low,
N
○
○
determining where M
○
○
E
○
units of vulnerability.
○
Remoteness
○
○
2
○
○
○
schedules, perhaps because incorporated they are generally There is often a considerable
○
○
○
they are not familiar with them. well tested and well thought amount of uncertainty associated
○
○
○
How much allowance should be out, but, even so, they have a with such projects and this lack of
○
○
○
made for remoteness? PAH tendency to go awry, often as a knowledge leads to vulnerability.
○
○
suggests adding 50 percent to result of unexpected interactions As stated in the previous
○
○
○
both cost and schedule for the with other well-established paragraph, projects incorporating
○
○
○
most extreme circumstances processes and methods. No unconventional processes usually
○
○
○
and ratio it down from there. mouse is an island! With proceed normally until startup;
○
unconventionality, engineering similarly, heap leach projects
○
○
○
Unconventionality and construction usually usually follow this pattern and
○
○
○
○
○
proceeds normally until plant then often struggle to reach
○
○
○
Unconventionality is certainly a startup; it is getting the project projected production rates and
○
○
○
○
factor in cost and schedule up to intended production rates efficiency. Perhaps it is more
○
○
overruns. While incorporating and efficiency that add cost and appropriate to discount projected
○
○
○
○
new processes and methods is delays. We suggest adding 50 production rates for these projects
○
○
○
○
sometimes essential to even percent to both cost and and assume increased operating
○
○
○
○
make a project viable, it does schedule in the most extreme costs, rather than add to the
○
○
increase vulnerability. This circumstances and ratio it down capital costs and schedule to
○
○
○
○
applies to those processes and from there. achieve them.
○
○
○
○
methods that have been applied
○
○
○
○
to a limited extent elsewhere, as One process that might be Earthwork
○
○
○
○
well as those that are completely considered quasi-unconventional
○
○
new. Of course, when new is heap leaching, though it is a Time and time again we see
○
○
○
processes or methods are fairly commonly applied process. earthwork estimates being
○
○
○
Unconventionality Earthwork
33
exceeded, with costs for this item percent to the earthwork estimate help. One must make allowances
often exceeding 100 percent of the of practically any project. for them so that, when plans do
estimated value. In contrast to go agley, we are not particularly
earthwork, estimating the rest of a Schedule Overruns surprised or disconsolate, as
project is not that problematical: Burns suggests we often are, in
quantities and costs for concrete, Schedule overruns are usually the final verse of his famous ode
steel, machinery, pipe, and cable closely related to cost overruns, but to the mouse:
can be closely estimated; there are this is not always the case; it seems
few unknowns in these areas. that schedule overruns occur even Still you are blest, compared
Fortunately for most projects, the where cost overruns do not occur. with me!
amount of money in the Schedules do not incorporate The present only touches thee:
earthwork account is less than 10 contingencies, they are set to But oh! I backward cast my
percent, so an increase in follow projected work sequences eye on prospects drear!
earthwork costs by 100 percent and equipment deliveries, and And forward, though I cannot
results in a total project cost including extra time for possible see, I guess and fear!
increase of 10 percent, which is upsets and delays is not rational.
not that critical. Some projects, But delays usually occur; if they are While we may yet, at times, have
however, have much more than minor it is often possible to catch reason to be fearful, healthy
10 percent of the project in the up, usually by working extra time; skepticism and anticipation of
earthwork account, especially if but just as often the cumulative possible disaster can make us,
they incorporate water-retention effect of delays is such that it is not perhaps, a little less so.
dams and/or underground possible to catch up, and most
workings. projects exceed the projected time
by about 10 percent as a matter of
It seems that, no matter how course. Such delays, unrelated to
extensive and how sophisticated specific problems related in This month’s article was provided
the geotechnical investigations, previous paragraphs, also add cost, by Dick Addison, P.E., and Princi-
surprises occur. Yet some generally about one percent of the pal Process Engineer who delights
responsibility also lies with the project total cost per month of in trapping blind mice and is ever
earthwork design and some with delay. reluctant to set them free.
the construction. Perhaps, by its dick.addison@pincock.com
very nature, it is impossible to be Conclusion
more precise; accordingly, The cartoons were drawn by
recognition of this we suggest Cutting off the tails of the three Aaron McMahon, Geologist, and
adding an overrun estimate of 100 blind mice does not seem to mouseketeer extraordinaire.
Pincock, Allen & Holt is a consulting and engineering firm serving the international mineral resource
industry. Your comments and suggestions are always welcome. Contact Pincock, Allen & Holt • 165 S.
Union Blvd., Suite 950, Lakewood, Colorado 80228 • TEL 303.986.6950 • FAX 303.987.8907 •
www.pincock.com. Pincock Perspectives is published as a free information service for friends and clients.