Professional Documents
Culture Documents
Abstract— The voltage control strategy in any generator is Controllers (AVC) according to a droop characteristic
arguably the most important feature for grid integration. determined by AEMO.
Grids with high penetration of variable renewable energy in
non-traditional locations are susceptible to larger voltage The algorithm and dynamic models are developed by LR
variations that could lead to detrimental effects on the overall and will utilize Power System Simulator for Engineering
voltage profile of the network. In the Australian context, the (PSS/E) software to validate the logic implemented.
voltage control strategy is bound by the National Electricity
Rules, which apply to any generator seeking connection to the II. SHWF BALANCE OF PLANT
grid. The rules determine a set of parameters which can be
negotiated during the connection process. For very large scale SHWF is a complex generator. The Balance of Plant
wind farms effectively composed of multiple smaller wind (BoP) is composed of one main 500/132 kV substation
farms, an additional challenge is faced as the performance (Haunted Gully Terminal Station – HGTS), two 50 MVAr
characteristics of the system are assessed at its connection switched capacitors are included in HGTS. From the
point and interface with the Network Service Provider. The terminal station, two major 132 kV Overhead Lines (OHL)
area controller described in this paper presents a novel method are connecting three local 132/33 kV substations (West,
of managing the steady state conditions of a large scale wind South and East), these are branches 6010 to 6400 and 6010
farm (currently under construction in Australia) by adjusting to 6014. From 6014, two branches are connecting east and
the voltage setpoint of multiple local wind farm controllers south substations, 6014 to 6200 and 6014 to 6300
performing fast voltage control. respectively. West substation is composed of two parts and is
subdivided in West A and West B. Fig. 1 shows a simplified
Keywords — large scale wind farm, voltage control, AEMO. BoP single line diagram of the generator system.
I. INTRODUCTION
As part of the grid connection process in Australia, every
generator must propose a set of Generator Performance
Standards (GPS). The GPS requirements are included in the
National Electricity Rules (NER) and are separated in
multiple clauses which requires the proposed generator to
study and simulate the system in multiple conditions, both in
steady state and dynamic operation. These studies cover (but
are not limited to) voltage and frequency response, reactive
power capability, power quality, reactive power, active
power and voltage control. The results of these studies will
form a proposed GPS, which is then assessed by the Network
Service Provider (NSP) responsible for the connection and
Australian Energy Market Operator (AEMO). Once
accepted, the GPS will form part of the connection contracts
and will determine the minimum performance of the system
for the entirety of its life cycle [1].
Lloyd’s Register (LR) is engaged by Goldwind Australia
(GW) as grid connection consultant for Stockyard Hill Wind
Farm (SHWF). SHWF has an approximate export capacity of
531 MW and will comprise of 149 Goldwind 3S
GW140/3570 (3.57 MW) wind turbine generators and
multiple reactive plant. As part of the voltage control
strategy definition and grid studies for GPS registration
purposes, an Area Controller has been proposed to operate in
the connection point of SHWF.
The Area Controller will be physically implemented by
the Goldwind Voltage Management Platform (VMP) located
at the Haunted Gully Terminal Station (HGTS). The main
objective of this master controller is to send voltage
reference setpoints to each local Automatic Voltage Fig. 1. SHWF simplified single line diagram.
Authorized licensed use limited to: UNIVERSITY OF BIRMINGHAM. Downloaded on July 26,2020 at 22:28:54 UTC from IEEE Xplore. Restrictions apply.
The Wind Turbine Generators (WTG) are divided and enough to meet its GPS obligations in the negotiated voltage
modelled in five aggregates: South, East, West A, West B control clause. This involves, amongst other requirements,
and North, being the latter connected at West B substation, having a settling time of less than 7.5 seconds and a rising
an additional 33 kV OHL, branch 6411 to 6130, connects time of 2 seconds for a 5% voltage disturbance (or reference
West B to north WTGs. Each substation has fixed 25 MVAr change) at the PoC.
capacitor harmonic filters connected for each aggregate
(meaning West B has 50 MVAr of filter connected). The There are multiple voltage control devices in the plant.
capacitors are used not only for harmonic filtering, but also To avoid hunting, none of the devices will operate in
due to the voltage drop on the reticulation. Finally, each opposition to each other. As shown in Tab. 2, the OLTC
substation has 16 MVAr STATCOMs which aid the plant in devices will control the voltages on the low voltage (LV)
steady state and transient phenomena. The total number of side of each of the transformers. The VMP and AVCs will
WTGs per substation is shown on Tab. 1. control the high voltage (HV) side on the 500 kV and 132 kV
networks in accordance to their pre-determined droop. The
STATCOMs and WTGs while not in grid support mode
TABLE I. NUMBER OF WTGS PER SUBSTATION. (fault ride through) will operate in Reactive Power Control
Number of Nameplate Capacity mode, receiving setpoints from the local AVCs. HGTS VMP
Substation also will implement a logic for switching the two 50 MVAr
WTGs (MW)
South 37 132.09 capacitor banks connected to the 132 kV bus, which
East 43 153.51 primarily is designed to account for the high losses on the
West A 34 121.38 reticulation during full production.
West B 20 71.40
North 15 53.55
Total 149 531 TABLE II. VOLTAGE CONTROL DEVICES.
Authorized licensed use limited to: UNIVERSITY OF BIRMINGHAM. Downloaded on July 26,2020 at 22:28:54 UTC from IEEE Xplore. Restrictions apply.
- Read: PK, QK and VK from each AVC (where K VQ Static Implementation
denotes each substation);
- Calculate: QLOSS in accordance with PK and VK d% = 5%
from each AVC and HGTS capacitors and QBASE = PBASE * 0.395
transformer flows;
- Summate: QFLOW desired with QLOSS; VPOC
QDROOP
- Calculate: Calculate setpoint QSET_K for each AVC
based on their Q capability; VREF
C1 C2 Pwest_A
VREF VQ Static
LDC LDC LDC LDC Q Q + PBRANCH Q(P)
6010 - 6400 6010 - 6014 6014 - 6200 6014 - 6300 Cap Comp Trafo Comp
Pwest_B QLOSS_1
+
+
Authorized licensed use limited to: UNIVERSITY OF BIRMINGHAM. Downloaded on July 26,2020 at 22:28:54 UTC from IEEE Xplore. Restrictions apply.
Q Multiplexer
A. Steady State Load Flow Calculation Validation
Using the functions described previously it is possible to
N = collector, BoP dispatch the system to a steady state condition close to the
QDROOP K = substation desired droop characteristic. A small steady state error is
expected due to model imperfections and simplifications on
QCOMP
CAP/TRAFO
+ QDES
the reactive power losses calculations.
QSET_K
To validate the methodology, the system can be
QLOSS_N
dispatched to any given operational point, for instance
Q(QBASE1,QBASE2,…,QBASEN) maximum active power export and reactive power equals to
zero (PMAXQ0) and the calculations can be compared with the
solved state of the load flow case in PSS/E. The goal is to
have a low steady state error in order to allow the system to
settle in a short period of time.
Fig. 6. Q multiplexer function diagram. On the example given, the desired reactive power flow on
the PoC branch is zero and adopting the convention that the
D. Voltage Reference Calculator normal voltage is 1.03 p.u. at the PoC, the Area Controller
must calculate the desired reactive power of each branch
The voltage reference calculation is set based on a droop based on their respective bases, which in this case will
characteristic. The droop percentage is set to 5% as this will compensate the losses in the BoP.
respond with the desired behavior to voltage disturbances at
the point of connection. Since the STATCOMs are dispatch At full export, the biggest losses component is given by
during steady state operation, the QBASE is adjusted to the reticulation and the main transformer. Tab. 3 shows a
account for their contribution as shown in Fig. 7. comparison between the estimated values and measured
values from the load flow solution on PSS/E.
Voltage Reference Calculator
The voltage reference VREF_K will be issued to each AVC QT = z × (PL/SBASE)2 × SBASE ()
and from there, normal voltage droop control will take place
at each substation. Where QT is the reactive power consumed by the
transformer in MVAr, z is the impedance in p.u., PL is active
power flow in MW and SBASE is the apparent power base in
VI. PSS/E SIMULATIONS AND PRELIMINARY RESULTS MVA. In the example mentioned, the difference in the
To validate the proposed control strategy the system has estimation is lower than 0.02 MVAr, but the equation does
been modeled and simulated using PSS/E software. A SMIB not correct the values based on the measured transformer
model has been developed and the simulation is carried using voltage, which means that for different PoC voltages the
detailed dynamic models obtained from the Original estimation will deteriorate. Tab. 4 shows the total reactive
Equipment Manufacturers (OEM). The network beyond the power loss of the BoP and the required QDES considering
connection point is modelled as an infinite bus with a slack QDROOP = 0 (voltage refence equals to voltage at the PoC).
generator with a suitable series impedance to achieve desired
fault level at the connection point. The internal network is TABLE IV. BOP REACTIVE POWER LOSSES MEASURED VS ESTIMATED
modelled as per SHWF detail design including all COMPARISON TOTALS.
reticulation and transformers impedances. Where applicable
an OLTC model based on the PSS/E standard library is used Device QLOSS Est. QLOSS Meas.
to simulate the tap changer. SHWF is connected on the 500 Transformer -65.03 -65.50
kV line between Moorabool and Tarrone substations [2]. The
Capacitors 49.50 49.30
expected minimum Short Circuit Ratio (SCR) at the PoC is
approximate 10. The specific details on how to configure the LDC -116.76 -109.20
models is confidential information and outside of the scope QDES -132.29 -125.40
of this paper.
Authorized licensed use limited to: UNIVERSITY OF BIRMINGHAM. Downloaded on July 26,2020 at 22:28:54 UTC from IEEE Xplore. Restrictions apply.
The QDES values is then processed by the reactive power resultant QCMD (reactive power command) is sent to the
multiplexer which divides QSET_K to each substation based on algorithm.
their respective QBASE. Tab. 5 shows the respective QSET and
VREF calculation for each substation in accordance with the
estimated values from Tab. 4.
Authorized licensed use limited to: UNIVERSITY OF BIRMINGHAM. Downloaded on July 26,2020 at 22:28:54 UTC from IEEE Xplore. Restrictions apply.