Chapter 3, Problem 14P 16 Bookmarks Show all steps: OFF


Post a question
Answers from our experts for your toug
homework questions
Problem
Enter question

Kelle Carpet and Trim installs carpet in commercial offices. Peter Kelle has been very concerned
with the amount of time it took to complete several recent jobs. Some of his workers are very
unreliable. A list of activities and their optimistic completion time, the most likely completion time, Continue to post
and the pessimistic completion time (all in days) for a new contract are given in the following
20 questions remaining
table:

TIME (DAYS)
Snap a photo from you
phone to post a questio
ACTIVITY a m b IMMEDIATE PREDECESSOR(S) We'll send you a one-tim
download link

A 3 6 8 —
888-888-8888 Text
By providing your phone number, you agre
B 2 4 4 — a one-time automated text message with a
the app. Standard messaging rates may ap

C 1 2 3 —

My Textbook Solutions
D 6 7 8 C

E 2 4 6 B, D

F 6 10 14 A, E Operations... Introduction The..


to...
11th Edition 4th Edition 5th Ed

View all solutions


G 1 2 4 A, E

H 3 6 9 F
Chegg tutors who can
right now
I 10 11 12 G

Maria
MSU-IIT
J 14 16 20 C

Brian
K 2 8 10 H,I Brown University

a) Determine the expected completion time and variance for each activity. Hardik
Punjabi University

b) Determine the total project completion time and the critical path for the project. Find me a tutor

c) Determine ES, EF, LS, LF, and slack for each activity.

d) What is the probability that Kelle Carpet and Trim will finish the project in 40 days or less?

Step-by-step solution

https://www.chegg.com/homework-help/kelle-carpet-trim-installs-carpet-commercial-offices-peter-k-chapter-3-problem-14p-solution-97801328633… 1/5
9/19/2020 Solved: Kelle Carpet and Trim installs carpet in commercial off... | Chegg.com

 
NEW!
Textbook Solutions Expert Q&A Study Pack Practice 
Step 1 of 6

Consider the following data showing the activities involved in a project along with its optimistic,
most likely, and pessimistic completion time.

Comment

Step 2 of 6

a.

Calculate the expected completion time and variance for each activity using given
formulas:

…… (1)

…… (2)

Where ‘a’ is the optimistic time estimate, ‘m’ is the most likely time estimate and ‘b’ is the
pessimistic time estimate.

Prepare an excel sheet incorporating above formulas to determine the expected


completion and variance of each activity as shown below:

Comments (1)

https://www.chegg.com/homework-help/kelle-carpet-trim-installs-carpet-commercial-offices-peter-k-chapter-3-problem-14p-solution-97801328633… 2/5
9/19/2020 Solved: Kelle Carpet and Trim installs carpet in commercial off... | Chegg.com

Step 3 of 6
 
NEW!
Textbook Solutions Expert Q&A Study Pack Practice 

b.

Initially prepare a network diagram using the mentioned data. The network diagram is
shown below:

Comment

Step 4 of 6

Calculate the length of each path by adding the expected time required for completion of each
activity present in a path. Calcualtiosn are shown below:

Paths Duration Total

2+7+4+10+6+7.33 36.33*
C+D+E+F+H+K A+F+H+K
5.83+10+6+7.33 29.17
A+G+I+K
5.83+2.17+11+7.33 26.33
B+E+F+H+K
3.67+4+10+6+7.33 31
B+E+G+I+K
3.67+4+2.17+11+7.33 28.17
C+D+E+G+I+K
2+7+4+2.17+11+7.33 33.5
C-J
2+16.33 18.33

The path that takes the longest duration is called the critical path. The duration of this path is
called the project duration. Hence, the critical path is

Therefore, the total project duration is 36.33 days.

Comment

Step 5 of 6

c.

Calculate the ES, EF, LS and LF of the activities as follows-

ES and EF are calculated from the left side of a network diagram and proceeds towards the right
side.

ES of an activity = EF of preceding activity

ES of beginning activity = 0

EF of beginning activity = ES + Activity time

LS and LF are calculated from the right side of a network diagram and proceeds towards the left
side.

LF of an activity = LS of following activity

Use the largest EF as LF of all activities.

LS = LF – activity time

Calculate the slack time using the following formula:

Slack time = latest Start – Earliest start

ST = LS-ES

https://www.chegg.com/homework-help/kelle-carpet-trim-installs-carpet-commercial-offices-peter-k-chapter-3-problem-14p-solution-97801328633… 3/5
9/19/2020 Solved: Kelle Carpet and Trim installs carpet in commercial off... | Chegg.com
The ES, EF, LS, LF and Slack time of the activities present on the critical path are given below:
 
NEW!
Textbook Solutions Expert Q&A Study Pack Practice 

Hence, the ES, EF, LS, LF, and slack of each activity present in the project are determined.
Activities having 0 slack is considered to be present in the critical path.

Comments (2)

Step 6 of 6

d.

Calculate the acitivity variance along critical path by adding the variance of each activity present
in the path.

Variance =

= 5.22

Determine the probability of completion of the project on or before week 40 days as shown
below:

Calculate the standard deviation of the critical path using given formula:

Initially calculate the z value for given data using given formula:

Now, determine the probability for given z value using =NORMSDIST (1.61) formula in excel
sheet. The probability comes out to be 0.9463 or 95% (approximately). Thus, the probability of
completion of the project on or before week 40 is 95%.

Please note that values might differ due to rounded figures taken in calculations.

Comment

Was this solution helpful? 23 2

https://www.chegg.com/homework-help/kelle-carpet-trim-installs-carpet-commercial-offices-peter-k-chapter-3-problem-14p-solution-97801328633… 4/5
9/19/2020 Solved: Kelle Carpet and Trim installs carpet in commercial off... | Chegg.com

 
NEW!
Textbook Solutions Expert Q&A Study Pack Practice 

Recommended solutions for you in Chapter 3


Chapter 3, Problem 3CS Chapter 3, Problem 21P

Southwestern University: (A)*Southwestern The estimated times and


University (SWU), a large state college in immediate predecessors
Stephenville, Texas, 30 miles southwest of the for the activities in a
Dallas/Fort Worth metroplex, enrolls close to project at Howard
20,000 students. In a typical town–gown Umrah’s retinal scanning
relationship, the school... company are...

See solution See solution

See more problems in subjects you study

ABOUT CHEGG

LEGAL & POLICIES

CHEGG PRODUCTS AND SERVICES

CHEGG NETWORK

CUSTOMER SERVICE

© 2003-2020 Chegg Inc. All rights reserved.

https://www.chegg.com/homework-help/kelle-carpet-trim-installs-carpet-commercial-offices-peter-k-chapter-3-problem-14p-solution-97801328633… 5/5

You might also like