You are on page 1of 2



 
Name : Rizal Hidayatullah Time : 08.00 AM -05.00 PM  
Position : Inspector Location : PT. Robutech  
Mounth : December Year : 2020  
NO DATE ACTIVITY
 Learning about ultrasonic thickness measurement
procedure (RBT-P-04)
 Learning about mindset of engineering towards
client expectation
Monday  Operating thickness testing equipment type 38 DL
1
14/12/2020 and probe type E790 (High-Temp) on the step weight
for calibration
 Operating thickness testing equipment type 38 DL
and probe type E790 (High-Temp) on pipe material to
thickness measurement
 Learning about input data logger to computer from
38 DL
 Learning about calibration of ultrasonic bore oxide
Tuesday use Olympus type epoch 650 and probe 20 Mhz type
2
15/12/2020 M2091
 Learning about Radiographic examination procedure
(RBT-P-05) and discussion about content of the
report for radiographic examination
 Safety induction from PT.Cargill in the meeting
room second floor of PT. ROBUTECH
Wednesday
3
16/12/2020  Learning about direct Visual Examination procedure
(RBT-P-16) than discuss about visual defect and
measurement instrument for measure defect
4 Thursday  Reading remote visual examination procedure (RBT-P-
17/12/2020
17)
 Discuss about hardness test procedure(RBT-P-09) and
empirical similarity with tensile strength
 Learning about operate hardness testing equipment
type equotip 550 with rebound method and type
novotest T-UD3 with Ultrasonic Contact Impedance
method.
 Learning about transfer data logger from proceeq
equotip 550 to computer and convert data to excel
document
 Safety induction from PT.Cargill about Elevated
work, Confined space, Hot work, and electrical
work.
Friday
5
18/12/2020  Learning about ultrasonic examination
Procedure(RBT-P-01)
 Draw Indication Mapping Eddy Current testing for LP
FEEDWATER No.1-4 PT.YTL.