Task Start Date Duration(Days)

Problem definition 9/9/2020 16


Presentation of ghantt chart 9/26/2020 7
Problem Analysis 10/5/2020 26
Presentation of Findings 11/9/2020 10
Identification of possible solutions 12/4/2020 13
Presentation of possible solutions 12/16/2020 10
Evaluation of solutions 12/28/2020 12
Selection of solutions 1/11/2021 14
Presentation of selected solution 1/27/2021 7
Presentation of justification of solution 2/5/2021 6
Implementation 2/12/2021 54
Review 4/7/2021 7

9/9/

Problem definition

Presentation of ghantt chart

Problem Analysis

Presentation of Findings

Identification of possible solutions

Presentation of possible solutions

Evaluation of solutions

Selection of solutions

Presentation of selected solution

Presentation of justification of solution

Implementation

Review
End
9/24/2020 44083 44299
10/2/2020
10/30/2020
11/18/2020
12/16/2020
12/26/2020
1/8/2021
1/24/2021
2/2/2021
2/10/2021
4/6/2021
4/13/2021

Gantt Chart
9/9/2020 10/29/2020 12/18/2020 2/6/2021 3/28/2021

Problem definition

Presentation of ghantt chart

Problem Analysis

Presentation of Findings

Identification of possible solutions Start Date


Duration(Days)
Presentation of possible solutions

Evaluation of solutions

Selection of solutions

Presentation of selected solution

esentation of justification of solution

Implementation

Review
tart Date
uration(Days)