You are on page 1of 8

ENDICOTT DEVELOPMENT-MAKING THE ARCTIC

OFFSHORE ECONOMICAL
M. I. Curtis, Vice President, Engineering & Special Projects, Standard Alaska Production
Company, U.S.A., 900 East Benson, Anchorage, Alaska 99519, U S A ; and D. B. Huxley,
Development Planning Manager, Standard Alaska Production Company, USA.

Abstract. Construction is underway on the development of Endicott, the first offshore oilfield in the Arctic.
Discovered in 1978 in shallow water in the Beaufort Sea about 15 miles northeast of Prudhoe Bay, the field
holds about 350 million barrels of recoverable liquids. Operated by Standard Alaska Production Company, the
field is expected to start u p by the end of 1987 and reach a peak production of 100000 barrels per day
(16 O00 m3/d) by early 1988. On the basis of initial studies, Endicott appeared uneconomical due to the high
cost of offshore arctic development. Subsequently, the project was rescoped and approached as a ‘no frills’
second generation arctic design. Through various scope changes, design-optimization studies and improved
well drilling techniques, the total cost of the project was reduced from the $3.8 billion conceptual estimate to
less than $2.0 billion. Concurrent with the design efforts, three years of intensive environmental study and
coordination with Federal, State, and local agencies were required to obtain the needed development permits.
This was followed by a decision of the owner companies in February, 1985 to proceed with full field development.
This paper traces the Endicott from its discovery in 1978 through a ten-year evolution to planned start-up at
the end of 1987.

Résumé. Le développement du gisement d’Endicott, premier champ pétrolier marin de l’Arctique, est en chantier.
Découvert en 1978 sous les eaux peu profondes de la mer d e Beaufort, à 25 kilomètres environ au nord-est de
la Prudhoe Bay, ce gisement contient environ 50 millions de tonnes de pétrole récupérables. Exploité par
Standard Alaska Production Company, il devrait commencer à produire en fin 1987 pour atteindre en début
1988 une production de pointe d e 5 Mt/an. D’après les premières études effectuées, Endicott semblait non-
rentable en raison du coût élevé de l’exploitation de l’Arctique marin. Ultérieurement, les objectifs ont été
redéfinis dans l’optique ‘sans fioritures’ d’une conception arctique de la seconde génération.
A la suite de divers changements d’objectifs, d’études d’optimisation de la conception et d’améliorations des
techniques de forage, le coût total d u projet s’est trouvé ramené, des 3,8 milliards de dollars estimé initialement,
à moins de deux milliards de dollars. En parallèle avec les études de conception, trois années d’études intensives
du milieu et une coordination avec les agences fédérales, l’administration de 1’Etat d’Alaska, et les autorités
locales ont été nécessaires pour obtenir les permis d’exploitation. Ceci fut suivi par la décision prise par les
sociétés exploitantes, en février 1985, d’entreprendre l’exploitation à fond du gisement.
La communication retrace l’évolution d u gisement d’Endicott depuis sa découverte en 1978 jusqu’au début
de sa mise en production prévue dix ans plus tard pour la fin de 1987.

1. INTRODUCTION 2. ENDICOlT RESERVOIR


The Endicott Field is located about 4 km offshore The Endicott Field discovery well, Sag Delta #4,
from the Sagavanirktok River delta in the Beaufort was completed by Standard in early 1978. The reser-
Sea about 24 km northeast of the Prudhoe Bay oilfield voir was delineated by 6 additional exploratory wells
(Fig. 1). The water depth in the project area ranges drilled by Standard and Exxon through the first quar-
from about 1.2 to 3.7 m. The field is located within ter of 1982 (Fig. 2). The oil was found in the Kekiktuk
the Duck Island Unit of which Standard Alaska Pro- formation, the lowermost portion of the Endicott
duction Company is the operator with a 57% equity group, of Mississippian age. The oil pool is overlain
share. The other Endicott owners include: Exxon by a gas cap with the gas-oil contact at a depth of
Corporation; Amoco Production Company; Union about 3004 m; the oil water contact is at about 3107 m.
Oil Company of California; ARCO Alaska, Inc.; The structure is a southwesterly plunging antiform,
Cook Inlet Region, Inc.; NANA Regional Corpor- bounded to the north/northeast and southjsouthwest
ation, Inc.; and Doyon, Limited. by major faults.

61
62 APPRAISAL OF ENGINEERING TECHNIQUES FOR ARCTIC FIELD DEVELOPMENT Pl1
of offshore Arctic development and the relatively
small size (compared to Prudhoe Bay and Kuparuk)
13 KUPARUK
MILNE
POINT
Beaufort Sea

1BURNE
of the resource. In late 1981 the owners set up a joint
study programme with the support of an engineering
<\ ,ENDICOTT
contractor to look at alternative development con-
NATIONAL
PETROLEUM cepts. This study programme was done at a time when
RESERVE
delineation drilling and reservoir definition were still
ALASKA
<; NATIONAL
underway. Therefore, rather than attempting to final-
)/ , , NORTH SLOPE '; WILDLIFE
REFUGE
ize an optimum project design at a time when the
/ ' 1 reservoir picture was still unfolding, the study focused
on the following:
(1) Evaluate the technical and cost feasibility of the
major project design alternatives.
Fig. 1. Alaska North Slope Fields. (2) Establish a broad project scope that could
accommodate the maximum anticipated reservoir
requirements in terms of areal extent and well
density.
(3) Use a 'building block' cost estimating approach
that would allow for future rescoping and re-
estimating utilizing the components of the initial
study.
(4) Provide sufficient engineering definition to sup-
port filing of initial project permits.
I
The conceptual studies produced a development
scheme which included the construction of four gravel
islands: a central processing and drilling island; two
satellite drilling islands; and an island in water deep
enough to provide a reliable year-round source of
seawater forthe anticipated waterñood (Fig. 3). Three
alternative routes were considered for the sales oil
Fig. 2. Endicott Reservoir. and gas pipelines. In the first case (West Dock
Marine) the pipelines were routed offshore on a sub-
marine approach to the existing Prudhoe Bay West
The areal extent of the reservoir is about 3480 ha. Dock; they were then routed overland to sales points
It is estimated that the field contains about one billion for oil (TAPS) and future gas (AGCF). The other
barrels (159 million m') of 23" gravity oil in place, of scenarios involved bringing the pipelines south to
which 350 million barrels (56 million m') are recover- shore, thence overland through the Sag Delta to sales
able. In addition there are an estimated 800 billion points. In one case (Delta-Marine) the pipeline sec-
standard cubic feet (23 billion m') of recoverable gas tion to shore was submarine while in the other case
although there are n o current plans to develop this (Delta-Causeway) the pipeline was carried on a gravel
resource due to the lack of a sales outlet and the need causeway connecting the Production Island to shore.
to reinject the gas into the reservoir for pressure In all three cases the pipelines between the islands,
maintenance. Field oil offtake will be 100 O00 barrels needed for transporting produced fluids, lift gas, and
per day (16 O00 m3/d) at start-up with a plateau of injection water, were proposed to be subsea. The
about four years. Based on a nominal 80 acre (32 ha) on-island facilities were proposed to be housed in
field wide well spacing, a total of about 100 develop- modules of a size similar to those used at Prudhoe
ment wells will be required to exploit the resource. Bay, or about 2000 tonnes maximum. Camps were to
be sited in the delta for housing personnel required
for construction (750 man) and operations (250 man).
3. CONCEPTUAL STUDIES
It was estimated that to fully develop the reservoir
From early studies, the Endicott Field appeared to up to 240 wells might be required, providing nominal
be a submarginal prospect because of the high cost 40 acre (16 ha) well spacing.
APPRAISAL OF ENGINEERING TECHNIQUES FOR ARCTIC FIELD DEVELOPMENT 63

Fig. 3. Early Endicott concepts.

The major issues resolved through conceptual 4. PROJECT RESCOPING


design included the selection o f
A major rescoping of the project took place in late
( 1 ) Centralized versus decentralized production pro- 1982 and early 1983 using the results of conceptual
cessing facilities. engineering and recent delineation drilling. This effort
(2) Conventional Prudhoe Bay type modules versus focused on resolving the major project scope issues:
barge-type facility packaging.
(1) Number of Islands. Drilling results concluded
( 3 ) Onshore type drilling plan (wells closely spaced
in a row) versus a more compact offshore-type that the reservoir could be fully developed from
as few as one or two drill sites. Also, if a drilling
drilling arrangement (template).
island was properly placed, it could provide a
The estimate of total costs for the development reasonably secure source of ice-free seawater for
scheme produced during conceptual design was $3.8 waterflooding. Therefore, the decision came
billion. The key factors that influenced costs included: down to one versus two drilling/production
a large number of wells (240) with a high average islands. The one-island case minimized gravel
cost ($5.7 million each); four islands; numerous and facility connections (no inter-island pipe-
‘small’ modules with a large number of interconnects; lines) but had the highest drilling costs and tech-
subsea pipelines between islands; and multi-train pro- nical risks (high step-out wells), provided the
cess facilities. It was apparent that the initial develop- least flexibility for reservoir development (chance
ment scheme, although technically feasible, would of putting the island in the wrong place), and
have to be reduced significantly in overall scope and was assured of leaving some of the oil reserves
cost before field development could be justified. behind. The two-island case was selected.
APPRAISAL OF ENGINEERING TECHNIQUES FOR ARCTIC FIELD DEVELOPMENT Pl1
Number of Wells. A review of additional well to shore; the Delta Causeway pipeline route; a
data and new reservoir performance predictions 100 O00 BPD (16 O00 m3/d) production processing
from computer simulation work concluded that facility; a waterflood intake system integral to the
the field could probably be developed adequately Main Production Island; and space for up to a total
with 80 acre (32 ha) rather than 40 acre (16 ha) of 120 wells. More than 90 studies were conducted
well spacing. This reduced the required number during preliminary engineering (May 1983 to June
of wells to about 100 to 120. 1984) in an effort to refine the project design and
Pipeline Route. The major decision on pipeline further reduce overall project costs.
route was: submarine (West Dock or Delta- Borrowing a term from the budget world, pre-
Marine) versus above ground (Delta Causeway). liminary design was conducted with a ‘zero-base’
Integral to this decision was a cost/benefit analy- approach in establishing the facilities requirements.
sis of the causeway, both from a standpoint of This meant that we not merely rely upon past practice
carrying pipelines and providing year around for establishing design criteria, but that we examine
road access to the islands. Since the shallow every piece of equipment, construction standard, and
waters allowed for a ‘relatively’ inexpensive design practice to ensure that each dollar invested
causeway, the Delta-Causeway alternative was was essential to meet our performance goals. The
selected. In addition to connecting the project to value of production ‘lost’ when the facility was down
shore, the causeway would also connect the was balanced against the cost of redundant equipment
islands, thus eliminating the need for any subsea to ensure a more reliable system. The focus was to
pipelines. remove redundancy and sparing where they could
Facility Sizing. An oil offtake of 100 O00 barrels not be economically justified. Taking advantage of
per day (16 O00 m3/d) was recognised as aggress- experience at Prudhoe Bay and Kuparuk, we sought
ive for the Endicott reservoir size. However, well to define a ‘second-generation’ arctic design
tests indicated the reservoir had a high produc- approach.
tivity potential and cost sensitivities showed ‘rela- During preliminary design it was found that
tively’ small savings with smaller processing module sizes greater than those used at Prudhoe were
facilities in the range of 70000 barrels per day cost effective at Endicott, where long module-trans-
(1 1 O00 m3/d). portation distances over roads will not be required.
The largest Endicott module was proposed to have
base measurements of 29 by 59 m and weigh in excess
5. PRELIMINARY DESIGN
of 3600 tonnes. It was determined that much of the
A $50 million preliminary design effort was begun non-rotating equipment could be installed outside,
in May 1983 with a design basis that was substantially rather than enclosed in modules as had often been
altered from the initial conceptual work (Fig. 4) and done at Prudhoe Bay. A single, rather than redundant,
included the following: two gravel islands; a gravel oil-processing train was employed and three stages
causeway connecting the islands to each other and of gas compression were set to run off a single turbine
driver. An existing exploration drilling island was
2 ISLANDS AND CONNECTING CAUSEWAY incorporated into the design as a breakwater and ice
protection feature for the seawater intake system on
DELTA CAUSEWAY PIPELINE ROUTE the north side of the Main Production Island. The
1 2 0 WELLS - 70 MPI. 5 0 SDI sideslopes of the islands and causeway were designed
to withstand severe ice and wave action with the use
CAMPS ON MAIN ISLAND of concrete mats, gravel bags, or shallow slopes; such
CONSTRUCTION 600 MAN systems were used individually or in combination,
OPERATIONS 150 MAN depending on water depth and location. The final
selection of materials was based on an economic
PROCESS FACILITIES trade-off of the higher initial cost of the more substan-
Oil Prod. 100 MBD tial concrete mats versus higher maintenance costs
Gas - Inj. & Fuel 200 MMCFD associated with the less durable alternatives.
- Lift 200 MMCFD In the drilling area, wells were designed on 3 m
Prod. Water 150 MBD
surface spacing as compared to 34 m at Prudhoe Bay
Source Water 140 MBD
for the purpose of conserving island space. This
Fig. 4. Endicott preliminary design basis. selection required a careful analysis of perma-frost
Pl1 APPRAISAL OF ENGINEERING TECHNIQUES FOR ARCTIC FIELD DEVELOPMENT 65

L
Fig. 5. Current Endicott Development.

thawing, and of facility and casing designs to ensure through a pipeline from MPI along the causeway to
that the resultant island subsidence and well bore soil shore, and from there to Pump Station 1 of the Trans
movements could be accommodated. An innovative Alaska Pipeline System. The Main Production Island,
cantilever design for drilling rigs was proposed to 18 ha in area, will include: a 600-person Main
speed up rig moves between wells. This design allows Construction Camp; a 150-person Base Operations
the rig to be moved more easily across the tightly Center; production separation and dehydration
spaced wells and well flowlines that are planned. A equipment;' gas compression facilities; produced
reduction in well costs resulted not only from the water and seawater treatment and injection facilities;
reduction in total number of wells, but also from a and equipment for providing power and other utilities
reassessment of improved drilling efficiencies (Fig. 6). This island also provides space for up to 70
experienced at Prudhoe Bay, improved rig design,
optimization of drilling support facilities, and an
overall improvement in market conditions which
brought down the cost of tubulars, and drilling rig
and support service rates.
The development scheme that resulted from the
studies and preliminary engineering is shown as Fig.
5. Beginning on the east side of the Sag River, a 16 km
access road leads through the delta to the shoreline
and continues with 8 km of gravel causeway in the
Beaufort Sea. At each end of the T-shaped causeway
is a gravel island; the Main Production Island (MPI)
to the northwest and the Satellite Drilling Island
(SDI) to the southeast. Sales oil will be pumped Fig. 6 . Endicott main production island.
66 APPRAISAL OF ENGINEERING TECHNIQUES FOR ARCTIC FIELD DEVELOPMENT

wells. The Satellite Drilling Island, 4 ha in area, will Conceptual engineering work during 1982 laid the
function as a drilling pad for up to 50 additional ground work for preparation of Engineering and
wells. The causeway connecting MPI and SDI will Environmental Overviews; these documents suppor-
carry pipelines for the transport of produced fluids ted the initial Corps of Engineers 404 permit applica-
to MPI, and lift gas and injection water to SDI. tion filed in September 1982 by fully defining the
Altogether, as a result of project rescoping, pre- project scope alternatives and assessing the antici-
liminary design and the improved cost climate, overall pated environmental impacts. The Corps permit filing
project costs were reduced to less than $2.0 billion was the trigger for the preparation of the EIS which
from the initial conceptual estimate of $3.8 billion began in late 1982 with the Corps as the lead agency.
(Fig. 7). The EIS process concluded in August, 1984 with
issuance of a 1,250 page final EIS document. The
COSTS, $ MILLIONS (MOD) process took approximately two years and cost several
INITIAL DESIGN
million dollars, including the baseline monitoring
CONCEPT ESTIMATE programmes. In the end, the EIS provided an exhaus-
FACILITIES 1620 940 tive analysis of the development alternatives and a
reasonable worst-case assessment of their potential
PIPELINES 270 120
impacts; in so doing, it supported Standard’s conten-
ISLANDS & CAUSEWAYS 300 290 tion that the proposed development scheme was
environmentally acceptable.
WELLS 1610 6 2 In all, 13 different regulatory agencies on three
TOTAL 3800 1970 levels of government were involved in the project
Fig. I . Endicott cost reductions. review and permitting effort. A total of 25 permits
was required before development could proceed. The
major Federal approval was received from the Army
6. PERMITTING
Corp of Engineers for placement of gravel on wet-
While eff Orts were being made to reduce the lands. Approval by the State of Alaska was required
development costs for Endicott, world oil prices were to ensure that the programme was consistent with the
beginning to soften. Thus, while the owners believed Alaska Coastal Management programme. The Alaska
in mid-1984 that Endicott might be a viable project, Department of Natural Resources also approved the
it could hardly be called robust. Two key questions owners’ proposal for unitization of the oil field. The
remained at that time which prevented a final decision North Slope Borough was the local agency that
to proceed: approved the overall project Master Plan and
Rezoning.
(1) Would we get the necessary environmental and
Of the various environmental issues that arose
other permits from the various governmental
throughout the EIS/permitting process, the most
agencies and get them in a timely manner?
difficult and potentially most costly related to con-
(2) How much would the stipulations attached to
struction of the offshore causeway; principally, the
these permits cost us?
3 km causeway section perpendicular to shore.
There was a real possibility that unnecessarily Although the EIS found that a subsea pipeline to the
restrictive environmental mitigation measures might West Dock was environmentally preferable to routing
be imposed that would push development costs above the pipeline to shore via a gravel causeway, the owners
an acceptable level. concluded that the cost of the subsea pipeline could
The owners had concluded in early 1982 that the probably not be absorbed in a viable project. The
magnitude of the Endicott Project, being the first environmental objections to the causeway stemmed
offshore arctic development and requiring up to 6 mil- from its potential impacts on anadromous fish. Since
lion cubic metres of gravel, would require the prepar- these fish normally move parallel to the coastline, it
ation of an Environmental Impact Statement (EIS). was feared that any obstruction to their movement
The collection of environmental baseline data had might adversely affect them as a result of the physical
already begun in the summer of 1981. These data, presence of the causeway itself or of changes in the
along with a fish overwintering study in the winter local water temperature and salinity created by the
of 1981/82 and an extensive field monitoring program causeway.
in the summer of 1982, provided the basis for the EIS The final EIS proposed that the causeway would
analysis. be environmentally acceptable if broken by breaches,
Pl1 APPRAISAL OF ENGINEERING TECHNIQUES FOR ARCTIC FIELD DEVELOPMENT 67

or open bridges, allowing passage of water and fish missioning of essential field facilities are expected to
across the causeway; however, the total length be completed and field production started by year-end
required to avoid unacceptable impacts was the sub- 1987. By early 1988 Endicott should be producing at
ject of long discussions among the various agencies a peak of 100 O00 barrels per day (16 O00 m'/d).
and with Standard. As a final arrangement, two Since the initial commitment was made, costs to
breaches, 200 feet (61 m) and 500 feet (152 m) long, develop Endicott have continued to come down. In
were agreed to be installed by Standard in the cause- the facilities area, construction has proceeded
way section to shore. extremely well and the current economic climate has
Furthermore, Standard is required to conduct a resulted in material and labour costs being sig-
comprehensive long-term environmental monitoring nificantly less than initially forecast. In the drilling
programme to assess the actual impacts of the project area, further reductions have been forecast based on
on the fish and wildlife in the area; if these pro- actual experience to date, more favourable market
grammes show greater impacts than expected, further conditions, and an expectation that no more than 100
mitigation measures may be required. wells will be required to develop the reservoir. In all,
total development costs are now estimated to be about
$1.3 billion, a reduction of nearly $700 million from
7 . DEVELOPMENT PROGRESS
the design estimate prepared in June, 1984.
Endicott construction got underway in March, 1985
when Standard began the largest single-season gravel
8. CONCLUSIONS
hauling operation ever to take place on the North
Slope. By October, 1985, more than 4.6 million cubic We are satisfied at present to have what we believe
metres of gravel had been placed in constructing the is a solid oil field development programme that is
islands, causeway, and onshore road. Lower-48 proceeding on schedule; however, getting to this point
module assembly began in August, 1985 at New has not been easy. The conditions for developing an
Iberia, Louisiana. The causeway bridge sections were offshore oil field in the Arctic have demanded the
sealifted to the North Slope during the summer of closest attention to reducing project costs, and finding
1985 and installed during the first quarter of 1986. ways to get the job done with less than we might have
The Main Construction Camp was trucked in small been able to afford in earlier projects. The ten years
modular sections to the North Slope, field-installed, required to bring Endicott from discovery to produc-
and placed in service by June, 1986. The Rase tion (Fig. 8) is staggering b y U.S. Lower-48 standards
Operations Center was transported in modular sec-
tions to the Slope partly via sealift from northern
Canada, and partly by truck from Anchorage; field
installation should be complete by year-end 1986. The
first facility modules, which included utility and life
support systems, were sealifted during 1986; com-
missioning of the utility module is scheduled to be
completed by November, 1986.
Drilling began in April, 1986 with one rig on each
Gravel Work Island Construction
island. Approximately 30 to 35 wells will be drilled Module Conslruclion íL48)

and completed by the start of production at year-end


1987.
The gravel placement and slope protection pro-
gramme was completed in August, 1986. In all,
Standard placed nearly 5 million cubic metres of
gravel and installed 24 thousand gravel bags and 27
thousand concrete blocks for sideslope protection on
the islands and causeway. Fig. 8. Endicott programme schedule.
Pipeline construction is underway and will be com-
pleted by mid-1987. Fabrication of the remaining and has placed a heavy economic burden on the
facility modules (approximately 20 O00 tons) is project. The interests and responsibilities of many
continuing in New Iberia; these units will be sealifted regulatory agencies have played a major role in shap-
during the summer of 1987. Installation and com- ing the course of our development programme. By
68 APPRAISAL OF ENGINEERING TECHNIQUES FOR ARCTIC FIELD DEVELOPMENT Pl 1
starting early and maintaining close coordination with can be economically developed only if engineering
the various agencies, we have been able to establish and planning are dedicated to achieving cost
an economically acceptable programme. We antici- effectiveness, and if reasonable tradeoffs are made
pate that other fields similar to Endicott will be dis- between environmental concerns and their cost and
covered. It is clear from our experience that these schedule implications.

You might also like