Project for Construction of Mumbai-Ahmedabad High Speed Rail Bidding Documents Part 2

Package No. MAHSR- C-7 Section VI-3 Requirements (Technical Specifications)


(CEM)

Sub-structure Pier Cap

the box-outs (cut-outs) in the substructures prior to launching the superstructure.


half way box outs in superstructures.
For example: When the stoppers are installed into box-outs in piers prior to launching the girder,

Cast-
For example: When the stoppers are installed into the Continuous girders or end diaphragms
of PSC I- -
Box-out: Stoppers installed in superstructure through full box-outs in the superstructures.
For example: When the stoppers are installed into the girders from the top of girder through the
full box- -
Full Box-out (post-installation): Stoppers installed in substructure and superstructure through full box-
outs in the superstructures.
For example: When the stoppers are installed into the piers and girders from the top of
girder through the full box- -out (post-

ii. Installation Method (illustrated examples)


(1) -

(2) Insert & Insert

Division 02000 Page 96 of 168