CONSTRUCTION PROJECTS OF IRAQ. Construction projects are commonly acknowledged as successful when it is completed at the specific time, within budget, and according to the specifications. The delay of projects has negative effects on the value of the contract because it is related to the elements of the expensive resources which often lead to claims or arbitration. However, the projects that investigated in this study included construction of ten hospitals with 400 beds in different cities of Iraq. A frequency, severity and importance indexes were determined for 77 factors of delay divided into ten categorizations according to the stages of the project, The results showed that the weakness of technical offers of companies nominated to assignment as a result of adopting the principle of the lowest bid price in the government tendering and ineffective delay penalties by the employer in addition to Poor planning and scheduling the project by the contractor were the major causes that delayed the projects in the middle and southern Iraq.