You are on page 1of 6

NexGen Technologies for Mining and Fuel Industries

ISBN 978-93-85926-40-2

Evaluation of safe stoping parameters at underground


manganese mine by numerical modelling
M.N. Bagde, A.G. Sangode and J.C. Jhanwar
Nagpur Research Center, CSIR-Central Institute of Mining and Fuel Research, Nagpur, India

ABSTRACT: The mine, which is named as Kandri mine, is an underground manganese mine of
M/s Manganese Ore India Ltd. The hydro-geological conditions of the mine are such that ground
water occurs within weathered, jointed and fractured zones of the rock. The movement of ground
water is controlled by the number of in-situ factors like; joint spacing, its extent and continuity as
well as interconnection of joints, thickness of the weathered zone and topography of the area, etc.
It also occurs under confined conditions wherein fractures, joints and shear zones are deep seated.
The paper deals with the various results obtained from the field studies, their interpretation and
application in planning suitable mining method to recover thick, wide and complex manganese
ore-body in south extremity of this mine. The numerical modelling is used to arrive at safe stoping
parameters in complex condition prevalent at this mine.

1. INTRODUCTION
appears near the southern edge of the Kandri

M /s Manganese Ore India Limited is the


country’s largest producer of high grade
manganese ore at the present. In early 1896, the
mine, where, again it is intimately folded. As a
result of the complex set of faults, rocks on the
footwall and the hanging wall sides of the main
establishment then known as Central Provinces ore body are badly fractured. The mine was
Prospective Syndicate (CPPS) started its first first worked by the opencast method of
mine at Kandri located in Ramtek Tehsil of working and after reaching its economic limits
Nagpur District of Maharashtra State in India. (i.e., R.L. 280 m), an underground method of
The total lease hold area is around 0.8306 Km2. working was adopted by driving an incline. The
The manganese deposit in this area belongs to S-shaped ore body in this mine is divided into
Munsar rock formation of Sausar Group. Rocks three sections: the North Limb, the South Limb
are mainly Meta-sediments comprised of mostly and the South Limb extension with extremity.
quartzite, schist and gneiss. It is overlain by The study area covered in the present study is
muscovite-schist and feldspathised-quartz-gneiss South Limb extremity in between crosscut 8
and underlain by mica-schist (Ramakrishnan and 11 and generally 70–90 m wide ore body
and Vaidyanadhan.[1]). Dolomite marble is seen dips at 20°–30°. The wide thick manganese ore
to be well developed in the area. The dolomite body encountered in the recent past in South
formation is folded and as a result of which the Extremity zone of the mine is of the great
exposure attains to appreciable width. The importance from the recovery point of view due
rocks generally strike approximately east-west to its high grade ore quality. At the same time,
along the foot of the hill. While, at the south of method for its recovery is also a challenge due
the Kandri mine, it is gradually swinging to the to the complex rock mass conditions, hydro-
north-west at its western edge. The rock re- geological as well as complex geological

591
sttructure. Sincee, the orebodyy in this partt is ground level (Figuree 1). The groound water
suuddenly plungiing to 25–30 degrees from the occurrennce is observeed underneathh the water
eaarlier 45–50 degrees.
d In thhe present papper, table condition
c andd mostly in weathered,
geeo-hydrologicaal parameters derived throuugh jointed and fractured zones of the rocks. The
vaarious field stu
udies conductedd are summarizzed. movemeent of groundd water flow is mostly
Thhe use of numeerical modellinng is applied in the controlled by the number of geological
prresent study too derive safe stooping parameters. parametters including joint spacing, its extent
Inn the present paper,
p results obtained throuugh and conntinuity along with
w interconneection of the
nuumerical modeelling studies as a well as hyddro- joints, thickness
t of the
t weatheredd zone and
geeological studyy is presented and
a discussed. topograpphy of the areea etc. The minem area is
comprissed of highly fractured,
f joinnted, faulted
and foldded rock masss. It is found to t be water
2.. GEOLOGY Y AND HYDR
RO-GEOLOGY
Y pervious or strong watter permeable and a average
OF THE MIINE permeabbility is found to decrease with
w increase
Thhe Sausar Folld Belt (SFB)) is an importtant in the depth
d due to thhe closing of jooints, faults
coonstituent of th
he Central Indiian Tectonic Zoone and otheer fractures. Thhe representativve borehole
(CCITZ)—a crusstal-scale Pre--cambrian mobbile profile from
f the mine area is shown in Figure 1.
beelt running E–W W through the Indian Peninsuular Also shhown in this figure is waater aquifer
Shhield (Radhak krishna and Naqvi
N [2]
). SSFB
B is presencee in the form m of “Dolom mitic Kast”
M
Meso-to-Neo-pr roterozoic in agge (Sarkar et all.;[3] (Source: Shrushti Sevaa Report[6]).
R
Roy et al.[4]) and comprisees of two maajor
litthotectonic en nsembles, viz., Tirodi Biootite
G
Gneiss (TBG) and migmaatite and meeta-
seedimentary saausar group (SSG). Lithoolo-
giically, SSG reepresents a craatonic assemblage
off metamorph hosed quartzite, pelites and a
caarbonate (Chatttopadhyay annd Ghosh[5]). The T
m of the regional area of thhe mine belongs to
most
thhe Sausar grou up of the rock formation. Thhese
roocks have beeen highly afffected by seveeral
cyycles of tecton nics activity inn the past on the
geeological part.. Based on the remote senssing
daata numerous lineaments
l havve been identifi
fied. Fig. 1. The representatiive borehole proofile showing
Thhe various stu udies carried out by the various the preseence of dolomiticc kast aquifer (ree-drawn from
orrganizations inn the area havve concluded that t the source data[6]).
thhe proposed mine
m is locatedd in the footw wall
roock and litho o-logically it is comprises of The ground water conddition was firsttly analyzed
doolomite and quartz
q muscovvite schist as the through the obtained data
d of boreholle, dug well
allternate formattion. The mangganese ore occcurs and hyddrological geoology of the mining
m area
beetween 174 to 192 m depth. The drilling raates through various studies conducted in the past.
suuggest that fo ormation is looose on the top The stuudies includedd are Verticall Electrical
foollowed by sem mi-compact inn nature. In doolo- Soundinng (VES) interrpretation of thhe first two
m formation,, there was suudden collapsee of
mite layers only by geophyysical survey caarried out in
thhe drilling rodd, which sugggests the soluttion the areaa. In addition to that pumpiing test for
chhannel presencce in the form mation. The high
h aquifer parameter determination
d has been
w
water dischargee (5–6 lps) at two sites in the conductted in the area. The pumpiing test for
caase of pumpin ng well (PW) and observattion aquifer parameter
p deteermination wass carried out
w (OW) was recorded at thhe depth of 1011 to
well in the area
a based on the geologicall report and
1007 m and 28 to t 34 m, respecctively, below the discussiion with thee mine plannner’s. The

592
geometry of aquifers is considered for mining 7233 m3/day, respectively. In case, all are
operation. The corresponding aquifer is con- activated simultaneously the peak flow will be
sidered for aquifer parameter determination. 8663 with 4235 m3/day as the stabilized flow.
Keeping in view the possible inter-connectivity Thus, it is expected that Mine Management
of all aquifers through cross-flow and fault may have arrangement for pumping of 10,000
zones, a multi aquifer well field is constructed m3/day. In normal condition the pumping
to carry out pumping test as well. Aquifer arrangement need is for 1500 m3/day. In the
parameters are the one of the most important to case of worst condition, it is expected that
derive at mine inflow estimation. The obser- arrangement of pumping water to the tune of
vation well data is analyzed and results 10,000 m3/day may be required during the
are provided in Table 1. The pumping well actual mining operation in the south extremity
was pumped at the constant discharge rate of area. The aquifer parameter of different rock
518.4 m3/day but after 70 minutes the discharge formations is also estimated and provided in
was dropped to 259.2 m3/day. The analysis of Table 1 (Source: Shrusti Seva Report[6]).
the data indicated that after 70 minutes of
pumping the cone of depression touched the Table 1. Aquifer parameter-formation wise
mine boundary with large diameter borehole at Multiple Aquifer
the distance of 55 m from the pumping well.
Quartz
This bore holes were connected to the Aquifer parameter Dolomite Dolomite Mica
underground mine and found to discharging kast fracture Schist
water into the mine, thus, creating a negative fracture
head for the pumping test under operation. The Transmissivity 79.10 86.29 41.38
mine bore hole is found to be acting as a barrier (m2/day)
zone and the discharge rate is determined to the Hydraulic 4.94 1.39 0.45
tune of 259.2 m3/day. The effective thickness conductivity (H)
of aquifer considered is based on fracture/ (m/day)
solution channel pattern of lithology and cross Aquifer Thickness 16 62 92
flow through aquiclude is at 92 m. The water (m)
head over ore body at pumping site is 155.88 m Source: Shrushti Seva Report.[6]
as on the test date.
Mine inflow prediction for underground 3. SUGGESTED MINING METHOD
manganese mine is a complex process since
there are so many non-ideal conditions which The manganese orebody in the south extremity
become operative during the mining. This at this mine is quite wide at 60 to 90 m and
suggests that adequate model may be an 15–20 m thick characterised by the presence of
approximation. In this approach, the open various geological disturbances, weak hangwall
section of drift is approximated as suitable and footwall rocks, water bearing strata, friable
dimension ellipsoid or cylindrical and the line orebody with intrusion of quartz mica schist,
section is ignored. Flow towards this opening water aquifer in the form of Dolomitic Kast. In
can be analyzed using non-linear equation. This view of this scenario, Room and Pillar method
have been used to incorporate inter granular of stoping with post pillar of 5 m thickness at
laminar, fracture and turbulent flow condition. every opening span of 10 m appears to be
It is expected that during mine development feasible. The proposed stope dimensions based
under in-situ condition the mine inflow will be on the various other studies carried out and
insufficient. In the case during blasting and keeping in mind above reported conditions
other mine operations, the fracture zone, fault related to the geology and hydro-geology are:
zone and solution channel zone may be stope length-30 m, stope height-30 m and stope
activated to encounter the predicted flow per width not to exceed 20 m at any time during the
day to the tune of 343 m3/day, 1087 m3/day and actual stoping operation. Bieniawski’s RMR

593
and Barton’s Q is used to characterize the rock practiced horizontal Cut-and-Fill method at
mass as well as to verify roof spans and to Kandri mine is substituted with the 'Room and
recommend support systems. Average combined pillar with post pillar' and proposed for its
RMR for rock masses was at 30–40, classified implementation. Zhang et al.[7] have successfully
as poor rock mass. According to Barton’s Q at implemented Room and Pillar mining in the
0.04 rock mass was classified as extremely case of hydro-geological problems at the
poor. Overall rock mass was rated as poor to Baixiangshan iron mine.
extremely poor in the South Extremity zone The geo-mechanical properties of intact rock
with the impact of the sheared claystone beds samples as obtained from laboratory tests are
and intrusion of quartz mica vein in the ore given in Table 3. The quartzitic ore materials is
body and also the presence of surcharged water relatively weak with average uniaxial com-
bearing strata in HW and FW. Also, rock mass pressive strength of 20 to 57 MPa in the case of
quality was much lower in the case of ore body South extremity ore body.
due to being friable in nature, presence of The simulated natural in-situ horizontal
sheared zone and intrusion of quartz and clay stress σh is nearly equal to the vertical stress σv;
bands. Also, Potvin’s Stability graph method this corresponds to a representative natural stress
along with Laubscher’s approach and other ratio σh/σv for the Indian mining conditions. The
empirical approaches are used to arrive at safe in-situ stresses is determined using equations
opening span and support system. Various provided by Sheorey[8] as applicable for Kandri
approaches in vogue are used to obtain various mine and is tabulated in Table 4. These values
design parameters including support system as along with geo-mechanical properties given in
provided in Table 2. Since orebody is wide, Table 3 are used in numerical simulation in the
thick and geologically disturbed, the present case of plan model considered.

Table 2. Stope design parameters using various approaches


Recommended
Parameter Approach applied Remarks
parameter
Opening span 2.5 m RMR = 35 and Q = 0.04 Working height and
unsupported span
Stable zone 10 × 10 m (Square), 5 m Potvin’s Stability Graph Adjustment factor of 0.5
(Tunnel) applied for entry methods
Roof bolt 1.5 m long @1.8 m RMR, Q and Potvin’s Stability Matches with the existing
support spacing Graph practices

Cable bolt 12 m@1.8 m spacing RMR, Q and Potvin’s Stability Matches with the existing
support in-between roof-bolts Graph practices
Safe pillar size 22 m (19.5 m solid and Laubscher and Sheorey Matches with Coal Mines
2.5 m opening width) regulation
Rib and Post 6 m rib and 5 m post Obert-Duval and Hoek-Brown SF ≈1.5 for 30 m working
pillar pillar height

Table 3. Average geo-mechanical properties of the tested rock


EY
Rock type UCS (MPa) ν ϲ (MPa) Φ (()) Remarks
(GPa)
Granitise schist/ 20 7 0.18 5 52 Mostly HW rock
Quartzitic schist
Dolomitic schist 29 10 0.28 7 40 Overlying Formation
Quartz schist 57 10 0.10 13 36 Mostly FW rock

594
Table 4. Modelled in-situ stresses[8] based program PHASE 2 of Rocscience Inc
Principal stress Magnitude Stress Canada.[9] The objective of the numerical
component (MPa) (MPa) modeling studies is to validate the proposed
Major (Horizontal), 3.2 + 5.45 stoping parameters derived from the various
σ1H 0.0122*H (m) empirical studies and also to decide the
Intermediate 3.2 + 5.45 extraction sequence of the four designated
(Horizontal), σ2H 0.0122*H (m) panels P1, P2, P3 and P4 considering safety of
Minor (Vertical), σ3V 0.027*H (m) 4.9 the workings, men and machineries. In
numerical simulation, four panels each of 20 m
Accordingly, it is planned that the ore body width and 30 m height with 6 m rib pillar in
shall be divided in-between four parts – Panel 1 strike as well as in dip direction is considered.
(P1), P2, P3 and P4 by providing in-situ rib Figure 3 shows the part geometry and strength
pillar of 6 m thickness along the strike as well factor within the rock mass and 6 m-rib pillar
as dip direction in the south extremity as shown after the extraction is carried out in stages of
in Figure 2. The main haulage roadway should 2.5 m and followed by sand backfilling after
be placed in the footwall rock, which should be every stages of extraction. After comparing
at a safe distance of 30 m from the footwall results presented in Figure 3, it is observed that
boundary and not less than 10 m at any time due strength factor within the surrounding rock
to the irregular shape of the ore body to facilitate mass and 6 m rib pillar after extraction
the extraction of the ore during stoping operation sequence followed is well above at 2.0 in most
(Figure 2). The systematic presentation of of the cases and 1.5 at few locations in the rib
mining and stoping parameters and operation pillar. The various extraction sequences are
plan is shown in Figure 2. followed in numerical simulation and finally
diagonal line of extraction is suggested as shown
in Figures 2 and 3. Based on the numerical
simulations carried out with various sequences
of extraction, the extraction sequence is
recommended as given in Table 5 for the
success of the proposed stoping operation. The
proposed extraction sequence is very necessary
to avoid build-up of stresses as well as inter-
section of mining induced stresses while
mining various panels simultaneously. Also,
diagonal line of extraction is suggested as shown
therein while re-treating and final recovery of
the ore.

Fig. 2. Systematic plan showing designed stoping


mining method in the case of south extremity ore zone.

Fig. 3. Strength Factor contouring after P1, P2 and P3


The extensive numerical modelling studies extracted and backfilled completely and P4 under
is carried out with the help of finite element extraction in final stage.

595
Table 5. Sequence of extraction recommended Thanks are also due to M/S Shrusti Sewa for
Panel Sequence of operation their valuable input on geo-hydrological study.
P1 Start extraction with P1 Sincere thanks are due to Dr. R.K. Goel, Chief
Scientist, CSIR-CIMFR, Research Centre
P2 Start P2 extraction when 25% extracted and
backfilled is done in P1 Roorkee for his valuable suggestions and review
of the manuscript. Permission granted to
P3 Start P3 extraction when 50% in P1 and
25% in P2 extracted and
publish this paper by Director, CSIR-CIMFR is
backfilled is done, respectively highly acknowledged. The views expressed
P4 Start P4 extraction when 75% in P1, 50% in
therein are of the authors and not necessarily of
P2 and 25% in P3 the Institute they belong to.
extracted and backfilled is done
respectively.
REFERENCES
[1] Ramakrishnan, M. and Vaidyanadhan, R.,
4. CONCLUSIONS “Geology of India”, Geol. Soc. India, Vol. 1,
537, p. 2008.
The wide and thick ore body in the South
[2] Radhakrishna, B.P. and Naqvi, S.M., “Pre-
Extremity at Kandri Mine is associated with cambrian continental crust and its evolution”,
complex geological structure and presence of J. Geol, Vol. 94, pp. 145–166, 1986.
water aquifers in the form of dolomitic karst. [3] Sarkar, S.N., Trivedi, J.R. and Gopalan, K.,
The presence of water aquifer and complex “Rb-Sr whole rock and mineral isochron age of
nature of manganese ore body make it a the Tirodi Gneiss, Sausar Group, Bhandara
daunting challenge towards mining and final district, Maharashtra”, J. Geol. Soc. India, Vol.
extraction of high quality manganese ore. Based 27, pp. 30–37, 1986.
on the rock mechanics studies and applications [4] Roy, A., Bandopadhyay, B.K., Chattopadhyay,
of empirical and numerical approaches, room A., Khan, A.S., Huin, A.K. and Pal, T., “Rb-Sr
and Sm-Nd dating of different metamorphic
and pillar stopnig method with post-pillar is events from the Sausar Mobile Belt, Central
suggested. Based on the hydrological studies, it India: implications for Proterozoic crustal
is recommended to have necessary pumping evolution”, J. Asian Earth Sci, Vol. 26, pp. 61–
water arrangement to the tune of 10,000 m3/day 76, 2006.
to deal with any exigencies arising during the [5] Chattopadhyay, A. and Ghosh, N., “Polyphase
actual mining operation in the south extremity deformation and garnet growth in politic schists
area. The success of the proposed mining of Sausar Group in Ramtek area, Maharashtra,
method will depend on the proper planning and India: A study of porphyroblast–matrix
relationship”, J. Earth Syst Sci., Vol. 116, No. 5,
execution with implementation of comprehens-
pp. 423–432, 2007.
ive instrumentation monitoring programme [6] Shrushti Seva Report, “Unpublished report on
during the actual stoping operation. hydrological investigation of Kandri manganese
mine tahsil-Ramtek, District Nagpur,
ACKNOWLEDGEMENT Maharashtra”, Submitted to CIMFR, 2009.
[7] Zhang, G., Li, J., Zheng, Z. and Ping, X.,
Thanks are due to the M/s MOIL Ltd for “Hydro-geological problems and solving
sponsoring this study and mine management measures of the Baixiangshan iron mine”,
for their help during field studies. Thanks are Express of Mining, Vol. 467, pp. 69–72, 2008.
also due to Dr. A.K. Soni, Dr. M.R. Saharan, [8] Sheorey, P.R., “A theory for insitu stresses in
Sri B. K. Jha and Sri Naseem Sheikh for their isotropic and transversely isotropic rock”, Int J
Rock Mech Min Sci Geomech Abstr, Vol. 31,
help during the course of the study. Thanks to pp. 23–34, 1994.
Sri G. G. Manekar for his valuable input and [9] PHASE2-FEM software, Rocscience Inc.,
discussion made during the course of the study. Canada, www.rocscience.com.

596

You might also like