CALCULATION SHEET

PROJECT NOTES

PREPARED BY Fady Farag INITIAL DATE 08-21-2019 PROJECT NO. MGA-19-05 REV. NO. 0
CHECKED BY INITIAL DATE SHEET 1 OF 1 PRELIM. FINAL
SUBJECT Area 40 Tunnel - Calculation of loads on tunnel walls

Tower -X2 Tower -X1

Filter

Hopper

Tower +X2 Tower +X1


Wind Case (A) (L100)
X-Dir :
L1. W (+X1 Tower BLC 35) + W(+X2 Tower BLC 36) + W(+X Filter BLC31) + W(+X Hopper BLC 43)
L2. W (-X1 Tower BLC 37) + W (-X2 Tower BLC 38) + W(-X Filter BLC32) + W(-X Hopper BLC 44)
Z-Dir :
L3 W (-Z1 Tower BLC 39) + W (-Z2 Tower BLC 40) + W(-Z Filter BLC 34) + W(-Z1 Hopper BLC 45) + W(-Z2 Hopper BLC 46)
L4. W (+Z1 Tower BLC 41) + W (+Z2 Tower BLC 42) + W (+Z Filter BLC 33) + W(+Z1 Hopper BLC 47) + W (+Z2 Hopper BLC 48)
Wind Case (C): (L300) from Case (A)
+X,+Z:
L5= (L1)*0.75 + (L4)*0.75 Wind Case (D): (L400) from Case (B)
+X,-Z: +X+Z Dir:
L6= (L1)*0.75 + (L3)*0.75 1. (L9)*0.38 + (L10)*0.75 + (L13)*0.38 + (L14)*0.75
-X,+Z: 2. (L9)*0.38 + (L10)*0.75 + (L13)*0.75 + (L14)*0.38
L7= (L2)*0.75 + (L4)*0.75 3. (L9)*0.75 + (L10)*0.38 + (L13)*0.38 + (L14)*0.75
-X,-Z: 4. (L9)*0.75 + (L10)*0.38 + (L13)*0.75 + (L14)*0.38
L8= (L2)*0.75 + (L3)*0.75 +X-Z Dir:
5. (L9)*0.38 + (L10)*0.75 + (L15)*0.38 + (L16)*0.75
6. (L9)*0.38 + (L10)*0.75 + (L15)*0.75 + (L16)*0.38
7. (L9)*0.75 + (L10)*0.38 + (L15)*0.38 + (L16)*0.75
8. (L9)*0.75 + (L10)*0.38 + (L15)*0.75 + (L16)*0.38
-X+Z Dir:
9. (L11)*0.38 + (L12)*0.75 + (L13)*0.38 + (L14)*0.75
10. (L11)*0.38 + (L12)*0.75 + (L13)*0.75 + (L14)*0.38
Wind Case (B) (L200)
11. (L11)*0.75 + (L12)*0.38 + (L13)*0.38 + (L14)*0.75
+X Dir :
12. (L11)*0.75 + (L12)*0.38 + (L13)*0.75 + (L14)*0.38
L9= W (+X1 Tower BLC 35) + W(+X Hopper BLC 43)
-X-Z Dir:
L10= W(+X2 Tower BLC 36) + W(+X Filter BLC31)
13. (L11)*0.38 + (L12)*0.75 + (L15)*0.38 + (L16)*0.75
-X Dir:
14. (L11)*0.38 + (L12)*0.75 + (L15)*0.75 + (L16)*0.38
L11= W (-X1 Tower BLC 37) + W(-X Hopper BLC 44)
15. (L11)*0.75 + (L12)*0.38 + (L15)*0.38 + (L16)*0.75
L12= W (-X2 Tower BLC 38) + W(-X Filter BLC32)
16. (L11)*0.75 + (L12)*0.38 + (L15)*0.75 + (L16)*0.38
+Z Dir :
L13= W (-Z1 Tower BLC 39) + W(-Z1 Hopper BLC 45)
L14= W (-Z2 Tower BLC 40) + W(-Z Filter BLC 34) + W(-Z2 Hopper BLC 46)
-Z Dir:
L15= W (+Z1 Tower BLC 41) + W(+Z1 Hopper BLC 47)
L16= W (+Z2 Tower BLC 42) + W (+Z Filter BLC 33) + W (+Z2 Hopper BLC 48)