Professional Documents
Culture Documents
Towards
Submitted to
Submitted by
OWNER’S CONSULTANT
ENERGY EFFICIENCY SERVICES LIMITED
4TH FLOOR, MAPLE PLAZA,OPP. ASHOK NAGAR, ROAD NO2, RANCHI – 834002
Registered and Corporate Office:
NFL BUILDING, 5TH & 6TH FLOOR, CORE – III, SCOPE COMPLEX, LODHI ROAD, NEW
DELHI – 110003
Website: www.eeslindia.
Prepared by
Submission Date
18th Nov’2019
Document reference
AP_SPV_FAR:GPS_EESL_HEC
V11.2019, R1
CONTENTS
Contents
1. ABOUT THE REPORT......................................................................................................................................3
All state and Union governments are trying to show a way out in the time of energy crises by
exploiting all possible natural means of energy.
Under green energy initiatives renewable energy based applications to be developed and to
explore opportunities with solar energy to undertake green initiative, reduce carbon
footprint, and to reduce electricity bills.
Broadly the need for a renewable energy expert is envisaged to guide the clients /further
advise on following aspects :
Assessment of the available resources in line with renewable energy on-site generation
requirement.
Assessment of feasible capacity with as-on-date design and what best can be possible
with improvements if agreed upon.
Feasibility report on the each aspect of all desired improvements, Pro-cons, budget and
modifications requirements.
Define the procurement specifications for revised requirements
Support the vender selection progress
Act as Nodal team for all renewable energy integration documentation
Assist client in PPA, statutory approvals and close coordination amongst on each stage of
project progress
Get the successful commissioning of the project
There are three separate plots on which, HEC intends to build the Solar Projects. The Site plan
and coordinates are shared in next photographs.
Plot Open Land plot bisected by a road from Opposite of HEC-JSCA 27.14 acre (23.313557,
# 2. HEC-JSCA to Jagannathpur Mandir road and cricket stadium. 85.273490)
in front of High court new campus and plant Parallel to HEC-JSCA
hospital and opposite of HEC-JSCA cricket
stadium
Site HEC Colony, sector 3, Dhurva, Ranchi Estimated (23.309942,
# 3. approx. 1 85.291162)
acre
Figure 3 : Plot #1
Figure 4 : Plot # 2
APRIL MAY JUNE JULY AUGUST SEPT OCT NOV DEC JAN FEB MARCH Total
HEC(Kwh) 3,078,900 2,612,824 2,650,580 2,684,560 3,031,318 2,684,560 2,789,740 2,971,260 3,108,700 3,008,780 2,697,240 2,827,920 34,146,382
HEC(Kvah) 3,609,496 3,027,606 3,434,015 3,392,145 3,492,302 3,626,531 3,517,770 3,619,276 3,760,082 3,596,889 3,273,484 3,506,311 41,855,907
max demand(KVA) 14,525 12,365 15,620 14,060 13,500 14,450 12,035 13,025 12,365 13,880 15,905 13,625 15,905
Energy Bill (Rs.) 23,600,589 21,458,736 24,431,586 23,722,834 24,130,737 25,187,553 24,277,178 24,860,837 26,144,472 24,846,112 23,593,997 24,248,752 290,503,381
per unit cost(Rs./Kwh) 7.67 8.21 9.22 8.84 7.96 9.38 8.70 8.37 8.41 8.26 8.75 8.57 9.38
Elec. Duty(Rs.) 129,013 105,880 105,487 112,755 117,035 123,598 117,339 118,690 123,274 121,944 109,603 116,329 1,400,947
Note : 1. Bill up to April 2018- kwh*6.25 + max. demand *300
2. Calculation from May 2018- kVAh*5.75 + max. demand*300
3. Energy bill mentioned is not including DPS
APRIL MAY JUNE JULY AUGUST SEPT OCT NOV DEC JAN FEB MARCH Total
HEC(Kwh) 2,682,020 2,559,240 2,539,980 2,577,720 2,723,600 2,465,160 - - - - - - 15,547,720
HEC(Kvah) 3,363,090 3,350,692 3,284,871 3,383,264 3,546,432 3,333,828 - - - - - - 20,262,177
max demand(KVA) 13,624 13,624 12,830 12,890 10,775 14,525 14,525
Energy Bill (Rs.) 23,265,703 23,370,806 22,791,791 23,332,952 23,276,628 23,419,801 - - - - - - 139,457,681
per unit cost(Rs./Kwh) 8.67 9.13 8.97 9.05 8.55 9.50 - - - - - - 9.50
Elec. Duty(Rs.) 110,585 127,962 126,999 128,886 136,180 123,258 753,870
Note : 1. Bill from april 2019- kvah*5.5 + max demand*350
2. Energy bill mentioned is not including DPS
requirement. Illustrative drawings for the broader understanding may be enclosed at the end
of this report.
It is advised to have proper design, engineering based quantity estimation and cost analysis
with backup offers from the technology providers and contractors.
Due to fluctuations in USD-INR exchange variations, taxation, market conditions there are
changes in the above basic cost estimations subject to proper sourcing agreements and
negotiations.
S Name Address Ow Area Solar Min Solar Solar Grid Solar Solar Gen Solar Gen Solar Gen Solar ROI
/ Of ner Capacity Capacity Self Availab Generation Self export Total investment
N Buildin feasible Consu ility in Consumpt
g mption sunny ion
hours
(Sq m) (kWp) (kWp) (%) (%) (kWh / Year) (Rs./ Year) (Rs./ Year) (Rs./ Year) (Approx. Rs.) (Year)
1350 6.00 4.35 36,000
1 Plot 1 (23.293849, HEC 71,468 5,361 4,500 100% 6,075,000 - 26,426,250 26,426,250 162,000,000 6.13
85.278062)
2 Plot 2 (23.313557, HEC 109,832 8,238 8,000 100% 10,800,000 - 46,980,000 46,980,000 288,000,000 6.13
85.273490)
3 Site 3 (23.309942, HEC 4047 304 200 50% 100% 270,000 810,000 587,250 1,397,250 8,280,000 5.93
85.291162)
181652.36 12,520 17,145,000 810,000 73,993,500 74,803,500 458,280,000
Broadly, it is expected to have around 4.5MW, 8MW and 200kWp capacities feasible on the
plot #1, Plot #2 and Site #3.
The expected PPA shall be around Rs. 3.80 to Rs. 4.50 / unit and for estimation purpose Rs.
4.35/Unit is considered.
It is presumed that the present cost of electricity (Total Energy Bill Paid per year / Total
Energy units consumed per year) shall be around Rs. 6.00. However, the energy payments
mentioned in previous section (clause 1.11) indicates it much higher i.e Rs. 8.50 to Rs
9.20/unit.
With these broad understanding, various assumptions it appears that the investments are
feasible to recover around 6 years for these ground mount projects.
Payment Terms:
Milestone based payment can be proposed in case of CAPEX projects. Incase of RESCO
(OPEX / PPA), it is monthly billing of energy to be paid for the agreement term (15 years
minimum).
Asset Ownership :
Incase of CAPEX, upon commissioning and handover, it is owned by the client.
Incase of PPA, it will remain the property of the service provider.
Force Majeure:
Standard Force Majeure Conditions shall apply to the project.
Validity:
The cost estimation has no validity as these are based on budgetary estimation, adjusted
to prevailing market scenarios. Since the order is going to be placed at a later date, it is
subject to variation due to exchange variation, market conditions, taxation etc.
This document is prepared without basic design & site visit but based on the information
shared by the client and knowledge referring to the public domain information available and
understanding of the subject to the best of our knowledge & experience on working with the
state-of-art renewable energy and conservation methods to be deployed at any green
campus.
Any reference to any brand, trademarks are only for academic purpose respecting all rights to
their owners. We don’t claim the information presented are originated or created by us. The
effort is put in to integrate the distributed information on various places and compile it in
user friendly manure only.
The content of this document has accuracy limited to our knowledge, understanding and
analysis of the data collected from open sources as best feasible and thus users are advised to
always refer to preliminary source information for any commercial decisions.
While efforts have been made to secure reliable results, the simulations done using
appropriate software, like all software products, may show deficiencies during use, which
may have escaped preparation team’s detection. Preparation team cannot, in any way, be
held responsible either to the use of the findings in this report or for any direct or indirect
losses arising from such use or from errors of any kind in the report content to the Client, its
Contractors or any third parties.
Stand-alone solar PV systems work with batteries. The solar energy is stored in the battery
and used to feed building loads after conversion from DC to AC power with a stand-alone
inverter. These systems are generally used in remote areas without grid supply or with
unreliable grid supply. The disadvantage of these systems is that the batteries require
replacement once in every 3 - 5 years.
Grid connected systems are connected to Grid and don’t have any backup system. The Solar
energy is either used by the load or exported to Grid and thus governed by Net-metering
arrangement. These systems will work only when both Grid and Sun are available.
The Ministry of New and Renewable Energy (MNRE) of the Government of India, provides
capital subsidies for solar PV systems subject to certain conditions. The capital subsidy for
rooftop solar PV systems is 30% of the benchmark cost or 30% of the actual cost, whichever is
less. The up-to-date benchmark cost and capital subsidy terms and conditions may be
checked on the website of MNRE (see: www.mnre.gov.in). Capital subsidy is presently not
applicable for Commercial, Industrial or Govt. installations.
Production of surplus energy may happen when solar energy produced exceeds the energy
consumption of the building. This surplus is fed into the grid. During the night, or when during
the day energy demand in the building exceeds solar energy generation, energy is drawn
from the grid. For buildings with grid-connected solar PV systems, the service connection
meter needs to be of the bidirectional type, whereby import kWh and export kWh are
separately recorded.
A grid-connected solar PV system consists of the solar panels, solar panels mounting
structure, one or more solar grid inverters, protection devices, meters, interconnection
cables and switches. Components and parts used in solar PV systems should conform to the
BIS or IEC or other international specifications, wherever such specifications are available and
applicable.
In order to promote the development of roof top & small solar photo voltaic systems
Electricity Regulatory Commissions has framed Net metering regulations for their respective
states. These regulations permit the consumers to install small solar photo voltaic roof top
system in their premises with the provision of net metering arrangement under which the
excess electricity generated by such Solar systems is delivered to the distribution licensee and
shall be utilized to offset the electricity supplied by the distribution licensee to the consumer
during the applicable billing period.
The consumer pays for the net-energy imported from the grid. To enable net-metering
DISCOM will provide with a bidirectional meter that displays the import and export energy
separately.
The solar panels may be installed on the roof of the building with a south facing tilt angle that
varies from 11 - 30 degrees depending on the latitude of the location. Sufficient area shall be
available for servicing the system. In between the rows of solar panels sufficient gap needs to
be provided to avoid the shading of a row by an adjacent row.
The solar grid inverter shall be placed indoor in a safe and easily accessible place. Outdoor
duty inverters can be mounted outdoor preferably under a canopy.
A Grid Tied Solar Rooftop Photo Voltaic (SPV) power plant is designed to last more than 25
years. Therefore it is essential that all system components and parts shall have a life cycle of
at least 25 years and all works shall be undertaken with the highest levels of quality and
workmanship with neatness and conformity with quality and safety norms such as BIS or IEC
or international specifications, wherever such specifications are available and applicable.
However, real life performance will depend on outdoor environment conditions which are
different from standard test conditions of the panels. The real life weather conditions (such
as Sun irradiation & Sunny Hours, temperature, wind velocity variation, cloud, moisture,
pollution, dust etc.), Grid availability for inter-connection and system design (such as panel
inclination & orientation, installation height, Shadow, maintenance, equipment’s quality &
efficiency, degradation etc.) has significant impact on overall system performance. It is
observed that typical systems can give 70-80% performance ratio (PR) i.e. the expected total
average annual energy generation shall be around 1200 kWh/kWp (PR 79% of 1513 ideal
conditions). The capacity utilization factor (CUF) of the solar plant is thus expected to be
around 13.7% (1200/365x24) in real life conditions.
The surface area required by Solar panels at rooftops is approx. 7 m 2 considering average
dimension of typical commercial Solar panel of 320Wp as 2 mt x 1 mt. However, considering
the inclination and shadow effects typically the average rooftop area of 12 m2 shall be
required per kWp. So 100kWh/m2 per year average solar energy generation is feasible under
normal environmental conditions.
The average degradation of equipment’s @ 0.4-1.0% per year is also expected over the life
time of generation i.e. the expected output in 10th year shall be 90% of the 1st year prediction
considering liner degradation over the years.
Thus it is proposed to consider 75% PR and 13% CUF as 1st year minimum performance
benchmark allowing linear degradation @1% per annum for system performance for next
years.
In locations where there are constraints such as shadows or panel tilt is not optimum or
orientation is not towards true south, it is advisable to consider loss of another 5-10% on
above indicated nos.
Figure 5 : TYPICAL WIRING DIAGRAM FOR GRID-CONNECTED SOLAR PV SYSTEM WITHOUT DIESEL GENERATOR
Note : The solar generation meter shown above is mandatory for consumers who avail of a
generation based incentive (GBI) and is optional for others.
Figure 6 : TYPICAL WIRING DIAGRAM FOR GRID-CONNECTED SOLAR PV SYSTEM WITH DIESEL GENERATOR
Note : The solar generation meter shown above is mandatory for consumers who avail of a
generation based incentive (GBI) and is optional for others.
source – www.climate.org
In winter, there is much less rainfall in Ranchi than in summer. Precipitation here averages
1397 mm. There is a difference of 344 mm of precipitation between the driest and wettest
months. During the year, the average temperatures vary by 14.4 °C.
Source
https://www.weatheronline.in/weather/maps/city?FMM=1&FYY=2000&LMM=12&LYY=2019&WMO=42701&CONT=inin®I
ON=0024&LAND=II&ART=WST&R=0&NOREGION=0&LEVEL=162&LANG=in&MOD=tab
http://www.synergyenviron.com/tools/solar-irradiance/india/jharkhand/ranchi