Cost Estimates
Column
CONCRETE
WORKS
COLUMN LENGTH WIDTH HEIGHT QUANTITY VOLUME CEMENT SAND GRAVEL
(m) (m) (m) (m3) (bags) (m) (m)
GROUND
FLOOR
COLUMN 0.4 0.4 3 16 7.68 69.12 3.84 7.68
1
m3
SAND 19.2 50 960 384
m3
GRAVEL 38.4 800 30720 12288
TOTAL PRICE 118080 47232 165312
=
REBAR WORKS
Beam (Two-Way)
CONCRETE WORKS
ROOF
m3
SAND 29.8125 50 1490.625 596.25
m3
GRAVEL 59.625 800 47700 19080
TOTAL PRICE = 183346.875 73338.75 256685.6
REBAR WORKS