Weekly Reports: Use this form for describing the weekly activities. Then compile the
weekly reports to one monthly reports and write an abstract about your activities, your
achievements, progress of project over the month.
Week No;1 (one) Dates:5/07/2008 to 9/07/2008

Week day Activities


Monday Visiting the site.
Meeting with supervisor and communicate with him about total Environment
of the site.
Tuesday Meeting with site Engineer and communicate with him about over all of the
site.
Observing excavation work for footing pad (F5, F4 and F3) on axis IH and
19 &20.
Equipment :- Backhoe
Wednesda Excavation for footing pad (F2, F5 & F3) on left side.
y Providing form work for pad (F5 ,F4 & F3)
Backfill soil for footing pad (f5,f4 and f3 )
Material:- wood, selected material, nails
Equipment:- backhoe, hammer, loader ,compactor and iron saw
Labours:- carpenter(4 person)
Thursday Lean concrete C-5 (1:4:8) under footing pad (F2,F3,F4 and F5)on both axis
Preparing bars for pad (F2,F3,F4 and F5)
Cover to reinforcement spacer (15cm thickness) used between bar and lean
concrete.
Material:- lean concrete (C-5),reinforced bar (ᶲ16mm) and spacer
Equipment:- drum mixer , crane and plastic rope
Labour :- Mason (concrete mixer and caster (10 person), bar bender (8
person)
Friday Concrete (C-25) (1:2:3) mixed by drum mixer and casted to pad
(F5,F4&F3
Form work for footing pad (F2,F3&F5) on left side
Material:- concrete (C-25),wood and iron saw
Equipment:- drum mixer, crane and hammer
Labour:- concrete mixer and caster (20 person)and carpenter (9 person)

4th year civil engineering students internship at Safer construction plc, monthly report
MADDA WALABU UNIVERSITY
SCHOOL OF ENGINEERING AND TECHNOLOGY
CIVIL ENGINEERING DEPARTMENT
________________________________________________________________
Weekly Reports: Use this form for describing the weekly activities. Then compile the
weekly reports to one monthly reports and write an abstract about your activities, your
achievements, progress of project over the month.
Week No:2 (two) Dates: 12/07/2008 to 16/07/2008

Week day Activities


Monday Concrete casted to pad footing (F2, F5 and F3).
Grade beam work along axis No GB11 (300x500) and GB8 (300x500)
Lean concrete mixed (C-5)
Reinforced bar (top 2 ᶲ16 and bottom 3 ᶲ14) for this beam.
Material:- concrete (C-25 ) for pad, lean concrete under beam &reinforced
bar(2ᶲ16 top and 3ᶲ14 bottom
Equipment:- drum mixer and cranes
Labour:- concrete mixer (12 person)and bar bender (8 person)
Tuesday Form work construction for Grade beam (GB11&GB8)
Concrete mixed (C-25)
Concrete casted to GB11 &GB8)
Material:-wood,concrete (C-25)
Equipment:-drum mixer,cranes and hammer
Labour:- concrete mixer (14 person) ,carpenter (4 person)
Wednesda Removal of form work from GB11 &GB8
y Curing GB11 & GB8
Curing footing pad F2,F3,F4 & F5
Material:-water
Equipment:-water bucket, hammer
Labour:- carpenter (4 person ),currier (6 person)
Thursday Excavation work for footing pad (F1,F2& F5) on axis NM & 14,15
Grade beam work on axis NM &13 ,14 & ML& 13,14
Material:-bar (2ᶲ16 top,3ᶲ14 bottom),plastic rope
Equipment:-backhoe
Labor:-bar bender (9 person)
Friday Form work for footing pad F1,F2,F3 & F5 on axis NM&14,15
Lean concrete (C-5) under GB7 &GB8
Material:-wood,lean concrete (C-5)
Equipment:-hammer,drum mixer,cranes
Labor:-carpenter (9 person),concrete mixer (10 person)

4th year civil engineering students internship at Safer construction plc, monthly report
MADDA WALABU UNIVERSITY
SCHOOL OF ENGINEERING AND TECHNOLOGY
CIVIL ENGINEERING DEPARTMENT
________________________________________________________________
Weekly Reports: Use this form for describing the weekly activities. Then compile the
weekly reports to one monthly reports and write an abstract about your activities, your
achievements, progress of project over the month.
Week No: 3 (three) Dates: 19/07/2008 To .23/07/2008

Week day Activities


Monday Width of borrow hole for pad F2, F3& F4 is checked.
Backfill soil for F2, F3 and F4 and compaction.
Material:- selected material
Equipment:-meter,compactor,loader
Labor:-soil worker (15 person)
Tuesday Concrete casted to GB7 & GB11 and footing pad F1,F2 & F5
Material:- concrete (C-25)
Equipment:-drum mixer,cranes and vibratory
Labor:-concrete worker (20 person)
Wednesday Footing column work (C2,C3 & C4) on axis HG&HI
Form work construction for C2,C3 & C4
Concrete casted to C2,C3 & C4
Material:-concrete (C-25) ,wood
Equipment:- drum mixer,cranes & hammer
Labor:-carpenter (6 person),concrete worker (8 person)
Thursday Removing form work from footing pad F3,F4 & F5 & C2,C3 & C4
Curing footing column
Material:-water
Equipment:-water bucket
Labor:-carpenter (6 person),currier (4 person)
Friday Grade beam work on axis 13,14 & 16
Lean concrete casted
Material:-lean concrete (C-5),bar top 2ᶲ16 & bottom 3ᶲ14
Equipment:- drum mixer. cranes
Labor:-bar bender (7 person),concrete worker (5 person)

4th year civil engineering students internship at Safer construction plc, monthly report
MADDA WALABU UNIVERSITY
SCHOOL OF ENGINEERING AND TECHNOLOGY
CIVIL ENGINEERING DEPARTMENT
________________________________________________________________
Weekly Reports: Use this form for describing the weekly activities. Then compile the
weekly reports to one monthly reports and write an abstract about your activities, your
achievements, progress of project over the month.
Week No:4 (four) Dates: 26/07/2008 to 30/07/2008

Week day Activities


Monday Back fill soil for footing column F3,F4 & F5 on axis GF & 16,17
Excavation for footing F3&F4 on axis ON & 12,13
Material:-selected material
Equipment:-compactor, loader & backhoe
Labor:-soil filler (8 person)
Tuesday Form work for footing pad F3,F4 & F5
Lean concrete casted
Reinforced bar (ᶲ14) and concrete casted
Material:-wood,lean concrete & concrete (C-25)&bar
Equipment:-drum mixer,cranes & hammer
Labor:-carpenter (4 person),bar bender (3 person) and concrete worker (8
person)
Wednesda Footing column work on axis GF& 16,17& ON 11-13
y Form work for this footing column
Bar and concrete casted
Material:-wood,concrete (C-25) bar ᶲ14 & ᶲ16
Equipment:-drum mixer,cranes
Labor:-carpenter (5 person),concrete worker (12 person)
Thursday Excavation for footing pad F2,F3,F4 & F5 on axis ON &MN
Centre of this footing is checked & footing column is erected
Material:-bar (12ᶲ14for rec & 12ᶲ16 for circular
Equipment:-backhoe,meter
Labor:-surveyor (3 person),bar bender (8 person)
Friday Trench excavation for masonary along axis JI,IH,ON respectively
Stone dressing and mortar used
Removing form work from footing column C9,C11 & C3
Material:-stone& water
Equipment:-backhoe, hammer
Labor:-Manson (5 person)

Weekly Reports: Use this form for describing the weekly activities. Then compile the
weekly reports to one monthly reports and write an abstract about your activities, your
achievements, progress of project over the month.

4th year civil engineering students internship at Safer construction plc, monthly report
MADDA WALABU UNIVERSITY
SCHOOL OF ENGINEERING AND TECHNOLOGY
CIVIL ENGINEERING DEPARTMENT
________________________________________________________________
Week No:5(five) Dates:03/08/2008 to 07/08/2008

Week day Activities


Monday Back fill for trench along axis JI,IH & ON
Excavation for footing pad F11,F9,F10,F4 & F5 on axis KJ,JI,IH
Lean concrete mixed
Material:- selected material, lean concrete (C-5)
Equipment:- compactor ,backhoe
Labor :- concrete mixer (10 person)
Tuesday Form work construction for footing pad F11,F9,F10,F4 & F5
Concrete mixed & casted
Preparing footing column F9,F8,F11& F10 isolated & combined footing
Form work for this column
Material:-concrete (C-25),wood
Equipment:- hammer, drum mixer, cranes
Labor :-carpenter (7 person),concrete mixer (13 person)
Wednesda Removing form work from footing pad and column C9,C9,C11&C10 &
y curing
Grade beam work GB11,GB13,& GB8 on axis NO,NM.ML
&13,12,8,7,14,&13
Form work for grade beam on this axis
Concrete casted & scheduled bar top & bottom
Material:- concrete (C-25),wood
Equipment :- hammer ,drum mixer
Labor:- concrete mixer (14 person),carpenter (6 person)
Thursday Removing form work from this GB & curing
Excavation for masonry work along ON,NM,ML,&13,12,7,8,14,13
Material:- water
Equipment :-backhoe & water bucket
Labor:- carpenter (8 person),water curing (6 person)
Friday Backfill soil for footing pad F11,F9& F10 on axis KJ,JI ,IH&
Compaction
Material:-selected material
Equipment:-compactor
Labor:-soil filler (15 person)
Weekly Reports: Use this form for describing the weekly activities. Then compile the
weekly reports to one monthly reports and write an abstract about your activities, your
achievements, progress of project over the month.
Week No: 6(six) Dates:10/08/2002 to 14/08/2008

4th year civil engineering students internship at Safer construction plc, monthly report
MADDA WALABU UNIVERSITY
SCHOOL OF ENGINEERING AND TECHNOLOGY
CIVIL ENGINEERING DEPARTMENT
________________________________________________________________

Week day Activities


Monday Compaction of back fill soil for ground slab along axis AB and 14,13,
BC and 13,12
Excavation for footing pad axis F5, F4 and F3 on axis N-C
Selected material provided by laborer to the above axis
Material:- soil for back fill
Equipment:- compacter, backhoe
Labor:- for compaction work 6 males
Tuesday Form work construction footing pad F5,F4 & F3
Compaction of back fill to the ground slab
Lean concrete mixed and concrete C-25 mixed casted this pad
Material:-wood, selected material, concrete(C-5&C-25)
Equipment:-drum mixer, hammer, compactor
Labor:carpenter(6person),concrete mixer(12person)
Wednesday Hard core fill for ground slab on axis AB&BC
Removing form work form footing pad F3,F4,F5 onaxisN-C
Material:stone,selected material
Equipment:hammer
Labor:mason(15person)
Thursday Curring footing padF3,F4,F5
Bar and concrete casted to ground slab above
Joint of expantion(10cm) casted
Material:water,concreteC-25 bar(O8mm)
Equipment:water bucket,
Labor:concrete worker(9person) currier(5person)
Friday Curring above slab
Construct footing column on axisN-C
Form work for this colum
Concrete casted to this footing column
Material:concreteC-25,water,wood
Equipment:drum mixer,craneshammer
Labor:concrete worker(13person),carpenter(6person)
Weekly Reports: Use this form for describing the weekly activities. Then compile the
weekly reports to one monthly reports and write an abstract about your activities, your
achievements, progress of project over the month.
Week No.7(seven) Dates. 17/08/2008 To .21/08/2008

Week day Activities


Monday Removing form work from column on axisN-C

4th year civil engineering students internship at Safer construction plc, monthly report
MADDA WALABU UNIVERSITY
SCHOOL OF ENGINEERING AND TECHNOLOGY
CIVIL ENGINEERING DEPARTMENT
________________________________________________________________

Curring ground slab and this column


Column work on axisK-Eand 15-20
Material:water,bar(12O14for both rectangular&circular)
Equipment:hammer,
Labor:bar bender(9person)
Tuesday Form work for column above
Concrete casted to this column
Back fill for footing column on axisN-C
Material:wood,cocreteC-25,selected material
Equipment:drum mixer ,cranes,compactor
Labor:carpenter(6person) ,concrete worker(8person)
Wednesda Removing form work from column above
y Curring this column
Checking the length of this column
Material:water
Equipment:water bucket ,meter
Labor:carpenter(7person)
Thursday HOLIDAY
Friday HOLIDAY

Weekly Reports
Use this form for describing the weekly activities. Then compile the weekly reports to one
monthly reports and write an abstract about your activities, your achievements, progress of
project over the month.
Week No:8(eight) Dates:24/08/2008 to 28/08/2008

Week day Activities

4th year civil engineering students internship at Safer construction plc, monthly report
MADDA WALABU UNIVERSITY
SCHOOL OF ENGINEERING AND TECHNOLOGY
CIVIL ENGINEERING DEPARTMENT
________________________________________________________________

Monday HOLIDAY
Tuesday HOLIDAY
Wednesday HOLIDAY
Thursday Column work on axis J-E&O-K
Form work construction to this column&concrete casted
Hard core filling on axis O-K
Material:- concrete C-25 ,wood ,stone
Equipment:- drum mixer ,cranes ,hammer
Labor:- carpenter(8person) ,mason(9person)
Friday Removing form work from column on axisJ-E&curring
Back fill for ground slab on axis O-K
Concrete casted to this slab
Material:- selected material, concrete
Equipment:- compacter, drum mixer, crane
Labour:-carpenter(6 person) and concrete worker(5 person)

Weekly Reports: Use this form for describing the weekly activities. Then compile the
weekly reports to one monthly reports and write an abstract about your activities, your
achievements, progress of project over the month.
Week No:.9(nine) Dates. 1/09/2008 To 5/09/2008

Week day Activities


Monday Back fill for ground slab on axis ML&13,12&12,11
Hard core fill on axisKJ&10,9,8,7,6
Bar schedule for ground slab on axis ML

4th year civil engineering students internship at Safer construction plc, monthly report
MADDA WALABU UNIVERSITY
SCHOOL OF ENGINEERING AND TECHNOLOGY
CIVIL ENGINEERING DEPARTMENT
________________________________________________________________

Material:-selected material ,stone bar(O8mm diam)


Equipment :- compactor ,hammer
Labor:-mason(13person)
Tuesday Bar provided on ground slab on axisML
Concrete casted to this slab
Shear wall work on axisIJ&15,16
Checking slump test for concrete strength
Material:-bar(ᶲ8mm dim) ,concrete C-25.
Equipment:-drum mixer cranes
Labor:-concrete worker(15person) bar bender(8person)
Wednesda Column work on axis L-G&2-7
y Form work work for this column
Grade beam work on axis N-L&GB21,GB32&GB15
Material:- bar(12ᶲ14 &12ᶲ 16 for both rec & cir) ,wood
Equipment:-hammer, cranes
Labor:-carpenter(8person),bar bender(6person)
Thursday Concrete casted both column GB above
Back fill soil for ground slab on axisIH&9-13
Hard core fill to ground slab on axisIH
Material:concreteC-25,stone ,selected material
Equipment:drum mixer,cranes,compactor
Labor:mason(8person) ,concrete worker(8person)
Friday Ground slab work on axis IH&HG
Sanitary installation on this slab
Concrete casted to this slab
Grade beam work on axis J-F
Form work for this GB
Material:elbo ,concrete C-25 ,wood
Equipment:drum mixer ,cranes ,hammer
Labor:carpenter(8person) ,concrete worker(12person) ,bar bender (4person)

Weekly reports: (use this form for describing the weekly activities. Then compile the
weekly reports to one monthly report and write an abstract about your activities, your
achievements, progress of the project over the month)
Week No: 10(ten) Dates: 8/09/2008 to 12/09/2008
weekday Activities
Monday Concrete casted to grade beam on axis J-F
Curing ground slab
Masonry work on axis ED and 14,13, b/n axis DC and 12,11
Material used: - concrete C-25, water, stone

4th year civil engineering students internship at Safer construction plc, monthly report
MADDA WALABU UNIVERSITY
SCHOOL OF ENGINEERING AND TECHNOLOGY
CIVIL ENGINEERING DEPARTMENT
________________________________________________________________

Equipment used:- drum mixer, cranes, hammer


Labor:- for water curing 3 Females, masons ( 4 males).
Tuesday Removing form work from grade beam axis J-F
Curing grade beam on axis f-J
Checking the length and width of masonry on axis ED and DC
Back fill soil for masonry wall of the above axis
Material used:- Water, soil for back fill
Equipment:- Meter, Timber, Hammer, compacter.
Labor: - carpenter( 3 males), for curing 4 females
Wednesday Erecting column along axis O-L and 5,4,3
Grade beam work axis GB22, GB17 and GB18
Form work fixing for grade beam and Column of some axis
Material: - Reinforced bar, timber for form work
Equipment:- Cranes, Hammer, Iron sow
Labor: - for erecting column 4 males, carpenter( 3 males)
Thursday Removing form work from column and curing along axis O-L
Back fill soil for footing pad on axis O-I and 6-2
Material :- Water, soil, reinforced bar
Equipment:- compacter, Hammer, cranes
Labor: - carpenter ( 4 males) , 4 females for curing column.
Friday Fixing form work for column on axis G-J of some axis
Lying bar for first floor slab on axis E-K and 14-20
Material:- Timber, reinforced bar
Equipment: - Iron sow, Hammer, Fins a , cranes
Labor:- carpenter( 5 males ), bar bender(4 males )

Weekly reports: (use this form for describing the weekly activities. Then compile the
weekly reports to one monthly report and write an abstract about your activities, your
achievements, progress of the project over the month)
Week No; 11(eleven) Dates: 15/09/2008 To .19/09/2008
Weekday Activities
Monday Bar lying for first beam on axis E-K(FB)
Sponda , pondo and font are constructed for FB
Iron sheet (modino) distributed first floor
Stair 2 and 3 design
Material:- reinforced bar , timber, iron sheet

4th year civil engineering students internship at Safer construction plc, monthly report
MADDA WALABU UNIVERSITY
SCHOOL OF ENGINEERING AND TECHNOLOGY
CIVIL ENGINEERING DEPARTMENT
________________________________________________________________

Equipment:- meter, Hammer, iron sow


Labor:- bar bender ( 4 males) , 8 for sponda, pondo and modino work
Tuesday Back fill soil for ground slab along axis E-H and 8,9 and 10
Reinforced bar (8mm dia. Distributed) on first floor slab
Hard core worked on ground slab for axis F-H
Material : - soil, reinforced, stone
Equipment: - Compacter, meter, Hammer
Labor:- bar bender( 4 males) , mason (6 males) , 3 males for back fill
Wednesday First beam dropped on first
Concrete casted to ground slab on axis K-H
Erection of column on axis KJ&4,5&6
Material: - bar(top2ᶲ16&3ᶲ14bottom),concrete(C-25)
Equipment:- drum mixer ,crane
Labor:- bar bender (6person);concrete worker(9)
Thursday Form work for column on axis KJ
Electrical installation for first floor slab
Material:- wood , elbow
Equipment:- hammer
Labor:- carpenter(9 person)
Friday Concrete casted to first floor slab
Retaining wall construction on axisKJ&R2
Material: - concrete C-25,stone and mortar
Equipment:- drum mixer, cranes
Labor:- concrete worker(8person);mason(5person)

Weekly reports. (use this form for describing the weekly activities. Then compile the
weekly reports to one monthly reports and write an abstract about your activities, your
achievements, progress of the project over the month)
Week No: 12(Twelve) Dates: 22/09/2008 To .26/09/2008
Weekday Activities
Monday Removing form work from column on axis KJ
Curing first floor slab and column
Back fill soil for ground slab on axis DE&56&E-K&5-13
Material:- water, selected material

4th year civil engineering students internship at Safer construction plc, monthly report
MADDA WALABU UNIVERSITY
SCHOOL OF ENGINEERING AND TECHNOLOGY
CIVIL ENGINEERING DEPARTMENT
________________________________________________________________

Equipment:- hammer ,water bucket


Labor:- carpenter(6 person),curing(4 females)
Tuesday Hard core filling on ground slab on axisD-E&5-6
Sanitary installation on axis DE
Grade beam work(GB37,GB38&GB36)
Material:- selected material, stone, bar
Equipment:- hammer, elbow
Labor:- mason(8person)
Wednesday Form work for GB37,GB36&GB38
Concrete casted toGB36,GB377GB38
Back fill soil for ground slab on axis IJ&JK
Material:- wood,concreteC-25,selected material
Equipment:- drum mixer, cranes, compactor
Labor:- carpenter(7 person),concrete worker(8)
Thursday Erection of second floor column on axis E-K
Construction of form work for second floor column
Hard core fill to ground slab on axis IJ&JK
Material:- bar(ᶲ16),Wood, stone
Equipment :- cranes, hammer
Labor:- carpenter(9person),mason(6person)
Friday Concrete casted to second floor column
Erection of ground column on axis CD,DE
Form work construction for this column
Material:- concrete C-25,bar(12ᶲ14),wood
Equipment:- drum mixer, cranes, hammer
Labor:- carpenter(4person),concrete worker(16person)

Weekly reports (use this form for describing the weekly activities. Then compile the weekly
reports to one monthly reports and write an abstract about your activities, your achievements,
progress of the project over the month)
Week No:13 (thirteen) Dates:29/09/2008 to 03/10/2008
Weekday Activities
Monday Bar lying for column second floor with bar of 12ᶲ14
Form work for column second floor slab C6 & C4 is fixed
Hard core work for ground slab of some panel
Material: - reinforced bar, timber, stone
Equipment:- meter, bar bender, barilla ,Hammer, iron sow
Labor:- 3 males for bar lying, carpenter( 10 males) , for hard core 8
person

4th year civil engineering students internship at Safer construction plc, monthly report
MADDA WALABU UNIVERSITY
SCHOOL OF ENGINEERING AND TECHNOLOGY
CIVIL ENGINEERING DEPARTMENT
________________________________________________________________

Tuesday Bar lying on the ground slab of some panel


Bar lying on the second floor slab with 8 & 10 dia. Of bar & c/c 15 for
short & 20 for long direction
Material:- reinforced bar
Equipment:- meter
Labor:- bar bender (8 males)
Wednesday Dismantling of form work from second floor column C3 & C6 of some
axis
Curing the column of second floor
Casting the reinforcement for ground slab of some panel
Material:- water, reinforced bar
Equipment:- Hammer, bar bender
Labor:- carpenter( 3 male), 4 females for curing
Thursday Casted the concrete on the ground slab of some panel by thickness of
15cm.
Used expansion joint for the ground slab to resist the super structure
load from the slab.
Material:- concrete, chip wood
Equipment:- cranes
Labor:- 8 males for cast concrete
Friday Form work fixed for circular & rectangular column of axis C20 & C21
Hard core work for ground slab of axis IJ & 18,17 , GF & 16,17
Material: - stone, wood
Equipment:- iron sow , Hammer, barilla
Labor:- Carpenter( 8 males ), 6 females & 4 males for hard work

Weekly reports . (use this form for describing the weekly activities. Then compile the
weekly reports to one monthly reports and write an abstract about your activities, your
achievements, progress of the project over the month)
Week no: 14(Fourteen) Dates: 06/10/2008 to 10/10/2008
Weekday Activities
False work construction to support top tie beam for second floor on
axis E-K & 14-21
Removing form work from stair case -3 on second floor
Monday Filling hard core b/n axis EF
Material:- wood, stone,
Equipment:- Hammer, barilla
Labor:- Carpenter( 12 males ), 3 males for dismantle form work
Tuesday Sanitary installation on ground slab IJ & IJ

4th year civil engineering students internship at Safer construction plc, monthly report
MADDA WALABU UNIVERSITY
SCHOOL OF ENGINEERING AND TECHNOLOGY
CIVIL ENGINEERING DEPARTMENT
________________________________________________________________

Back fill ground slab on axis IH


Hard core fill on axis GH & GF, 18,17 &16
Sanitary excavation
Material: - elbow pipe, soil, stone
Equipment:- compactor, fire, iron sow
Labor:- 4 males for sanitary, 4 males & 5 females for back fill
Wednesday Back fill for ground slab on axis GF & 18,19
Hard core fill on axis FG & EF , 18,17,&16
Ground slab work on axis GF & 18,17,16&15
Material:- selected material, stone
Equipment:- compactor, Hammer
Labor: - 12 males & 6 females for back fill & hard core work
Thursday Lying bar for ground slab on axis JI & 14,15 & IH & 15,16 by O10
dia. Bar
Hard core filling on HG & 16,17, GF & 15,16
Material: - reinforced bar, stone
Equipment:- bar bender , hammer, meter
Labor:- 3 males for lying bar, 2 males & 6 females for hard core
Friday Back fill soil on axis IJ & 15,16 on ground slab
Hard core fill on IJ& 13,14 on ground slab for resist seepage
Bar lying on ground slab axis IH & 17,18 by ᶲ12 dia. bar & c/c 20cm
Material:- soil, stone 20cm thick, reinforced bar
Equipment:- compactor, Hammer, meter
Labor: - 4 males & 6 females for back fill, 4 males for bar lying

Weekly reports (use this form for describing the weekly activities. Then compile the
weekly reports to one monthly reports and write an abstract about your activities, your
achievements, progress of the project over the month)
Week NO: 15 (Fifteen) Dates: 13/10/2008 to 17/10/2008
weekday Activities
Monday Construction of stair -4 on axis NM & 3,4
Hard core fill on axis HG & 8,9
Casting concrete to ground slab on axis CB, CD, DE & EF & 5-9
Material : - reinforced bar(ᶲ8,14,16,20), Conc. C-25, Stone
Equipment:- Drum mixer, cranes, hammer
Labor:- mason(8 person), conc. Work(12 person), Stair worker(4)
Tuesday Casting concrete to stair-4 on axis NM & 3,4
First beam for second floor along axis O-J
Form work fixe for first floor slab on axis L-J & 1-5

4th year civil engineering students internship at Safer construction plc, monthly report
MADDA WALABU UNIVERSITY
SCHOOL OF ENGINEERING AND TECHNOLOGY
CIVIL ENGINEERING DEPARTMENT
________________________________________________________________

Material:- conc. C-25, bar(top 2ᶲ24 & bottom 3ᶲ16)


Equipment:- cranes, drum mixer, hammer
Labor: - conc. Worker(12 person), carpenter(6 person), bar bender (13
person)
Wednesday Form work construction on axis D-K & 3-5
Concrete casted to ground slab on axis CD & 6,7
Hard core fill on axis BC & 7,8
Material:- concrete C-25, Stone, timber
Equipment:- hammer, compacter
Labor:- carpenter(12 person), mason(8)
Thursday Day after report
Friday Day after report

4th year civil engineering students internship at Safer construction plc, monthly report