BEAMS COLUMNS FLOOR SLAB

NOTE :
SINGLE & TWO (2) BAR BUNDLE THREE (3) BAR BUNDLE VERTICAL REINFORCEMENT Ld = DEVELOPMENT LENGTH OF
SINGLE & TWO (2)
BAR SIZE BAR SIZE BAR SIZE RE-BARS ABOVE VALUES SHALL BE THE
BOTTOM BOTTOM TOP SINGLE & TWO (2) BAR THREE (3) BAR BUNDLE BAR BUNDLE
TOP BARS MINIMUM SPLICE OR DEVELOPMENT LENGTH.
BARS BARS BARS BUNDLE ADDITIONAL MODIFICATION FACTORS OF ACI
16 mm Ø 600 mm 750 mm 800 mm 925 mm 20 mm Ø 1000 mm 10 mm Ø 400 mm ( CHAPTER 12 ) SHALL BE USED WHEREVER
APPLICABLE. 36mm Ø BARS FOR BEAMS
20 mm Ø 750 mm 950 mm 900 mm 1200 mm 25 mm Ø 1500 mm 12 mm Ø 500 mm SHALL NOT BE BUNDLED.

25 mm Ø 925 mm 1200 mm 1100 mm 1450 mm

REMOVAL OF FORMS AND SHORING CAMBER REQUIREMENT

STRUCTURAL ELEMENTS CLEAR SPAN BET. SUPPORTS MINIMUM TIME PERIOD DAYS ELEMENT MINIMUM CAMBER

WALLS, COLUMNS, BEAMS,


GIRDER SIDES & SLAB ON - 1 REINFORCED CONCRETE BEAMS 6 mm FOR EVERY 4.50 m SPAN
GRADE
UNDER 3.00 m 7
JOIST, BEAMS, & GIRDER CANTILEVER REINFORCED CONCRETE BEAMS 18 mm FOR EVERY 3.00 m SPAN
3.00 m TO 6.00 m 14
SOFFIT
OVER 6.00 m 21
REINFORCED CONCRETE SLAB 3 mm FOR EVERY 3.00 m SHORTER SPAN
UNDER 3.00 m 4
ONE-WAY FLOOR SLABS 3.00 m TO 6.00 m 7
OVER 6.00 m 10

SPLICING REQUIREMENTS OF REINFORCING BARS


"Ls" OR "Ld"
2 - 16mm Ø DIAGONAL BARS
TRANSVERSE BEAM
PER CORNER L = 80 Ø
NOTE :
SPACING - S SPACING - S
REBARS COLUMN CONFINEMENT TIES AS PER COLUMN CLEAR DISTANCE BETWEEN
2 - 12mm Ø CLOSED RE-BARS ARE TO BE STRICTLY INTERIOR
SCHEDULE
500 mm (MINIMUM) TERMINATION BEND 500 mm ( MINIMUM) TERMINATION BEND STIRRUPS ( TYPICAL ) COLUMN
MAINTAINED
GIRDER TOP BARS ARE
LAID OVER OF BEAM
TOP BARS

h/3
BEAM DEPTH - h
h/3
100 mm MIN.

Ldh

h/3
BEAM

NOTE : OUTSIDE DIMENSION THAN 31 THE OVERALL


DEPTH OF THE BEAM.
50 mm
1. CENTER TO CENTER SPACING OF PIPE
SLEEVES SHALL IN NO CASE BE LESS THAN 3 4. PIPE SLEEVES SHALL BE LOCATED WITHIN THE
TIMES THE SLEEVE DIAMETER MIDDLE THIRD OF THE BEAM DEPTH..

2. PIPE SLEEVES OF ALUMINUM SHALL NOT BE 5. PIPE SLEEVES SHALL BE LOCATED WITHIN THE
INTERIOR COLUMN MIDDLE THIRD OF BEAM CLEAR SPAN.
EMBEDED IN STRUCTURAL CONCRETE.
REBARS
50 mm 50 mm
3. PIPE SLEEVES SHALL NOT BE LARGER IN

GIRDER

TYPICAL BEAM PENETRATION


INTERIOR COLUMN TERMINATION BEND TYPICAL PLAN OF BEAM / GIRDER COLUMN JOINT
DETAIL
Ldh INTERIOR COLUMN REBARS COLUMN CONFINEMENT
Ldh INTERIOR COLUMN AS PER COLUMN COLUMN REBARS TO BE
REBARS COLUMN CONFINEMENT BEAM SCHEDULE EXTENDED AS PART OF BEAM
TRANSVERSE BEAM AS PER COLUMN REINFORCEMENTS
CLEAR SPAN " L " EXTRA TOP BARS
REBARS SCHEDULE BEAM REBARS ( TOP BARS
BEAM TOP BARS Ld
COLUMN CONFINEMENT ) LAID OVER ON GIRDER L/4 ROOF BEAM
GIRDER
500 mm (MINIMUM) TERMINATION BEND

AS PER COLUMN TOP BARS Ldh CONT. TOP &


SCHEDULE 50 mm REINFORCEMENTS GIRDER TOP BOTTOM BARS

500 mm (MINIMUM) TERMINATION BEND


BEAM
REBARS BARS
500 mm (MINIMUM) TERMINATION BEND

50 mm

GIRDER
BEAM
50 mm
50 mm

50 mm
BEAM BOTTOM
BARS

COLUMN
COLUMN 50 mm
50 mm GIRDER 50 mm
GIRDER BOTTOM REBARS
BARS 50 mm

COLUMN 50 mm AT COLUMN INTERSECTION AT GIRDER SPAN CORNER END COLUMN

TYPICAL BEAM AND GIRDER CORNER / EXTERIOR


BEAM RE-BAR TERMINATION BEND DESIGNED STRUCTURAL :

RUBEN A. ABA-A JR.


RE-BAR LAY-OUT COLUMN TERMINATION BEND
DATE:

PDS - BUK3RD : 2 0 2 3
DRAWN :
PROJECT AND LOCATION : SHEET CONTENTS : SUBMITTED : RECOMMENDING FOR APPROVAL : APPROVED : SET NO. SHT. NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS SPLICING REQUIREMENTS OF ROSANNO GABRIEL D. SANICO
ARCHITECT I
REGIONAL OFFICE X REINFORCING BARS "Ls" OR PDS
BUKIDNON THIRD DISTRICT ENGINEERING OFFICE
CONSTRUCTION OF DATE:
CHECKED / REVIEWED : S
DICKLUM, MANOLO FORTICH, BUKIDNON MULTI-PURPOSE BUILDING
BARANGAY MAMPAYAG, MANOLO FORTICH, BUKIDNON
"Ld" AND OTHER IMPORTANT
NOTES
RYAN CAESAR B. FERNANDEZ ROMULO F. ANDRES, AEr. RONALDO C. PAHANG, AEr. S-2
BARANGAY MAMPAYAG, MANOLO FORTICH, BUKIDNON MCKENLY B. HONG ENGINEER II ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER 2023
ENGINEER II OIC - PLANNING AND DESIGN SECTION, CHIEF
DATE: DATE: DATE: DATE:
2 - 12mm Ø TOP BARS REQUIRED BEAM
ADDITIONAL STIRRUPS SCHEDULE OF MASONRY WORKS 2 - 10mm Ø DOWEL BARS
LINTEL BEAMS MASONRY 10mm Ø DOWEL BARS
REQUIRED BEAM CHB STIFFENER COLUMN REBARS
TOP & BOTTOM WALL B ( mm ) H ( mm ) HORZ.
10mm Ø U-BARS STIRRUPS HORIZONTAL BARS VERTICAL BARS 10mm Ø DOWEL BARS
BARS t ( mm ) BARS
SPACED AT 300 mm SLAB
O.C. REBARS FLOOR DEPRESSION ( VER. ARCH'L PLANS ) 100 100 200 2 - 10mm Ø 10mm Ø @ 300 10mm Ø @ 600 mm O.C. 10mm Ø @ 600 mm O.C. 100 mm THK. MORTAR FILLER W/
150 150 200 4 - 10mm Ø 10mm Ø @ 300 10mm Ø @ 600 mm O.C. 10mm Ø @ 600 mm O.C. 1-10mm Ø HOR. BARS ( TYPICAL )

300 mm
TOILET & 200 200 200 4 - 10mm Ø 10mm Ø @ 300 10mm Ø @ 600 mm O.C. 10mm Ø @ 600 mm O.C. 10mm Ø HOR. BARS
BATH NOTE : 12mm THK. STYROPHOR
6. STRUCTURAL GAPS SHALL

BEAM DEPTH - h
FILLER ( NON-TOXIC )
300 mm 1. REFER TO ARCHITECTURAL PLANS TO VERIFY LOCATIONS OF IN NO CASE BE COVERED
ALL CHB WALLS. W/ PLASTER.
12 mm

h/2
2. REFER TO THICKNESS OF FINISHES TO ARCHITECTURAL
BEAM DEPTH

PLANS.

300 mm
3. 12mm THICK GAP SHALL BE PROVIDED IN BETWEEN WALLS & 100 mm
COLUMNS, WALLS & BEAMS, WALLS & SLABS ON TOP.

4. SILICONE SEALANT SHALL BE PROVIDED FOR ALL EXTERNAL


WALL ( CHB ). FOR INTERNAL WALLS, SEALANT NEED NOT BE
PROVIDED.

5. STRUCTURAL R.C. WALLS ( i.e. WATER TANK, ETC. ) SHALL


2 BLOW-UP DETAIL
BEAM DEPTH - h ( VER. ARCH'L PLANS )
NOT BE PROVIDED W/ 12mm THICK GAPS ALL AROUND.
S 3 SCALE 1:20 M

1
S 3
TOP ANCHORAGE OF LINTEL ACTING AS
REQUIRED SLAB
ADDITIONAL 10mm Ø U-BARS SPACED AT
300 mm O.C.
STIFFENER COLUMN
BARS ADDITIONAL 2 - 12mm Ø TOP
SLAB THICKNESS

BARS
MORTAR FILLER W/ 1-10mm Ø B
SEE 2 50 mm VERT. BARS ( TYPICAL )
TOP OF ROOF DETAIL S 3 300 mm 10mm Ø DOWEL BARS AT TOP OF ROOF LINTEL BEAM REINF. STEEL BAR LINTEL BEAM REINF. STEEL
BEAM 400mm O.C. ( TYPICAL ) BEAM ON TOP OF WALL OPENING ( BAR ON TOP OF WALL
300 mm

200mm VERIFY REBARS ) OPENING ( VERIFY REBARS,


10mm Ø DOWEL ( HOR. BARS & STIRRUPS )

H
300mm TYPICAL ) CHB WALL

H
REBARS
FLOOOR BEAM DEPTH - D

H
BEAM DEPTH - h 2ND FL.
REQUIRED BEAM
REINFORCING BARS 2ND FL. FFL
FFL

LINTEL BEAM DEPTH - d

300 mm
10mm Ø HOR. BARS
AT EVERY 3RD LAYER
1 DETAILED SECTION OF CHB 10mm Ø HOR. DOWEL ( BENDED )
AT EVERY 3 LAYERS OF CHB OR
10mm Ø VERT.
BAR. PER SIDE OF
CHB THICKNESS ( t )

H
S 3 SCALE 1:10 M 0.60m O.C. OPENING

10mm Ø VERT. BARS


H

HEIGHT - h
AT 400 mm O.C. (
10mm Ø DOWEL AT B
WALL
400mm O.C. ( TYPICAL )
BEAM DETAIL FOR T & B DEPRESSION OPENING

TYPICAL )
LINTEL BEAM REINF. STEEL
BAR ON TOP OF WALL
10mm Ø DOWEL BAR
OPENING ( VERIFY REBARS,
ANCHOR TO WALL
HOR. BARS & STIRRUPS )

H
FOOTING (WF) CHB WALL
REQUIRED
TOP & REBARS
GR. FL.
SLAB TOP BARS WHEN BOTTOM FFL
Ld DEPRESSION - d ( VER. ARCH'L PLANS ) GR. FL.
CALLED FOR IN THE BARS
SCHEDULE FFL
SLAB THICKNESS - t

300 mm

WF
WF WF 200 mm WIDTH - w 200 mm
C/F CHB THICKNESS ( t )
Ld

t
Ld C/F C/F

TYPICAL SLAB DEPRESSION DETAIL TYPICAL MASONRY ELEVATION W/ LINTEL TYPICAL CHB WALL OPENING ELEVATION
BEAMS & STIFFINER COLUMNS TYPICAL LINTEL BEAM DETAIL
SHOWING STEEL REINFORCEMENTS
REFLECTING REINF. STEEL BARS
300 mm 1 - 10mm Ø VERT. BAR PER CORNER 1 - 10mm Ø VERT. BAR PER NOTE :
100 mm 10mm Ø HOR. DOWEL BARS 10mm Ø VERT. BARS AT 400 mm INTERSECTION
10mm Ø HOR. BARS AT EVERY 3 LAYERS OF
12 mm O.C. 10mm Ø HOR. BARS AT EVERY 3 LAYERS CHB
FINISHED SURFACE
300 mm OF CHB 300 mm 10mm Ø VERT. BARS AT 400 PURSUANT TO SECTION 4 OF ANNEX "A" OF THE REVISED IMPLEMENTING
INTERIOR CHB REBARS FINISHED mm O.C. RULES AND REGULATIONS OF R.A. 9184, APPROVAL BY THE AUTHORIZED DPWH
COLUMN

SURFACE
OFFICIALS OF DETAILED ENGINEERING SURVEYS AND DESIGN UNDERTAKEN BY
RC

CONSULTANTS NEITHER DIMINISHES THE RESPONSIBILITY OF THE LATTER FOR THE


300 mm

TECHNICAL INTEGRITY OF THE SURVEYS AND DESIGN NOR TRANSFER ANY PART OF
FINISHED
SURFACE
THAT RESPONSIBILITY TO THE APPROVING OFFICIALS.
1 - 10mm Ø VERT. BAR PER
INTERSECTION
THE DESIGN CONSULTANT SHALL BE HELD FULLY RESPONSIBLE FOR THE
FAILURE OF THE FACILITY / IES STRUCTURES DUE TO FAULTY DESIGN EXCEPT FOR
THE CHANGES MADE WITHOUT THE CONFORMITY OF THE CONSULTANTS.

CHB EXTERIOR WALL SIDE ANCHORAGE CORNER WALL DETAIL DESIGNED STRUCTURAL : WALL INTERSECTION
DETAIL RUBEN A. ABA-A JR.
ENGINEER II
DATE:

PDS - BUK3RD : 2 0 2 3
DRAWN :
PROJECT AND LOCATION : SHEET CONTENTS : SUBMITTED : RECOMMENDING FOR APPROVAL : APPROVED : SET NO. SHT. NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS TYPICAL MASONRY ELEVATION ROSANNO GABRIEL D. SANICO
ARCHITECT I
REGIONAL OFFICE X W/ LINTEL BEAMS & STIFFINER PDS
BUKIDNON THIRD DISTRICT ENGINEERING OFFICE
CONSTRUCTION OF DATE:
CHECKED / REVIEWED : S
DICKLUM, MANOLO FORTICH, BUKIDNON MULTI-PURPOSE BUILDING COLUMNS REFLECTING REINF.
STEEL BARS AND
RYAN CAESAR B. FERNANDEZ ROMULO F. ANDRES, AEr. RONALDO C. PAHANG, AEr. S-3
BARANGAY MAMPAYAG, MANOLO FORTICH, BUKIDNON MCKENLY B. HONG ENGINEER II ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER 2023
OTHER IMPORTANT NOTES ENGINEER II OIC - PLANNING AND DESIGN SECTION, CHIEF
DATE: DATE: DATE: DATE:
SCHEDULE OF COLUMN
A
2.50
B C
3.50 11.50 5.50
D SCHEDULE OF FOOTING LEVEL C1 C2

FOOTING DIMENSIONS (MM) REINFORCEMENT REMARKS

TO ROOF BEM LEVEL


2.35 FOOTING 350

2ND FLR. LEVEL


F1C1 F1C1 F1C1 F1C1 MARK LENGTH WIDTH DEPTH THICKNESS SPACING
REBARS

250
(L) (W) (D) (T) (BOTHWAYS)
BAR-X BAR-Y
1 1.23 1.00
MAIN BARS 6-16MMØ
F1 1500 1500 1200 300 180 B.W. 9-16MMØ 9-16MMØ ISOLATED FOOTING TIE BARS 10MMØ
3.50

F3C3 F2 1150 1000 800 200 180 B.W. 6-16MMØ 7-16MMØ ISOLATED FOOTING 350

GROUND FLR. LEVEL


TO 2ND FLR. LEVEL
F1C1 ELEV.-1.50M F1C1 F1C1
F3C3

250
7.00

SF-1
ELEV.-0.25M

2
MAIN BARS 10-16MMØ
F1C1 ELEV.-1.50M
TIE BARS 10MMØ
N.G.L N.G.L
3.50

TO GROUND FLR. LEVEL


F2C2ELEV.-1M 350 300

FOUNDATION LEVEL
F1C1 ELEV.-1.50M F1C1 F1C1 F1C1

250

200
3

SF-2ELEV.-0.25M N.G.L.

1.20
COMPACTED COMPACTED MAIN BARS 10-16MMØ
EARTH FILL EARTH FILL MAIN BARS 4-16MMØ
TIE BARS 10MMØ

1.50
TIE BARS 10MMØ

0.80
COMPACTED COMPACTED ROOF BEAM

1.00
EARTH FILL EARTH FILL

0.30
0.30

0.30
0.05

0.05

0.20
16-12mmØ DSB W/

LAP SPLICE
TYPICAL FOOTING
10mmØ TIES
FOUNDATION PLAN

0.60M
SPACE 3 @ 0.05M.

3.00
SCALE: 1:100 MTRS. 2 @ 0.10M, 50mm THK. GRAVEL BEDDING
@ REST 0.15M O.C. 12- 12mmØ MATTING BARS
(LONGITUDINAL BAR)
6PCS- 12mmØ MATTING 10MMØ @ 100MM O.C.
EXTRA TIES

0.22
BARS (CROSS BAR)
1.50 2ND FLR. LN.

1.00

0.35
0.55 0.40 0.55
0.35 0.30 0.35

LAP SPLICE
1

0.20

0.60M
0.60

3.00
0.75
1.15
0.30

1.50
10MMØ TIES SPACED @ 5-0.05M,
8-0.075 AND THE REST IS 0.15M UP
TO MIDDLE LENGTH.

4"THK. CONCRETE FLOORING WITH

0.20
TILE FINISHED WITH 10MMØ RSB
0.60

F.F.L./TIE BEAM LEVEL AT EVERY 0.60M. O.C. BOTH WAYS


0.18

VARIES
12- 12mmØ MATTING BARS

0.04
COMPACTED COMPACTED
GRANULAR GRANULAR
(LONGITUDINAL BAR) MATERIALS MATERIALS

0.18 0.04 6PCS- 12mmØ MATTING


NATURAL GROUND LINE

0.55 0.40 0.55 BARS (CROSS BAR)

D
FOOTING ON GRADE(F2C2)
SCALE: 1:20 MTRS.

T
FOOTING (F1C1)
SCALE: 1:20 MTRS.

DESIGNED STRUCTURAL :
FOOTING SECTION (FIC1)
SCALE: NDTS
RUBEN A. ABA-A JR.
ENGINEER II
DATE:

PDS - BUK3RD : 2 0 2 3
DRAWN :
PROJECT AND LOCATION : SHEET CONTENTS : SUBMITTED : RECOMMENDING FOR APPROVAL : APPROVED : SET NO. SHT. NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS FOUNDATION PLAN ROSANNO GABRIEL D. SANICO
ARCHITECT I
REGIONAL OFFICE X PDS
BUKIDNON THIRD DISTRICT ENGINEERING OFFICE
CONSTRUCTION OF TYPICAL FOOTING PLAN DATE:
CHECKED / REVIEWED : S
DICKLUM, MANOLO FORTICH, BUKIDNON MULTI-PURPOSE BUILDING TYPICAL FOOTING SECTION
COLUMN SCHEDULE
RYAN CAESAR B. FERNANDEZ ROMULO F. ANDRES, AEr. RONALDO C. PAHANG, AEr. S-5
BARANGAY MAMPAYAG, MANOLO FORTICH, BUKIDNON MCKENLY B. HONG ENGINEER II ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER 2023
ENGINEER II OIC - PLANNING AND DESIGN SECTION, CHIEF
FOOTING SCHEDULE DATE: DATE: DATE: DATE:
BEAM SCHEDULE OF REINFORCE BEAM STIRRUPS/
MARK SUPPORT MID-SPAN SUPPORT HOOPS

0.15 0.15 0.15

10mm Ø STIRRUPS
LB 2-16mm Ø
TOP BAR
2-16mm Ø
TOP BAR
2-16mm Ø
TOP BAR SPACED 5@50mm;
4@100mm; REST @
0.30 0.30 0.30
200mm TO MIDSPAN
2-16mm Ø 2-16mm Ø 2-16mm Ø
BOT. BAR BOT. BAR BOT. BAR

LINTEL BEAM
SCALE 1 : 10 M.

BEAM SCHEDULE OF REINFORCE BEAM STIRRUPS/


MARK SUPPORT MID-SPAN SUPPORT HOOPS

0.25 0.25 0.25

10mm Ø STIRRUPS
A B C D TB 3-16mm Ø
TOP BAR
3-16mm Ø
TOP BAR
3-16mm Ø
TOP BAR SPACED 5@50mm;
4@100mm; REST @
0.35 0.35 0.35
200mm TO MIDSPAN
3-16mm Ø 3-16mm Ø 3-16mm Ø
BOT. BAR BOT. BAR BOT. BAR
11.50

2.35 2.50 3.50 5.50

LB LB LB TIE BEAM (TB) DETAIL


1 SCALE 1 : 10 M.
1.23 1.00

LB
3.50

LB

LB

A B C D
LB
7.00

2
11.50

2.35 2.50 3.50 5.50


3.50

TB TB TB
1

1.23 1.00
3 TB

3.50

TB

TB

TB

TB

TB
TB TB TB

7.00
2

3.50

TB

TB

TB

TB
LINTEL BEAM
SCALE: 1:100 MTRS. TB TB TB
3

DESIGNED STRUCTURAL : TIE BEAM


SCALE: 1:100 MTRS.
RUBEN A. ABA-A JR.
ENGINEER II
DATE:

PDS - BUK3RD : 2 0 2 3
DRAWN :
PROJECT AND LOCATION : SHEET CONTENTS : SUBMITTED : RECOMMENDING FOR APPROVAL : APPROVED : SET NO. SHT. NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS FOUNDATION PLAN ROSANNO GABRIEL D. SANICO
ARCHITECT I
REGIONAL OFFICE X PDS
BUKIDNON THIRD DISTRICT ENGINEERING OFFICE
CONSTRUCTION OF TYPICAL FOOTING PLAN DATE:
CHECKED / REVIEWED : S
DICKLUM, MANOLO FORTICH, BUKIDNON MULTI-PURPOSE BUILDING TYPICAL FOOTING SECTION
COLUMN SCHEDULE
RYAN CAESAR B. FERNANDEZ ROMULO F. ANDRES, AEr. RONALDO C. PAHANG, AEr. S-5
BARANGAY MAMPAYAG, MANOLO FORTICH, BUKIDNON MCKENLY B. HONG ENGINEER II ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER 2023
ENGINEER II OIC - PLANNING AND DESIGN SECTION, CHIEF
FOOTING SCHEDULE DATE: DATE: DATE: DATE:
SCHEDULE OF FOOTING 0.80
0.20
FOOTING FOOTING DIMENSIONS (MM) REINFORCEMENT REMARKS 5-16mm Ø BED BARS SPACED EQUALLY
BOTHWAYS

MARK LENGTH WIDTH DEPTH THICKNESS SPACING


REBARS

(L) (W) (D) (T) (BOTHWAYS)


BAR-X BAR-Y

0.80
0.20
SF-1 1200 550 250 300 O.C 3-10MMØ FOOTING ON FFL
SF-2 1100 1000 250 240 B.W. 10-10mmØ 10-10mmØ FOOTING ON GRADE
WF-1 500 250 100 O.C 3-10MMØ WF ON FFL 10mmØ LATERAL TIES SPACED
@ 3 - 0.05, 3 - 0.10

WF-2 400 400 200 300 O.C 3-10MMØ WF ON GRADE REST @ 0.15 M O.C

4- 16 mm Ø VERTICAL REBARS

1.00

0.75m
1.00

0.30
0.15 0.10
0.25

0.10

0.25
0.15 0.20m 0.15
0.15 0.10
0.25

0.15
0.15 0.20m 0.15
F3C3
SCALE
DETAIL
1:20 m

WALL FOOTING (WF2)


SCALE: NTS

1.20
VARIES

1.10
0.40

0.55
0.20

FOOTING ON FFL (STF-1)


SCALE: 1:15 MTRS.

0.40

1.00
WALL FOOTING (WF1) DESIGNED STRUCTURAL :
FOOTING ON GRADE (STF-2)
SCALE: 1:15 MTRS.
SCALE: NTS

RUBEN A. ABA-A JR.


ENGINEER II
DATE:

PDS - BUK3RD : 2 0 2 3
DRAWN :
PROJECT AND LOCATION : SHEET CONTENTS : SUBMITTED : RECOMMENDING FOR APPROVAL : APPROVED : SET NO. SHT. NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS ROSANNO GABRIEL D. SANICO
FOUNDATION PLAN ARCHITECT I
REGIONAL OFFICE X PDS
BUKIDNON THIRD DISTRICT ENGINEERING OFFICE
CONSTRUCTION OF FOOTING TIE BEAM DETAILS
DATE:
CHECKED / REVIEWED : S
DICKLUM, MANOLO FORTICH, BUKIDNON MULTI-PURPOSE BUILDING WALL FOOTING DETAILS RYAN CAESAR B. FERNANDEZ ROMULO F. ANDRES, AEr. RONALDO C. PAHANG, AEr. S-6 2 3
BARANGAY MAMPAYAG, MANOLO FORTICH, BUKIDNON MCKENLY B. HONG ENGINEER II ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER 2023
ENGINEER II OIC - PLANNING AND DESIGN SECTION, CHIEF
DATE: DATE: DATE: DATE:
BEAM SCHEDULE
A B C D
BEAM S T E E L R E I N F O R C E M E N T S
SEE STEEL DECK DIMENSIONS
DETAIL FLOOR BEAM
IN/MM LEFT MIDSPAN RIGTH 16MMØ STIRRUPS
LEVEL MARK REBAR WEB BAR 10MMØ
B2
1 (MMØ) (UNLESS NOTED OTHERWISE)
B1 B1 B H TOP BOTTOM TOP BOTTOM TOP BOTTOM

CB1
2ND FLOOR LEVEL B1 250 350 16 4 3 3 4 4 3 5@50, 10@100, REST@175
B1 B1 B1 B1 B1
CB1 2ND FLOOR LEVEL B2 300 400 16 5 4 4 5 5 4 5@50, 10@100, REST@200
CB1
B1 B1 B2 B2 CANTILEVER BEAM CB-1 250 350 16 5 3 5 3 5 3 5@50, 10@100, REST@175
2
DN
ROOF LEVEL RB 200 300 16 2 2 2 2 2 2 3@50, 10@100, REST@150
STAIR LANDING
OPEN BEAM SLB-1 150 200 16 2 2 2 2 2 2 3@50, 10@100, REST@150
B1 TO B1 B1 B1 B1
BELOW
FOOTING TIE BEAM FTB 300 200 16 4 2 2 4 4 2 5@50, 4@100,3@150, REST@200
B1 B1
3 200 200 250 250
B2
150 250 250 200
B1 B1
0.075m. THICK SLAB W/ 0.075m. THICK SLAB W/
10mmØ MATT BARS B1 10mmØ MATT BARS
DISTANCE @ 0.15m. BW OC DISTANCE @ 0.15m. BW OC

300

300

350

350

350

350
200

300
FTB FTB STAIRBEAM CB-1 CB-1
TYPICAL FLOOR BEAM/STEEL DECK/CONCRETE CANOPY
BEAM(B1) BEAM(B1) ROOF BEAM(RB)
(LEFT/RIGHT) MIDSPAN (LEFT/RIGHT) MIDSPAN (STB-1) (LEFT/RIGHT) MIDSPAN
SECOND FLOOR FRAMING PLAN
SCALE: 1:100 MTRS.

10MMØ STIRRUPS SPACE 3 @


0.05M, 10 @ 0.10M, REST @
0.15M O.C.
A B C D

2-16MMØ
1
RB RB RB
2-12MMØ

RB RB RB RB

LANDING BEAM(LB) DETAIL


2 SCALE: NTS
RB RB RB
DN

RB RB RB RB

RB RB RB
3
10MMØ STIRRUPS SPACE
0.075m. THICK SLAB W/ 5 @0.05M,
10mmØ MATT BARS
DISTANCE @ 0.15m. BW OC 4 @ 0.10M,
3 @ 0.15M REST
@ 0.20M O.C.

TYPICAL ROOF BEAM/ CONCRETE CANOPY

ROOF BEAM PLAN


SCALE: 1:100 MTRS. FOOTING TIE BEAM

FOOTING TIE BEAM(FTB) DETAIL


DESIGNED STRUCTURAL : SCALE: 1:20 MTRS.

RUBEN A. ABA-A JR.


ENGINEER II
DATE:

PDS - BUK3RD : 2 0 2 3
DRAWN :
PROJECT AND LOCATION : SHEET CONTENTS : SUBMITTED : RECOMMENDING FOR APPROVAL : APPROVED : SET NO. SHT. NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS ROSANNO GABRIEL D. SANICO
ROOF FRAMING PLAN ARCHITECT I
REGIONAL OFFICE X PDS
BUKIDNON THIRD DISTRICT ENGINEERING OFFICE
CONSTRUCTION OF DATE:
CHECKED / REVIEWED : S
DICKLUM, MANOLO FORTICH, BUKIDNON MULTI-PURPOSE BUILDING RYAN CAESAR B. FERNANDEZ ROMULO F. ANDRES, AEr. RONALDO C. PAHANG, AEr. S-7
BARANGAY MAMPAYAG, MANOLO FORTICH, BUKIDNON MCKENLY B. HONG ENGINEER II ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER 2023
ENGINEER II OIC - PLANNING AND DESIGN SECTION, CHIEF
DATE: DATE: DATE: DATE:
A B C D
SEE STEEL DECK
DETAIL

B2
1
B1 B1

CB1
B1 B1 B1 B1 B1
B C .25

CB1

CB1 3.50 2ND FLOOR LINE

.10
B1 B1 B2 B2

.15
2
DN
BEAM-1
OPEN
B1 TO B1 B1 B1 B1
BELOW
1 2nd FLOOR BEAM-1
BLOW-UP SECTION
B1 B1
3

2nd FLOOR BEAM-1

2nd FLOOR BEAM-1


B2
CB1 B1 B1 B1 B1 B1
0.075m. THICK SLAB W/ 0.075m. THICK SLAB W/
10mmØ MATT BARS B1 10mmØ MATT BARS 150mm THICK STEELDECK

3.50
DISTANCE @ 0.15m. BW OC DISTANCE @ 0.15m. BW OC

3.50 3.50 1.88

SECTION
TYPICAL FLOOR BEAM/STEEL DECK/CONCRETE CANOPY
2 2nd FLOOR BEAM-1
SECOND FLOOR FRAMING PLAN

B E L O W
0.15 m. DEPTH Ø12mm.Ø DSB MATTING
SPACED @ 0.30M. O.C. B.W.
SCALE: 1:100 MTRS.

2nd FLOOR BEAM-1

2nd FLOOR BEAM-1


CONCRETE SLAB H: 0.15M.

3.50
16 SECOND FLOOR LINE

T O
15
SLAB

O P E N
14

DECK SLAB SECTION


BEAM
13
1.20
12
11 12mm Ø NOSING BARS 3 2nd FLOOR BEAM-1

STEELDECK
STEELDECK
12mm Ø STEP BARS
10 SPACED @ 0.20m. OC GAUGE 22

1.88
SEE BEAM DETAIL
9 16mm Ø MAIN BARS
LANDING 8 TOP AND BOTTOM

3.00
SPACED @ 0.10m. OC TYPICAL STEEL DECK
7
6
0.30 16mm Ø TEMP. BARS
SPACED AS SHOWN
CANOPY BEAM-1
ISOMETRIC
SCALE: NTS
0.19

5
4
1.50

3 3.50
2
1
TYPICAL STEEL DECK
FINISH FLOOR LINE
STEEL DECK FRAMING PLAN
0.15 0.10
0.25

SCALE: 1:50MTRS.
0.15 0.20m 0.15

LONGITUDINAL SECTION

MAIN STAIR DETAILS


SCALE: 1:25 MTRS.
DESIGNED STRUCTURAL :

RUBEN A. ABA-A JR.


ENGINEER II
DATE:

PDS - BUK3RD : 2 0 2 3
DRAWN :
PROJECT AND LOCATION : SHEET CONTENTS : SUBMITTED : RECOMMENDING FOR APPROVAL : APPROVED : SET NO. SHT. NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS ROSANNO GABRIEL D. SANICO
ROOF FRAMING PLAN ARCHITECT I
REGIONAL OFFICE X PDS
BUKIDNON THIRD DISTRICT ENGINEERING OFFICE
CONSTRUCTION OF GIRT DETAILS
DATE:
CHECKED / REVIEWED : S
DICKLUM, MANOLO FORTICH, BUKIDNON MULTI-PURPOSE BUILDING FASCIA FRAME DETAILS RYAN CAESAR B. FERNANDEZ ROMULO F. ANDRES, AEr. RONALDO C. PAHANG, AEr. S-8
BARANGAY MINDAGAT, MALITBOG, BUKIDNON MCKENLY B. HONG ENGINEER II ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER 2023
ENGINEER II OIC - PLANNING AND DESIGN SECTION, CHIEF
DATE: DATE: DATE: DATE:
A B C D A B C D
TOP CHORD, BOTTOM CHORD AND WEB MEMBER
PREFORMED PRE-PAINTED G.I. GUTTER PREFORMED PRE-PAINTED G.I. GUTTER 38mm x 38mm x 6mm ANGLE BAR
4.65 9.95 4.65
1.00 2.65 1.00 8.95 1.00

0.25

0.25
G U T T E R L I N E
FASCIA FRAME-2 @GUTTER LINE FASCIA FRAME-2 @GUTTER LINE
G U T T E R L I N E 0.55 0.55 0.55 0.55 0.55 0.55

78
TOP AND BOTTOM CHORD & TOP AND BOTTOM CHORD &

0.
WEB 38mm x 38mm x WEB 38mm x 38mm x

0.90

0.90
6mm ANGLE BAR 6mm ANGLE BAR
GIRT GIRT GIRT GIRT
1 1
12mm x .30 m. TURN BUCKLE 12mm x .30 m. TURN BUCKLE

0.55
FASCIA FRAME-2 @ SIDE FLASHING FASCIA FRAME-2 @ SIDE FLASHING
TOP AND BOTTOM CHORD & TOP AND BOTTOM CHORD &
WEB 38mm x 38mm x WEB 38mm x 38mm x
6mm ANGLE BAR 6mm ANGLE BAR

17
SWAY BRACE SWAY BRACE 17

16
SAG ROD SAG ROD 16

TRUSS-1

TRUSS-1

TRUSS-1

TRUSS-1

TRUSS-1

TRUSS-1
15 2"x4"x2mm C-PURLINS 2"x4"x2mm C-PURLINS 15
7.15

7.15
9.50

9.50
14 14
2 13
16
15 1
2 13
16
15 1 UPPER AND LOWER ROOF
12 12

FASCIA FRAME-1 DETAIL


14 2 14 2
11 11
DN 13 3 DN 13 3 FASCIA FRAME-2 @ SIDE FLASHING
10 10

9
12 4
9
12 4 TOP AND BOTTOM CHORD &
11 5 11 5 WEB 38mm x 38mm x
8

7
10 6
8

7
10 6 6mm ANGLE BAR SCALE: 1:25 MTRS.
6 9 7 6 9 7
TOP AND BOTTOM CHORD &
5 TOP AND BOTTOM CHORD & 5
WEB 38mm x 38mm x
4 WEB 38mm x 38mm x 4
8 6mm ANGLE BAR 8
3 6mm ANGLE BAR @ FRONT FASCIA FRAME-1 3
@ FRONT FASCIA FRAME-1
2 2 TOP AND BOTTOM CHORD & WEB
3 1
GIRT 3 1
GIRT GIRT GIRT 0.30 MEMBER 38mm x 38mm x 6mm ANGLE
BAR
1.20

1.20

0.30
UPPER AND LOWER ROOF
UPPER ROOF LOWER ROOF
ROOF FRAMING PLAN ROOF FRAMING PLAN FASCIA FRAME-2 DETAIL
SCALE: 1:25 MTRS.
SCALE: 1:100 MTRS. SCALE: 1:100 MTRS.

3 2 1 0.40mm x 2.44 mm
TOP AND BOTTOM CHORD
38mm x 38mm x 6mm ANGLE BAR
PRE PAINTED SPANISH GUTTER 0.30 42
4.5MM THK. FIBER CEMENT BOARD IN 2-38mm x 38 mm x 6mm, 0. 38mm x 38mm x 6mm
0.29 38mm x 38mm x 6mm ANGLE BAR FASCIA FRAME TOP CHORD, BOTTOM CHORD 0.25 ANGLE BAR WEB MEMBER
1.00
1.00 & WEB MEMBER DISTANCE @ 0.60 BW. OC.
1.00
1.00 9.32 2" x 4" x 2mm C-PURLINS

0.30

0.30
1.00
1.00 Hi-Rib PRE-PAINTED ROOFING G.I SHEET
0.40

1.00
1.00
4.5MM THK. FIBER
0.

1.00
55

SEE BLOW-UP DETAILS CEMENT FACIA BOARD


1.44

0.60
0.60
0.60 UPPER AND LOWER ROOF
3" Ø PVC
0.89

0.60 0.25

GIRT DETAIL
0.60

ELBOW 90°

0.30
TOP OF BEAM
RB RB 3"Ø PVC PIPE DOWN SPOUT SCALE: 1:25 MTRS.
1.20

UPPER AND LOWER ROOF


0.90
4.5MM THK. FIBER CEMENT CEILING BOARD IN 4-10mmØ x 300mm ANCHOR BOLT
METAL CARRYING CHANNEL(CEILING JOIST)
12mm x 38mm x 5m x 0.8mm THK. @ 1200mm
W/ NUTS and WASHERS ON
12mm THK. BASE PLATE(SEE SPOT DETAILS)
LOWER ROOF
ROOF GUTTER DETAIL .35
5mm THICK STEEL PLATE
SCALE: 1:30 MTRS. .25
TRUSS-2 DETAIL
38mm x 38mm x 6mm ANGLE BAR
SCALE: 1:50 MTRS.

.20
.25
FULL WELDED TO Hi-Rib PRE-PAINTED ROOFING G.I SHEET 0.40 m x 1090mm x LS
STEEL PLATE 4-16mmØ X 10" BOLTS 2.5" STEEL TEKSREW
3 2 1 W/ NUTS AND WASHERS
0.30 M.
2-38mm x 38 mm x 6mm,
0.29
4.5MM THK. FIBER CEMENT BOARD IN
38mm x 38mm x 6mm ANGLE BAR FASCIA FRAME TOP CHORD, BOTTOM CHORD 0.25 2 mm. X 12 mm. X 50mm. X 100 mm. CEE- PURLINS
1.00 12mm THK. BASE PLATE
1.00 & WEB MEMBER DISTANCE @ 0.60 BW. OC.
1.00 4-10mmØ x 300mm SLOPE >
1.00 9.32 2" x 4" x 2mm C-PURLINS ANCHOR BOLT 12 MM Ø PLAIN BARS WITH STANDARD NUT AND
1.00 38mm x 38mm x 6mm ANGLE BAR
1.00 Hi-Rib PRE-PAINTED ROOFING G.I SHEET W/ NUTS and WASHERS WASHER
0.40

1.00
1.00
0.

1.00
55

0.35

SEE BLOW-UP DETAILS 5mm THICK STEEL PLATE


0.60
0.60
0.60 0.25 ROOF BEAM 50mm. X 50 mm. CLIP ANGLE WELDED TO
2.05

0.60
0.60 PURLINS & TOP CHORD
RB COLUMN
1.51

0.30

CONNECTION OF G.I SHEET ROOFING TO PURLINS


TOP OF BEAM BASE PLATE DETAIL SCALE: NTS
RB RB 0.90

STEEL RAFTER TO ROOF BEAM


4-10mmØ x 300mm ANCHOR BOLT
4.5MM THK. FIBER CEMENT CEILING BOARD IN
METAL CARRYING CHANNEL(CEILING JOIST) W/ NUTS and WASHERS ON UPPER ROOF CONNECTION DETAIL
12mm x 38mm x 5m x 0.8mm THK. @ 1200mm 12mm THK. BASE PLATE(SEE SPOT DETAILS)
TRUSS-1 DETAIL DESIGNED STRUCTURAL : SCALE: NDS.
SCALE: 1:50 MTRS.
RUBEN A. ABA-A JR.
ENGINEER II
DATE:

PDS - BUK3RD : 2 0 2 3
DRAWN :
PROJECT AND LOCATION : SHEET CONTENTS : SUBMITTED : RECOMMENDING FOR APPROVAL : APPROVED : SET NO. SHT. NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS SECOND FLOOR BEAM PLAN ROSANNO GABRIEL D. SANICO
ARCHITECT I
REGIONAL OFFICE X PDS
BUKIDNON THIRD DISTRICT ENGINEERING OFFICE
CONSTRUCTION OF SCHEDULE OF BEAM DATE:
CHECKED / REVIEWED : S
DICKLUM, MANOLO FORTICH, BUKIDNON MULTI-PURPOSE BUILDING BEAM DETAILS
STEEL DECK FRAMING PLAN RYAN CAESAR B. FERNANDEZ ROMULO F. ANDRES, AEr. RONALDO C. PAHANG, AEr. S-9
BARANGAY MAMPAYAG, MANOLO FORTICH, BUKIDNON MCKENLY B. HONG ENGINEER II ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER 2023
ENGINEER II OIC - PLANNING AND DESIGN SECTION, CHIEF
DATE: DATE: DATE: DATE:
PLUMBING
PLUMBING SPECIFICATIONS:
1. ALL PLUMBING WORKS INCLUDED HEREIN SHALL CONFORMED TO THE 9. ROOF DRAIN
LATEST EDITION OF 'THE PHILIPPINE PLUMBING CODE". "NATIONAL - RAINWATER PIPING SHALL NOT BE USED AS SOIL, WASTE &
SOIL PIPE 4"Ø FROM GROUND FLOOR
BUILDING CODE", AND THE RULES AND REGULATIONS OF THE LOCAL VENT PIPES
VTR 2"Ø TO SECOND FLOOR AUTHORITY.
3"Ø DOWNSPOUT - ROOF DRAINS SHALL BE EQUIPPED WITH STRAINERS
TO SECOND FLOOR 4"Ø 4"Ø 4"Ø
2. ALL SLOPE FOR ALL HORIZONTAL WASTE LINE SHALL MOUNTAIN 2% EXTENDING NOT LESS THAN 102MM ABOVE THE SURFACE OF
CB CB CB CB
F 1
2"Ø PE PIPE SDR WATER LINE
c.o. SOIL PIPE 4"Ø SOIL PIPE 4"Ø
MINIMUM UNLESS OTHERWISE SPECIFIED. THE ROOF IMMEDIATELY ADJACENT TO THE DRAIN
D.S.
2"Ø D.S. D.S. D.S.
3. ALL SEWER PIPELINES EMBEDDED ON GROUND AND BELOW
W.C.
3"Ø DOWNSPOUT LAV. CONCRETE SLAB HAD BEEN PROVIDED WITH SAND BEDDING WASTE - SOIL PIPE LINE

2"Ø
W.C. URI.
2% LAV. F.D. 2URI.
%
SL SL
O OP
PE
TO
F.D
.
PANTRY
ET
OF
.D.
PANTRY
MATERIALS. ▬ SOIL PIPE LINE - 4" Ø PVC PIPE SERIES - 1000
F
ST 4. ALL SOIL PIPE & WASTE PIPE LINES SHALL BE PVC PIPE AND SHALL BE ▬ WASTE PIPE LINE (FLOOR DRAIN) - 4" Ø PVC PIPE SERIES - 1000

2"Ø

SOIL PIPE 4"Ø


PROPERLY JOINTED WITH PVC SOLVENT CEMENT ▬ WASTE PIPE LINE (LAVATORY) - 2" Ø PVC PIPE SERIES - 1000

4"Ø
2"Ø
1
D 4 EXIT D 4 EXIT 5. WASTE PIPE LINES SHALL BE A MINIMUM OF 100MMØ PVC PIPE (S -1000) ▬ MAIN VENT PIPE - 2" Ø PVC PIPE SERIES - 1000

PE PIPE SDR WATER LINE


FOR MAIN PIPE , WATER CLOSET AND FLOOR DRAIN; 50MMØ PVC PIPE ▬ DOWNSPOUT OR ROOF LEADER - 3" Ø PVC PIPE SERIES - 1000
(S-1000) FOR MAIN VENT AND BRANCH VENT, 75MMØ (S -1000)FOR SINK
DRAIN WATER SUPPY LINE
U P

U P
F LAV. 6. VENT THRU ROOF SHALL BE 0.30M FROM ANY OPENNING ▬ SUPPLY LINE - 1" Ø PE PIPE SDR
R A M P

R A M P
-0.35m LAV. -0.35m

7. ALL FLOOR DRAIN & SINK SHALL BE WITH ITS RESPECTIVE P-TRAPS ▬ DISTRIBUTION PIPE - 21" Ø PE PIPE SDR

4"Ø
F F.D.

W.C W.C
8. CHANGES IN DIRECTION:
HORIZONTAL DRAINAGE LINES TO VERTICAL STACK

TO PUBLIC SEWER
c.o.
– 45 OR 60 WYE BRANCHES LEGEND:
– COMBINATION OF WYE AND 1/8 BEND BRANCHES
– SANITARY TEE

TO PUBLIC SEWER
SOIL PIPE LINE

G.V.
HORIZONTAL DRAINAGE LINES TO ANOTHER HORIZONTAL DRAINAGE
WASTE PIPE LINE

WATER SOURCE
LINES

POTABLE
TAP TO
- 45 WYE BRANCHES WATER SUPPLY PIPE LINE
- COMBINATION WYE AND 1/8 BEND BRANCHES
GATE VALVE
VERTICAL DRAINAGE LINES CONNECTING TO HORIZONTAL DRAINAGE
LINE F FAUCET
- 45 BRANCHES W.C. WATER CLOSET
FD FLOOR DRAIN
LAV. FLOOR DRAIN
PIPE LINE PLUMBING LAYOUT PIPELINE PLUMBING LAYOUT C.O. CLEAN OUT
GROUND FLOOR WATER LINE GROUND FLOOR SANITARY LINE VTR VENT TRU ROOF
SCALE: 1:100 MTRS. SCALE: 1:100 MTRS. CB CATCH BASIN
ST SEPTIC TANK

SOIL PIPE 4"Ø FROM GROUND FLOOR


VTR 2"Ø TO SECOND FLOOR
FROM GROUND FLOOR

c.o.

W.C. W.C. FD FD
W.C W.C.
F F

2"Ø

2"Ø
F LAV.-0.05m LAV.
-0.05m F LAV.
-0.05m LAV.
-0.05m

DN DN

PIPE LINE PLUMBING LAYOUT PIPE LINE PLUMBING LAYOUT


SECOND FLOOR WATER LINE SECOND FLOOR SANITARY LINE
SCALE: 1:100 MTRS. SCALE: 1:100 MTRS.

DESIGNED :

JUSTIN JOSEPH R. ADRALES


REG. MASTER PLUMBER
DATE:

PDS - BUK3RD : 2 0 2 3
DRAWN :
PROJECT AND LOCATION : SHEET CONTENTS : SUBMITTED : RECOMMENDING FOR APPROVAL : APPROVED : SET NO. SHT. NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS LOCATION MAP ROSANNO GABRIEL D. SANICO
ARCHITECT I
REGIONAL OFFICE X PLUMBING SPEC'S PDS
BUKIDNON THIRD DISTRICT ENGINEERING OFFICE
CONSTRUCTION OF WATERLINE PLUMBING LAYOUT
DATE:
CHECKED / REVIEWED : P
DICKLUM, MANOLO FORTICH, BUKIDNON MULTI-PURPOSE BUILDING SANITARY PLUMBING LAYOUT RYAN CAESAR B. FERNANDEZ ROMULO F. ANDRES, AEr. RONALDO C. PAHANG, AEr. P-1
BARANGAY MAMPAYAG, MANOLO FORTICH, BUKIDNON LEGENDS MCKENLY B. HONG ENGINEER II ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER 2023
ENGINEER II OIC - PLANNING AND DESIGN SECTION, CHIEF
DATE: DATE: DATE: DATE:
PLUMBING SPECIFICATIONS:
1. ALL PLUMBING WORKS INCLUDED HEREIN SHALL CONFORMED TO THE
LATEST EDITION OF 'THE PHILIPPINE PLUMBING CODE". "NATIONAL
BUILDING CODE", AND THE RULES AND REGULATIONS OF THE LOCAL
AUTHORITY.
2. ALL SLOPE FOR ALL HORIZONTAL WASTE LINE SHALL MOUNTAIN 2%
MINIMUM UNLESS OTHERWISE SPECIFIED.
3. ALL SEWER PIPELINES EMBEDDED ON GROUND AND BELOW
.
D.S CONCRETE SLAB HAD BEEN PROVIDED WITH SAND BEDDING
MATERIALS.
4. ALL SOIL PIPE & WASTE PIPE LINES SHALL BE PVC PIPE AND SHALL BE
PROPERLY JOINTED WITH PVC SOLVENT CEMENT
5. WASTE PIPE LINES SHALL BE A MINIMUM OF 100MMØ PVC PIPE (S -1000)
.
D.S FOR MAIN PIPE , WATER CLOSET AND FLOOR DRAIN; 50MMØ PVC PIPE
(S-1000) FOR MAIN VENT AND BRANCH VENT, 75MMØ (S -1000)FOR SINK
DRAIN
R
L OO D.S
. 6. VENT THRU ROOF SHALL BE 0.30M FROM ANY OPENNING
DF 7. ALL FLOOR DRAIN & SINK SHALL BE WITH ITS RESPECTIVE P-TRAPS
O UN
8. CHANGES IN DIRECTION:
GR D.S
.
OM HORIZONTAL DRAINAGE LINES TO VERTICAL STACK
FR – 45 OR 60 WYE BRANCHES
– COMBINATION OF WYE AND 1/8 BEND BRANCHES
C. F OR – SANITARY TEE
W.
V .F F LO HORIZONTAL DRAINAGE LINES TO ANOTHER HORIZONTAL DRAINAGE
W .C
. -0.0
LA
5m

O ND LINES
F A-0V.0
.5m
EC
FL OS - 45 WYE BRANCHES
2" ØT
V TR - COMBINATION WYE AND 1/8 BEND BRANCHES
VERTICAL DRAINAGE LINES CONNECTING TO HORIZONTAL DRAINAGE
DN
LINE
- 45 BRANCHES
OR
LO 9. ROOF DRAIN
DF OR
UN FLO .FD2"Ø - RAINWATER PIPING SHALL NOT BE USED AS SOIL, WASTE &
GRO . N D C
W.
M c.o
E CO LA
V. VENT PIPES
RO
5m

OS
C -0.0

F W.
ØT FD 2"Ø V. - ROOF DRAINS SHALL BE EQUIPPED WITH STRAINERS
4E"Ø
5m
-0.0

R2"
LA
P I P EXTENDING NOT LESS THAN 102MM ABOVE THE SURFACE OF
IL VT
SO THE ROOF IMMEDIATELY ADJACENT TO THE DRAIN
DN
T WASTE - SOIL PIPE LINE
OU
SP ▬ SOIL PIPE LINE - 4" Ø PVC PIPE SERIES - 1000
WN
DO ▬ WASTE PIPE LINE (FLOOR DRAIN) - 4" Ø PVC PIPE SERIES - 1000
3"Ø ▬ WASTE PIPE LINE (LAVATORY) - 2" Ø PVC PIPE SERIES - 1000
UT
PO UT ▬ MAIN VENT PIPE - 2" Ø PVC PIPE SERIES - 1000
W NS S PO
DO WN CB ▬ DOWNSPOUT OR ROOF LEADER - 3" Ø PVC PIPE SERIES - 1000
T
3"Ø
3"Ø
DO
N SP
OU
PO
UT D.S
. ST
OW S WATER SUPPY LINE
2 "1Ø
WN
ØD
PE 4"Ø
O
R E
PIP
ES 3"
3" Ø D 4"Ø IP4E

▬ SUPPLY LINE - 1" Ø PE PIPE SDR
OOTER LIN
DR
L W SO
IL P ▬ DISTRIBUTION PIPE - 21" Ø PE PIPE SDR
F A AT
ER PIPE 4"Ø

NDE SDR
W LIN E
O E ST CB .

EC PE P I P WA D.S
TO
S 1 2"Ø RC
E
2"Ø 4E"Ø
2"Ø PU
TO V. TO BL
OULE 4"Ø IL PIP PU IC
G.
RY
S B
SO BL SE
NT ATEROTAP TO
RY IC
SE
WE
R N
A OR NT
W P TA
P CB . WE
F
LO OR D.S PA R
F THIS

N
V. D O 4"Ø

E
LA
RI. TO F.D. UN FL 2"Ø LAV
.
W E
C.
2U% SLOPE
GRO OND CB.S.
.
c.o . .U R I. TO F.D.
SITE
OM SEC
SLOPE
W. F.D
2%
C
W.

E
w
D

S
F R
F O
IT 4
E "Ø 2"ØT SO
IL P S
EX IP TR 2"Ø
I IT
D4 IL P V D4
EPX4E"Ø
SO
V. -0.35m
FLA -0.3
5m

F W.
C V.
LA .D.
F C .
W. c.o
P
R
U

OO
P P
M U

FL
A P
R M

ND
A
R

CO
O SE
"ØT
VTR2

D
B

A
R
G
Y
.

O
WATER LINE PLUMBING LAYOUT SANITARY LINE PLUMBING LAYOUT R
O
A

ISOMETRIC VIEW ISOMETRIC VIEW LEGEND:


D

R
.
SCALE: 1:100 MTRS. SCALE: 1:100 MTRS.

Y
SOIL PIPE LINE

G
WASTE PIPE LINE

R
WATER SUPPLY PIPE LINE

B
TO MALI
TBOG
GATE VALVE B
R
G
Y
.
F FAUCET R
O
A
D
W.C. WATER CLOSET TO K
IABO
FD FLOOR DRAIN
LAV. FLOOR DRAIN
C.O. CLEAN OUT
LOCATION MAP
VTR VENT TRU ROOF N D S

CB CATCH BASIN
DESIGNED :
ST SEPTIC TANK

JUSTIN JOSEPH R. ADRALES


REG. MASTER PLUMBER
DATE:

PDS - BUK3RD : 2 0 2 3
DRAWN :
PROJECT AND LOCATION : SHEET CONTENTS : SUBMITTED : RECOMMENDING FOR APPROVAL : APPROVED : SET NO. SHT. NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS LOCATION MAP ROSANNO GABRIEL D. SANICO
ARCHITECT I
REGIONAL OFFICE X PLUMBING SPEC'S PDS
BUKIDNON THIRD DISTRICT ENGINEERING OFFICE
CONSTRUCTION OF ISOMETRIC VIEW
DATE:
CHECKED / REVIEWED : P
DICKLUM, MANOLO FORTICH, BUKIDNON MULTI-PURPOSE BUILDING LEGENDS RYAN CAESAR B. FERNANDEZ ROMULO F. ANDRES, AEr. RONALDO C. PAHANG, AEr. P-2
BARANGAY MAMPAYAG, MANOLO FORTICH, BUKIDNON MCKENLY B. HONG ENGINEER II ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER 2023
ENGINEER II OIC - PLANNING AND DESIGN SECTION, CHIEF
DATE: DATE: DATE: DATE:
0.60
0.10

100MM Ø PVC PIPE

2ND FLOOR LINE FLOOR DRAIN

0.60
0.40
TO CANAL
SEAL
HORIZONTAL - HORIZONTAL
50MMDIA. VENT
AT 45-degree WYE
HORIZONTAL - HORIZONTAL
WYE 1/8 BEND VERTICAL - HORIZONTAL
WYE 1/8 BEND
PIPE TOP VIEW
HORIZONTAL - VERTICAL PIPE HANGER 0.25
SANITARY TEE P - TRAP
SECTION 0.10
10MM Ø HANDLE BAR W/
REMOVABLE CONC. COVER

NAT. GROUND LINE

TO CANAL
TO CANAL

4" THK. CHB

0.10
10MM Ø DSB BARS
0.40
SPACED @ 0.25M O.C.

SECTION
10mm THK. CONC. SLAB w/
10mm Ø REINF. BARS @ 0.15m O.C.
PROVIDED BOTHWAYS

CATCH BASIN DETAILS


SCALE: 1:25 MTS.
4.00
2.00 1.00 1.00

OUTLET
4'' Ø BRASS C.O.

4'' Ø BRASS C.O.


PLUMBING SPECIFICATIONS:
4'' Ø BRASS C.O.
0.60 M. x 0.60 M.
MANHOLE
0.60 M. x 0.60 M. 1. ALL PLUMBING WORKS INCLUDED HEREIN SHALL CONFORMED TO THE
MANHOLE
1.30

LATEST EDITION OF 'THE PHILIPPINE PLUMBING CODE". "NATIONAL


BUILDING CODE", AND THE RULES AND REGULATIONS OF THE LOCAL
AUTHORITY.
10MMØ DSB HANDLE
2. ALL SLOPE FOR ALL HORIZONTAL WASTE LINE SHALL MOUNTAIN 2%
4'' Ø BRASS C.O.
MINIMUM UNLESS OTHERWISE SPECIFIED.
4'' Ø BRASS C.O. 3. ALL SEWER PIPELINES EMBEDDED ON GROUND AND BELOW
CONCRETE SLAB HAD BEEN PROVIDED WITH SAND BEDDING
4'' Ø BRASS C.O. MATERIALS.
10mm Ø EXTRA BARS 4. ALL SOIL PIPE & WASTE PIPE LINES SHALL BE PVC PIPE AND SHALL BE
PROPERLY JOINTED WITH PVC SOLVENT CEMENT
5. WASTE PIPE LINES SHALL BE A MINIMUM OF 100MMØ PVC PIPE (S -1000)
INLET

FOR MAIN PIPE , WATER CLOSET AND FLOOR DRAIN; 50MMØ PVC PIPE
PLAN (S-1000) FOR MAIN VENT AND BRANCH VENT, 75MMØ (S -1000)FOR SINK
DRAIN
6. VENT THRU ROOF SHALL BE 0.30M FROM ANY OPENNING
7. ALL FLOOR DRAIN & SINK SHALL BE WITH ITS RESPECTIVE P-TRAPS
4.00 8. CHANGES IN DIRECTION:
HORIZONTAL DRAINAGE LINES TO VERTICAL STACK
2.00 1.00 1.00 – 45 OR 60 WYE BRANCHES
– COMBINATION OF WYE AND 1/8 BEND BRANCHES
– SANITARY TEE
HORIZONTAL DRAINAGE LINES TO ANOTHER HORIZONTAL DRAINAGE
4'' Ø BRASS C.O. 4'' Ø BRASS C.O. 4'' Ø BRASS C.O. 4'' Ø BRASS C.O. LINES
- 45 WYE BRANCHES
0.26

- COMBINATION WYE AND 1/8 BEND BRANCHES


AIR SPACE
VERTICAL DRAINAGE LINES CONNECTING TO HORIZONTAL DRAINAGE
OUTLET LINE
0.30

0.30

- 45 BRANCHES
0.30

9. ROOF DRAIN
0.30

- RAINWATER PIPING SHALL NOT BE USED AS SOIL, WASTE &


DIGESTIVE
1.20

VENT PIPES
CHAMBER LEACHING LEACHING - ROOF DRAINS SHALL BE EQUIPPED WITH STRAINERS
CHAMBER CHAMBER EXTENDING NOT LESS THAN 102MM ABOVE THE SURFACE OF
THE ROOF IMMEDIATELY ADJACENT TO THE DRAIN

10% SLOPE WASTE - SOIL PIPE LINE


▬ SOIL PIPE LINE - 4" Ø PVC PIPE SERIES - 1000
▬ WASTE PIPE LINE (FLOOR DRAIN) - 4" Ø PVC PIPE SERIES - 1000
▬ WASTE PIPE LINE (LAVATORY) - 2" Ø PVC PIPE SERIES - 1000
0.10 M. THK. SLAB w/ WATER PROOFING
COMPOUND & 10MM Ø DSB SPACED ▬ MAIN VENT PIPE - 2" Ø PVC PIPE SERIES - 1000
SECTION AT 0.40 M. O.C. BOTHWAYS ▬ DOWNSPOUT OR ROOF LEADER - 3" Ø PVC PIPE SERIES - 1000
4" THK. CHB WALL w/ INSIDE PLASTER FIN.
w/ 10mmØ VERT.BARS SPACED @ 0.60m & WATER SUPPY LINE
HOR. BAR@ EVERY 3RD LAYER OF CHB
w/ WATER PROOFING COMPOUND
▬ SUPPLY LINE - 1" Ø PE PIPE SDR
▬ DISTRIBUTION PIPE - 21" Ø PE PIPE SDR

SEPTIC TANK DETAIL SEPTIC TANK DETAIL


SCALE 1:30MTS. SCALE: 1:80 MTRS.
DESIGNED :

PDS - BUK3RD : 2 0 2 3
DRAWN :
PROJECT AND LOCATION : SHEET CONTENTS : JUSTIN JOSEPH R. ADRALESSUBMITTED : RECOMMENDING FOR APPROVAL : APPROVED : SET NO. SHT. NO.
REPUBLIC OF THE PHILIPPINES REG. MASTER PLUMBER
DATE:
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGIONAL OFFICE X DATE: PDS
BUKIDNON THIRD DISTRICT ENGINEERING OFFICE CHECKED / REVIEWED :
DICKLUM, MANOLO FORTICH, BUKIDNON
LOCATION MAP ROSANNO GABRIEL D. SANICO RYAN CAESAR B. FERNANDEZ ROMULO F. ANDRES, AEr. RONALDO C. PAHANG, AEr.
PLUMBING SPEC'S MCKENLYARCHITECT
B. HONGI ENGINEER II 2023PDS
CONSTRUCTION OF SEPTIC TANK DETAIL, ENGINEER II
DATE:
OIC - PLANNING AND DESIGN SECTION, CHIEF
DATE:
ASSISTANT DISTRICT ENGINEER
DATE: DATE:
DISTRICT ENGINEER
P
MULTI-PURPOSE BUILDING
BARANGAY MAMPAYAG, MANOLO FORTICH, BUKIDNON
GREASE TRAP DETAIL
CATCH BASIN DETAIL
P-TRAP DETAIL
P-3
ELECTRICAL
LEGEND:
S 3W THREE WAY SWITCH CEILING MOUNTED EXHAUST FAN
14 WATTS LED BULB W/ 6" DIA. PORCELAIN HOLDER
RACEWAY CONDUIT CONCEALED IN CEILING
14W LED DAYLIGHT 4" DIA. W/ OUTDOOR LIGHTING FIXTURE EMERGENCY LIGHT OUTLET
EO
GENERAL NOTES 2 X 16 WATTS LED TUBE DAYLIGHT W/ REFLECTOR
RACEWAY CONDUIT CONCEALED UNDER FLOOR
CALL POINT/MANUAL PULL STATION
HOUSING BOX TYPE. PANELBOARD, MARKED AS DP & LPP
1. ALL ELECTRICAL WORKS HEREIN SHALL BE DONE IN ACCORDANCE W/
THE PROVISION OF THE LATEST EDITION OF THE PHILIPPINE ELECTRICAL CODE,
S SINGLE POLE SWITCH
CKT. BREAKER, RATINGS AS INDICATED CONVENTIONAL SMOKE DETECTOR
REQUIREMENTS OF THE LOCAL POWER COMPANIES, RULES AND REGULATIONS S2 DOUBLE SWITCH, 2 SINGLE POLE SWITCHES
OF THE LOCAL ENFORCING AUTHORITIES. ON ONE-GANG PLATE DUPLEX CONVENIENCE OUTLET, 3-PRONG OR CON
THREE SINGLE POLE SWITCHES ON GROUNDING TYPE 15AMPS, 240 VOLT
2. ALL ELECTRICAL WORKS HEREIN INCLUDED SHALL BE EXECUTED BY A S3 CONVENTIONAL HEAT DETECTOR
ONE-GANG SWITCH PLATE EMERGENCY LAMP, SIMPLEX CONVENIENCE OUTLET, CON
PERSONNEL W/ ELECTRICAL EXPERIENCE UNDER THE DIRECT SUPERVISION OF A EL
FULL TIME LICENSED ELECTRICAL ENGINEER. WORKS SHALL BE NEATLY PLACED, GROUNDING TYPE IS 15AMPS, 240 V
SPEAKER
SECURELY FASTENED AND PROPERLY FINISHED.

3. THE TYPE OF POWER SERVICE SHALL BE 220 VAC, SINGLE PHASE, 60Hz, B 4X4 JUNCTION BOX
2-WIRE PLUS GROUND. SD
FIRE ALARM BELL/SOUNDER STROBE
4. THE CONTRACTOR SHALL VERIFY AND ORIENT THE ACTUAL LOCATION
2-1.25 mm2 THHN
OF SERVICE ENTRANCE FOR CONNECTION TO POWER SUPPLY AND MANUAL PUSH BOTTON
15 mmØ uPVC
COMMUNICATION.

5. ALL MATERIALS SHALL BE BRAND NEW AND SHALL CONFORM W/ THE


PROVISIONS UNDER WRITERS LABORATORIES INC., IN EVERY CASE WHERE SUCH A
DP-2 POWER SOURCE
STANDARD HAS BEEN ESTABLISHED. 40 AT
6. UNLESS OTHERWISE SPECIFIED, ALL ELECTRICAL WIRING INSTALLATION 2P
FOR LIGHTING AND POWER SHALL USE PVC, FOR AUXILIARY SYSTEM USE PVC. THE
MINIMUM CONDUIT SIZE SHALL BE 20mmØ. 2-1.25 mm2 THHN
15 mmØ uPVC
7. ALL WIRE SHALL BE COPPER AND THERMOPLASTIC INSULATED TYPE 2-5.5 mm2 THHN 2-8mm2 THHN
"THHN". THE MINIMUM SIZE FOR LIGHTING AND POWER SHALL BE 3.5 sq.mm. AND 1-3.5 mm2 THHN (G) 1-5.5mm2 THHN
1-25KVA
MANUFACTURED BY PHILFLEX. 20 mmØ uPVC 25 mmØ uPVC DISTRIBUTION-TYPE
POLE MOUNTED
8. COLOR CODING OF WIRES AND CABLES SHALL BE AS FOLLOWS; 23KV-138Y/240V
PHASES- BLACK, GROUND- GREEN. 125KV BIL
2ND FLOOR FFL 60CYCLES PER SECOND
9. PROVIDE ADEQUATE AND EFFECTIVE GROUNDING SYSTEM TO ALL
LIGHTING AND POWER CIRCUIT AS PER PHILIPPINE ELECTRICAL CODE
REQUIREMENT.
B SD
10. CONVINIENCE OUTLET FOR GENERAL USE SHALL BE DUPLEX 20AT, 230
VOLTS, GROUNDING TYPE, LIGHT SWITCHES SHALL BE 15AT, 230 VOLTS.

11. ALL OUTLET BOXES SHALL BE GALVANIZE GAUGE NO. 16, DEEP TYPE W/
FACTORY KNOCKOUTS. 2-1.25 mm2 THHN
15 mmØ uPVC
12. FIRE ALARM DEVICES SHALL COMPLY WITH THE NFPA PROVISIONS AND SHALL DP-1 MDP
BEAR THE "UL" STANDARD MARK.

13. ALL ELECTRICAL PANEL BOARD AND CIRCUIT BREAKERS SHALL BE


60 AT 110 AT FACP
"SQUARE D", BOLT-ON TYPE. 2P 2P
14. ALL ELECTRICAL CIRCUITS SHALL BE WIRED ACCORDING TO THE PANEL 3-5.5 mm2 THHN ALL BREAKERS AND DEVICES ARE NEMA-3R ENCLOSED
2-5.5 mm2 THHN
BOARD LOAD SCHEDULE. 1-2.0 mm2 THHN
1-3.5 mm2 THHN (G)
20 mmØ uPVC 25 mmØ uPVC Monitoring Devices
15. ALL MOUNTING HEIGHTS OF DEVICES SHALL BE AS FOLLOWS:
( SUBJECTS TO ARCHITECT'S APPROVAL PRIOR TO INSTALLATION) ATS Standby Generator Set
A. PANEL BOARD - 1.40 M CENTER OF THE FINISHED FLOOR Main Loads DIESEL DRIVEN
B. SWITCH - 1.40 M ABOVE FINISHED FLOOR TO CENTER OF THE DEVICE Distribution MCB
C. CONVINIENCE OUTLET - 0.30 M ABOVE FINISHED FLOOR TO CENTER OF THE DEVICE Panel
D. INTERCOM OUTLETS. - 1.40 M FROM FINISHED FLOOR TO CENTER OF THE DEVICE. 2-38mm2 THHN
E. CONTROL CABINETS
F. MANUAL STATION
- 1500 MM ABOVE FINISHED FLOOR TO TOP OF ENCLOSURE (VERTICAL)
- 1400 MM ABOVE FINISHED FLOOR TO CENTER OF DEVICE
2-14 mm2 THHN
1-5.5 mm2 THHN (G)
1-8.0 mm2 THHN
50 mmØ RSC 3P
3P Normal
Power
Supply
Gen.
G
G. BELL - 200 MM BELOW BEAM OR FINISHED CEILING 32 mmØ RSC
ATS BREAKER FLUSHED TYPE
H. EMERGENCY LIGHT - 300 MM BELOW BEAM OR FINISHED CEILING
I. EXIT LIGHT - 150 MM ABOVE DOOR JAMB GND FLOOR FFL
16. THE PLANS AS DRAWN ARE BASED UPON THE ARCHITECTURAL PLANS
AND DETAILS AND SHOWN CONDITION AS ACCURATELY AS POSSIBLE TO
INDICATE THEM IN SCALE. THE PLANS ARE DIAGRAMMATICAL AND DOES NOT
NECESSARILY SHOW ALL FITTINGS NECESSARY TO FIT TO THE BUILDING
CONDITIONS. THE LOCATION OF OUTLETS, APPARATUS AND APPLIANCES SHOWN
ON THE PLANS ARE APPROXIMATE. THE CONTRACTOR SHALL BE HELD
RESPONSIBLE FOR THEIR PROPER LOCATION IN ORDER TO MAKE THEM FIT W/ THE
ARCHITECTURAL DETAILS AND INSTRUCTIONS FROM THE ENGINEER'S
REPRESENTATIVE AT THE SITE. POWER
SCALE NTS.
RISER DIAGRAM
DESIGNED :
17. COVER ALL JUNCTION BOXES ( STRICTLY NO EXPOSED WIRE).

PROFESSIONAL ELECTRICAL ENGINEER


DATE:

PDS - BUK3RD : 2 0 2 3
DRAWN :
PROJECT AND LOCATION : SHEET CONTENTS : SUBMITTED : RECOMMENDING FOR APPROVAL : APPROVED : SET NO. SHT. NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS ROMY S. BANTOLIO
GENERAL NOTES ENGINEER I
REGIONAL OFFICE X PDS
BUKIDNON THIRD DISTRICT ENGINEERING OFFICE
CONSTRUCTION OF LEGEND AND SYMBOLS
POWER RISER DIAGRAM
DATE:
CHECKED / REVIEWED : E
DICKLUM, MANOLO FORTICH, BUKIDNON MULTI-PURPOSE BUILDING RYAN CAESAR B. FERNANDEZ ROMULO F. ANDRES, AEr. RONALDO C. PAHANG, AEr. E-1
BARANGAY MAMPAYAG, MANOLO FORTICH, BUKIDNON MCKENLY B. HONG ENGINEER II ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER 2023
ENGINEER II OIC - PLANNING AND DESIGN SECTION, CHIEF
DATE: DATE: DATE: DATE:
A
LEGEND:
B C D
A B C D 11.50
14 WATTS LED BULB W/ 6" DIA. PORCELAIN HOLDER
1.13 2 X 16 WATTS LED TUBE DAYLIGHT W/ REFLECTOR
2.43 11.50
2.50 3.50 5.50 HOUSING BOX TYPE.
1.20 1.23 2.50 3.50 5.50
14W LED DAYLIGHT 4" DIA. W/ OUTDOOR LIGHTING FIXTURE

1 1 Sa SINGLE POLE SWITCH

1.60
0.60
EL 1

1.60
DP2
Sab DOUBLE SWITCH, 2 SINGLE POLE SWITCHES

3.50
Sa Sa ON ONE-GANG PLATE

3.50
2
EL DP2
THREE SINGLE POLE SWITCHES ON

1.90
Sa Sabc
1.90

ONE-GANG SWITCH PLATE

7.00
EL

7.00
2 S 3W

7.00
THREE WAY SWITCH
7.00

2 S3W Sa to
downstair
6.08

Sab switch

5.64
U P

DN
EL RACEWAY CONDUIT CONCEALED IN CEILING
2.30

PEBBLES to
R A M P

3.50
upstair

3.50
switch
Sab

3.50
RACEWAY CONDUIT CONCEALED UNDER FLOOR
Sa 1
DP2 PANELBOARD, MARKED AS DP & LPP
1.20

Sa
EL EL EL
3 3 CKT. BREAKER, RATINGS AS INDICATED

1.88
0.50 1.30
1.88

2 DUPLEX CONVENIENCE OUTLET, 3-PRONG OR


DP2
GROUNDING TYPE 15AMPS, 240 VOLT

EL EMERGENCY LAMP, SIMPLEX CONVENIENCE OUTLET,


3.75 GROUNDING TYPE IS 15AMPS, 240 V
3.75
2.50 3.50 5.50 2.50 6.25 2.75 CEILING MOUNTED EXHAUST FAN
11.50 11.50
EMERGENCY LIGHT OUTLET
EO

GROUND FLOOR LIGHTING PLAN SECOND FLOOR LIGHTING PLAN


N D S N D S

LOCKNUT AND BUSHING

SEE BLOW-UP DETAIL PVC ADAPTER


PVC CONDUIT EMBEDDED

TO NEXT FIXTURE TO NEXT FIXTURE


CEILING SLAB
BOX EXTENSION SADDLE

LIGHTING FIXTURE SUPPORT METALLIC FLEXIBLE CONDUIT

LIGHTING FIXTURE

INSTALLATION DRAWING FOR


EXIT LIGHT DETAIL LIGHTING FIXTURE IN DROP CEILING PINLIGHT SUPPORTS & HANGER DETAIL

ASSORTED DETAILED DRAWINGS


N D S

DESIGNED :

PROFESSIONAL ELECTRICAL ENGINEER


DATE:

PDS - BUK3RD : 2 0 2 3
DRAWN :
PROJECT AND LOCATION : SHEET CONTENTS : SUBMITTED : RECOMMENDING FOR APPROVAL : APPROVED : SET NO. SHT. NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS ROMY S. BANTOLIO
LOCATION MAP ENGINEER I
REGIONAL OFFICE X PDS
BUKIDNON THIRD DISTRICT ENGINEERING OFFICE
CONSTRUCTION OF GROUND FLOOR LIGHTING LAYOUT
SECOND FLOOR LIGHTING LAYOUT
DATE:
CHECKED / REVIEWED : E
DICKLUM, MANOLO FORTICH, BUKIDNON MULTI-PURPOSE BUILDING ASSORTED DETAILED DRAWINGS
ELECTRICAL LEGEND & SYMBOLS
RYAN CAESAR B. FERNANDEZ ROMULO F. ANDRES, AEr. RONALDO C. PAHANG, AEr. E-2
BARANGAY MAMPAYAG, MANOLO FORTICH, BUKIDNON MCKENLY B. HONG ENGINEER II ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER 2023
ENGINEER II OIC - PLANNING AND DESIGN SECTION, CHIEF
DATE: DATE: DATE: DATE:
A B C D
A B C D 11.50
2.43 11.50
1.13
2.50 3.50 5.50
LEGEND:
1.20 1.23 2.50 3.50 5.50
14 WATTS LED BULB W/ 6" DIA. PORCELAIN HOLDER

1 1 2 X 16 WATTS LED TUBE DAYLIGHT W/ REFLECTOR


HOUSING BOX TYPE.

1.60
0.60
1.60
EO 14W LED DAYLIGHT 4" DIA. W/ OUTDOOR LIGHTING FIXTURE

3.50
3.50
Sa

1.90
SINGLE POLE SWITCH
1.90

EO
0.92 Sab DOUBLE SWITCH, 2 SINGLE POLE SWITCHES

7.00
EO

7.00
2 EO

7.00
ON ONE-GANG PLATE
7.00

2
6.08

5.64
4 THREE SINGLE POLE SWITCHES ON
Sabc
U P

DN
DP1
EO
2.30

PEBBLES ONE-GANG SWITCH PLATE


R A M P

3.50

3.50
S 3W

3.50
THREE WAY SWITCH
3
DP1 EO
EO
1.20

EO RACEWAY CONDUIT CONCEALED IN CEILING

3 3 RACEWAY CONDUIT CONCEALED UNDER FLOOR

1.88
0.50 1.30
1.88

3 4
DP2 DP2
PANELBOARD, MARKED AS DP & LPP

CKT. BREAKER, RATINGS AS INDICATED

3.75 DUPLEX CONVENIENCE OUTLET, 3-PRONG OR


3.75
2.50 3.50 5.50 GROUNDING TYPE 15AMPS, 240 VOLT
2.50 6.25 2.75
11.50 11.50 EMERGENCY LAMP, SIMPLEX CONVENIENCE OUTLET,
EL
GROUNDING TYPE IS 15AMPS, 240 V
CEILING MOUNTED EXHAUST FAN
GROUND FLOOR POWER PLAN SECOND FLOOR POWER PLAN
N D S N D S
EO EMERGENCY LIGHT OUTLET

5/ 16" Hot Dip


Galvanized Steel
1" Dia. Lift Hole at Cover
Center of Cover LEGEND:
Grade Typicaal Installation
Weld At Column Base
40cm x 40cm x 60m w/ COVER
First Floor HAND HOLE w/ 3/4 x 3m COPPER CLAD

3' - 0"
CADWELD
Type GT
Ground Rod Grade COPPER CLAD GROUND ROD W/
Hollow Block Connection EXOTHERMIC WELD
40cm X 40cm
X 60 cm
30 cm

Ground Grid
3.00

Conductor

SPECIFICATION:
3/4 Copper Clad 1. THE GROUND RING SHOULD BE IN DIRECT CONTACT WITH THE EARTH AT A DEPTH
Ground Rod
Ground Rod BELOW THE EARTH SURFACE OF AT LEAST 1.0m.
3.00 m

2. INSPECTION PIT WILL BE 40cm x 40cm x 60cm w/ COVER.


Typical Down Conductor
3. MINIMUM OF 100mm² ... WILL BE USED FOR THE GROUND WIRE THAT WILL TOUCH THE
EARTH SURFACE.
CADWELD DETAIL 4. MINIMUM 3/4 OF AN INCH FOR THE COPPER CLAD GROUND ROD.
GROUNDING CONNECTION (w/ EXOTHERMIC WELD) 5. USE CADWELD FOR ALL EXOTHERMIC CONNECTION.
6. MAXIMUM OF 5Ω (OHM) FOR THE VALUE OF EACH GROUND ROD LOCATION BEFORE AND
AFTER BONDING OF THE GROUND RING.

DESIGNED :

PROFESSIONAL ELECTRICAL ENGINEER


DATE:

PDS - BUK3RD : 2 0 2 3
DRAWN :
PROJECT AND LOCATION : SHEET CONTENTS : SUBMITTED : RECOMMENDING FOR APPROVAL : APPROVED : SET NO. SHT. NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS ROMY S. BANTOLIO
GROUND FLOOR POWER LAYOUT ENGINEER I
REGIONAL OFFICE X PDS
BUKIDNON THIRD DISTRICT ENGINEERING OFFICE
CONSTRUCTION OF SECOND FLOOR POWER LAYOUT
GROUNDING DETAILED DRAWINGS
DATE:
CHECKED / REVIEWED : E
DICKLUM, MANOLO FORTICH, BUKIDNON MULTI-PURPOSE BUILDING ELECTRICAL LEGEND & SYMBOLS RYAN CAESAR B. FERNANDEZ ROMULO F. ANDRES, AEr. RONALDO C. PAHANG, AEr. E-3
BARANGAY MAMPAYAG, MANOLO FORTICH, BUKIDNON MCKENLY B. HONG ENGINEER II ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER 2023
ENGINEER II OIC - PLANNING AND DESIGN SECTION, CHIEF
DATE: DATE: DATE: DATE:
SCHEDULE OF LOADS
GROUND DISTRIBUTION PANEL: DP1 FLUSH MOUNTED, ENCLOSURE: NEMA-1 W/ GROUND TERMINAL
CKT. NO. LOAD DESCRIPTION VA LOAD V AT AF POLE kAIC WIRE AND CONDUIT SIZE MAIN DISTRIBUTION PANEL: MDP FLUSH MOUNTED, ENCLOSURE: NEMA-1 W/ GROUND TERMINAL
2-3.5mm² THHN + 1-2.0mm² TW (G) CKT. NO. LOAD DESCRIPTION VA LOAD V AT AF POLE kAIC WIRE AND CONDUIT SIZE
1 LIGHTING OUTLETS 1,000 230 15 50 2 10 IN 20mmØ PVC.
2-14mm² THHN + 1-5.5mm² TW (G)
2 2-3.5mm² THHN + 1-2.0mm² TW (G) 1 DP1 9,595 230 60 50 2 10
LIGHTING OUTLETS 1,000 230 15 50 2 10 IN 32mmØ PVC.
IN 20mmØ PVC.
2-8mm² THHN + 1-5.5mm² TW (G)
3 2-5.5mm² THHN + 1-2.0mm² TW (G) 2 DP2 6,866 230 40 50 2 10
CONVENIENCE OUTLET 1260 230 20 50 2 10 IN 20mmØ PVC.
IN 25mmØ PVC.

3 2-5.5mm² THHN + 1-2.0mm² TW (G)


2-5.5mm² THHN + 1-2.0mm² TW (G) FACP 2,500 230 30 50 2 10
4 CONVENIENCE OUTLET 1440 230 20 50 2 10 IN 20mmØ PVC.
IN 20mmØ PVC.
2-5.5mm² THHN + 1-2.0mm² TW (G) TOTAL CONNECTED LOAD 18,961
5 ACU SPLIT-TYPE 1HP 1,500 230 30 50 2 10 IN 20mmØ PVC.
2-5.5mm² THHN + 1-2.0mm² TW (G)
6 ACU SPLIT-TYPE 1HP 1,500 230 30 50 2 10 IN 20mmØ PVC. COMPUTATIONS: FOR MDP SIZE OF AUTOMATIC TRANSFER SWITCH (ATS):
2-5.5mm² THHN + 1-2.0mm² TW (G) USE: ENCLOSED MANUAL TRANSFER SWITCH, CIRCUIT BREAKER
7 ACU TWO SPLIT-TYPE 1HP 1,500 230 30 50 2 10 IN 20mmØ PVC.
TYPE, 250AT 2 POLE-DOUBLE THROW 230V. 60 Hz IN NEMA-3R
STUB-OUT ONLY
8 SPARE 3,000 230 30 50 2 10 IT = 18961WATTS = 82.43AMP
230 V
RECOMMENDED SIZE OF TRANSFORMER:
COMPUTATIONS: FOR DP1 THEREFORE USE: CONNECTED LOAD = 230 X 82.43= 18.958mkVA
OTHER LOAD: CAPACITY @ 1.2 DIV. FACTOR =18.958 kVA (1.2)
PB: SIZE MIAN CIRCUIT BREAKER: =22.75kVA
TOTAL LIGHTING LOAD = 2,000WATTS SPARE @ 80% DF (3000 X 0.8) = 2400 WATTS 110 AT CIRCUIT BREAKER 220V, 60Hz
TOTAL CONVENIENCE LOAD = 2,700 WATTS ACU-1.0 @ 80% DF (4,500 X 0.80) = 3,600 WATTS USE: 1 - 37.5 kVA Oil Immersed Distribution Type-Pole Mounted,
SIZE OF MAIN FEEDER CABLE: 23kV-138Y/240V, 60 cycles per second, Single Phase
TOTAL = 4,700 WATTS TOTAL = 6,000 WATTS
2-38mm^2 THHN COPPER WIRE (AWG #2) ON 50mmØ RSC.
1-5.5mm^2 THHN COPPER WIRE GROUND
APPLYING DEMAND FACTOR: TOTAL LOAD =9,595 WATTS
1ST 3,000W @ 100% DF = 3,000 WATTS
REMAINING @ 35% DF (1,700 x 0.35) = 595 WATTS
TOTAL (L AND CO LOAD) = 3,595 WATTS IT = 9,595WATTS = 41.71AMP
230 V

THEREFORE USE:
2 - 38mm² THHN/THWN
SIZE OF CIRCUIT BREAKER:
60 AT CIRCUIT BREAKER 220V, 60Hz 1 - 8.0mm² THWN wire (G)
M
SIZE OF FEEDER CABLE:
2-14.0mm^2 THHN COPPER WIRE ON 32mmØ RSC.
1-5.5mm^2 THHN COPPER WIRE GROUND
MCB
2 - 14mm² THHN/THWN
110AT 2 - 8mm² THHN/THWN
SECOND DISTRIBUTION PANEL: DP2 FLUSH MOUNTED, ENCLOSURE: NEMA-1 W/ GROUND TERMINAL 1 - 5.5mm² THWN wire (G) 1 - 5.5mm² THWN wire (G)
CKT. NO. LOAD DESCRIPTION VA LOAD V AT AF POLE kAIC WIRE AND CONDUIT SIZE
2-3.5mm² THHN + 1-2.0mm² TW (G)
1 LIGHTING OUTLETS 1,100 230 15 50 2 10 IN 20mmØ PVC.
2-3.5mm² THHN + 1-2.0mm² TW (G) MAIN 60AT/60AF, 2P, MAIN40AT/40AF, 2P, 230V
2 LIGHTING OUTLETS 1,200 230 15 50 2 10 MCCB INDUSTRIAL TYPE MCCB INDUSTRIAL TYPE
IN 20mmØ PVC.

3 2-5.5mm² THHN + 1-2.0mm² TW (G)


CONVENIENCE OUTLET 1,440 230 20 50 2 10 15 AT 15 AT 15 AT 15 AT
IN 20mmØ PVC.
L.O. 1 2 L.O. L.O. 1 2 L.O.
2-5.5mm² THHN + 1-2.0mm² TW (G)
4 CONVENIENCE OUTLET 1,620 230 20 50 2 10 IN 20mmØ PVC.
2-5.5mm² THHN + 1-2.0mm² TW (G)
5 ACU SPLIT-TYPE 1.5HP 1,800 230 30 50 2 10 IN 20mmØ PVC.
2-5.5mm² THHN + 1-2.0mm² TW (G) 20 AT 20 AT 20 AT 20 AT
6 ACU SPLIT-TYPE 0.5HP 500 230 30 50 2 10 C.O 3 4 C.O. C.O 3 4 C.O
IN 20mmØ PVC.
2-5.5mm² THHN + 1-2.0mm² TW (G)
7 SPARE 1,500 230 30 50 2 10 IN 20mmØ PVC.

COMPUTATIONS: FOR DP2 S-ACU 5 30 AT 30 AT 6 S-ACU S-ACU 5 30 AT 30 AT 6 SPARE

PB:
TOTAL LIGHTING LOAD = 2,300WATTS SPARE @ 80% DF (1,500 X 0.80) = 1,200 WATTS
TOTAL CONVENIENCE LOAD = 3,060 WATTS ACU-1.0 @ 80% DF (2,300 X 0.80) = 1,840 WATTS
TOTAL = 5,360WATTS _____________________ S-ACU 7 30AT 30 AT 8 SPARE S-ACU 7 30 AT 30 AT 8 SPARE
3,040 WATTS
APPLYING DEMAND FACTOR:
1ST 3,000W @ 100% DF = 3,000 WATTS TOTAL LOAD =6,866 WATTS BUS BAR COPPER GROUND BUS BAR COPPER GROUND
REMAINING @ 35% DF (2,360 x 0.35) = 826 WATTS TERMINAL TERMINAL
TOTAL = 3,826 WATTS
IT = 6,866WATTS =29.85AMP 5.5MM² TW 5.5MM² TW
230 V GROUND WIRE GROUND WIRE

5/8" Ø X 3.0MTR. GROUND ROD 5/8" Ø X 3.0MTR. GROUND ROD


THEREFORE USE: (COPPERWELD) W/ HEAVY DUTY CLAMP (COPPERWELD) W/ HEAVY DUTY CLAMP

SIZE OF CIRCUIT BREAKER:


40 AT CIRCUIT BREAKER 220V, 60Hz

SIZE OF FEEDER CABLE: SINGLE LINE DIAGRAM


2-8.0mm^2 THHN COPPER WIRE ON 32mmØ RSC. N D S
1-5.5mm^2 THHN COPPER WIRE GROUND

DESIGNED :

PROFESSIONAL ELECTRICAL ENGINEER


DATE:

PDS - BUK3RD : 2 0 2 3
DRAWN :
PROJECT AND LOCATION : SHEET CONTENTS : SUBMITTED : RECOMMENDING FOR APPROVAL : APPROVED : SET NO. SHT. NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS ROMY S. BANTOLIO
ELECTRICAL SCHEDULE OF LOADS ENGINEER I
REGIONAL OFFICE X PDS
BUKIDNON THIRD DISTRICT ENGINEERING OFFICE
CONSTRUCTION OF SINGLE LINE DIAGRAM DATE:
CHECKED / REVIEWED : E
DICKLUM, MANOLO FORTICH, BUKIDNON MULTI-PURPOSE BUILDING RYAN CAESAR B. FERNANDEZ ROMULO F. ANDRES, AEr. RONALDO C. PAHANG, AEr. E-4
BARANGAY MAMPAYAG, MANOLO FORTICH, BUKIDNON MCKENLY B. HONG ENGINEER II ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER 2023
ENGINEER II OIC - PLANNING AND DESIGN SECTION, CHIEF
DATE: DATE: DATE: DATE:
ELECTRICAL ANALYSIS
VOLTAGE DROP CALCULATION:
CABLE SIZE AMPACITY
@ V.D #1 (SE TO MDP):
LOAD CURRENT = 87.4A Article 2.10 .2.2 (A)(1)(a) Overcurrent Protection PEC 1 2017 page 43
TO LTG. CIRCUITS
PHASE = 1-PHASE WIRE x5.5, x8 OR x14
VOLTAGE = 230V MAIN LINE: LOCKNUT AND BUSHING
SQUARE BOX PVC ADAPTER
WIRE SIZE = 1-38 mm² COPPER WIRE
PVC CONDUIT
DISTANCE = 20m (RSC PIPE) I = (18961/ 230) = 82.43 A WIRE SPLICED WITH TO BRANCH TYPE THHN/THWN TO BRANCH
BOLTED TYPE SQUARE BOX CKT. WIRING WIRES CKT. WIRING
WIRE IMPEDANCE = 0.01282+j0.00202Ω = 82.43 x 125% Full Continuous Load PRESSURE CONNECTORS
AND INSULATING TAPE
POWER FACTOR = 0.80 103.03 OR SCREW-ON
θ = 36.87° PIGTAIL CONNECTORS
EQUIPMENT
THEREFORE, AS PER PEC MINIMUM REQUIREMENT LEAVE ENOUGH SLACK ULLISTED INSULATED
GROUND WIRE CEILING SLAB
WIRE CONNECTOR
V.D = I x (Rcosθ + Xsinθ) USE NOT LESS THAN 38MM2 THHN/THWN STRANDED WIRE OR TWIST-WITH
LOCK CONNECTOR FIXTURE WIRES TYPE AF
= 87.4A x [(0.01282 x 0.80) + (0.00202 x 0.60)] TO LIGHTING FIXTURE
PVC CONDUIT
= 1.002V FEEDER 1:
NEW VOLTAGE = 230V - 1.002V = 228.998V COVER
TO LIGHTING PANELBOARD
VD% = [1 - (228.998V/230V)] x 100 = 0.435% I = (9595/ 230) = 41.71 A BRANCH CIRCUIT BREAKER
WIRE SIZE x3.5 SPLICING CONNECTION BLOW-UP DETAIL
= 41.71 x 125% Full Continuous Load
@ V.D #2 (MDP TO DP2): = 52.13 A

LOAD CURRENT = 47.2A


WIRE SPLICED DETAIL FOR BRANCH
THEREFORE, AS PER PEC MINIMUM REQUIREMENT CIRCUIT WITH DIFFERENT WIRE SIZES
PHASE = 1-PHASE USE NOT LESS THAN 14MM2 THHN/THWN STRANDED WIRE
VOLTAGE = 228.998V (NEAR PANELBOARD LOCATION)
WIRE SIZE = 1-8mm² COPPER WIRE
FEEDER 2:
DISTANCE = 7m (µPVC PIPE)
WIRE IMPEDANCE = 0.0156+j0.000833 Ω
POWER FACTOR = 0.80 I = (6866/ 230) = 29.85 A
θ = 36.87° = 29.85 x 125% Full Continuous Load
= 37.31 A
V.D = I x (Rcosθ + Xsinθ)
= 47.2A x [(0.0156 x 0.80) + (0.000833 x 0.60)]
= 0.612V THEREFORE, AS PER PEC MINIMUM REQUIREMENT
USE NOT LESS THAN 8MM2 THHN/THWN STRANDED WIRE
NEW VOLTAGE = 228.998V - 0.612V = 228.386V
VD% = [1 - (228.386V/228.998)] x 100 = 0.267% LOCKNUT AND BUSHING

DP2 CIRCUIT # 2, LIGHTING: SEE BLOW-UP DETAIL PVC ADAPTER


SUMMARY: PVC CONDUIT EMBEDDED
% VOLTAGE DROP FROM TRANSFORMER - LPP - I = 1200/ 230 = 5.21 A
BRANCH CKT. # 2 = 5.21 x 1.25 TO NEXT FIXTURE TO NEXT FIXTURE
CEILING SLAB
TOTAL VDROP = 1.002 + 0.612 = 1.614V = 6.51 A BOX EXTENSION SADDLE

TOTAL VDROP PERCENT = (1.614/230) x 100% = 0.7017% LIGHTING FIXTURE SUPPORT METALLIC FLEXIBLE CONDUIT
THEREFORE, AS PER PEC MINIMUM REQUIREMENT
OVER CURRENT PROTECTION USE NOT LESS THAN 3.5MM2 THHN/THWN STRANDED WIRE LIGHTING FIXTURE

Article 2.10 .2.2 (A)(1)(a) Overcurrent Protection PEC 1 2017 page 43 DP2 CIRCUIT # 4,CONVENIENCE OUTLET: INSTALLATION DRAWING FOR
LIGHTING FIXTURE IN DROP CEILING PINLIGHT SUPPORTS & HANGER DETAIL
LIGHTING & POWER PANEL, MAIN CB: I = 1620/ 230 = 7.04 A
I = (18961/ 230) = 82.43A = 7.04 x 1.25
= 82.43 x 125% Full Continuous Load = 8.8 A
= 103.03 A
THEREFORE, AS PER PEC MINIMUM REQUIREMENT
THEREFORE, PEC MINIMUM REQUIREMENT USE NOT LESS THAN 5.5MM2 THHN/THWN STRANDED WIRE
CIRCUIT BREAKER , USE NOT LESS THAN 110AT/110AF, 2POLE,10KAIC
INDUSTRIAL TYPE MCCB AIR CONDITIONING UNIT: (FOR PROVISION)

LIGHTING & POWER PANEL, DP2 CIRCUIT # 2, LIGHTING: I = 1800/ 230 = 7.82 A
= 7.82 x 1.25
I = 1200/ 230 = 5.21 A = 9.775 A
= 5.21 x 1.5
= 7.815 A THEREFORE, AS PER PEC MINIMUM REQUIREMENT
USE NOT LESS THAN 5.5MM2 THHN/THWN STRANDED WIRE
THEREFORE, PEC REQUIREMENT MINIMUM
CIRCUIT BREAKER , USE 15AT,50AF,2POLE,10KAIC MCCB FOR GROUND WIRE:

LIGHTING & POWER PANEL, DP2 CIRCUIT # 4,CONVENIENCE OUTLET: Article 2.50. Table 2.50.6.13 Minimum Size Equipment Grounding
Conductors for Grounding Raceway and Equipment
I = (1620/ 230) = 7.04 A
= 7.04 x 150% Full Continuous Load FOR CONDUIT SIZING:
= 10.56 A EMERGENCY LIGHT DETAIL SMOKE/ HEAT DETECTOR SUSPENDED CEILING MOUNTED
Article 3.0 Table 3.0.1.1© Metric Designator and Trade Size
THEREFORE, PEC REQUIREMENT
CIRCUIT BREAKER, USE 20AT/20AF, 2POLE,10KAIC MCCB

LIGHTING & POWER PANEL, AIR CONDITIONING UNIT: (FOR PROVISION)

I = 1800/ 230 = 7.82 A


= 7.82 x 1.5 ASSORTED DETAILED DRAWINGS
= 11.73 A N D S

THEREFORE, PEC REQUIREMENT MINIMUM


CIRCUIT BREAKER, USE 30AT/50AF,2POLE,10KAIC MCCB

DESIGNED :

PROFESSIONAL ELECTRICAL ENGINEER


DATE:

PDS - BUK3RD : 2 0 2 3
DRAWN :
PROJECT AND LOCATION : SHEET CONTENTS : SUBMITTED : RECOMMENDING FOR APPROVAL : APPROVED : SET NO. SHT. NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS ROMY S. BANTOLIO
ELECTRICAL ANALYSIS ENGINEER I
REGIONAL OFFICE X PDS
BUKIDNON THIRD DISTRICT ENGINEERING OFFICE
CONSTRUCTION OF ELECTRICAL ASSORTED DETAILED DATE:
CHECKED / REVIEWED : E
DICKLUM, MANOLO FORTICH, BUKIDNON MULTI-PURPOSE BUILDING RYAN CAESAR B. FERNANDEZ ROMULO F. ANDRES, AEr. RONALDO C. PAHANG, AEr. E-5
BARANGAY MAMPAYAG, MANOLO FORTICH, BUKIDNON MCKENLY B. HONG ENGINEER II ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER 2023
ENGINEER II OIC - PLANNING AND DESIGN SECTION, CHIEF
DATE: DATE: DATE: DATE:
ILLUMINATION LEVEL LIGHTNING ROD ARRESTER

LIGHTNING ROD
MOUNTING BASE

EARTH DOWN CONDUCTOR


LED LUMENS CHART (High Voltage Shielded Cable)

LED LAMP
EQUIVALENT LUMENS F F F F
WATTAGE

15 1400 W1 W2 W2 W2 D 3

32 2600
F F F F

CONDUCTOR STRAP

MINSURO
ADMINISTRATIVE D 1 W2 W2 LIGHTNING STRIKE
BUILDING RECORDER
BARANGAY MINDAGAT, MALITBOG, BUKIDNON

GROUND ROD CLAMP


GROUND FLOOR GROUND ROD CLAMP
EARTH ENHANCING COMPOUND EARTH ENHANCING COMPOUND

ROOM NUMBER OF LIGHTING ILLUMINATION GROUND ROD GROUND ROD


AREA DESCRIPTION AREA LAMPS LUMENS LEVEL
m2 15W 32W EQUIVALENT (LUX)

1 8.2 1 0 1400 170.73


PORCH

18.61
GROUNDING PROTECTION SYSTEM
2 WAITING AREA 4 0 5600 300.91 N D S
LIGHTNING PROTECTION SYSTEM
3 TREASURER'S OFFICE 10.6 3 0 4200 396.22 N D S

4 SECRETARY OFFICE 10.6 3 0 4200 396.22


5 BRGY. CAPTAIN OFFICE 14.84 0 3 7800 525.60
6 PANTRY 4.62 1 0 1400 303.03

7 STORAGE 2.64 1 0 1400 530.30


IMPORTANT
8 PWD COMFORT ROOM 3.22 1 0 1400 434.78

9 RAMP 9.98 2 0 2800 280.56

9 TOILET 2.3 1 0 1400 608.69

SECOND FLOOR
ROOM NUMBER OF LIGHTING ILLUMINATION
AREA DESCRIPTION AREA LAMPS LUMENS LEVEL
m2 15W 32W EQUIVALENT (LUX)

1 OFFICE 1 34.45 9 0 12600 365.74

2 CONFERENCE ROOM 22.50 6 0 8400 373.33

3 OFFICE 2 6.76 2 0 2800 414.20

4 COMFORT ROOM 4 2 0 2800 700

5 STAIRWAY 8.05 2 0 2800 347.82

7 FIRE EXIT 6.37 2 0 2800 439.56

COMPUTATION FORMULA:

LIGHTING LUMENS = NUMBER OF LAMPS x EQUIVALENT LUMENS PER LAMP

LIGHTING LUMENS
ILLUMINATION LEVEL = _____________________ LIGHTNING ARRESTER DETAILS
ROOM AREA N D S
LIGHTNING PROTECTION GROUNDING DETAILS
N D S

DESIGNED :

PROFESSIONAL ELECTRICAL ENGINEER


DATE:

PDS - BUK3RD : 2 0 2 3
DRAWN :
PROJECT AND LOCATION : SHEET CONTENTS : SUBMITTED : RECOMMENDING FOR APPROVAL : APPROVED : SET NO. SHT. NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS ROMY S. BANTOLIO
LIGHTNING PROTECTION SYSTEM PLAN ENGINEER I
REGIONAL OFFICE X PDS
BUKIDNON THIRD DISTRICT ENGINEERING OFFICE
CONSTRUCTION OF AND LAY-OUT
LIGHTNING ARRESTER DETAILS
DATE:
CHECKED / REVIEWED : E
DICKLUM, MANOLO FORTICH, BUKIDNON MULTI-PURPOSE BUILDING RYAN CAESAR B. FERNANDEZ ROMULO F. ANDRES, AEr. RONALDO C. PAHANG, AEr. E-6
BARANGAY MAMPAYAG, MANOLO FORTICH, BUKIDNON MCKENLY B. HONG ENGINEER II ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER 2023
ENGINEER II OIC - PLANNING AND DESIGN SECTION, CHIEF
DATE: DATE: DATE: DATE:
ELECTRONICS
A B C D A B C D
2.43 11.50 11.50
1.13
1.20 1.23 2.50 3.50 5.50 2.50 3.50 5.50

1 1 LEGEND:

0.60
1.60

1.60
TO
FACP

3.50
-CALL POINT/MANUAL PULL STATION

3.50
to Fire Alarm

1.90
Control Panel

1.90
-CONVENTIONAL SMOKE DETECTOR

7.00
B
0.92
7.00

7.00
2

7.00
to Fire Alarm 2 M A
CON
6.08

M
B
Control Panel

U P

5.64
TO
2.30

A
DN
PEBBLES
FACP -CONVENTIONAL HEAT DETECTOR
R A M P

3.50
CON

3.50

3.50
-SPEAKER
1.20

3 3 -4X4 JUNCTION BOX


0.50 1.30
1.88

1.88
-FIRE ALARM BELL/SOUNDER STROBE

-MANUAL PUSH BOTTON


3.75
2.50 3.50 5.50 3.75
11.50 2.50 6.25 2.75
11.50

GROUND FLOOR FIRE ALARM SYSTEM PLAN SECOND FLOOR FIRE ALARM SYSTEM PLAN
N D S N D S

17 - 1.25 mm² TF Wire


in 25 mm. dia. EMT
2nd flr. CEILING LN.
eolr
SD SD

3 - 1.25 mm² TF Wire


in 15 mm. dia. EMT
Mezzanine CEILING LN.
PB

B
A

ZONE 1D

4 - 1.25 mm² TF Wire


in 15 mm. dia. EMT
Ground Floor
SD

FACP
3 ZONES
MANUAL STATION & BELL/ HORN MOUNTING DETAIL
FIRE ALARM RISER DIAGRAM
FDAS SYSTEM LAY-OUT N D S
ELPD-18

N D S

DESIGNED :
FIRE ALARM ASSORTED DETAILS
N D S

PROFESSIONAL ELECTRICAL ENGINEER


DATE:

PDS - BUK3RD : 2 0 2 3
DRAWN :
PROJECT AND LOCATION : SHEET CONTENTS : SUBMITTED : RECOMMENDING FOR APPROVAL : APPROVED : SET NO. SHT. NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS LOCATION MAP ROMY S. BANTOLIO
ENGINEER I
REGIONAL OFFICE X GROUND FLOOR FIRE ALARM SYSTEM PLAN PDS
BUKIDNON THIRD DISTRICT ENGINEERING OFFICE
CONSTRUCTION OF SECOND FLOOR FIRE ALARM SYSTEM PLAN
DATE:
CHECKED / REVIEWED : E
DICKLUM, MANOLO FORTICH, BUKIDNON MULTI-PURPOSE BUILDING FDAS SYSTEM LAY-OUT PLAN
RYAN CAESAR B. FERNANDEZ ROMULO F. ANDRES, AEr. RONALDO C. PAHANG, AEr. EcE-1
BARANGAY MAMPAYAG, MANOLO FORTICH, BUKIDNON
FIRE ALARM RISER DIAGRAM
FIRE ALARM ASSORTED DETAILS MCKENLY B. HONG ENGINEER II ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER 2023 2
ELECTRICAL LEGEND & SYMBOLS ENGINEER II OIC - PLANNING AND DESIGN SECTION, CHIEF
DATE: DATE: DATE: DATE:
MECHANICAL
A B C D A B C D LEGEND:
11.50
2.43 11.50 1.13 14 WATTS LED BULB W/ 6" DIA. PORCELAIN HOLDER PANELBOARD, MARKED AS DP & LPP
1.20 1.23 2.50 3.50 5.50 2.50 3.50 5.50 2 X 16 WATTS LED TUBE DAYLIGHT W/ REFLECTOR
HOUSING BOX TYPE. CKT. BREAKER, RATINGS AS INDICATED
1 1 14W LED DAYLIGHT 4" DIA. W/
OUTDOOR LIGHTING FIXTURE DUPLEX CONVENIENCE OUTLET, 3-PRONG OR

0.60
1.60

1.60
GROUNDING TYPE 15AMPS, 240 VOLT
5 Sa SINGLE POLE SWITCH

3.50
1-ACCU

3.50
1.5HP DP1 EL EMERGENCY LAMP, SIMPLEX CONVENIENCE
Sab DOUBLE SWITCH, 2 SINGLE POLE SWITCHES
1.90 OUTLET, GROUNDING TYPE IS 15AMPS, 240 V

1.90
ON ONE-GANG PLATE
THREE SINGLE POLE SWITCHES ON CEILING MOUNTED EXHAUST FAN
Sabc

7.00

7.00
7.00

7.00
2 2 ONE-GANG SWITCH PLATE
6.08

1-ACCU 6
EMERGENCY LIGHT OUTLET
U P
S 3W

5.64
1.0HP DP1
DN THREE WAY SWITCH EO
2.30

R A M P PEBBLES

3.50
3.50

3.50
RACEWAY CONDUIT CONCEALED IN CEILING
1-ACCU 7 RACEWAY CONDUIT CONCEALED UNDER FLOOR
DP1
1.20

1.5HP
1-ACCU 1-ACCU
1.5HP 0.5HP

3 3
0.50 1.30
1.88

1.88
5 6
DP2 DP2

3.75
2.50 3.50 5.50 3.75
11.50 2.50 6.25 2.75
11.50

GROUND FLOOR AIR-CONDITION LAY-OUT SECOND FLOOR AIR-CONDITION LAY-OUT


N D S N D S

AIR CONDITION CALCULATION


GROUND FLOOR: SECOND FLOOR: SECOND FLOOR:
GROUND FLOOR: GROUND FLOOR:
DP1 (7): DP2 (5): DP2 (6):
DP1 (5): DP1 (6):
ROOM SIZE=10.6 sq.m ROOM SIZE= 22.5 sq.m ROOM SIZE= 8.415 sq.m
ROOM SIZE=14.84 sq.m OOM SIZE=10.6 sq.m
REQUIRED COOLING CAPACITY: REQUIRED COOLING CAPACITY: REQUIRED COOLING CAPACITY:
REQUIRED COOLING CAPACITY: REQUIRED COOLING CAPACITY:
=(Room size x 500) x (110%) =(Room size x 500) x (110%) =(Room size x 500) x (110%)
=(Room size x 500) x (110%) =(Room size x 500) x (110%)
+ additional occupant + lighting + additional occupant + lighting + additional occupant + lighting
+ additional occupant + lighting +additional occupant + lighting
=(10.6 x 500) x (1.10) + (45x3.6) =(22.5 x 500) x (1.10) + (84 x3.6) =(8.415 x 500) x (1.10) + (30 x3.6)
=(14.84 x 500) x (1.10) + (96 x3.6) =(10.6 x 500) x (1.10) + 45 x3.6) DETAIL "A"
= 5992 kJ/h = 12,677.4 kJ/h = 4,736.25 kJ/h
= 8,507.6 kJ/h =5992 kJ/h
RECOMMENDED MODEL: 1.0 HP RECOMMENDED MODEL: 1.5 HP RECOMMENDED MODEL: 0.5 HP
RECOMMENDED MODEL: 1.5 HP RECOMMENDED MODEL: 1.0 HP

180

100

INSTALLATION OF REFRIGERANT EXPOSED PIPES INSTALLATION OF SPLIT TYPE AIR CONDITION


REFRIGERANT PIPES THRU REINFORCED CONCRETE

DESIGNED :
ASSORTED DETAILED DRAWINGS
N D S

PROFESSIONAL ELECTRICAL ENGINEER


DATE:

PDS - BUK3RD : 2 0 2 3
DRAWN :
PROJECT AND LOCATION : SHEET CONTENTS : SUBMITTED : RECOMMENDING FOR APPROVAL : APPROVED : SET NO. SHT. NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS ROMY S. BANTOLIO
LOCATION MAP ENGINEER I
REGIONAL OFFICE X PDS
BUKIDNON THIRD DISTRICT ENGINEERING OFFICE
CONSTRUCTION OF GROUND FLOOR AIR-CONDITION LAYOUT
SECOND FLOOR AIR-CONDITION LAYOUT
DATE:
CHECKED / REVIEWED : M
DICKLUM, MANOLO FORTICH, BUKIDNON MULTI-PURPOSE BUILDING ELECTRICAL LEGEND & SYMBOLS
AIR-CONDITION CALCULATION
RYAN CAESAR B. FERNANDEZ ROMULO F. ANDRES, AEr. RONALDO C. PAHANG, AEr. M-1 2
BARANGAY MAMPAYAG, MANOLO FORTICH, BUKIDNON MCKENLY B. HONG ENGINEER II ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER 2023
ENGINEER II OIC - PLANNING AND DESIGN SECTION, CHIEF
DATE: DATE: DATE: DATE:
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
REGIONAL OFFICE X
BUKIDNON 3RD DISTRICT ENGINEERING OFFICE
DICKLUM, MANOLO FORTICH, BUKIDNON

C.Y. 2023 PROJECT


DETAILED ENGINEERING DESIGN PLAN FOR
CONSTRUCTION OF MULTI-PURPOSE BUILDING
BARANGAY MAMPAYAG, MANOLO FORTICH BUKIDNON

SUBMITTED: RECOMMENDED: APPROVED:

RYAN CAESAR B. FERNANDEZ ROMULO F. ANDRES, AseanEngr.. RONALDO C. PAHANG, AEr.


OIC - PLANNING AND DESIGN SECTION CHIEF ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER

DATE: DATE DATE


ARCHITECTURAL
P E R S P E C T I V E
TABLE OF CONTENTS
ARCHITECTURAL STRUCTURAL PLUMBING ELECTRICAL ELECTRONICS
A-1 PERSPECTIVE, TABLE OF CONTENTS S-1 STRUCTURAL NOTES P-1 LOCATION MAP E-1 GENERAL NOTES EO-1 LOCATION MAP
A-2 DISTRICT MAP S-2 SPLICING REQUIREMENTS OF REINFORCING BARS "Ls" OR "Ld" PLUMBING SPEC'S LEGEND AND SYMBOLS GROUND FLOOR FIRE ALARM SYSTEM PLAN
VICINITY MAP AND OTHER IMPORTANT NOTES WATERLINE PLUMBING LAYOUT POWER RISER DIAGRAM SECOND FLOOR FIRE ALARM SYSTEM PLAN
LOCATION PLAN S-3 TYPICAL MASONRY ELEVATION W/ LINTEL BEAMS & STIFFINER SANITARY PLUMBING LAYOUT E-2 LOCATION MAP FDAS SYSTEM LAY-OUT PLAN
A-3 LOCATION MAP COLUMNS REFLECTING REINF. STEEL BARS AND LEGENDS GROUND FLOOR LIGHTING LAYOUT FIRE ALARM RISER DIAGRAM
SITE DEVELOPMENT PLAN SECOND FLOOR LIGHTING LAYOUT FIRE ALARM ASSORTED DETAILS
OTHER IMPORTANT NOTES P-2 LOCATION MAP
A-4 GROUND FLOOR PLAN ASSORTED DETAILED DRAWINGS ELECTRICAL LEGEND & SYMBOLS
S-4 FOUNDATION PLAN S-11 RAMP DETAILS PLUMBING SPEC'S
SECOND FLOOR PLAN ELECTRICAL LEGEND & SYMBOLS
ELEVATIONS UPPER BEAM ISOMETRIC VIEW E-3 GROUND FLOOR POWER LAYOUT
FLOOR FINISHES LOWER BEAM LEGENDS SECOND FLOOR POWER LAYOUT
SCHEDULE OF FINISHES S-5 FOUNDATION PLAN P-3 LOCATION MAP GROUNDING DETAILED DRAWINGS
A-5 SECTIONS TYPICAL FOOTING PLAN PLUMBING SPEC'S ELECTRICAL LEGEND & SYMBOLS
SCHEDULE OF DOORS TYPICAL FOOTING SECTION SEPTIC TANK DETAIL, E-4 ELECTRICAL SCHEDULE OF LOADS MECHANICAL
SCHEDULE OF WINDOWS COLUMN SCHEDULE GREASE TRAP DETAIL SINGLE LINE DIAGRAM
SCHEDULE OF FINISHES FOOTING SCHEDULE E-5 ELECTRICAL ANALYSIS M-1 LOCATION MAP
CATCH BASIN DETAIL
A-6 REFLECTED CEILING PLANS ELECTRICAL ASSORTED DETAILED GROUND FLOOR AIR-CONDITION LAYOUT
CEILING DETAILS SECTION
S-6 FOUNDATION PLAN P-TRAP DETAIL
E-6 LIGHTNING PROTECTION SYSTEM PLAN SECOND FLOOR AIR-CONDITION LAYOUT
PERSPECTIVE(CEILING DETAILS) FOOTING TIE BEAM DETAILS AND LAY-OUT ELECTRICAL LEGEND & SYMBOLS
A-7 ROOF PLANS WALL FOOTING DETAILS LIGHTNING ARRESTER DETAILS AIR-CONDITION CALCULATION
ROOF SECTION DETAILS S-7 ROOF FRAMING PLAN
A-8 RAMP PLAN S-8 SECOND FLOOR BEAM PLAN
RAMP SECTION DETAILS
MAIN STAIR PLAN
SCHEDULE OF BEAM
MAIN STAIR SECTION DETAILS BEAM DETAILS
A-9 FIRE ESCAPE STAIR PLAN STEEL DECK FRAMING PLAN
FIRE ESCAPE ELEVATIONS S-9 MAIN STAIRS DETAILS
FIRE ESCAPE DETAILS
FIRE ESCAPE STAIR DETAILS
AUXILLIARY
A-10 BALCONY RAILING DETAILS
PWD/MALE TOILET PLAN DETAILS
S-10 ROOF DETAILS AUX-1 STANDARD PROJECT BILLBOARD
GIRT DETAILS SAFETY SIGNAGES
FASCIA FRAME DETAILS DESIGNED ARCHITECTURAL :
S-10 ROOF DETAILS
GIRT DETAILS JOVEL K. PANGAN
FASCIA FRAME DETAILS ARCHITECT II
DATE:

PDS - BUK3RD : 2 0 2 3
DRAWN :
PROJECT AND LOCATION : SHEET CONTENTS : SUBMITTED : RECOMMENDING FOR APPROVAL : APPROVED : SET NO. SHT. NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS ROSANNO GABRIEL D. SANICO
ARCHITECT I
REGIONAL OFFICE X PERSPECTIVE PDS
BUKIDNON THIRD DISTRICT ENGINEERING OFFICE
CONSTRUCTION OF TABLE OF CONTENTS
DATE:
CHECKED / REVIEWED : A
DICKLUM, MANOLO FORTICH, BUKIDNON MULTI-PURPOSE BUILDING RYAN CAESAR B. FERNANDEZ ROMULO F. ANDRES, AEr. RONALDO C. PAHANG, AEr. A-1
BARANGAY MAMPAYAG, MANOLO FORTICH, BUKIDNON MCKENLY B. HONG ENGINEER II ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER 2023
ENGINEER II OIC - PLANNING AND DESIGN SECTION, CHIEF
DATE: DATE: DATE: DATE:
13.93

A B C D
A
A B C D 3 2 1
11.50
2.50 3.50 5.50 11.50
2.43 9.95
1.20 1.23 4.65 9.50

W4 W3 W2 W2 1.00 1.00 1.00

ROOF APEX LINE ROOF APEX


1
ROOF APEX LINE ROOF APEX

1.60
2% FT-1
PWD/MALE SL
OP +0.40m
ET
BRGY.

1.51
CR

1.44
OF
.D.
FT-3 PANTRY

1.30
FT-3
D5
D 3 CAPTAIN
+0.40m
FT-1
B 1.90 +0.40m OFFICE W2 TOP OF ROOF BEAM TOP OF ROOF BEAM
CEILING LINE CEILING LINE
D 4 EXIT
D2 F F F F 1.15

1.21

BOUNDARY LINE

BOUNDARY LINE
WAITING

3.00

3.00
7.00

2 AREA W1
D6 1 1.00 W2 W2 W2 W2 W2

8.45

8.45
FT-1 SECRETARY
U P
2
+0.40m D2
FT-1
2.30
4.90

3
PEBBLES FT-3

1.00
R A M P 4
+0.40m
-0.35m
F F F F

6.40

6.40
FEMALE 5
W4 CR
6
W2 CEILING LINE
FT-4
RECORD CEILING LINE 800mm Ø BRGY SEAL
FT-1 TREASURER IN ALUMINUM FINISH
+0.40m
KEEPER
1.20

3.00

3.00
3D LETTER SIGNAGE
IN ALUMINUM FINISH
STORAGE D7
D1
1.20
MINSURO
ADMINISTRATIVE D 1 W2 W2 W2 W2
3 BUILDING
PORCH W2 W2 BARANGAY MINDAGAT, MALITBOG, BUKIDNON

0.90
1.88

FT-2

0.33

0.40
+0.40m FINISH FLOOR LINE/ TOP LINTEL BEAM-2 FINISH FLOOR LINE/ TOP LINTEL BEAM-2

0.40
1

0.50
2

3.75
2.50 3.50 5.50
11.50
15.00
FRONT ELEVATION RIGHT-SIDE ELEVATION
SCALE: 1:100 MTRS. SCALE: 1:100 MTRS.

GROUND FLOOR PLAN


SCALE: 1:100 MTRS. 1 2 3 D C B A

11.50

A B C D 4.65

A ROOF APEX
9.50

ROOF APEX LINE


1.00

1.13 11.50 ROOF APEX ROOF APEX LINE


2.50 3.50 5.50

1.44

1.44
1.25 1.25
TOP OF ROOF BEAM TOP OF ROOF BEAM

W4 W4 W2 W2 W2 CEILING LINE CEILING LINE

1 1.15
1.00
1.30 0.60

BOUNDARY LINE

BOUNDARY LINE
FEMALE

3.00
MALE

3.00
1.60

CR CR

8.05
FT-3
-0.05m
FT-3
-0.05m
D 3 W2 W2 W2 1.00

D6 D6
OFFICE W2
B

1.00

1.00
6.00

6.00
FT-2
D 3 EXIT
1.90

-0.05m

0.30

0.30
17 DN CEILING LINE
16
CEILING LINE
15
7.00

3.00

3.00
14
2 13
16
15 1 D2 D2 D2 1.20
12
14 2 W2 W2
11
DN
2.30
4.90

13 3
10
12 4
9

0.90
11 5
8

7
10 6 CONFERENCE OFFICE W2
FINISH FLOOR LINE/ TOP LINTEL BEAM-2 FINISH FLOOR LINE/ TOP LINTEL BEAM-2

0.40
6 9 7

5
1.20

4
8
3

3 1

W1 W2 W2 W2
1.88

3.75
LEFT-SIDE ELEVATION REAR ELEVATION
SCALE: 1:100 MTRS. SCALE: 1:100 MTRS.
2.50 3.50 2.75 2.75
11.50
15.00

FLOOR FINISH LEGEND:


FT-1 GLAZED 0.60M X 0.60MFLOOR TILES

FT-2 UNGLAZED 0.60M X 0.60M FLOOR TILES

SECOND FLOOR PLAN FT-3 UNGLAZED 0.40M X 0.40M FLOOR TILES DESIGNED ARCHITECTURAL :
SCALE: 1:100 MTRS. FT-4 CONCRETE FLOOR W/ GROOVE
JOVEL K. PANGAN
ARCHITECT II
DATE:

PDS - BUK3RD : 2 0 2 3
DRAWN :
PROJECT AND LOCATION : SHEET CONTENTS : SUBMITTED : RECOMMENDING FOR APPROVAL : APPROVED : SET NO. SHT. NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS GROUND FLOOR PLAN ROSANNO GABRIEL D. SANICO
ARCHITECT I
REGIONAL OFFICE X PDS
BUKIDNON THIRD DISTRICT ENGINEERING OFFICE
CONSTRUCTION OF SECOND FLOOR PLAN DATE:
CHECKED / REVIEWED : A
DICKLUM, MANOLO FORTICH, BUKIDNON MULTI-PURPOSE BUILDING ELEVATIONS
FLOOR FINISHES
RYAN CAESAR B. FERNANDEZ ROMULO F. ANDRES, AEr. RONALDO C. PAHANG, AEr. A-4
BARANGAY MAMPAYAG, MANOLO FORTICH, BUKIDNON MCKENLY B. HONG ENGINEER II ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER 2023
ENGINEER II OIC - PLANNING AND DESIGN SECTION, CHIEF
SCHEDULE OF FINISHES DATE: DATE: DATE: DATE:
1 2 3 A B C D

11.50
7.00 9.95
4.65
9.50
1.00 1.00 1.00

ROOF APEX ROOF APEX LINE

ROOF APEX ROOF APEX LINE

1.51
1.44

E
SEE TRUSS DETAILS

N
1.20
TOP OF ROOF BEAM TOP OF ROOF BEAM

I
CEILING LINE CEILING LINE

I
1.15

L
BOUNDARY LINE

BOUNDARY LINE
3.00

3.00
CEILING HT. 2.60

Y
W2 W2 D6 D6 W2 W2 W2

Y
1.00

8.45

8.45
R

R
1.00
OFFICE CONFERENCE ROOM OFFICE OFFICE

A
6.40

6.40

A
0.30
CEILING LINE

D
CEILING LINE

N
3.00

3.00
U
CEILING HT. 2.60

U
1.20

D2 D1 D5 D3 W2 W2

O
0.90
B

B
PANTRY WAITING AREA ENTRY WAITING AREA BRGY. CAPTAIN OFFICE

0.40

0.40
FINISH FLOOR LINE FINISH FLOOR LINE

0.40
NATURAL GROUND LINE NATURAL GROUND LINE

CROSS SECTION(A) LONGITUDINAL SECTION(B)


SCALE: 1:100 MTRS. SCALE: 1:100 MTRS.

2.15
2.00
0.50
1.80 1.80 0.60

0.60
1.20
2.65
2.50

1.60
2.10

2.10

2.10
1.50
0.90
0.50
FINISHED FLOOR LINE
SECOND FLOOR LINE

W1 W2 W4 W5
AWNING WINDOW - 1 SET SLIDING GLASS WINDOW - 14 SETS SLIDING GLASS WINDOW - 1 SET SLIDING GLASS WINDOW - 4SET

6mm THICK TINTED GLASS 6mm THICK TINTED GLASS 6mm THICK TINTED GLASS 6mm THICK TINTED GLASS
AWNING WINDOW ON ANALOK SLIDING WINDOW ON ANALOK SLIDING WINDOW ON ANALOK SLIDING WINDOW ON ANALOK
FRAMING POWDER COATED FRAMING POWDER COATED FRAMING POWDER COATED FRAMING POWDER COATED

1.80 0.80 0.90 0.90 0.60


0.90 0.90 0.80

0.60
2.15

2.15

2.15

2.15

2.15

2.15
2.10

2.10

2.10

2.10

2.10

2.10
STAINLESS STEEL STAINLESS STEEL

1.30
KICKING PLATE KICKING PLATE

1.25
FINISHED FLOOR LINE

D 1 D 2 D 3 D 4 D 5 D 6 D 7
MAIN DOOR- 1 SET OFFICE- 5 SETS PANTRY/EXIT DOOR - 2 SETS EXIT DOOR(GF) - 1 SET PWD/MALE CR - 1 SET MALE/FEMALE CR - 3 SETS STORAGE - 1 SET
6mm THICK TINTED GLASS 6mm THICK TINTED GLASS HOLLOW CORE FLUSH TYPE
SOLID WOOD PANEL SWING DOOR ON SOLID WOOD PANEL SWING DOOR ON SOLID WOOD PANEL SWING DOOR ON FLUSH DOOR ON DOOR JAMB(COATED
DOUBLE SWING DOOR ON ANALOK SWING DOOR ON ANALOK FRAMING SWING DOOR ON
DOOR JAMB(COATED WITH PAINT) DOOR JAMB(COATED WITH PAINT) DOOR JAMB(COATED WITH PAINT) WITH PAINT)
FRAMING POWDER COATED POWDER COATED DOOR JAMB(COATED WITH PAINT)

SCHEDULE OF DOORS AND WINDOWS


SCALE: 1:50 MTRS. DESIGNED ARCHITECTURAL :

JOVEL K. PANGAN
ARCHITECT II
DATE:

PDS - BUK3RD : 2 0 2 3
DRAWN :
PROJECT AND LOCATION : SHEET CONTENTS : SUBMITTED : RECOMMENDING FOR APPROVAL : APPROVED : SET NO. SHT. NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS ROSANNO GABRIEL D. SANICO
ARCHITECT I
REGIONAL OFFICE X PDS
BUKIDNON THIRD DISTRICT ENGINEERING OFFICE
CONSTRUCTION OF SECTIONS DATE:
CHECKED / REVIEWED : A
DICKLUM, MANOLO FORTICH, BUKIDNON MULTI-PURPOSE BUILDING SCHEDULE OF DOORS
AND WINDOWS
RYAN CAESAR B. FERNANDEZ ROMULO F. ANDRES, AEr. RONALDO C. PAHANG, AEr. A-5
BARANGAY MAMPAYAG, MANOLO FORTICH, BUKIDNON MCKENLY B. HONG ENGINEER II ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER 2023
ENGINEER II OIC - PLANNING AND DESIGN SECTION, CHIEF
DATE: DATE: DATE: DATE:
A B C D

A B C D
11.35 11.35
1.10 1.10 8.80
1.10 1.10 8.80
12MM X 38MM X 5MM X 0.80MM THK, 0.60
1.20
12MM X 38MM X 5MM X 0.80MM THK, METAL FURRING CHANNEL(CEILING JOIST) 0.60
METAL FURRING CHANNEL(CEILING JOIST) AT 1200MM ON CENTER
AT 1200MM ON CENTER (SEE BLOW-UP DETAIL) 0.60
(SEE BLOW-UP DETAIL)
1 1 0.60 1.20

1.45

1.45

2.79
3.35
1.75

1.75
17

16

15
6.85

6.85

6.85

6.85
14
2 13
16
15 1
2
12

U P
14 2
11
DN 13 3

2.10

R A M P
10
12 4

4.00
9
11 5

3.35
3.30

7
10 6
9 7
FT-4
1. 0
6

5
20 0.6
4
8

1.25
3

2
0
3 1
3 0.6

0
1. 0.6
20
2.35 6.10 2.60 2.35 3.35 5.35 0
11.35 11.35 0.6

NOT TO SCALE

GROUND FLOOR SECOND FLOOR


REFLECTED CEILING PLAN REFLECTED CEILING PLAN
SCALE: 1:100 MTRS. SCALE: 1:100 MTRS. PERPECTIVE(CEILING)
SCALE: NTS

1.20
0.10

0.05

0.05
0.10

0.10
0.30
A B C D A B C D

0.10
4.65 9.95
1.00 2.65 1.00 PREFORMED PRE-PAINTED G.I. GUTTER 8.95 1.00
0.25

0.25
PREFORMED PRE-PAINTED G.I. GUTTER PREFORMED PRE-PAINTED G.I. GUTTER

1.20
CEILING VENT(SEE DETAILS)
0.90

0.90
1 1

0.10
CEILING VENT(SEE DETAILS)
PRE-PAINTED ROOFING G.I FLASHING
PRE-PAINTED ROOFING G.I FLASHING

17 12MM X 38MM X 5MM X 0.80MM THK, 17

16 METAL FURRING CHANNEL(CEILING JOIST) 16


12MM X 38MM X 5MM X 0.80MM THK,
0.10
15
AT 1200MM ON CENTER 15
METAL FURRING CHANNEL(CEILING JOIST)
7.15

7.15
9.50

9.50
2
14
(SEE BLOW-UP DETAIL) 2
14

13
16
15 1
13
16
15 1
AT 1200MM ON CENTER
(SEE BLOW-UP DETAIL)
0.30
12
14 2
12
14 2
ANGLE 20 X 20 X 2 ATTACHED TO

A B
11

10
DN 13 3
11

10
DN 13 3 CHB WALL Q/ TOKS SCREWS @ 600mm
12 4 12 4
9 9

8
11 5
8
11 5 ROD SUSPENSION HANGER
10 6 10 6
7
9 7
7
9 7
WITH ADJUSTMENT SPRING
6 6
CEILING VENT(SEE DETAILS)
5

4
5

4
CEILING VENT(SEE DETAILS) METAL DOUBLE FURRING CHANNEL(NAILER)
8 8
3 3 12mm x 38mm x 5m x 0.8mm THK. AT 400mm O.C.
0.25 0.25
2 2

3 1
3 1 METAL CARRYING CHANNEL(CEILING JOIST)
12mm x 38mm x 5m x 0.8mm THK. @ 1200mm
1.20

1.20
4.5MM THK. FIBER CEMENT BOARD
IN 38mm x 38mm x 6mm
TOP OF BEAM
ANGLE BAR FASCIA FRAME

0.10 0.35

0.10 0.35
4.5MM THK. FIBER CEMENT BOARD
IN 38mm x 38mm x 6mm
ANGLE BAR FASCIA FRAME
CEILING LINE
B-1
UPPER ROOF CEILING EAVES B-1
LOWER ROOF CEILING EAVES
CHB WALL
REFLECTED CEILING PLAN REFLECTED CEILING PLAN
4.5MM THK. FIBER CEMENT CEILING BOARD

SCALE: 1:100 MTRS.


SCALE: 1:100 MTRS.
CEILING DETAIL(SECTION)
DESIGNED ARCHITECTURAL :

JOVEL K. PANGAN
ARCHITECT II
DATE:

PDS - BUK3RD : 2 0 2 3
DRAWN :
PROJECT AND LOCATION : SHEET CONTENTS : SUBMITTED : RECOMMENDING FOR APPROVAL : APPROVED : SET NO. SHT. NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS ROSANNO GABRIEL D. SANICO
REFLECTED CEILING PLANS ARCHITECT I
REGIONAL OFFICE X PDS
BUKIDNON THIRD DISTRICT ENGINEERING OFFICE
CONSTRUCTION OF CEILING DETAILS SECTION
DATE:
CHECKED / REVIEWED : A
DICKLUM, MANOLO FORTICH, BUKIDNON MULTI-PURPOSE BUILDING PERSPECTIVE(CEILING DETAILS) RYAN CAESAR B. FERNANDEZ ROMULO F. ANDRES, AEr. RONALDO C. PAHANG, AEr. A-6
BARANGAY MAMPAYAG, MANOLO FORTICH, BUKIDNON MCKENLY B. HONG
ENGINEER II
ENGINEER II
ENGINEER II
OIC - PLANNING AND DESIGN SECTION, CHIEF
ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER 2023
DATE: DATE: DATE: DATE:
A B C D 3 2 1
4.65
1.00 2.65 1.00

0.25
PREFORMED PRE-PAINTED G.I. GUTTER
3" Ø DOWNSPOUT 4.5MM THK. FIBER CEMENT BOARD IN 38mm x
38mm x 6mm ANGLE BAR FASCIA FRAME 9.31 Hi-Rib PRE-PAINTED ROOFING G.I SHEET

0.90

0.40
1 SEE TRUSS DETAILS
Hi-Rib PRE-PAINTED ROOFING G.I SHEET

0.
PRE-PAINTED ROOFING G.I FLASHING

55
0.40mm x 2.44 mm
PRE PAINTED SPANISH GUTTER

2.05
17

16

15 0.25

1.51
7.15
9.50
14
2 13
16
15 1

0.30
12
14 2
11

10

9
SLOPE
DN 13
12
3
4

7
11
10
5
6
4.5MM THK. FIBER
6

5
9 7
CEMENT FACIA BOARD
4

3
8
TOP OF BEAM 3" Ø PVC
2

3 ELBOW 90°
RB RB
1

0.90
1.20

3"Ø PVC PIPE DOWN SPOUT

4.5MM THK. FIBER CEMENT CEILING BOARD IN 4-10mmØ x 300mm


UPPERANCHOR
ROOF BOLT
METAL CARRYING CHANNEL(CEILING JOIST) W/ NUTS and WASHERS ON
12mm x 38mm x 5m x 0.8mm THK. @ 1200mm 12mm THK. BASE PLATE
UPPER ROOF
ROOF PLAN
SCALE: 1:100 MTRS. ROOF SECTION
SCALE: 1:30 MTRS.

A B C D
3 2 1
9.95
8.95 1.00

0.25
PREFORMED PRE-PAINTED G.I. GUTTER
3" Ø DOWNSPOUT
9.31
0.90
1
Hi-Rib PRE-PAINTED ROOFING G.I SHEET
4.5MM THK. FIBER CEMENT BOARD IN 38mm x
38mm x 6mm ANGLE BAR FASCIA FRAME Hi-Rib PRE-PAINTED ROOFING G.I SHEET

0.89 0.40
PRE-PAINTED ROOFING G.I FLASHING
SEE TRUSS DETAILS
17

0.
16

15

1.44

55
0.40mm x 2.44 mm
7.15
9.50

14
2 13
16
15 1
12
14 2 PRE PAINTED SPANISH GUTTER
SLOPE
11
DN 13 3
10
12 4
9 0.25
11 5
8

7
10 6
9 7

0.30
6

4
8 TOP OF BEAM
3

4.5MM THK. FIBER


3
2

1
RB RB CEMENT FACIA BOARD
1.20

1.20
3" Ø PVC
ELBOW 90°
0.90
4.5MM THK. FIBER CEMENT CEILING BOARD IN 4-10mmØ x 300mm ANCHOR BOLT
METAL CARRYING CHANNEL(CEILING JOIST) W/ NUTS and WASHERS ON 3"Ø PVC PIPE DOWN SPOUT
12mm x 38mm x 5m x 0.8mm THK. @ 1200mm 12mm THK. BASE PLATE
LOWER ROOF
ROOF PLAN LOWER ROOF
SCALE: 1:100 MTRS.
ROOF SECTION
DESIGNED ARCHITECTURAL : SCALE: 1:30 MTRS.

JOVEL K. PANGAN
ARCHITECT II
DATE:

PDS - BUK3RD : 2 0 2 3
DRAWN :
PROJECT AND LOCATION : SHEET CONTENTS : SUBMITTED : RECOMMENDING FOR APPROVAL : APPROVED : SET NO. SHT. NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS ROSANNO GABRIEL D. SANICO
ROOF PLANS ARCHITECT I
REGIONAL OFFICE X PDS
BUKIDNON THIRD DISTRICT ENGINEERING OFFICE
CONSTRUCTION OF ROOF SECTION DETAILS
DATE:
CHECKED / REVIEWED : A
DICKLUM, MANOLO FORTICH, BUKIDNON MULTI-PURPOSE BUILDING RYAN CAESAR B. FERNANDEZ ROMULO F. ANDRES, AEr. RONALDO C. PAHANG, AEr. A-7
BARANGAY MAMPAYAG, MANOLO FORTICH, BUKIDNON MCKENLY B. HONG ENGINEER II ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER 2023
ENGINEER II OIC - PLANNING AND DESIGN SECTION, CHIEF
DATE: DATE: DATE: DATE:
3 2

0.2
0
0.2
0
9
2.5

0.2

0.90
1.20 2.10

0
TREADS@300mm
16 SECOND FLOOR LINE
1.20 15 2
A 13
14

2ND FLOOR
12 8"X16" GLAZED GRANITE WALL TILES FINISHED

1.21

0.90
11 WITH PLASTIC TILES TRIM AT EDGE

DN
0.30 2.7
10
2
2ND FLOOR
LANDING

10
11
12
13
14
15
16
9
LANDING 8 25mm Ø STAINLESS PIPE
8

7 50mm Ø STAINLESS PIPE


6
7

4
6
5

2
1
3
LANDING 5

1.21
BEAM
4

1.50
FEMALE

0
3

0.2
STORAGE
A A CR

3.00
2

0.2
0
0.2
1
B FFL

2.10

1.93
PLAN

1.40
ELEVATION "A-A"
STAIR PLAN FFL
SCALE: 1:30 M +0.40m FFL -0.35m

SECTION
50mm x 150mm x 6mm
RECTANGULAR TUBE
4-10mmØ X 200mm
EXPANSION BOLT W/
2

DN
0.20 NUTS AND WASHERS

1.05

1.00
12mm THK. BASE PLATE

11
15

13
16

12
17

14

10

3
9

2
4

1
7
2.15
0.28 0.28
1.16 4.48

5.64
0.30

PLAN FF-3
D6
-0.35m FEMALE

1.06
EXPANSION BOLT DETAIL CR
A A
1.06

2-50mm x 150mm x 2mm


A
0.30

RECTANGULAR TUBE
0.50
1.00

0.83 0.64 0.68


50mm x 150mm x 2mm
0.20

0.20 RECTANGULAR TUBE


PLAN
0.35

12mm THK. BASE PLATE


5.
41
4-10mmØ x 300mm
ANCHOR BOLT 0.28 50mmØ STAINLESS
W/ NUTS and WASHERS
STEEL PIPE
0.20

STAIR RAILINGS TOILET DETAILS


4.35
0.30

50mm x 150mm x 6mm


RECTANGULAR TUBE
SCALE: 1:30 MTRS.
3.00

5.
23
1.21

BASE PLATE DETAIL SECTION 1.00

25
0.

NGL
1
0.40

4
0.
0.20
12
0.

FIRE ESCAPE STAIRS DETAILS DESIGNED ARCHITECTURAL :


SCALE: 1:30 MTRS.
JOVEL K. PANGAN
ARCHITECT II
DATE:

PDS - BUK3RD : 2 0 2 3
DRAWN :
PROJECT AND LOCATION : SHEET CONTENTS : SUBMITTED : RECOMMENDING FOR APPROVAL : APPROVED : SET NO. SHT. NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS ROSANNO GABRIEL D. SANICO
RAMP PLAN ARCHITECT I
REGIONAL OFFICE X PDS
BUKIDNON THIRD DISTRICT ENGINEERING OFFICE
CONSTRUCTION OF RAMP SECTION DETAILS
DATE:
CHECKED / REVIEWED : A
DICKLUM, MANOLO FORTICH, BUKIDNON MULTI-PURPOSE BUILDING MAIN STAIR PLAN
MAIN STAIR SECTION DETAILS
RYAN CAESAR B. FERNANDEZ ROMULO F. ANDRES, AEr. RONALDO C. PAHANG, AEr. A-8
BARANGAY MAMPAYAG, MANOLO FORTICH, BUKIDNON MCKENLY B. HONG
ENGINEER II
ENGINEER II
ENGINEER II
OIC - PLANNING AND DESIGN SECTION, CHIEF
ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER 2023
DATE: DATE: DATE: DATE:
2 3 2
0.09
CONCRETE GROOVE

A
2 3 8"X16" GLAZED GRANITE WALL TILES FINISHED

0. 01
10mm DIA. RSB

GRAVEL BEDDING
WITH PLASTIC TILES TRIM AT EDGE

1.15

0.10
NON-SKID CEMENT FLOOR 1.23
2-38mm Ø G.I PIPE HANDRAIL (1@900mm, 1
@700MM HIGH FROM RAMP/LANDING FLOOR
LEVEL) FULLY WELDED ON 38mmØ G.I.
2ND FLOOR
ROUGH FINISH W/ GROOVE LINE VERTICAL PIPE RAILING

0.05
4.90

0.60 0.60 0.96 0.98 0.98 0.98 1.00

+0.40m
FT-3
FT-4 0.28

1.20

1.00
U P R A M P SECTION
L A N D I N G

0.90

0.20
SPOT DETAIL

1.30
NDTS
FFL

0.90
0.70
0.40
NGL NGL
100mm CHB WITH PLAIN CEMENT
PWD/MALE
1.30 4.90 PLASTER(painted finish) NON-SKID CEMENT FLOOR
ROUGH FINISH W/ GROOVE LINE
CR
6.20 0.20

3.05
ELEVATION
PLAN
2-38mm Ø G.I PIPE HANDRAIL (1@900mm, 1
@700MM HIGH FROM RAMP/LANDING FLOOR
LEVEL) FULLY WELDED ON 38mmØ G.I.

1.40
VERTICAL PIPE RAILING

0.20
2 3

0.80
0.75
100mm x100mm

0.90
CONCRETE SKIRTING
10mmØ @300 TEMP.

0.70
BARS BOTHWAYS 100X100 CONCRETE SKIRTING
NON-SKID CEMENT 2% SLOPE TO F.D FFL +0.40m
FLOOR ROUGH FINISH
0.125

0.10
FFL RAMP FINISH FLOOR LINE
0.10

0.125
SECTION

0.40
0.40

NGL NGL
NGL

0.50
100mm THK. GRAVEL BEDDING

SECTION A B
SECTION RAMP DETAILS 2.35
SCALE: 1:50 MTRS. 0.40 0.84 0.80 0.31
0.90

1
DOORKNOBS
300mm

0.75
LATCHES 2%
SL

1.45
OP
WHITE GRAPHICS
2.15

2.10

ET
PWD/MALE OF
.D.
STAINLESS STEEL CR
KICKING PLATE A A
FF-3 D5
UNITED NATION
0.90

200mm MAX. FROM 0.20

300mm
LATCH SIDE OF DOOR BLUE BACKGROUND
0.30

PLAN
C:\Users\Administrator\Pictures\imgbin_disability-international-symbol-of-access-disabled-parking-permit-sign-accessibility-png.png

WHITE BORDER
ELEVATION
TOILET DETAILS(MALE/PWD)
0.92

SCALE: 1:30 MTRS.


920mm-1200mm
FROM FLOOR
DOOR JAMB FFL
FACE OF DOOR

PWD LOGO
SCALE: NDTS
SWITHCES FOR PWD
CLEAR WIDTH
0.90
(SWING DOOR FULLY
OPEN IN 90° POSITION) SCALE: 1:20 MTRS.

PLAN

DOOR DETAIL(PWD) DESIGNED ARCHITECTURAL :


SCALE: 1:30 MTRS.
JOVEL K. PANGAN
ARCHITECT II
DATE:

PDS - BUK3RD : 2 0 2 3
DRAWN :
PROJECT AND LOCATION : SHEET CONTENTS : SUBMITTED : RECOMMENDING FOR APPROVAL : APPROVED : SET NO. SHT. NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS FIRE ESCAPE STAIR PLAN ROSANNO GABRIEL D. SANICO
ARCHITECT I
REGIONAL OFFICE X FIRE ESCAPE ELEVATIONS PDS
BUKIDNON THIRD DISTRICT ENGINEERING OFFICE
CONSTRUCTION OF
FIRE ESCAPE DETAILS
DATE:
CHECKED / REVIEWED : A
DICKLUM, MANOLO FORTICH, BUKIDNON MULTI-PURPOSE BUILDING RAMP DETAILS RYAN CAESAR B. FERNANDEZ ROMULO F. ANDRES, AEr. RONALDO C. PAHANG, AEr. A-9
BARANGAY MAMPAYAG, MANOLO FORTICH, BUKIDNON
DOOR DETAIL MCKENLY B. HONG ENGINEER II ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER 2023
ENGINEER II OIC - PLANNING AND DESIGN SECTION, CHIEF
TOILET DETAIL DATE: DATE: DATE: DATE:
STRUCTURAL
GENERAL NOTES: 3.3. BACK FILL SHALL BE PLACED IN LAYER AND EACH LAYER SHALL BE 200mm THK. AND
SHALL BE COMPACTED TO 95% MAXIMUM DRY DENSITY.
1. STANDARDS AND REFERENCES 3.4. WHERE LOOSE / SOFT MATERIAL ID ENCOUNTERED AT DEPTH OF EMBEDMENT INDICATED, EXCAVATE TOOLED
50 mm
THE FOLLOWING SHALL GOVERN THE DESIGN, FABRICATION AND CONSTRUCTION OF THE PROJECT. EDGES
TO FIRM LAYER AND REPLACE LOOSE / MATERIALS UNDERNEATH THE FOOTING AREA PLUS 21 DEPTH
1.1. NATIONAL STRUCTURAL CODE OF THE PHILIPPINES ( NSCP ) VOL. 1, 6TH EDITION. 2010. OF SOFT MATERIAL ON ALL SIDES WITH SELECT GRANULAR BACKFILL. COMPACT SELECT GRANULAR

T/3 T/3 T/3


BACKFILL TO 95% OF MAXIMUM DRY DENSITY.

T
2. DESIGN CRITERIA Bukidnon
2.1. LOADINGS 4. MATERIALS
A. DEAD LOAD 4.1. CONCRETE CONSTRUCTION
CONCRETE - 23.56 KN/M³ 4.1.1. CONCRETE COVER OVER REINFORCING BARS SHALL BE AS FOLLOWS JOINT
STEEL - 76.93 KN/M³ A. FOOTINGS, FOOTING-TIE BEAMS ( CAST AGAINST EARTH ) 75mm 3 mm SAWED JOINT W/
150MM THK. CHB WALL - 2.73 KPA SEALANT
B. BEAMS AND COLUMNS ( TO STIRRUPS AND TIES ) 40mm
100MM THK. CHB WALL - 2.11 KPA C. WALLS, SIDE OF FOOTING-TIE BEAMS ( CAST AGAINST FORMS ) 40mm

T/2
B. LIVE LOAD D. SUSPENDED SLAB 20mm

T
ROOF - 1.00 kPa 4.1.2. BEFORE CONCRETE IS POURED, CHECK WITH ALL TRADES TO ENSURE PROPER PLACEMENT OF ALL OPENINGS,
CLASSROOMS, LABORATORY - 1.90 kPa SLEEVES, CURBS, CONDUITS, ETC. RELATING TO THE WORK
TOILETS - 2.40 kPA 4.2. REINFORCING BARS WEAKEND PLANE
CORRIDORS ABOVE, STAIRS - 3.80 KPA 4.2.1. ALL REINFORCING BARS SHALL BE CLEAN OR RUST, GREASE OR OTHER MATERIALS THAT WILL IMPAIR BOND. NOTE : JOINT
CORRIDORS ON GROUND - 4.80 KPA 4.2.2. ALL REINFORCING BARS SHALL BE ACCURATELY AND SECURELY PLACED BEFORE POURING CONCRETE OR APPLYING CONTROL JOINT CAN BE EITHER
CONSTRUCTION JOINT OR WEAKENED
C. WIND LOAD (NSCP 2010) MORTAR OR GROUT. PLANE JOINT.
BASIC WIND VELOCITY, V = 250 KPH 4.2.3. LAPPED SPLICES SHALL BE STAGGERED WHERE POSSIBLE.
P = qh [ (GCpf) - (GCpi) ] ( DESIGN WIND PRESSURE ) 4.2.4. UNLESS OTHERWISE INDICATED. SPLICING OF REINFORCEMENT SHALL BE IN ACCORDANCE WITH ACI-318M. EXCEPT
WHERE : qh = VELOCITY PRESSURE, kPa
GCpf = EXTERNAL PRESSURE COEFFICIENT 4.2.5.
THAT THE MINIMUM LAP SPLICE SHALL BE 40 BAR DIAMETER BUT NOT LESS THAN 600mm.
UNLESS SHOWN OTHERWISE ON PLANS, SPLICES SHALL BE AS FOLLOWS:
CONSTRUCTION JOINT FOR SLAB
GCpi = INTERNAL PRESSURE COEFFICIENT
D. SEISMIC LOAD (NSCP 2010)
A.
B.
INTERMEDIATE BEAMS; TOP BARS SHALL BE SPLICED AT MID-SPAN, AND BOTTOM BARS AT THE SUPPORT.
BEAMS FRAMING TO COLUMNS; TOP BARS SHALL BE SPLICED AT MID-SPAN AND BOTTOM BARS SHALL NOT BE
ON-FILL
V = ( CVL / RT ) W ( DESIGN BASE SHEAR ) d
SPLICED W/IN A DISTANCE OF TWICE THE MEMBER DEPTH FROM THE FACE OF THE COLUMN. THE SPLICED
12d
VMAX = ( 2.50 CAL / R ) W VMIN = 0.11 CALW LENGTH SHALL NOT BE LESS THAN 1.4 TIMES THE DEVELOPMENT LENGTH ( Ld ) IN 4.2.8 BELOW BUT NOT LESS 4d - 60mm Min.
D
VMIN = (0.80 ZNVL / R) W (ZONE 4) THAN 600mm.
WHERE : C. COLUMNS; LAP SPLICES SHALL BE MADE WITHIN THE CENTER HALF OF HEIGHT AND THE SPLICE SHALL NOT BE
D
W = TOTAL DEAD LOAD LESS THAN 30 BAR DIAMETER. WELDING OR THE USE OF APPROVED MECHANICAL DEVICES MAY BE PERMITTED 6
1
T = NATURAL PERIOD = CT ( HN ) 23 ; PROVIDED NOT MORE THAN ALTERNATE BARS ARE WELDED OR SPLICED AT ANY LEVEL AND THE MINIMUM
WHERE : VERTICAL DISTANCE BETWEEN TWO ADJACENT BAR SPLICES SHALL BE 600mm. 10d Min.
C = NUMERICAL COEFFICEINT D. CHB WALLS; VERTICAL BARS SHALL BE SPLICED AT THE TOP OF WALL FOOTINGS OR FOOTING-TIE BEAMS AND d d OFFSET
H = BUILDING HEIGHT AT THE BOTTOM OF REINFORCED CONCRETE LINTEL BEAMS OR BEAMS.
4.0.1. UNLESS OTHERWISE INDICATED: ALL BEAMS TERMINATING AT A COLUMN SHALL HAVE TOP AND BOTTOM BARS 90 ° HOOK 180 ° HOOK
I = IMPORTANCE FACTOR = 1.50 EXTENDING TO THE FAR FACE OF THE COLUMN. TERMINATING IN A STANDARD 90 HOOK LENGTH OF ANCHORAGE SHALL
R = NUMERICAL FACTOR = 8.50 NOT BE LESS THAN 600mm.
WIRE TIGHTLY TOGETHER
SEISMIC COEFFICIENT CV = 0.44NV 4.0.2. SHOP DRAWING FOR REINFORCEMENT SHALL BE SUBMITTED FOR APPROVAL OF THE ENGINEER PRIOR TO FABRICATION TIE HOOK
4d - 600mm Minimum
CA = 0.64N & INSTALLATION.
NEAR SOURCE FACTOR ( 10KM ) NV = 1.2 4.0.3. DEVELOPMENT LEGTH ( Ld ) OF REINFORCING BARS SHALL BE AS FOLLOWS:
NA = 1.0 SIZE OF REBARS DEVELOPMENT LENGTH
d
Z = SEISMIC ZONE = 0.40 ( ZONE 4 ) 10 mm 170 mm NOTE :
S = SOIL TYPE = D 12 mm 220 mm 1. ALL BENDS SHOWN IN DETAILS / SCHEDULES SHALL LAP
BE SPLICE
18 mm 270 mm
STANDARD HOOK OTHERWISE NOTED.
2.1. DESIGN STRESSES 20 mm 360 mm
A. CONCRETE 25 mm 600 mm 2. 180° HOOKS MAY BE SUBSTITUTED FOR 90° HOOKS.
COMPRESSIVE STRENGTH @ 28 DAYS fc' = 20.7 MPa ( 3,000 psi ) 4.1. STRUCTURAL STEEL
B. REINFORCING BARS 4.1.1. ALL STRUCTURAL STEEL SHALL CONFORM TO ASTM A36 AND SHALL HAVE A MINIMUM YIELD STRESS, Fy = 248 MPa (
a. FOR BARS 16mm Ø AND GREATER fy = 275 MPa ( 40,000 psi ) 36,000 psi ) TYPICAL REINFORCEMENT DETAIL
b. FOR BARS LESS THAN 16mm Ø fy = 230 MPa ( 33,000 psi ) 4.1.2. ALL STRUCTURAL STEEL BE FABRICATED AND ERECTED IN ACCORDANCE WITH THE AISC SPECIFICATIONS AND CODE OF
C. STRUCTURAL STEEL, ASTM-A36 STANDARD PRACTICE AS AMMENDED TO DATE.
CONSTRUCTION
FOR TRUSSES, BRACINGS, & STRUTS fy = 248 MPa ( 36,000 psi ) 4.1.3. ALL BOLTS SHALL CONFORM TO ASTM A-307 UNLESS OTHERWISE INDICATED.
30mm JOINT
D. PURLINS 4.1.4. SHOP AND FIELD WELDING SHALL BE IN ACCORDANCE WITH AWS D1.1 AND PERFORMED BY QUALIFIED 3 EXTRA STIRRUPS @ 75mm ON
CENTER
COLD FORMED LIGHT CAGE SHAPES fy = 248 MPa ( 36,000 psi ) 4.1.5. UNLESS OTHERWISE INDICATED, WELDING ELECTRODES SHALL BE E60.
E. MASONRY UNIT ( CHB ) 4.1.6. NO STEEL SHALL BE FABRICATED OR ERECTED UNTIL SHOP DRAWINGS HAVE BEEN APPROVED BY THE STRUCTURAL

H/3
NON-LOAD BEARING CHB WALLS fm' = 3.45 MPa ( 500 psi ) ENGINEER.
F. WELDS-USED E-60xx ELECTRODE 4.1.7. WELDS / ( CONFORM WITH AMERICAN WELDING STANDARDS ) USING E 60xx ELECTRODES. Fy = 93.77 MPa.
G. STRUCTURAL BOLTS, ASTM-A307 4.1.8. ANCHOR BOLTS ( CONFORM WITH ASTM A - 307 ) ft. = 96.60 MPa. fv = 69 MPa.
a. Ft = 96.60 MPa ( 14,000 psi ) b. Fv = 69 MPa ( 10,000 psi ) 4.2. CONCRETE HOLLOW BLOCKS ( CHB ):

H/3
4.2.1. UNLESS OTHERWISE INDICATED, CHB USED IN THIS WORK SHALL HAVE A MINIMUM ULTIMATE COMPRESSIVE STRENGTH

H
f' m = 3.45 MPa ( 500 psi )
3. FOUNDATION
4.2.2. ALL CHB CELL SHALL BE FILLED SOLIDLY WITH GROUT.
3.1. ASSUMED SOIL BEARING CAPACITY SHALL BE 96 kPa ( 2000 PSF )
3.1.1. IN CASE THE ACTUAL LOCATION OF THE STRUCTURE IS LESS THAN THE ASSUMED DISTANCE FROM THE SEISMIC

H/3
SOURCE OF 40 km; NOTIFY THE DIRECTOR, BUREAU OF DESIGN FOR PROPER REVISION OF THE DESIGN. REFER TO THE
5. CONSTRUCTION JOINT
SEISMIC SOURCE MAP PROVIDED IN THE NATIONAL STRUCTURAL CODE OF THE PHILIPPINES OR PHIVOLCS SEISMIC 5.1. CONSTRUCTION JOINT NOT INDICATED ON THE PLANS SHALL BE MADE SO AS TO LEAST IMPAIR THE STRENGTH OF THE
SOURCE MAP. STRUCTURE AND SHALL BE SUBJECT TO THE APPROVAL OF THE ENGINEER EXCEPT SLAB ON GRADE.
5.2. UNLESS SHOWN OTHERWISE, SLAB ON GRADE SHALL HAVE CONTROL JOINTS SPACED AT 600mm MAXIMUM CENTER TO BEAM 75mm
3.1.2. SOIL TEST SHALL BE CONDUCTED PRIOR TO START OF CONSTRUCTION. 3 EXTRA STIRRUPS @ 75mm ON
REINFORCEMENT
CENTER. 75mm 75mm
3.1.3. IN CASE THE ACTUAL SOIL BEARING CAPACITY IS FOUND LESS THAN THE ASSUMED, 96 kPa; NOTIFY THE DIRECTOR, DO NOT INTERRUPT CENTER
5.3. BEAMS CONSTRUCTION JOINTS SHALL BE LOCATED WITH IN THE MIDDLE THIRD OF THE SPAN, IT SHALL BE PROVIDED WITH 3 50mm
BUREAU OF DESIGN FOR PROPER REVISION OF FOUNDATION. 3 EXTRA STIRRUPS @ 75mm ON 75mm

3.1.4. NO FOOTING SHALL REST ON FILL. EXTRA STIRRUPS @ 75mm O.C. ON EACH SIDE OF THE JOINT. CENTER 50mm

3.1.5. BOTTOM OF FOOTING SHALL BE AT LEAST 1.00m. BELOW NATURAL GRADE LINE.
3.1.6. SOIL BEARING CAPACITY SHALL BE INCREASED BY 33% WHEN IN COMBINATION WITH SEISMIC OR WIND LOAD
3.2. ALL COLUMN FOOTINGS AND TIE BEAMS SHALL REST ON 100mm THK. WELL COMPACTED GRAVEL BASE COURSE. DESIGNED STRUCTURAL :

RUBEN A. ABA-A JR.


ENGINEER II
DATE:

PDS - BUK3RD : 2 0 2 3
DRAWN :
PROJECT AND LOCATION : SHEET CONTENTS : SUBMITTED : RECOMMENDING FOR APPROVAL : APPROVED : SET NO. SHT. NO.
REPUBLIC OF THE PHILIPPINES
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS ROSANNO GABRIEL D. SANICO
STRUCTURAL NOTES ARCHITECT I
REGIONAL OFFICE X PDS
BUKIDNON THIRD DISTRICT ENGINEERING OFFICE
CONSTRUCTION OF DATE:
CHECKED / REVIEWED : S
DICKLUM, MANOLO FORTICH, BUKIDNON MULTI-PURPOSE BUILDING RYAN CAESAR B. FERNANDEZ ROMULO F. ANDRES, AEr. RONALDO C. PAHANG, AEr. S-1 2
MCKENLY B. HONG ENGINEER II ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER 2023