You are on page 1of 1

SEACOM ENGINEERING COLLEGE

ELECTRICAL ENGINEERING DEPARTMENT


CONTINUOUS ASSESSMENT -2
SUBJECT: Power Generation & Economics SUBJECT CODE:EE 704C
Full Marks: 25 Time: 45 mins
…………………………………………………………………………………………………………………………………………………………

Answer all questions 5*5=25

1. What are the functions of Super heater & Economiser in Steam Power
Plant. (5)
2. A 100 MW steam station uses coal of calorific value 6400 kcal/kg.
Thermal efficiency of the station is 30% and electrical efficiency is 92%.
Calculate the coal consumption per hour when the station is delivering its
full rated output. (5)
3. What is Surge tank and Penstocks? (5)
4. Draw the Schematics arrangement of Nuclear Power Station. (5)
5. Define Load Factor, Plant capacity factor, Plant use factor (5)

…………………………..