Professional Documents
Culture Documents
Remedial Measures at The Plavinas Power Plant Hydropower & Dam
Remedial Measures at The Plavinas Power Plant Hydropower & Dam
T
he Plavinas powerhouse is located on the
Daugava river and is the main Station in the
Daugava cascade development. The power-
house was built between 1961 and 1966, and as shown
in Fig. 1, consists of two blocks, each about 90 m
long, with abutment structures on the right and left
sides. Each powerhouse block houses five generating
Units, and together the 10 units have a capacity of
approximately 875 MW. The top of the powerhouse
was designed to be at approximately el. 75.6, but the
structure settled considerably.
On the left of the left abutment (looking in the direc-
tion of the water flow) there is a retaining wall leading
to an embankment dam made of hydraulic fill.
Similarly, on the right of the right abutment structure,
General view of the Plavinas plant.
there is a retaining wall leading to a dyke constructed
of Sandy loam fill. The left retaining wall is founded
on hydraulic fill and the right one is founded on sandy Vertical elastic construction joints
loam. This explains why the left retaining wall settled The vertical elastic construction joints consist of an
more than the right one. Adjoining the left abutment open gap between two rigid blocks with bitumen
and just upstream there is a low level retaining wall waterstops to stop water inflows. Since the bitumen is
parallel to the water flow, to protect the intake Chan- a viscous material, it would tend to flow out were it
nel. Next to the right abutment structure and upstream not for V-shaped concrete plugs, which themselves are
there is a retaining structure which is also parallel to retained by the iiquid' pressure exerted from the bitu-
the water flow to protect the intake. men. Between the concrete plugs and the concrete
An upstream apron is cast on undisturbed moraine, walls of the joints are 10 mm-thick bituminous feit
and on top of this there is a loam and sand filter with a Strips, which were glued to each side of the concrete
concrete mantel. The upstream 14.76 m of the power- walls during construction. Specially formed wires
house foundation slab is founded directly on moraine, were used to keep the concrete plugs in? position dur-
after which there is a filter section between the slab and ing construction.
the moraine; which is a notable feature of this power- The bitumen of these waterstops consists of 35 per
plant. There is also a downstream apron, which is part Cent asphalt, and 65 per cent cement (by weight). Three
of a concrete basin founded on moraine. The down- vertical elastic joints, each with a bitumen waterstop,
stream apron also acts as the spillway basin. h has 0.56 m^ in cross-section, lead to Joints No. 7 and No. 8
pressure relief holes to reduce the porewater pressure, of the apron gallery. In addition, two vertical steel pipes
which could otherwise cause uplift of the apron. 326 mm in diameter lead to Joint No. 8. These vertical
In view of the foundations, the designer provided waterstops are essential for replenishing the losses of
elastic construction joints to allow for some differen- bitumen in Joint No. 8, and providing a sufficient head
tial movement between the rigid bodies. of bitumen to avoid water Infiltration at that Joint.
-'2
Horizontal elastic construction stops together and would then also have connected Fig. 2. Section of
joints these to the lower Joint waterstops of the apron gallery the apron.
The horizontal elastic construction joints are very sim- if it had not been damaged in 1987.
ilar to the vertical ones, and function essentially in the The damage occurred when the lower horizontal
same way. Each is composed of a gap between two bituminous waterstop with concrete Supports blew up.
rigid blocks with bitumen waterstops to stop water The inflow of bitumen caused the level of bitumen in
inflows. However, the gap is smaller in the case of the the left vertical Joint of the right abutment structure to
horizontal joints, measuring only 4 cm as opposed to lower suddenly, replacing the bitumen inflowing into
the 10 to 16 cm for the vertical joints. The horizontal the lower gallery. The top bitumen of the vertical
joints are constructed as foUows: a strip of 65 x waterstop did not flow as quickly as the lower portion,
10 mm-thick bituminous feit formed in a V-shape is either because it was more viscous, or as a result of a
placed at the fentre of the Joint. A concrete wedge small obstruction, causing a gap to form in the bitu-
plug is placed on top of this, and bitumen is then minous waterstop near el. 38 in Joint No. 3. Water
poured above to the desired elevation. Within the bitu- flowed through this gap, submerging the lower section
men there are two pairs of heating electrodes kept in of the right abutment structure.
place by wires. According to Hydroproject, these heat- With some difficulty it was possible to stop the water
ing electrodes were never used. On top of the bitumen, from flowing further into the gallery. This repair Oper-
the top concrete wedge plug is placed and is covered ation consisted of pouring concrete into the left gallery
by a bituminous V-shaped feit. The adjacent concrete up to el. 40, adding more bitumen at the top of the ver-
was provided with an asphalt coating and the protec- tical Joint and heating it, and placing a new cylindrical
tive concrete mantel was placed. Anchors on each side bituminous Joint some 83 cm upstream of the original
of the Joint keep the concrete mantel in place. bituminous waterstop.
O Daugava hydro plant for the past eight years. During this time
he has gained experience in many areas, including drainage
Systems, pump houses, deformation joints and the repair of
concrete structures. From 2000 to 2002, he was Head of the
Dam Safety Department at Latvenergo, and his responsibilities
included the evaluation of the behaviour of various hydro-
R. Guimond V. Tveritnev
MiM A. Krumins
technical structures. In 2001, he acquired additional experience
assessing dam safety conditions working with the US Bureau
of Reclamation. At present, he is the Head of the Dam
Improvement Department of the Daugava hydro plant.
Latvenergo, Pulkveza Brieza St. 12, Riga, LV - 1230,
Latvia.
Geokon Incorporated
ENGINEERING OF DAMS AND APPURTENANT
WORKS INCLUDING POWERHOUSES CEOHON 48 Spencer Street
LebanonJH 03766. USA
The Wsfld Leader in Vibrating Wire Technology
is the title of a Conference organized by:
The Dams Society of India Dam Monitoring Instrumentation
The Indian National Hydropower Association Geokon manufactures a füll ränge ofgeotechnical Instrumentation
in association with the suitable for monitoring earth and concrete dams
Council of Power Utilities Crack Meters • Piezometen