You are on page 1of 3

TECHNICALLY SPEAKING SQ

Phantom Flow
By Kenneth E. Isman, P.E.

F
or situations where there The situation that the Phantom Flow floor, it is not a wall of any kind) then the
are two different hazard rule is designed to deal with is one where Extra Hazard Group 2 protection has to
classifications in the same there are two hazard classifications in a extend 15 ft beyond the perimeter of the
building, NFPA 13 does not building and the higher hazard area is actual Extra Hazard activities, which is
contain very many special considerations. less than the required design area. For shown in Figure 1 by the dashed line. All of
For the most part, the sprinkler system example, consider the situation where a the sprinklers within the dashed lines need
is designed with the sprinklers over single building has an Extra Hazard Group to be designed to protect Extra Hazard
each hazard capable of protecting the 2 area and an Ordinary Hazard Group 2 Group 2. In addition, sprinklers 18 and 24,
hazard underneath. If there is no physical area. How do you perform the hydraulic while they are technically outside of the
separation between the two hazard areas, calculations when the Extra Hazard Group dashed lines, do protect area within the
there is a rule that requires the sprinkler 2 area is only 400 sq ft? Table 11.2.3.1.1 dashed lines, so they need to be designed
protection for the higher hazard to be requires a minimum design area of 2,500 to protect Extra Hazard Group 2 as well.
carried 15 ft into the lower hazard space. sq ft for Extra Hazard, which can be This means that sprinklers 1, 2, 3, 4, 8, 9,
But for most editions of NFPA 13, that’s reduced to 2,000 sq ft if high temperature 10, 11, 15, 16, 17, 18, 22, 23, and 24 (a total
pretty much all that the standard has had sprinklers are used. of 15 sprinklers) will need to be designed
to say about situations where there are Under the old rules, the hydraulic to cover a maximum of 100 sq ft and will
two different hazard conditions. calculations would be required to have need to discharge at least a density of 0.4
In the 2013 edition of NFPA 13, a new the design area for the Extra Hazard gpm per sq ft, even though some of them
rule was added to make the water supply extended into the Ordinary Hazard space are physically over the Ordinary Hazard
requirements a little less stringent for until the minimum design area (2,000 or Group 2 activities.
situations where the higher hazard is a 2,500 sq ft) was met. Note that the Extra
very small area compared to the lower Hazard density would not necessarily
hazard. The new rule is in the form of need to discharge from the sprinklers Old Rules Applied to Example
permissive language, meaning that you in the Ordinary Hazard space, but the Under the old rules applied to the ex-
can use this new rule as an option, or sprinklers in the Ordinary Hazard space ample, the design area calculated for
you can choose to ignore it and perform would generally be over-discharging the Extra Hazard Group 2 space would
your hydraulic calculations in accordance because of the pressure in the system have to include 2,500 sq ft. This would
with the old rules, just like you have been necessary to make sure that the Extra encompass many more than just the 15
doing for years. The option is up to you Hazard sprinklers discharge sufficient sprinklers named above. The design area
as the person performing the hydraulic water would also be present (or higher) at of 2,500 sq ft would need to include the
calculations, but if you understand the the Ordinary Hazard sprinklers. 24 sprinklers shown in the shaded area of
new rule, you’ll want to use it because it Rather than talk in the abstract about Figure 2. Note that some of the sprinklers
decreases the water supply (pressure and different spaces, this might be more clear protecting the Ordinary Hazard space
flow) requirements in many cases. with a concrete example. So, consider > > CONTINUED ON PAGE 14

The new rule is in a pair of sections in Figure 1, a building with a mostly Ordinary
Chapter 23. Specifically, the new rule is Hazard Group 2 sprinkler system, but with
Vice President, Engineering
in sections 23.4.4.1.1.4 and 23.4.4.1.1.5. In a small Extra Hazard Group 2 situation in
for NFSA. Ken represents
this article, I refer to these two sections the upper right hand corner. Assume for

www.nfsa.org
NFSA on the NFPA Technical
together as the “Phantom Flow” rule, the sake of discussion that the sprinklers
Committee on Sprinkler
although those words don’t actually are all ordinary temperature. If there is
System Discharge Criteria
appear in the standard. But they are an no separation between the Extra Hazard
interesting summary of how to deal with space and the Ordinary Hazard space (the
Kenneth E. Isman, P.E.
the subject. line in the plan view is just painted on the
13
Group 2. It has been included in the design to provide relief from some of the very
area in order to complete the 2,500 sq ft stringent rules in NFPA 13 regarding hy-
in accordance with the NFPA 13 rules, but draulic calculations in buildings with two
it is not required to discharge at a density (or more) hazard classifications where the
of 0.4 gpm per sq ft. higher hazard space is relatively small.
So, the old method of hydraulic As this example showed, it helps when a
calculations would require a water supply small Extra Hazard space is in an other-
capable of providing 1,042 gpm at 50 psi wise Ordinary Hazard building, but there
at the top of the riser for this system. Now are other examples where it would also
let’s calculate the same system using the help, such as:
new Phantom Flow rules and see what • A small dry-pipe system adjacent to a
kind of difference it makes. wet system (this would be especially
helpful where there is a small loading
dock protected on the exterior of the
New Phantom Flow Rules Applied building.
to Example
• Two or more hazard classifications
New section 23.4.4.1.1.4 of NFPA 13 allows
where the higher hazard is not in a
the user to just start out by calculating the
FIGURE 1 — EXAMPLE OF TWO DESIGN AREAS room with walls having a fire resistance
area that encompasses the Extra Hazard
rating sufficient to meet the Room De-
(such as sprinkler 6) cover 120 sq ft per the rest of the main. activities, plus the 15 ft extension since FIGURE 3 – EXTRA HAZARD DESIGN AREA USING NEW PHANTOM FLOW RULES
sign Method.
sprinkler, which is completely acceptable It is interesting to note the flow at there is no barrier to heat and smoke
because they only need to meet the rules sprinkler 6 from the hydraulic calculation between the Extra Hazard and the Ordi- 639.7 gpm. This means that the Phantom adjustments up or down to end up with • A small area protected with spray sprin-
for Ordinary Hazard. This additional area report. According to the output from the nary Hazard. This would be a calculation Flow would be 360.3 gpm (1000 – 639.7 the correct final flow. The correct final klers (perhaps an Extra Hazard situa-
allows 24 sprinklers to cover 2,500 sq ft. calculations, the flow from this sprinkler that includes sprinklers 1, 2, 3, 4, 8, 9, 10, = 360.3). flow will be the minimum design area tion or a dry-pipe system) adjacent to a
In fact, the actual area covered by the 24 will be 47.1 gpm. Since this sprinkler covers 11, 15, 16, 17, 18, 22, 23, and 24. These 15 Section 23.4.4.1.1.5 of NFPA 13 says multiplied by the design density. In our storage area with ESFR protection.
sprinklers in the shaded area is 2,520 sq ft an area of 120 sq ft, this means that the sprinklers, covering a total of 1,500 sq ft that the Phantom Flow is required to be example, the correct final flow is 1,000 When performing the hydraulic
(63 x 40 = 2520). density that this sprinkler is producing is are all that are required to be calculated in added to the system, “at the connection gpm (0.4 gpm per sq ft x 2500 sq ft = calculations with a computer program,
Hydraulic calculation of the 24 sprinklers 0.39 gpm per sq ft (47.1/120 = 0.39). Note accordance with section 23.4.4.1.1.4. of the branch line to the cross main 1000). It took me three iterations to get to the Phantom Flow could be treated
in the shaded area of Figure 2 show that that this is well in excess of the 0.2 gpm Then, section 23.4.4.1.1.5 requires the furthest from the source.” For our this value with a combination of the flow like an inside hose demand that can be
the demand at the top of the riser is about per sq ft density required for Ordinary user to add an additional flow “at the point example, that will be node “B” on Figure to the sprinklers and the Phantom Flow. added to the system at the proper node
1,042 gpm at 50 psi. This assumes 1-1/2 Hazard Group 2, but short of the 0.4 gpm of connection of the branch line to the 3, which is at the bottom of the riser In the first calculation, I calculated the (the connection of the branch line to
inch pipe for the last two pieces of pipe on per sq ft necessary for Extra Hazard Group cross main furthest from the source.” This nipple going to the most remote branch sprinklers without any Phantom Flow. I the cross main that is furthest from the
the branch lines, 2 inch pipe for the rest of 2. This is acceptable because sprinkler 6 additional flow is calculated by figuring line. Note that we put the Phantom Flow in subtracted this number from 1,000 to get water supply). Most hydraulic calculation
the branch lines, 4 inch pipe for three of is one of the sprinklers that only needs to out the minimum flow that would work at the bottom of the riser nipple because my first guess at a Phantom Flow. programs can handle variable inside hose
the pieces of the main and 6 inch pipe for worry about protecting Ordinary Hazard for the hazard being calculated (density NFPA 13 talks about adding this flow at My second iteration used this Phantom demands at any node.
times the minimum design area) and then the connection “to the cross main.” Flow, but caused the final flow to be
calculating the actual sprinklers covering Since the node where the Phantom greater than 1,000 gpm, so I went back
the hazard. The additional flow will be the Flow was added to the calculations is and reduced my Phantom Flow guess by Summary
minimum flow minus the flow required for actually between nodes where flow goes a little bit. That third iteration produced a In summary, the Phantom Flow rule is a
the actual sprinklers. to different sprinklers, the calculations final flow of exactly 1,000 gpm, which is all term that is not found in NFPA 13. Instead,
Since the additional flow is not become difficult. You can’t calculate section 23.4.4.1.1.5 requires. The pressure this author has coined this term to refer
associated with any sprinklers, I call it a the Phantom Flow without knowing demand at this flow at the top of the riser to sections 23.4.4.1.1.4 and 23.4.4.1.1.5
“Phantom Flow.” It is not really intended the demand for the sprinklers, but you was 42 psi. of NFPA 13. The term “Phantom Flow”
to flow from any additional sprinklers. can’t figure out the demand for the As this example shows, using the is used because the flow is not actually
Instead, the Phantom Flow is intended sprinklers without knowing the Phantom Phantom Flow reduces the flow demand assigned to any sprinklers (and because
to beef up the water supply so that the Flow because the extra flow in the main by 42 gpm (which is only a 4% savings) this author likes alliteration).
sprinklers that are over the hazard flow causes more friction loss in the main, and the pressure demand by 8 psi (16%). The Phantom Flow rule can be used
more than their minimum when they which then causes a higher pressure Such savings could be considered small, to reduce the water flow and pressure
open. demand in the main at the connections but they might be significant in a system demand in a building where there are two
For our example, the minimum flow to the branch lines closer to the water with a marginal water supply. Other uses or more hazard classifications where the
SQ • may – june 2014

would be 1,000 gpm (0.4 gpm per sq supply. This, in turn, requires a larger flow of the Phantom Flow rule would yield higher hazard is a relatively small area.

www.nfsa.org
ft x 2500 sq ft = 1000 gpm). Hydraulic demand at these branch lines. much greater savings. The person performing the calculations
calculation of the sprinklers named above In order to solve the paradox presented is not required to use the Phantom Flow
(1, 2, 3, 4, 8, 9, 10, 11, 15, 16, 17, 18, 22, 23, and in the previous paragraph, the user rule, but they should be familiar with
FIGURE 2 — EXTRA HAZARD DESIGN AREA UNDER THE OLD RULES 24, which are shown in the shaded area needs to assume a Phantom Flow and Use of the Phantom Flow Rule it because it will help conserve water
of Figure 3) reveals that they will need see how closely it works out, then make The Phantom Flow rule was developed supplies.
14 15
Group 2. It has been included in the design to provide relief from some of the very
area in order to complete the 2,500 sq ft stringent rules in NFPA 13 regarding hy-
in accordance with the NFPA 13 rules, but draulic calculations in buildings with two
it is not required to discharge at a density (or more) hazard classifications where the
of 0.4 gpm per sq ft. higher hazard space is relatively small.
So, the old method of hydraulic As this example showed, it helps when a
calculations would require a water supply small Extra Hazard space is in an other-
capable of providing 1,042 gpm at 50 psi wise Ordinary Hazard building, but there
at the top of the riser for this system. Now are other examples where it would also
let’s calculate the same system using the help, such as:
new Phantom Flow rules and see what • A small dry-pipe system adjacent to a
kind of difference it makes. wet system (this would be especially
helpful where there is a small loading
dock protected on the exterior of the
New Phantom Flow Rules Applied building.
to Example
• Two or more hazard classifications
New section 23.4.4.1.1.4 of NFPA 13 allows
where the higher hazard is not in a
the user to just start out by calculating the
FIGURE 1 — EXAMPLE OF TWO DESIGN AREAS room with walls having a fire resistance
area that encompasses the Extra Hazard
rating sufficient to meet the Room De-
(such as sprinkler 6) cover 120 sq ft per the rest of the main. activities, plus the 15 ft extension since FIGURE 3 – EXTRA HAZARD DESIGN AREA USING NEW PHANTOM FLOW RULES
sign Method.
sprinkler, which is completely acceptable It is interesting to note the flow at there is no barrier to heat and smoke
because they only need to meet the rules sprinkler 6 from the hydraulic calculation between the Extra Hazard and the Ordi- 639.7 gpm. This means that the Phantom adjustments up or down to end up with • A small area protected with spray sprin-
for Ordinary Hazard. This additional area report. According to the output from the nary Hazard. This would be a calculation Flow would be 360.3 gpm (1000 – 639.7 the correct final flow. The correct final klers (perhaps an Extra Hazard situa-
allows 24 sprinklers to cover 2,500 sq ft. calculations, the flow from this sprinkler that includes sprinklers 1, 2, 3, 4, 8, 9, 10, = 360.3). flow will be the minimum design area tion or a dry-pipe system) adjacent to a
In fact, the actual area covered by the 24 will be 47.1 gpm. Since this sprinkler covers 11, 15, 16, 17, 18, 22, 23, and 24. These 15 Section 23.4.4.1.1.5 of NFPA 13 says multiplied by the design density. In our storage area with ESFR protection.
sprinklers in the shaded area is 2,520 sq ft an area of 120 sq ft, this means that the sprinklers, covering a total of 1,500 sq ft that the Phantom Flow is required to be example, the correct final flow is 1,000 When performing the hydraulic
(63 x 40 = 2520). density that this sprinkler is producing is are all that are required to be calculated in added to the system, “at the connection gpm (0.4 gpm per sq ft x 2500 sq ft = calculations with a computer program,
Hydraulic calculation of the 24 sprinklers 0.39 gpm per sq ft (47.1/120 = 0.39). Note accordance with section 23.4.4.1.1.4. of the branch line to the cross main 1000). It took me three iterations to get to the Phantom Flow could be treated
in the shaded area of Figure 2 show that that this is well in excess of the 0.2 gpm Then, section 23.4.4.1.1.5 requires the furthest from the source.” For our this value with a combination of the flow like an inside hose demand that can be
the demand at the top of the riser is about per sq ft density required for Ordinary user to add an additional flow “at the point example, that will be node “B” on Figure to the sprinklers and the Phantom Flow. added to the system at the proper node
1,042 gpm at 50 psi. This assumes 1-1/2 Hazard Group 2, but short of the 0.4 gpm of connection of the branch line to the 3, which is at the bottom of the riser In the first calculation, I calculated the (the connection of the branch line to
inch pipe for the last two pieces of pipe on per sq ft necessary for Extra Hazard Group cross main furthest from the source.” This nipple going to the most remote branch sprinklers without any Phantom Flow. I the cross main that is furthest from the
the branch lines, 2 inch pipe for the rest of 2. This is acceptable because sprinkler 6 additional flow is calculated by figuring line. Note that we put the Phantom Flow in subtracted this number from 1,000 to get water supply). Most hydraulic calculation
the branch lines, 4 inch pipe for three of is one of the sprinklers that only needs to out the minimum flow that would work at the bottom of the riser nipple because my first guess at a Phantom Flow. programs can handle variable inside hose
the pieces of the main and 6 inch pipe for worry about protecting Ordinary Hazard for the hazard being calculated (density NFPA 13 talks about adding this flow at My second iteration used this Phantom demands at any node.
times the minimum design area) and then the connection “to the cross main.” Flow, but caused the final flow to be
calculating the actual sprinklers covering Since the node where the Phantom greater than 1,000 gpm, so I went back
the hazard. The additional flow will be the Flow was added to the calculations is and reduced my Phantom Flow guess by Summary
minimum flow minus the flow required for actually between nodes where flow goes a little bit. That third iteration produced a In summary, the Phantom Flow rule is a
the actual sprinklers. to different sprinklers, the calculations final flow of exactly 1,000 gpm, which is all term that is not found in NFPA 13. Instead,
Since the additional flow is not become difficult. You can’t calculate section 23.4.4.1.1.5 requires. The pressure this author has coined this term to refer
associated with any sprinklers, I call it a the Phantom Flow without knowing demand at this flow at the top of the riser to sections 23.4.4.1.1.4 and 23.4.4.1.1.5
“Phantom Flow.” It is not really intended the demand for the sprinklers, but you was 42 psi. of NFPA 13. The term “Phantom Flow”
to flow from any additional sprinklers. can’t figure out the demand for the As this example shows, using the is used because the flow is not actually
Instead, the Phantom Flow is intended sprinklers without knowing the Phantom Phantom Flow reduces the flow demand assigned to any sprinklers (and because
to beef up the water supply so that the Flow because the extra flow in the main by 42 gpm (which is only a 4% savings) this author likes alliteration).
sprinklers that are over the hazard flow causes more friction loss in the main, and the pressure demand by 8 psi (16%). The Phantom Flow rule can be used
more than their minimum when they which then causes a higher pressure Such savings could be considered small, to reduce the water flow and pressure
open. demand in the main at the connections but they might be significant in a system demand in a building where there are two
For our example, the minimum flow to the branch lines closer to the water with a marginal water supply. Other uses or more hazard classifications where the
SQ • may – june 2014

would be 1,000 gpm (0.4 gpm per sq supply. This, in turn, requires a larger flow of the Phantom Flow rule would yield higher hazard is a relatively small area.

www.nfsa.org
ft x 2500 sq ft = 1000 gpm). Hydraulic demand at these branch lines. much greater savings. The person performing the calculations
calculation of the sprinklers named above In order to solve the paradox presented is not required to use the Phantom Flow
(1, 2, 3, 4, 8, 9, 10, 11, 15, 16, 17, 18, 22, 23, and in the previous paragraph, the user rule, but they should be familiar with
FIGURE 2 — EXTRA HAZARD DESIGN AREA UNDER THE OLD RULES 24, which are shown in the shaded area needs to assume a Phantom Flow and Use of the Phantom Flow Rule it because it will help conserve water
of Figure 3) reveals that they will need see how closely it works out, then make The Phantom Flow rule was developed supplies.
14 15

You might also like