You are on page 1of 1

DETAIL 1150

Minimum #12 galvanized rubber-grommeted


screw with 1-inch embedment (typ. both sides)
Duro-Last custom-fabricated parapet flashing
Cap
Field weld
between
fasteners
Factory (Note 3)
weld

Field weld
(Note 3)

Approved vapor
Approved Duro-Last barrier (Note 4)
plates/fasteners Approved insulation (Note 4)
Fiberglass insulation Approved cover
board (Note 4)

Note 1: Tabs that are parallel to the expansion joint must be mechanically fastened with
the same fastening pattern used on the membrane in the field area.
Note 2: Leave the membrane covering the expansion joint loose enough to allow for
movement of the building on either side of the joint.
Note 3: All field welds shall be a minimum of 1-1/2 inches wide.
Note 4: Refer to specifications for vapor barrier, insulation and cover board requirements.

REVISED: 01/31/2017 GENERAL DETAIL FOR MECHANICALLY FASTENED SYSTEMS


PREVIOUS: 01/01/2009 CURB-STYLE EXPANSION JOINT WITH CAP
SCALE: NONE NEW CONSTRUCTION OR RE-ROOF