DETAIL 1090

Factory weld Duro-Last custom-fabricated


parapet flashing
Approved Duro-Last
plates/fasteners Approved Duro-Last sealant

Approved Duro-Last
caulk

Approved cover
board (Note 4)

Approved
insulation
(Note 4)
Wood nailer
Approved (Note 3)
vapor barrier
(Note 4) Termination Bar and approved Duro-Last
fasteners spaced 6 inches on center

Existing single-ply membrane; or Duro-Last


membrane greater than 1 year old

Note 1: Finished detail must not impede the drainage or flow of water.
Note 2: Tie-in detail for all flat surfaces. The use of Detail Drawing 1070 will be required
in conjunction with Detail Drawing 1090 when tie-in is across metal flutes.
Note 3: Wood nailers must withstand a minimum force of 180 pounds per lineal foot (per
building code). Any pull values greater than 270 pounds will allow for a fastener
spacing of 18 inches on center. Pull values less than 270 pounds will require
additional fasteners. The installing contractor is responsible for meeting
building codes.
Note 4: Refer to specifications for vapor barrier, insulation and cover board requirements.

REVISED: 01/31/2017 GENERAL DETAIL FOR MECHANICALLY FASTENED SYSTEMS


PREVIOUS: 01/01/2009 SINGLE-PLY ROOF TIE-IN
SCALE: NONE RE-ROOF