Professional Documents
Culture Documents
VOLUME 2
CONTENTS LIST
SECTION J2 EARTHWORKS 26
J2.1 SCOPE............................................................................................................................. 26
J2.1.1 General 26
J2.1.2 Definitions 26
J2.2 REFERENCE STANDARDS ....................................................................................... 26
J1.1 GENERAL
J1.1.1 Scope
Site Investigation, includes Site Operations, Laboratory Testing, and the submission of draft and
final Reports, and is required in connection with completion of the design of by the Engineer of
those part of the Works not specified to be designed by the Contractor.
The nature of the proposed Site Operations (and Ancillary Works if any) and Laboratory Testing
is described in the Specification and the Schedules.
The quantities of work which are thought likely to be required are itemised in the Bill of
Quantities.
Depending on circumstances and conditions found on the Site, the nature and the quantity of
work may be subject to change as ordered by the Engineer.
J1.1.3 Definitions
The following terms shall have the meanings hereby assigned to them except where the context
otherwise requires:-
A ‘hole’ shall mean and include any borehole, hand-auger hole, drillhole, inspection pit, trial pit
or trial trench required for the Investigation.
‘Boring’ shall mean advancing a hole using a mechanical auger, shell, chisel or clay-cutter. The
rig used shall be called a boring rig and the hole formed shall be called a borehole.
‘Hand-augering’ shall mean advancing a hole using a portable soil auger rotated by hand
principally for shallow exploration and disturbed sampling. The hole formed shall be called an
auger hole.
‘Drilling’ shall mean the use of a machine-driven rig for advancing a hole in rock or soil with a
rotary cutting tool. The hole formed shall be called a drillhole and the rig used shall be called a
drilling rig, which term shall include a boring rig with auxiliary equipment for drilling.
‘Coring’ shall mean drilling for the purpose of recovering cores of rock or soil. Core shall mean
material having a circular clearly defined exterior.
A ‘sample tube’ shall mean the container into which undisturbed soil is forced during sampling
and in which the soil is extracted from the ground and stored, after sealing against loss of
moisture.
A ‘sampler’ shall mean the sample tube and all the accessories that are required to obtain an
undisturbed sample of soil.
‘Made ground’ means any deposits or construction which has been formed by man as distinct
from geological agencies.
Such right of rejection of equipment does not attribute any responsibility for safety of said
equipment, which remains the Contractor’s sole responsibility.
The Contractor shall take and record water levels in observation wells daily for seven days and
weekly thereafter until completion of the field work.
J1.4 BORING
J1.5 DRILLING
J1.6.3 Backfilling
Permission for a trial pit or trench to be backfilled will normally be given as soon as the logging
sampling and testing in that pit has been completed.
Material shall be replaced and well compacted in the holes at the same levels from which it was
excavated.
The Contractor shall backfill and compact all trial pits, trenches and inspection pits in such a
manner and using such materials that no subsequent depression is formed at the ground surface
due to settlement of the backfill. Where required by the Engineer, the Contractor shall return
during the Period of Maintenance to fill any subsequent depression or to remove any surplus soil
which has failed to settle sufficiently, without reducing the original depth of topsoil at the ground
surface.
J1.6.5 Photographs
Where required by the Engineer colour photographs of pits and trenches and their arisings shall
be supplied by the Contractor. Each photograph shall show clearly details of the ground
conditions in each pit and trench face with any support in place, and shall contain an indicated
scale which shall be the same in every photograph. A standard colour chart and monochrome
step wedge shall also be included in each photograph. Photographs will generally be required at
the rate of three for every pit or as directed by the Engineer. A single gloss colour print
size178mm x 127mm of each photograph shall be submitted to the Engineer for his approval and
retention not more than 1 week after the excavation of the pit involved. In the event that the
photographs are of a quality unacceptable to the Engineer they shall be re-taken, if reasonably
possible, at the Contractor’s expense.
On acceptance of the quality of the photographs, complete sets of prints size 178mm x 127mm of
all the photographs shall be mounted and submitted by the Contractor in bound volumes together
with the photograph negatives with the Report.
The number of copies required shall be as specified in the Bill of Quantities.
J1.7 SAMPLING
shall then be added and followed by more molten wax to form a plug of total thickness not less
than 25mm. Any space remaining in the ends of the sample tube shall be filled with damp
sawdust or other material approved by the Engineer and the ends of the sample tube shall be
covered with tight-fitting screw caps.
The sample tube shall immediately be labelled as specified and a second label giving the same
information shall be placed inside the sample tube at the top end.
J1.7.18 Cores
Core barrels shall be held horizontally whilst the core is extruded, in the same direction as it
entered the barrel, by applying a constant pressure, without vibration and in a manner to prevent
disturbance to the cores and shall be extruded directly into the core box or into a correctly sized
detachable channel which forms part of the core box. After extrusion all cores shall immediately
be sealed with transparent flexible sheeting or other approved sealant to prevent drying out and
damage. They shall be resealed immediately following examination, logging and photography.
Where the core is contained in an expendable triple tube liner, the ends of the tube shall be sealed
and waxed as specified for undisturbed open-drive samples. Field moisture samples shall be
taken from the part of the core remaining in the bit.
Core shall be placed in the boxes in the correct sequence, with increasing depth from left to right
in the box and from the hinged side to the hasp side of the box.
Fractured material which does not conform to the definition of core shall be spread throughout its
length and packed securely. Core losses shall be shown by wooden blocks of a square cross
section of approximately the same area and of a length equal to that of the core lost; these should
be inserted immediately after the core is placed in the core box.
Each core run shall be segregated by labelled wooden blocks 25mm thick and the depth of the
bottom of each run shall be marked on the partitions in the core box with paint.
No box shall contain more than 3m of core. The total weight of cores and box shall together not
exceed 60kg.
8. all piping, hoses, and other equipment necessary to conduct the tests.
All pumping materials used for water pressure testing shall have a minimum inside diameter of
25 mm. All equipment shall be in first class working order and shall be subject to approval at all
times
The Engineer will require proof of recent calibration of the water meter(s) and pressure gauge(s)
and a reasonable amount of testing at the site to demonstrate that the equipment is working
properly and accurately.
The Contractor shall calibrate the packer assembly, piping, and valves for friction loss as
required prior to the start of the testing. Friction loss adjustments shall be applied as needed in
the calculation of water pressure test (lugeon) results.
The hole shall be advanced to the required depth(s) as specified elsewhere for Drilling. Tests will
be conducted in accordance with the method of Houlsby, or equivalent international standards for
lugeon testing in rock that require a series of increasing and then decreasing, step-wise
increments in injection pressure (A. C. Houlsby, 1976. Routine interpretation of the lugeon
water-test, Quarterly knl. Engineering Geol., vol. 9, 1976, pp. 303-313). The hole shall be
flushed with clear water prior to actual pressure tests. Tests may be required either progressively
from the bottom of the hole upward, for the entire portion of the hole in rock, or for isolated
segments of the hole. The following information shall be recorded:
1. Hole number;
2. Depth of bottom of hole;
3. Depth of zone tested;
4. Pressure of water supply;
5. Rate of water take;
6. Depth of casing;
7. Date and time of test, and name of person(s) conducting test.
backfilled upon completion of sampling. Excess backfill shall be mounded up over the test
pit/trench and shaped to drain off water.
The Contractor shall collect bulk and jar samples from the sides and bottom of the test
pits/trenches at intervals as required by the Engineer and/or the Contractor’s geologist. At least
one sample will be taken from each stratum encountered during excavation. The Engineer
reserves the right to reject the samples that are non-representative, contaminated by other
materials, or otherwise unsatisfactory for testing purposes and no payment will be made for such
samples.
Bulk samples will be about 20 kg in size. Bulk samples shall be sealed in plastic bags or plastic
pails in accordance with ASTM Standard d 4220, “Standard practices for Preserving and
Transporting Soil Samples”. Plastic bags shall be placed in a sturdy wooden crate or a metal or
plastic pail for shipment to the testing laboratory. Each sample shall be labelled with the Project
Name, test pit number, sample number, sample depth, and date of sampling.
At least one jar sample for moisture content determination shall be taken with each bulk sample,
and otherwise as required. Jar samples shall be placed in glass or plastic jars of at least 250 ml
capacity. The jar shall be sealed with a moisture-tight self –sealing screw top. Each sample shall
be labelled with the Project Name, test pit or trench number, sample number, sample depth, and
date of sampling.
The Contractor shall furnish a sketch plan of each test pit/trench and two vertical sections, one
parallel to the length and one parallel to the width of the each test pit/trench. The plan shall show
the general dimensions of the pit/trench at the ground surface, at any general change in cross-
section, and at bottom, and the location of samples. The section shall be in the form of geologic
logs, showing the shape and dimensions of the pit/trench, the depth to any change in soil strata,
the depth to any water inflows, and the location and depth of samples. Visual soil classification
shall be performed in accordance with ASTM D-2488. The type of bracing and sheathing or
sloping of the sides shall be noted on the plan and sections. The test pit and the test trench logs
shall include the Project Name, test pit/trench number, elevation of the ground surface, date
excavation started, date excavation completed, date backfilled, the type and size of equipment
used to make the excavation, the amounts of any water pumped from the excavation and the
name of the Contractor’s employee in charge of the excavation.
J1.9 INSTRUMENTATION
Instrumentation materials and installation are covered in Section 2.
All soil on which laboratory tests have been carried out including that wasted during the
preparation of test specimens, shall be retained in labelled airtight containers until otherwise
directed by the Engineer.
J1.11 REPORTING
7. Full records of all laboratory tests including any which have been carried out by
nominated or approved sub-contractors. The records shall include a detailed
description of each sample tested.
A summary of the results should be included in the main volume of the Report. If the size of the
Report warrants it, detailed records may be included in separate volume(s) and shall include
graphs of laboratory tests where appropriate.
1. Representative colour print photographs of borehole cores, material and trial holes
when required.
2. Appraisal of ground conditions at each location with recommendations for
foundation design and construction.
SECTION J2 EARTHWORKS
J2.1 SCOPE
J2.1.1 General
This Part contains requirements which, where relevant to this Contract, shall apply to site
clearance; general excavation; trench excavation; embankments; topsoiling and landscaping.
J2.1.2 Definitions
The following terms shall have the meanings hereby assigned to them:—
‘Topsoil’ any surface material capable of supporting vegetation and suitable for use
in soiling areas to be grassed or cultivated.
‘Rock’ naturally-occurring material which in the opinion of the Engineer would
normally have to be loosened either by blasting or by the use of pneumatic
tools (other than clay spades) or by other rock quarrying methods or, if
excavated by hand, by the use of wedges and sledge hammers. An isolated
solid boulder or detached piece of rock shall qualify as Rock only if it
exceeds 1.0m³ in volume.
‘Bulk excavation in open cut (excluding Trench Excavation) down to levels
Excavation’ specified in the Drawings or otherwise as being the general levels after
completion of excavation other than Incidental Excavation.
‘Trench excavation, to levels and limits specified in the Drawings or otherwise, of
Excavation’ trenches into which pipes and the like are to be laid.
‘Incidental excavation (generally in small quantities) below or outside the limits of
Excavation’ Bulk Excavation and Trench Excavation, but excluding Excess Excavation.
‘Excess excavation outside the limits specified for Bulk, Trench or Incidental
Excavation’ Excavation.
J2.4 MATERIALS
J2.4.3 Geotextiles
Geotextiles shall have the mechanical and hydraulic properties of the geotextile types and
manufacture specified or equivalent types approved by the Engineer. The materials shall be
sufficiently durable to last for the design life of the structure, and the Contractor shall provide
evidence of similar applications where the proposed material has been used.
J2.5 WORKMANSHIP
Contractor each day or at such shorter intervals as the Engineer may require. Overbreak (that is,
excavation in Rock outside the nominal limits of excavation) shall be kept to a minimum and
shall be held to be Excess Excavation.
Employer’s use but shall otherwise be burnt to ash or disposed of off the Site as directed by the
Engineer.
J2.5.10 Trees
Where directed by the Engineer trees shall be uprooted or cut down as near to ground level as
possible. Branches and foliage shall be removed and burnt to ash or disposed of off the Site.
Useful timber shall, as between the Employer and the Contractor, be deemed to be the property
of the Employer and shall be cut into suitable lengths and transported a distance not exceeding
5km to a location provided by the Employer where it shall be off-loaded and stacked.
J2.5.11 Stumps
Stumps and roots whether existing or remaining after tree felling shall where directed by the
Engineer be grubbed out and disposed of off the Site. The resulting hole shall be filled with
approved material deposited and compacted in layers to the same dry density as the adjoining
soil.
The Contractor shall ensure that no excavated material which is suitable for and is required for
reuse in the Works is disposed of outside the Site.
where open Trench Excavations may become flooded, and these precautions may include the
partial refilling of the trench leaving pipe joints exposed while awaiting tests of the joints.
If the Engineer considers that the Contractor is not complying with any of the foregoing
requirements he may prohibit further Trench Excavation until he is satisfied with the progress of
laying and testing of pipes and refilling of Trench Excavation.
J2.5.29 Geotextiles
Geotextiles shall be protected at all times against mechanical or chemical damage. Those
geotextiles which are susceptible to damage by light shall be stored under cover.
over hollows or humps. Operation of construction plant directly on the installed geotextile will
not be permitted. Care shall be taken in placing fill material to avoid damage to the geotextile.
J2.6 TESTING
J3.1 SCOPE
This Section contains requirements for the manufacture, transportation, placement, finishing,
repair and curing of concrete; for the detailing, supply and placing of reinforcement; for
formwork; for joints, joint materials, joint treatment and bearing pads; and for all other work
associated with cast-in-place and precast concrete.
BS 6744 Stainless steel bars for the reinforcement of and use in concrete – Requirements
and test methods
BS 6949 Specification for bitumen-based coatings for cold application excluding use in
contact with potable water
BS 8000 Code of practice for water proofing
BS 8007 Code of practice for design of concrete structures for retaining aqueous liquids
BS 8102 Code of Practice for protection of structures against water from the ground
BS ISO 14654 Epoxy-coated steel for the reinforcement of concrete
BS ISO 14656 Epoxy powder and sealing material for the coating of steel for the reinforcement
of concrete
U.S. Army Corps of Engineers (US COE)
CRD C568 Rubber - preparation of pieces for test from other than standard vulcanized sheets
CRD C570 Test for brittleness temperature of plastics and elastomers by impact
CRD C571 Test for stiffness of plastics by means of a cantilever beam
CRD C572 Specifications for polyvinyl chloride waterstop
CRD C573 Test for rubber properties in tension
US Federal Specifications (US)
SS S1614 Sealing compound, jet-fuel resistant, hot-applied, one-component, for Portland
cement and tar concrete pavements
TT C598C Caulking compound oil and resin base type (for building construction)
TT S00227E Sealing compound elastomeric type, multi-component (for caulking, sealing, and
glazing in buildings and other structures)
U.S. Federal Test Method Standard No. 601 for rubber waterstops
J3.3.1 General
Requirements for submissions by the Contractor in relation to concrete work are described in the
relevant clauses of these Specifications. For convenience, these submissions are summarised
hereunder.
The Contractor shall also submit appropriate mill analysis and laboratory test data of samples
tested by the supplier. Mill analysis and test data shall be representative of materials furnished
for the Permanent Works. The frequency of sampling and testing by the supplier shall conform to
applicable standards.
All materials that may be in contact with water that is or will become part of a potable supply
shall be approved for such contact in accordance with the relevant requirements of Part A of the
Specification.
J3.3.4 Samples
The Contractor shall provide samples of all materials, together with manufacturers' technical
information, to be used in the Permanent Works as may be required by the Engineer. Reference
samples shall be kept in suitable containers, properly labelled, and stored on Site.
J3.4 MATERIALS
J3.4.1.1 General
Cementitious materials shall normally consist of Ordinary Portland cement (OPC), Sulphate
Resistant Cement (SRC), or a combination of OPC, or SRC and pozzolanic material (either raw
or calcined natural pozzolan, fly ash or blast-furnace slag). The sources of cement and pozzolanic
material shall be proposed by the Contractor and shall be subject to approval by the Engineer.
J3.4.1.2 Cement
Cement used in the Permanent Works shall conform to ASTM C595, with the additional
requirements that the cement shall:
a) have a reduction of mortar bar expansion greater than 75% at 14 days when tested in
accordance with ASTM C441 and compared to the expansion of mortar bars made
with the cement having a zero slag content,
b) have a heat of hydration of less than 70 calories per gram at 7 days when tested in
accordance with ASTM C186,
c) be non-false setting, defined as having a minimum final penetration of 50% of initial
penetration when tested in accordance with ASTM C451, and
d) have an autoclave expansion or contraction of less than 0.8% when tested in
accordance with ASTM C151.
The Contractor may propose alternatives to the above for the approval of the Engineer including:
e) separate furnishing of slag or other pozzolanic materials and OPC conforming to BS
12 for blending at the Site, provided that the blend conforms with all the above
additional requirements;
f) use of a Portland low alkali cement (having a reactive alkali content not exceeding a
maximum value of 0.6% by mass as Na2O) meeting all the above additional
requirements.
Preference shall be given to the use of cement with a total alkali content, expressed as the sodium
oxide (Na2O) equivalent, not exceeding 0.6%, where: % Na2O equivalent = % Na2O + (0.658 x
% K2O).
Should it not be possible to obtain cement with a total equivalent alkali content as low as 0.6%,
then the potential occurrence of alkali aggregate reaction (both alkali silica and alkali carbonate)
with the specific aggregates to be applied must be investigated through laboratory testing.
the shipments in the order in which they are received. Sufficient cement from a single source
shall be in storage at the Site to complete any lift of concrete started. Adequate storage capacity
shall be furnished to provide sufficient cement to meet the peak needs of the approved
construction schedule.
Cement of different types and from different sources shall be kept in clearly marked separate
storage facilities. Cement delivered to the Site in drums or bags provided by the supplier or
manufacturer shall be stored in the unopened drums or bags until used in the Permanent Works.
Any cement in drums or bags which have been opened on the Site shall be used immediately, or
shall be disposed of. Unless otherwise permitted, cement from not more than three plants shall be
used and, in general, only the product of one plant shall be used in any particular section of the
Permanent Works.
Any cement which is, in the opinion of the Engineer, lumpy or partially set shall be rejected and
the Contractor shall promptly remove such cement from the Site. Cement which has been stored
on the Site for more than 91 days and cement which, in the opinion of the Engineer, is of
doubtful quality shall not be used in the Permanent Works unless it is retested and the test results
show that it complies in all respects with these Specifications. Cement stored on Site for more
than 183 days shall not be used in the Permanent Works and shall be removed promptly from the
Site by the Contractor.
Accurate records of deliveries of cement and its use in the Permanent Works shall be kept by the
Contractor. Copies of these records shall be supplied to the Engineer in such form as he may
require.
J3.4.3 Aggregates
J3.4.3.1 General
Aggregates for concrete shall be processed and shall consist of natural particles or a blend of
natural and manufactured particles. Aggregates shall be produced from suitable material from
required excavations or borrow areas as approved by the Engineer. The approval of any source
from which aggregates are to be produced by the Contractor shall not be construed as
constituting approval or acceptance of all materials taken from the source.
The Contractor shall provide all labour and equipment and shall maintain a testing laboratory for
the quality control of aggregates produced for the Permanent Works. At least once per shift, the
Contractor shall sample and test for grading each coarse aggregate produced during that shift.
The gradation of fine aggregate shall be determined at a minimum frequency of one test per hour
of production unless, in the opinion of the Engineer, the test results show the aggregate grading
to be sufficiently consistent to allow less frequent testing. The Contractor shall also sample and
test aggregates for gradation at various stages in the processing, transporting, stockpiling and
reclaiming as may be required by the Engineer. The Contractor shall submit a daily report to the
Engineer which shall include production quantities and gradation test results.
The Contractor shall promptly correct any excesses or deficiencies in gradation of coarse and fine
aggregates during processing. Rejected or waste material shall be disposed of in approved areas
or re-processed.
The maximum percentages of deleterious substances in the fine aggregate, as delivered to the
mixer, shall not exceed the following values:
- Clay lumps and friable particles (ASTM C33) 1% by weight
- Shale 1% by weight
- Total of other deleterious substances (such as mica, 1% by weight
chlorite, coated grains and soft flaky particles)
The sum of the percentages of all deleterious substances shall not exceed 2% by weight.
Aggregates shall be tested in accordance with ASTM C40 for content of organic impurities. Any
aggregate producing a colour darker than the standard shall be rejected.
When tested in accordance with ASTM C136, fine aggregate shall be uniformly graded within
the following gradation requirements:
U.S. Standard Percent Passing
Sieve Size by Weight
9.5 mm (0.375 in.) 100
4.75 mm (No. 4) 95-100
2.36 mm (No. 8) 80-100
1.18 mm (No. 16) 50-85
0.60 mm (No. 30) 25-60
0.30 mm (No. 50) 5-30
0.15 mm (No. 100) 0-10
75 µmm (No. 200) 0-3
Fine aggregate, as delivered to the batching and mixing plant storage bin, shall have a uniform
and stable free-moisture content which shall not exceed 7%. Excessive moisture shall be
removed mechanically or by the 3-pile drainage method.
The Contractor shall protect the piles of fine aggregate against inclement weather. Windbreaks
shall be provided where aggregates might suffer contamination by wind-blown materials.
J3.4.4 Water
Water for washing aggregates and mixing concrete shall be reasonably clean and free from the
detrimental amount of salts, alkalis, oil, organic matter or other deleterious substances and shall
comply with the recommendations contained in the Appendix to BS 3148. The concentration of
sulphates and chlorides shall be such that the concrete mix as a whole complies with the limits of
salts content also recommended in BS 3148.
River water is suitable for the mixing and curing of concrete. However, during floods, the river
water will contain silt and some ponding to settle out the sediments may be necessary under such
circumstances.
The Contractor shall make arrangements to protect water from direct sun and contamination by
wind-blown materials. The Engineer shall order retesting of water whenever deemed necessary.
J3.4.5 Admixtures
Admixtures shall mean chemical materials added to the concrete materials during mixing for the
purpose of altering the properties of the concrete mix. They shall not contain calcium chloride.
The Contractor shall furnish and use a water-reducing and/or water-reducing set-retarding
admixture as approved by the Engineer. The water-reducing and/or water-reducing set-retarding
admixture shall conform to ASTM C494, Type A or D as appropriate. The amount of admixture
used per batch shall be proposed by the Contractor for the Engineer’s approval following suitable
tests but, in general, the amount will be in accordance with the manufacturer's recommendations.
No admixture shall be considered for approval that has not been used with satisfactory service in
works of similar nature. A manufacturer's technical data sheet and certification of compliance
with ASTM C494, Type A or D as appropriate, shall be submitted at the time of request for
approval. After approval is granted, a manufacturer's certificate of compliance shall be furnished
with each shipment to the Site. Admixtures may be sampled and tested by the Engineer for
compliance with ASTM C494. If tests prove that any admixture which has been delivered is
unsatisfactory, it shall be promptly removed from the Site.
The Contractor shall furnish and use an approved air-entraining admixture in all concrete unless
otherwise approved or instructed by the Engineer. The air-entraining admixture shall be a
neutralised vinsol resin and shall conform to the requirements of ASTM C260.
The admixtures shall each be accurately batched by mechanical batcher and shall be added in a
manner which ensures uniform distribution throughout the batch.
The compatibility of different admixtures used in the same batch shall be established to the
satisfaction of the Engineer.
The amount of air-entraining admixture used in each concrete mix shall be just enough to cause
entrainment of air in the following percentages when concrete is discharged from the mixer:
Nominal maximum size of coarse
Total percent of air by volume
aggregate
75 mm (3 in) 4 to 5*
37.5 mm (1 ½ in) 4 to 6
19.0 mm (3/4 in) 5 to 7
* based on the minus 37.5 mm portion of a sample after sieving through a 37.5 mm sieve.
Field tests on air-entrained mixes shall be made in accordance with ASTM C231. Concrete
produced with air contents exceeding the above limits may be rejected by the Engineer.
Admixtures shall be stored in suitable containers which will maintain them in uniform solution
and will protect them from weather and contamination.
Admixtures which have been in storage for more than 6 months shall not be used unless retest
proves them to be satisfactory. Costs of all such retests shall be borne by the Contractor. Rejected
materials shall be removed immediately from the Site.
Waterstop shall be dense, homogeneous and free of holes or other imperfections. The cross
section shall be uniform along the length and symmetrical transversely so that the thickness at
any given distance from either edge will be uniform. Where not otherwise shown on the
Drawings:
• the width of the waterstop shall be not less than 80% of the thickness of the concrete
section and not less than 230mm;
• the web thickness shall be not less than 9mm in the case of waterstop for use within
the concrete thickness or 5mm in the case of waterstop for use on the outer face;
• all waterstop shall incorporate a solid bulb or major rib at or near each edge;
• waterstop wider than 180mm which is for use on the outer face shall incorporate a
total of at least two major ribs each side of the centreline;
• waterstop at movement joints shall incorporate a central hollow bulb;
• waterstop for use at induced contraction joints shall incorporate a crack inducer;
• waterstop for use within the concrete thickness shall be of rubber.
Rubber waterstop shall be of natural rubber, suitable synthetic rubber, or a blend of the two. PVC
waterstop shall be of an elastomeric plastic compound; no reground material shall be used.
All intersections and junctions in waterstop shall be factory-produced by the manufacturer of the
waterstop, normally as moulded special pieces, so that the only joints remaining to be made at
Site shall be straight butt joints between straight lengths of waterstop of the same section and
material. Jointing materials used in the work shall conform to the following standards:
Material Standard
ASTM D1190 or US SS S1614 Sealer;
Hot-poured joint sealing compound
Hot-poured type for joints in concrete
Cold application type ASTM D1850
Polysulphide-base or
US TT S00227E
polyurethane-base joint sealant
Preformed expansion joint filler ASTM D1751, ASTM D1752 Type II
US TT C598C, Grade 1 or 2, colour as shown
Caulking compound
on the Drawings or as approved
Extruded plasticised polyvinyl US COE Specification CRD C572 for
chloride resin (PVC) waterstop polyvinyl chloride waterstop
PVC waterstop shall be extruded from an elastomeric plastic compound, the basic resin of which
shall be PVC. The compound shall contain such additional resins, plasticizers, stabilisers or other
materials needed to ensure that when the compound is extruded to the shapes and dimensions
shown, it will have the following physical characteristics, when tested by the US Army Corps of
Engineers test method specified below:
Test method
Physical characteristics Requirement
(US COE)
Tensile strength using die III not less than 12 MPa C568
Ultimate elongation using die III not less than 350% C573
Low temperature brittleness, no sign of failure
2° C C570
such as cracking or chipping at
Stiffness in flexure, 12.5 mm span, not less than 2.75 MPa C571
Rubber waterstops shall be of natural rubber, synthetic rubber or a blend of both the rubbers.
When tested in accordance with U.S. Federal Test Method Standard No. 601, rubber waterstops
shall have the following properties:
Physical characteristics Requirement Test method
Tensile strength - not less than 17 MPa 4111
Elongation at break - not less than 450% 4121
Tensile strength at 300% elongation - not less than 6 MPa 4131
Durometer hardness - Shore Type A 60-70 3021
Water immersion, change in weight - maximum 5% 6631
Tensile strength after ageing; percent of tensile
strength before ageing (oxygen bomb method) not 55 7111
less than
Compression set – maximum 30% 3311
Adhesion on 510 grams cotton fabric - not less than 320 grams/mm 8011 and 8021
Where there is no appropriate standard to which reference may be made in respect of any
proprietary jointing material, the Contractor shall prove by demonstration, tests or otherwise the
suitability, adequacy and performance of the material under Site conditions. In other instances
the Contractor shall supply manufacturer's test sheets to certify compliance with relevant quality
standards. Only such materials as have been approved by the Engineer shall be used in the
Permanent Works.
Where bond-breaking coating or bitumen coating for application to concrete surfaces to prevent
bonding of fresh concrete to concrete previously placed is shown on the Drawings it shall be a
bituminous paint or other compound of a type that will adhere to damp surfaces of concrete and
perform its function of breaking bond without any damage to the new concrete. The Contractor
shall furnish detailed specifications and samples of the material he proposes to use for the
approval by the Engineer.
J3.4.8 Formwork
Formwork shall be constructed of timber, sheet metal or other approved material depending on
the class of finish to be obtained. The Contractor shall use only approved material for exposed
surfaces of the same class of finish.
Ties shall be of the rod and cone or other approved proprietary type. Embedded material rods
shall terminate not less than 50 mm inside the formed faces of the concrete. Wire ties shall not be
permitted.
Ties for use in water-retaining structures, which are continuous through the section, shall
incorporate a diaphragm, not less than 50 mm diameter and 4 mm thick, welded normal to the
midpoint of the tie, designed to prevent water passing along the tie.
J3.4.10 Accessories
Spacer blocks for maintaining concrete cover to reinforcement shall be of concrete of the same
texture, colour and composition as the in situ concrete. They shall be cast in the form of a
truncated cone or pyramid with the smaller face having a minimum dimension of 50 mm (2 in).
PVC spacer blocks of colour matching with the concrete shall be used where formed surfaces are
designated F3 or F4. The Contractor shall submit samples and manufacturer's technical data to
the Engineer for his approval. They shall not be used for any surface that may be in contact with
water.
Chairs and other accessories for maintaining reinforcement in position shall be of steel and shall
not be placed within the specified minimum cover to steel. Binding wire shall be 2 mm soft iron
wire.
• the load required to compress the test specimen to 50% of its thickness before test
shall be no less than 0.13 N/mm² or greater than 0.3 N/mm²;
• 10 minutes after release of the compressive load (or 1 hour if the retest provision
applies) the test specimen shall have recovered not less than 80% of its initial
thickness.
Joint filler for use in joints which may be submerged shall be of closed-cell polyethylene or self
expanding cork.
Joint filler for use in joints across which little load needs to be transferred shall be of sponge
rubber, closed-cell polyethylene or polyvinyl foam.
Capping strip to joint filler shall be of grey plasticised PVC, formed to shape and sized for use
with the appropriate thickness of joint filler.
J3.5 EQUIPMENT
J3.5.1 General
Plant and equipment shall be sufficient to meet the requirements of both the Specifications and
the construction programme. Special requirements for plant and equipment for concrete
production are described below.
The aggregate production plant will be required to screen natural material in separate sizes and
crush the oversized down to the required sizes. The whole process will require plant for crushing,
sizing, washing, material handling, transportation equipment, conveyors and feeders.
mixer. This shall be accomplished by control of the batcher discharge gates. The operation of the
gates shall allow precise cut-off of the aggregate flow such that the exact required quantity is
discharged.
An approved electric resistance device shall be provided in the sand batcher for indicating
moisture content. The electrodes shall extend to within 300 mm of the batcher discharge gates.
The monitoring instrument shall be located in plain view of the plant operator. Plant controls
shall be capable of ready adjustment to compensate for varying moisture contents of aggregate
and for effecting changes in the concrete mix proportions.
The plant shall include suitable devices for the batching of each admixture. Admixtures may be
discharged with the fine aggregate, ice or water but in no case shall admixtures be permitted to
intermix until they enter the mixer. Equipment for admixture batching shall be designed for
visual confirmation of the accuracy of the measurement through a vertical glass cylinder. The
filling mechanism of the device shall be capable of ready adjustment to permit varying the
quantity of admixture. Equipment for admixture batching shall be within full view of the
operator and shall be interlocked with the other measuring mechanisms.
All batching equipment shall be interlocked so that a new weighing cycle cannot be started until
all batchers are completely emptied and the batcher discharge gates and valves are closed; the
batcher discharge gate cannot be opened until the correct weights of materials are in the batching
hoppers and the scales in balance; and the discharge gates can not be closed until all the materials
are entirely discharged from the hopper and the scales return to zero. The filling and discharge
valves for the water batcher shall be interlocked with the other weighing mechanism. The pipe
for delivering water to the mixer shall be such that leakage will not occur when the valve is
closed and the pipe will quickly drain without water trail.
The Contractor shall provide standard test weights and any other auxiliary equipment required
for checking the operating performance of each scale and other measuring device from zero to
full capacity of the scale or device within an accuracy of 0.2%.
The accuracy of the batching equipment in delivery of materials shall be as follows:
Cement: ± 2% of the required weight of material being weighed, or
± 0.3% of scale capacity, whichever is greater;
Pozzolan: same as cement material;
Water (ice): ± 2% of the required weight of material being weighed, or
± 0.3% of scale capacity, whichever is greater, or
± 1% of the required volume of material being batched or ± 5 litres, whichever is
greater
Aggregates: for each aggregate size,
± 3% of the required weight of material being weighed, or
± 0.3% of the scale capacity, whichever is greater.
Admixture: ± 0.3% of the required weight or volume of material being batched.
The plant computer control system shall have a capacity to input and store no less than 20
different mix designs. The proportions for each mix design shall be easily adjustable and shall be
based on aggregate weights in surface dry condition. Actual batch weights shall be automatically
adjusted by input of aggregate moisture contents and shall be readily changed within the system
as the aggregate moisture content changes. The system shall store and output the number and size
of batches of each mix design batched and the cumulative quantity of each material used during
each shift of operation.
All batching and mixing operations shall be automatically operated by the computer on
command. An accurate display shall be in full view of the operator which shall display the target
batch weights based on mix design used and, when batching is completed, the actual batch
weights of each material. The system shall not discharge materials from the batchers until all
materials are within tolerance. A printed record shall be made showing the mix design, target
batch weights, actual batch weights, moisture content of each aggregate, mixing time, placement
to which the batch is designated, date and time of day for each batch. The printed sheet shall be
made in triplicate and the original shall become the property of the Engineer upon completion of
each shift. The print-out shall be readily and conveniently available for review by the Engineer at
any time during concrete production and a copy of the print-out for each batch shall travel with
the concrete to the placement area.
The plant operator's platform shall be closed, air-conditioned, soundproofed, completely
protected from dust and vibration and shall be positioned where the operator can readily observe
the mixing action of concrete in at least one mixer and the discharge of all mixers. Suitable
location of the operator will be required for adequate control of concrete consistency. In addition,
the plant shall include facilities for sampling each aggregate size from under the storage bin
gates.
The plant shall be equipped with one or more batch type tilting drum mixer, vertical shaft pan
mixer, or horizontal shaft pan mixer and a discharge hopper. Each mixer shall be capable of
combining the aggregates, cement, pozzolan, admixtures and water (including ice) into a uniform
mixture, in colour and consistency, and of discharging the mixture without segregation. The
mixers shall be interlocked with the batching plant such that they cannot be charged until empty
or discharged until the required mixing time has elapsed. The Contractor shall be required to
prove the adequacy of his proposed mixing time for each mix to be manufactured. Mixing time
shall start when all solid materials are in the mixer. The timing device for mixing time on each
mixer shall be equipped with a bell or other suitable warning device adjusted to give a clearly
audible signal to the plant operator each time mixing is completed. The mixing plant shall have
means for readily wasting material or concrete that is improperly batched, mixed, or held in the
mixer too long.
The discharge hopper shall be fitted with a suitable device to facilitate obtaining representative
samples of concrete and delivering them to the ground for unit weight and consistency tests. All
necessary platforms, tools, equipment and personnel to assist the Engineer in obtaining samples
shall be furnished by the Contractor.
The Engineer will conduct mixer performance tests in accordance with ASTM C94 to determine
the uniformity of the mix when mixed to the specified or approved mixing time. Should the
mixer performance tests show that operations fail to result in the required uniformity of
composition and consistency of concrete within the mixed batch, the Engineer may require
repairs to the mixing plant or increase in mixing time until satisfactory results are achieved. If the
repairs do not remove the defects from the mixing plant and the necessary increase in the mixing
time could affect the production progress, the Engineer may order immediate removal of the
defective mixing plant or provision of additional mixer capacity.
The mixer shall revolve at a uniform speed and shall not be charged in excess of the capacity
recommended by the manufacturer. Excessive over-mixing, requiring addition of water to
preserve the required consistency, will not be permitted.
Should any mixer at any time produce unsatisfactory results, its use shall be promptly
discontinued until it is repaired or replaced. Mixers shall be maintained in clean and good
working condition at all times.
Each mixer shall have attached in a prominent place a manufacturer's plate showing the capacity
of a drum or pan in terms of volume of mixed concrete and the speed of rotation of the mixing
drum or blades.
The batching and mixing plant shall be maintained free of set concrete or cement and shall be
clean before commencing mixing. The accuracy of calibration of every weighing device, water
measuring device and admixture dispenser, shall be checked by the Contractor in the presence of
the Engineer before carrying out trial mixes, before the first mixing of concrete for inclusion in
the Works, after each service or adjustment to the mixing plant and in any case at least once per
month.
J3.6 WORKMANSHIP
measured on specimens of apparently identical concrete show statistical variations that follow a
Normal Distribution and this variation can be measured as the Coefficient of Variation (standard
deviation / mean strength). A certain proportion of test results can be below the Characteristic
Strength and this proportion is termed the Failure Rate. For each Failure Rate there is a factor
derived from the properties of the Normal Distribution which when multiplied by the Standard
Deviation gives the Margin. This factor is 0.842 for a failure rate of 20%, 1.280 for a Failure
Rate of 10% and 1.645 for a Failure Rate of 5%. The Target Strength is the sum of the
Characteristic Strength and the Margin. The Target Strength shall be the strength used as a basis
for design of the mixtures. At the commencement of the concrete programme the Standard
Deviation will not be known. Coefficients of variation can be estimated on the basis of
characteristics of concrete manufacture, transport, placing and other factors. Until such times as
the strength test data from the concrete mixtures are available and reliable coefficients of
variation calculated, the Coefficient of Variation shall be 30% for a tilting drum mixer
installation and 25% for a twin-shaft batch type pug-mill mixer installation. These coefficients
are based on truck transport between the mixers and the point of placement. The allowable
Failure Rate for all Classes of conventional concrete shall be 10%.
As strength data from production mixes becomes available, the variance (Standard Deviation)
and a revised Target Strength shall be calculated. Based on all the information available, the
Contractor shall propose adjustments to the mix proportions to reflect the revised Target Strength
for the Engineer’s approval. For the purposes of determining the variance (Standard Deviation)
for any one Class of concrete a series of test results from not less than 40 separate batches of
concrete from the same batch plant produced over a period of not less than 5 days but not
exceeding 26 weeks shall form the basis for the determination.
The trial mix programme shall include mixes with a range of mix proportions for each Class of
concrete which will ensure that at least one mixture for each Class of concrete will conform to
this specification in all respects. Any delays caused by failure to produce mixtures which so
conform shall not relieve the Contractor of any of his obligations under the Contract. Under no
circumstances shall concrete of a particular Class be placed in the permanent works until the trial
mix programme has established the mix proportions for that concrete Class to the satisfaction of
the Engineer.
Test cylinders shall be cast from each mixture in sufficient numbers for testing at 3, 7, 14, 28 and
91 days after casting. The test cylinders shall be made and cured in accordance with ASTM C31.
The number of cylinders cast from each mixture and workability shall be not less than 18. The
cylinders shall be tested for compressive strength in accordance with ASTM C39.
The testing shall be carried out at the Contractor’s laboratory. The laboratory shall be furnished
with all equipment, facilities, personnel and materials necessary to perform the trial mix
programme including testing in accordance with the specified Standards.
The Contractor shall produce a report on the trial mix programme at the time of completion of
the manufacture of concrete cylinders, and shall provide all data from testing daily as the tests
proceed. The Contractor shall provide a final report which shall include all test data, description
of test procedures, evaluations of data and proposals for mix proportions to be used in various
Classes of concrete, including maximum allowable water/cementitious ratios, for the approval of
the Engineer. The Engineer will require 2 weeks to evaluate the proposals.
improve workability subject to the approval of the Engineer. Cementitious materials shall consist
of cement and pozzolanic material. Epoxy resin shall be used to produce epoxy concrete/mortar
when so ordered by the Engineer.
The design of the mixtures shall be based on securing a plastic workable mixture both suitable
for the specific conditions at placement and, when properly cured, a product having durability,
impermeability and strength in accordance with the requirements of the structures covered by
these Specifications. For all concrete placements, the Contractor will be required to handle and
place low-slump mixtures in order to achieve high-quality concrete, except for pumped concrete
for which the slump will be appropriate for the application. In the placement of any single
concrete lift, the Contractor may be required to handle and place several different concrete
mixtures containing different maximum size coarse aggregate for producing higher quality, more
durable exterior concrete and for placement in highly reinforced and congested areas. The
mixtures shall contain no more cementitious material than needed to meet the structural design
requirement. The use of pozzolanic material with OPC will result in a slow early rate of gain in
concrete strength, and the Contractor shall have due regard for this when designing his formwork
and planning his programme for form removal.
The Contractor shall keep the fine aggregate content to the minimum that is compatible with
producing a concrete with the maximum possible compacted density for that concrete Class as
well as other specified criteria.
Aggregate shall be a mixture of coarse and fine aggregate. Coarse aggregate shall consist of one
or more of the specified size ranges to produce a well graded aggregate mixture with the required
nominal maximum size aggregate. The nominal maximum size aggregate to be used in the
various parts of the Permanent Works shall be in accordance with the following unless otherwise
directed or approved:
NOMINAL MAXIMUM
GENERAL USE
AGGREGATE SIZE
37.5 mm Walls, columns and slabs – more than 300 mm thick.
Thin walls, slabs, and beams - up to 300 mm thick; heavily
19 mm reinforced concrete, pre-stressed concrete, and blinding layer
concrete.
In no event shall the nominal maximum size aggregate exceed one-fifth of the narrowest
dimension between sides of forms; one-third the depth of slabs; nor three-fourths of the
minimum clear spacing between individual reinforcing bars, bundles of bars, or post-tensioned
cable conduits.
The Contractor shall provide effective means such as pre-cooling of aggregates, refrigerating the
mixing water, adding flake, chip, crushed, tube, or other forms of ice up to the full amount of
added mixing water, or a combination of these or other methods, as necessary to maintain the
temperature of concrete at or below the specified temperature as it is placed. The size of the ice
particles shall be such that the ice is completely melted before the end of the mixing time for
each batch.
SLUMP (mm)
SPECIFIED CONCRETE WORK SPECIFIED SPECIFIED
WORKING
WORKING REJECTION
RANGE
LIMIT LIMIT
Mass concrete and reinforced
concrete walls, slabs and piers 50 25 to 50 75
more than 900 mm thick
Walls, slabs and columns less
75 50 to 75 100
than 300 mm thick
Bedding mortars 150 100 to 150 175
Under no circumstances shall the quantity of water and ice added cause the water/cementitious
ratio to exceed the maxima allowable as determined in the trial mix programme. If these limits
are exceeded in any batch of concrete, the batch will be rejected by the Engineer.
Concrete with a slump equal to or greater than the rejection limit as measured by the Engineer at
the point of placement will be rejected by the Engineer. Concrete consistency shall be uniform
from batch to batch. The Contractor shall vary the quantity of mixing water from batch to batch
if necessary to offset variation in free moisture content or grading of the aggregates. Water shall
not be added to compensate for stiffening of concrete held in the mixer too long or for delays in
placement.
The specified working limit is the permitted upper limit of a range of slumps selected to provide
the required concrete properties including the ability to be readily compacted by the specified
vibration equipment during concrete placement. The slump of concrete as placed shall average
approximately 10 mm less than the specified working limit. The 25 mm margin between the
working limit and the rejection limit is provided for occasional inadvertent batches which may
exceed the working range. Batches of concrete with slumps exceeding the working limit, but
within the inadvertency margin, will be rejected if the frequency of their occurrence is such that
the average of three successive tests exceeds the working limit by more than 12 mm.
Concrete that has been rejected for failure to meet slump limits shall not be used in the
Permanent Works.
The Contractor shall determine the aggregate grading of fresh concrete by wet sieving at least
once a day when concrete is being placed and at such times and locations as the Engineer may
direct.
Where there is evidence that concrete production and placement has resulted in work that does
not meet the quality requirements of these Specifications, core boring will be ordered by the
Engineer in accordance with ASTM C42. In the event that examination and tests on samples
removed from the structure show that the concrete does not conform to these Specifications,
measures as prescribed by the Engineer shall be taken by the Contractor to correct the deficiency.
The entire cost of testing and corrective action shall be borne by the Contractor.
Concrete samples containing aggregate particles larger than 37.5 mm shall be wet-screened to
remove such particles in accordance with ASTM C172 before making the slump test or casting
150 mm by 300 mm cylindrical compression test specimens.
- Clearance of the Engineer for concreting of the lift has been received.
In no case shall the cover be less than 1.5 times the maximum size of the aggregate used in the
concrete, nor 2.5 times the maximum diameter of the steel reinforcement.
Top reinforcement in slabs shall be maintained in position with the use of chairs, sized and
spaced to provide adequate support and fixity for the reinforcement. The reinforcement closest to
the form shall be positioned parallel to the direction of flow in water passages.
No part of the reinforcement shall be used to support formwork, access ways, working platforms,
or the placing equipment or for the conducting of an electric current.
curvature, the form lumber or plywood shall be built up of laminated splints cut to make tight,
smooth form surfaces.
All exposed joints, edges and external corners shall be chamfered 1 in x 1 in (25 mm x 25 mm)
except when shown otherwise on the Drawings. Internal corners shall be filleted as indicated on
the Drawings or as directed by the Engineer. Forms for external concrete surfaces shall not be
constructed continuous but shall be removed and reset for each placement. Form sheathing shall
not overlap previously placed hardened concrete by less than 1 in (25 mm) and shall be drawn
tight against the hardened concrete so that an offset at the construction joint and loss of mortar
are avoided.
Minimum times shall be determined by the Engineer when pozzolanic materials are used.
Cold weather is defined as the situation where either or both of the following conditions exist at
the Site:
- The air temperature at the time considered is below 2° C.
- The mean daily air temperature over three or more successive days has dropped below
5° C.
Normal weather is at all other times.
Where soffit formwork is constructed in a manner that allows the removal of the majority of the
formwork and the retention, during and after such removal, of a sufficient number of adequate
supporting props in an undisturbed condition, the Contractor may, with the agreement of the
Engineer, remove the formwork at the earlier times listed above provided that the props are left
in position and are not disturbed during removal of the majority of the formwork.
Notwithstanding the foregoing, the Contractor shall be held responsible for any damage arising
from removal of formwork before the structure is capable of carrying its own weight and any
incidental loading.
placement will not relieve the Contractor of his responsibility for their adequacy and the
Contractor shall remain solely responsible for satisfactory construction of the Permanent Works.
For each concrete placement, the Contractor shall provide the Engineer with written notice, a
drawing and a pre-placement checkout sheet signed by the Contractor's appropriate supervisory
personnel that demonstrate that foundation preparation, construction joint cleanup, formwork,
installation of reinforcing steel, block-outs and all embedded items for the placement have been
completed according to the Drawings or as specified. Before concrete placement is permitted,
each item on the checkout sheet shall be initialled by the Engineer showing that the item has been
inspected and is ready to receive concrete. Concrete placement will not be permitted when, in the
opinion of the Engineer, conditions prevent proper placement, consolidation, finishing and
curing.
Concrete mixed in stationary mixers and transported by non-agitating equipment shall be placed
within thirty minutes of mixing. When an agitator is used for transporting concrete, the concrete
shall be delivered to the site of the work and discharge shall be completed within 1½ hours after
introduction of cement to the aggregates except that, when the temperature of the concrete
exceeds 21° C, the time shall be reduced to 45 minutes. The concrete shall be placed within
20 minutes after it has been discharged.
Concrete shall be carefully placed in horizontal layers not exceeding 450 mm thick. Concrete
shall not be allowed to slide or flow down sloping surfaces, except in underground galleries, but
shall be placed in its final position from skips, trucks, barrows, down pipes or other placing
machine or device or, if this is impossible, it shall be shovelled into position with care being
taken to avoid separation of the constituent materials. Concrete placed in horizontal slabs from
barrows or other tipping vehicles shall be tipped into the face of the previously placed concrete.
Bedding mortars shall only be used when the Engineer so directs. Where bedding mortars are
directed to be used they shall be spread to the thicknesses and over areas given by the Engineer.
Bedding mortar shall be covered by concrete within 15 minutes of the bedding mortar being
placed. If this period should be exceeded the Engineer may direct the Contractor to remove the
bedding mortar and halt the concrete placement until such time as the area has been prepared for
receiving concrete.
Concrete dropped into place shall be dropped vertically. It shall not strike the formwork between
the point of its discharge and its final place. Concrete shall not be dropped freely through a
height greater than 1.5 m. Chutes and conveyor belts shall be so designed that there is no
segregation or loss of mortar and shall be provided with a vertical tapered down pipe, or other
device, to ensure that concrete is discharged vertically into place.
Where a lift of concrete is built up in a series of layers, each layer shall be properly merged into
the preceding layer before initial set takes place.
When pumps are used, the end of the supply pipe shall be arranged so as to avoid segregation.
Mortar or water used at the beginning or end of a run shall be discharged outside the formwork.
Where concrete abuts against earth or other materials liable to become loose or to slip, the
Contractor shall take steps to prevent any such loose material falling onto the surface of the
concrete.
The elapsed time between adjacent pours shall not be less than 14 days or as otherwise directed
by the Engineer.
When slabs or beams are monolithic with supporting walls or columns, there shall be a
construction joint near the top of the wall or column. The position of the joint shall be subject to
the approval of the Engineer.
When placing concrete directly onto existing concrete or new concrete that is more than 21 days
old the above maximum depths of concrete shall be half that given in the above table.
J3.6.20 Compaction
All concrete, other than blinding concrete, shall be compacted with power driven, immersion
type vibrators supplemented by hand spading and tamping.
Vibrators shall be inserted into the un-compacted concrete vertically and at regular intervals such
that the radius of action overlaps that of the previously vibrated concrete. A layer shall not be
covered with a succeeding layer until it has been thoroughly vibrated as specified. Where the un-
compacted concrete is in a layer above freshly compacted concrete, the vibrator shall be allowed
to penetrate vertically for about 100 mm (4 in) into the previous layer. In no circumstances shall
vibrators be allowed to come into contact with the formwork or embedded parts, nor shall they
be withdrawn quickly from the mass of concrete, but shall be drawn back slowly so as to leave
no voids. Internal-type vibrators shall not be placed in the concrete in a random or haphazard
manner, nor shall concrete be moved from one part of the work to another by means of the
vibrators. Care shall be taken properly to vibrate concrete placed in contact with previously
placed concrete or embedded parts.
The duration of vibration shall be limited to that required to produce satisfactory compaction,
without causing segregation. Compaction of the concrete by vibration shall be such as to produce
a concrete that has the maximum practicable density, is free from pockets of coarse aggregate
and entrapped air and makes complete contact with the foundation, previously placed hardened
concrete, embedded items and the formwork.
Blinding concrete shall be compacted by hand spading and tamping.
J3.6.23 Joints
The operation employed shall be continued until all unsatisfactory concrete, all laitance, coatings,
stains, debris and other foreign materials are thoroughly removed. Before concreting is resumed,
all loose matter shall be completely removed and the surface shall be clean and slightly wet.
The method used in disposing of waste water employed in cutting, washing and rinsing of
concrete surfaces shall be such that the waste water does not stain or discolour the exposed
surfaces of the structure. Methods of disposal shall be subject to approval by the Engineer.
Should any delay in placement occur so that previously placed concrete begins to stiffen, the
exposed leading edge of the placement shall be thoroughly vibrated to a uniform and stable
slope. The sloping surface shall be treated as a construction joint and shall be properly cleaned
before covering with fresh concrete.
The Contractor shall submit his proposals, which shall be subject to approval by the Engineer,
for all construction joints not shown on the Drawings.
Caulking grooves shall be provided as shown on the Drawings. At all joints where a caulking
groove is formed, immediately prior to caulking, the groove shall be sand-blasted or high
pressure water blasted and loose material removed and blown out by compressed air. After the
groove has dried, it shall be primed and caulked with approved caulking compound in strict
accordance with the manufacturer's recommendations.
Swelling waterstop shall be fixed in accordance with the manufacturer’s recommendations.
The coating shall be continued to at least 150mm above the ground surface. Where exposed
above ground two additional coats of an aluminium paint shall be applied or as many coats as are
necessary to ensure bleed of the bitumen system through the top coat does not occur.
Blinding concrete to 75mm thickness shall be provided beneath all structural concrete. Blinding
to buildings shall be placed over two layers of polythene sheeting to prevent damp rising.
Blinding to water tanks shall omit the polythene sheet to enhance friction resistance.
of form shall be at least 1 m in the direction of movement. The screed shall be drawn up the
slope at a steady and uniform rate which shall be consistent with the rate of concrete placement.
The screed shall ride on guide rails which shall be located outside the placement. The required
finish shall be applied to the concrete emerging from the trailing edge of the form. The slip-form
screed shall be subject to the approval of the Engineer.
MAXIMUM TOLERANCE
CLASS OF
FINISH LINE AND ABRUPT GRADUAL CONCRETE
LEVEL IRREGULARITY IRREGULARITY DIMENSION
U1, F1 12 mm 6 mm 12 mm +12 mm –6 mm
U2, F2 6 mm 6 mm 6 mm +12 mm –6 mm
U3, F3 6 mm 3 mm 6 mm +12 mm –6 mm
U4, F4 6 mm 0 6 mm +12 mm –6 mm
Where, in the opinion of the Engineer, the defect is too extensive to permit satisfactory repair,
either from the point of view of structural integrity or appearance, the concrete containing the
defect shall be broken out and replaced at no cost to the Employer.
less than 3m 6 mm
additional for every subsequent 3m 3 mm
When considering the squareness of a corner, the longer of the two adjacent sides being checked
shall be taken as the baseline, and a line perpendicular to the baseline shall be taken as the check-
line. The distance of the shorter side from the check-line shall be such that the difference
between the greatest and shortest such distances shall not exceed:
J4.1 GENERAL
J4.1.1 Scope
This Section covers requirements for pipes, valves, fittings, cable ducts and appurtenances.
The main transmission pipelines and fittings shall be either Carbon Steel CS “For 1200mm &
1600mm Diameter pipes or Ductile Iron DI “Pipes smaller than 1000mm” unless otherwise
specified. For CS Pipes welding joints shall be used and joints at valve chambers and above
ground shall be bolted flanges. For DI Pipes joints shall be spigot and socket push in joints.
Joints at fittings shall be flanged, push fit or (bolted gland) mechanical joints. Valves shall have
flanged joints, and adapters for ease of dismantling.
Cable ducts shall be of uPVC or, where installed by trenchless methods, high density
polyethylene (HDPE).
J4.1.2 Definitions
The following terms shall have the meanings hereby assigned to them:
‘Pipes’ Straight pipes, whether whole or cut and their joints
‘Pipeline’ or ‘Pipework’ The whole pipeline inclusive of pipes, fittings, valves and pipeline
appurtenances
‘Fittings’ All components fitted to a pipe for jointing, connecting or changing
the direction or bore of a pipe (including bends, tees, tapers, collars
and couplings)
‘Valves’ Valves installed on the pipeline including isolation valves and air
valves
‘Pipeline appurtenances’ All items additional to pipes and fittings required to complete a
pipeline including but not limited to internal and external
protection systems, supports and anchors, chambers, marker posts
and any apparatus or construction required for testing, cleaning,
disinfecting or operating the pipeline
‘Ducts’ uPVC Pipeline inclusive of all fittings and appurtenances including
drawpits and draw cords
‘Accessories’ Nuts, bolts, gaskets, glands, lubricants and all other items necessary
to lay and joint the pipework
BS EN 545 Ductile iron pipes, fittings accessories and their joints for water
pipelines – Requirements and test methods
AWWA C651-99 Disinfecting water mains.
AWWA M12-02 Simplified Procedures for Water Examination. 5th Edition
BS 1377 Parts 1 to 9 Methods of test for soils for civil engineering purposes.
BS EN 681-1:1996 Elastomeric seals. Material requirements for pipe joint seals used
in water and drainage applications. Vulcanized rubber
BS EN 681-2:2000 Elastomeric seals. Material requirements for pipe joint seals used
in water and drainage applications. Thermoplastic elastomers
BS EN 681-3:2000 Elastomeric seals. Material requirements for pipe joint seals used
in water and drainage applications. Cellular materials of
vulcanized rubber
BS EN 681-4:2000 Elastomeric seals. Material requirements for pipe joint seals used
in water and drainage applications. Cast polyurethane sealing
elements
BS 7874:1998 Method of test for microbiological deterioration of elastomeric
seals for joints in pipework and pipelines
BS 970-1:1996 Specification for wrought steels for mechanical and allied
engineering purposes. General inspection and testing procedures
and specific requirements for carbon, carbon manganese, alloy
and stainless steels
BS EN 10088-1:1995 Stainless steels. List of stainless steels
BS EN 10088-2:1995 Stainless steels. Technical delivery conditions for sheet/plate and
strip for general purposes
BS EN 10088-3:1995 Stainless steels. Technical delivery conditions for semi-finished
products, bars, rods and sections for general purposes
BS EN 22063:1994 Metallic and other inorganic coatings. Thermal spraying. Zinc,
aluminium and their alloys
BS 2569-2:1965 Specification for sprayed metal coatings. Protection of iron and
steel against corrosion and oxidation at elevated temperatures
BS 3251:1976 Specification for indicator plates for fire hydrants and emergency
water supplies.
BS 3927:1986 Specification for rigid phenolic foam (PF) for thermal insulation
in the form of slabs and profiled sections.
BS EN 1295-1:1998 Structural design of buried pipelines under various conditions of
loading
BS 4190:2001 ISO metric black hexagon bolts screws and nuts
BS 4320:1968 Specification for metal washers for general engineering purposes.
Metric series.
BS EN 1092-1:2002 Flanges and their joints. Circular flanges for pipes, valves,
fittings and accessories, PN designated. Steel flanges
BS EN 1092-2:1997 Flanges and their joints. Circular flanges for pipes, valves,
fittings and accessories, PN designated. Cast iron flanges
BS EN 1515-1:2000 Flanges and their joints. Bolting. Selection of bolting
BS EN 545:2002 Ductile iron pipes and fittings, accessories and their joints for
water pipelines. Requirements and test methods.
ISO 7005-2:1998 Metallic Flanges: Cast iron flanges
ISO 2531:1998 Ductile iron pipes, fittings and accessories and their joints for
water or gas applications for pressure pipelines.
ISO 8179-1 01:2002 Ductile iron pipes - External zinc coating - Part 1: Metallic zinc
with finishing layer
ISO 8179-2 01:1995 Ductile iron pipes - External zinc coating - Part 2: Zinc rich paint
with finishing layer
AWWA C502-94 Dry-barrel fire hydrants.
AWWA C504-00 Rubber Sealed Butterfly Valves
BS EN 837-1:1998 Pressure gauges. Bourdon tube pressure gauges. Dimensions,
metrology, requirements and testing
BS EN 837-2:1998 Pressure gauges. Selection and installation recommendations for
pressure gauges
BS EN 837-3:1998 Pressure gauges. Diaphragm and capsule pressure gauges.
Dimensions, metrology, requirements and testing
BS 1041 Various Parts Code for temperature measurement
BS 1042 Various Parts Measurement of fluid flow in closed conduits.
BS EN 1982:1999 Copper and copper alloys. Ingots and castings
BS EN 1561:1997 Founding. Grey cast irons
BS EN 12163:1998 Copper and copper alloys. Rod for general purposes
BS EN 12164:1998 Copper and copper alloys. Rod for free machining purposes
BS EN 12167:1998 Copper and copper alloys. Profiles and rectangular bar for
general purposes
BS EN 1171:2002 Industrial valves. Cast iron gate valves
BS 3416:1991 Specification for bitumen-based coatings for cold application,
suitable for use in contact with potable water.
BS 4147:1980 Specification for bitumen-based hot-applied coating materials for
protecting iron and steel, including suitable primers where
required.
BS 4999 Various Parts General requirements for rotating electrical machines.
BS EN 13397:2002 Industrial valves. Diaphragm valves made of metallic materials
BS 5163:1986 Specification for predominantly key-operated cast iron gate
valves for waterworks purposes.
BS 6755-2:1987 Testing of valves. Specification for fire type testing requirements
BS EN 12266-1:2003 Industrial valves. Testing of valves. Pressure tests, test
procedures and acceptance criteria. Mandatory requirements
BS EN 12266-2:2002 Industrial valves. Testing of valves. Tests, test procedures and
acceptance criteria. Supplementary requirements
BS EN 593:2004 Industrial valves. Metallic butterfly valves.
BS EN 558-1:1996 Industrial valves – Face to face and centre to face dimensions of
metal valves for use in flanged pipe systems – PN designated
valves
ISO 8770 01:2003 Plastics piping systems for soil and waste discharge (low and
high temperature) inside buildings - Polyethylene (PE)
ISO 8772 01:1991 High density polyethylene (PE-HD) pipes and fittings for buried
drainage and sewerage systems; specifications
BS EN ISO 1461:1999 Hot dip galvanized coatings on fabricated iron and steel articles.
Specifications and test methods
BS 3643-1:1981 ISO metric screw threads. Principles and basic data
BS 3643-2:1981 ISO metric screw threads. Specification for selected limits of size
BS EN 12334:2001 Industrial valves. Cast iron check valves
ASTM D1000-99 Standard Test Method for Pressure-Sensitive Adhesive-Coated
Tapes Used for Electrical and Electronic Applications
ASTM D638-03 Standard Test Method for Tensile Properties of Plastics
ASTM D1004-03 Standard Test Method for Initial Tear Resistance of Plastic Film
and Sheeting
ASTM G13-89(1996)e1 Standard Test Method for Impact Resistance of Pipeline Coatings
(Limestone Drop Test)
ASTM D570-98 Standard Test Method for Water Absorption of Plastics
ASTM E96-00e1 Standard Test Methods for Water Vapor Transmission of
Materials
BS 4607-1:1984 Non-metallic conduits and fittings for electrical installations.
Specification for fittings and components of insulating material
BS 3505:1986 Specification for unplasticized polyvinyl chloride (PVC-U)
pressure pipes for cold potable water
BS EN 1452-1:2000 Plastics piping systems for water supply. Unplasticized
poly(vinyl chloride) (PVC-U). General
BS EN 1452-2:2000 Plastics piping systems for water supply. Unplasticized
poly(vinyl chloride) (PVC-U). Pipes
BS EN 1452-3:2000 Plastics piping systems for water supply. Unplasticized poly
(vinyl chloride) (PVC-U). Fittings
BS EN 1452-4:2000 Plastics piping systems for water supply. Unplasticized poly
(vinyl chloride) (PVC-U). Valves and ancillary equipment
BS EN 1452-5:2000 Plastics piping systems for water supply. Unplasticized poly
(vinyl chloride) (PVC-U). Fitness for purpose of the system
BS 4660:2000 Thermoplastics ancillary fittings of nominal sizes 110 and 160
for below ground gravity drainage and sewerage
BS EN 13598-1:2003 Plastics piping systems for non-pressure underground drainage
and sewerage. Unplasticized poly (vinyl chloride) (PVC-U),
polypropylene (PP) and polyethylene (PE). Specifications for
ancillary fittings including shallow inspection chambers
BS 5481:1977 Specification for unplasticized PVC pipe and fittings for gravity
sewers
BS EN 1401-1:1998 Plastics piping systems for non-pressure underground drainage
and sewerage. Unplasticized poly vinylchloride (PVC-U).
Specifications for pipes, fittings and the system
ASTM B418-01 Standard Specification for Cast and Wrought Galvanic Zinc
Anodes
BS EN 12201-1 Plastics piping systems for water supply Polyethylene (PE), Part
1 – General
BS EN 12201-2 Plastics piping systems for water supply Polyethylene (PE), Part
1 – Pipes
BS EN 12201-3 Plastics piping systems for water supply Polyethylene (PE), Part
1 - Fittings
ANSI/ASME B16.9 Factory made wrought butt-welding fittings.
ANSI MSS-SP-97 Integrally reinforced forged branch outlet fittings - socket
welding, threaded and butt welding ends.
ASME B16.11 Forged fittings, socket welding and threaded.
ASME B36.10M Welded and seamless wrought steel pipe.
BS EN 1092-1 Flanges and their joints. Circular flanges for pipes, valves,
fittings and accessories, PN designated. Steel flanges.
BS EN 1514-1 Flanges and their joints.Dimensions of gaskets for PN-designated
flanges. Non-metallic flat gaskets with or without inserts
BS EN 1515-1 Flanges and their joints.Bolting. Selection of bolting
BS EN 1515-2 Flanges and their joints.Bolting.Classification of bolt materials
for steel flanges, PN designated
BS 7361-1 Cathodic protection. Code of practice for land and marine
applications
BS EN 10204 Metallic materials - Types of Inspection Documents.
BS EN 13480-1 Metallic industrial piping. Part 1: General
BS EN 13480-2 Metallic industrial piping. Part 2: Materials.
BS EN 13480-3 Metallic industrial piping. Part 3: Design and calculation.
BS EN 13480-4 Metallic industrial piping. Part 4: Fabrication and installation.
BS EN 13480-5 Metallic industrial piping. Part 5: Inspection and testing.
BS EN 13480-6 Metallic industrial piping: Additional requirements for buried
piping.
BS EN 13480-7 Metallic industrial piping.Guidance on the use of conformity
assessment procedures.
BS EN 13636 Cathodic protection of buried metallic tanks and related piping.
NACE RP0286 Standard Recommended Practice - Electrical Isolation of
Cathodically Protected Pipelines
Welding & Joining
BS/EN 287-1 Approval testing of welders - Fusion welding - Part 1: Steels.
BS/EN 288-2 Specification and approval of welding procedures for metallic
materials - Part 2: Welding procedure specification for arc
welding.
BS/EN 288-3 Specification and approval of welding procedures for metallic
materials - Part 3: Welding procedure tests for arc welding of
steels.
BS/EN- 288-9: 1999 Specification and approval of welding procedures for metallic
materials - Part 3: Welding procedure tests for pipeline welding
Drawings
Submissions by the Contractor shall include but will not be limited to the following:
• Typical drawings of standard items.
• Detail drawings of special items.
• Setting out proposals for achieving curvature by joint deflection.
• Shop drawings for valve chambers and drawpits including:
- Details of pipes and fittings.
- Foundation and support details for pipes, valves and fittings.
- Setting out dimensions.
- Reinforcement details.
- Metalwork and supports.
- Valve spindle details.
- Method of building pipes into structure walls.
• Details of supports to buried services.
• Temporary work details, including temporary supports.
Data
Submissions by the Contractor shall include but will not be limited to the following:
• External protection details;
• Method for control of line and level of pipeline during installation
• Manufacturers’ calculations, catalogues and data sheets;
• Methods for pipe handling, installation and backfill;
Records to be kept
The Contractor shall keep detailed and up-to-date records in a form to be approved by the
Engineer of all pipes, fittings and pipeline appurtenances, the quantities of each type, size and
class which have been:
a) ordered during the course of the Works;
b) delivered during the course of the Works;
c) declared on delivery to be faulty, damaged or deficient;
d) broken, damaged or lost during the course of the Works;
e) repaired;
f) laid or installed.
Each week the Contractor shall provide the Engineer with an up-to-date copy of the above
records.
Certificates of tests
The Contractor shall forward to the Engineer the following certificates, where relevant:
a) works tests on pipes and fittings;
b) material tests;
c) inspections;
d) welder-qualification tests;
e) non-destructive tests on completed welds.
The Contractor shall submit for the approval of the Engineer details of his proposed methods and
programme for pipeline testing, swabbing, and cleaning (including details of test and cleaning
equipment).
J4.4 MATERIALS
J4.4.1 General
Materials shall be manufactured to the requirements specified and shall be provided by the
Contractor. All items shall be of the diameter and/or dimensions detailed in the Drawings and
shall be suitable for the test and working pressures specified or detailed on the Drawings. The
class and pressure rating shall not be less than that specified.
For the pipes and fittings that are offered to be used in the Works the Contractor shall give the
name and address of the factories at which the required material will be manufactured, together
with a complete specification in English language, catalogues, a certified programme of delivery,
and evidence of satisfactory service in similar installations for a period in excess of five years.
The normal temperature of the water in the pipelines will be up to 40ºC. All materials that are
close to or in contact with the water shall be suitable for long-term exposure to such
temperatures.
Before commencing manufacture the Contractor shall supply to the Employer for approval
detailed drawings for all the offered materials complete with all technical information, catalogues
and tabulation showing:
a) The overall dimensions of each type and size of the offered materials.
b) The chemical compositions of the various alloy components and the quality of metal
used for the offered materials.
Materials quoted must comply in every respect with this Specification.
so as to prevent injury to the coating. The use of tongs, bare pinch bars, chain slings, protruding
rivets, pipe hooks, or any other handling equipment that may be injurious to the coating shall not
be permitted. The coated pipes will be padded while being transported and the Contractor shall
take due account of the likely road condition throughout the year.
The bolster of the trailer shall have a bearing surface not less than 30 mm to give necessary
support to the padding which protects the coating. Sacks partly filled with sand or sawdust
should be placed on the bolster and between the outside bottom pipes and the bolster stakes
The maximum piling heights for various types of coated pipe shall be limited to such heights as
will prevent damage to pipe when nested with regular coated pipe.
J4.4.3 Damage
No pipes, fittings, valves or accessories with significant damage to the internal or external
coatings shall be installed. Where in the opinion of the Engineer damage to the coating is minor,
it shall be repaired as far as possible in accordance with the manufacturer’s recommendations to
the original coating system. Acceptance of repairs will be subject to the satisfaction and approval
of the Engineer
J4.4.4.1 General
Carbon Steel & Ductile iron pipes and fittings shall be procured from a supplier acceptable to the
Employer.
Pipes materials shall be selected based on the pressure requirements and conform to an ASTM or
BS EN Standard. Minimum yield point of steel shall be 38,000 psi. Pipe shall be manufactured as
fabricated pipe per AWWA C200 as modified herein.
J4.4.4.2.2 FITTINGS
All fittings shall be in accordance with the drawing and shall conform to ASME B 16.9 or
AWWA C208.
J4.4.4.2.3 FLANGES
Flanges shall be in accordance with ASME 16.47 Series B / BS 4504 rated at PN 16, 25 & 40
depend on the location and specified pipes rating.
J4.4.4.2.4 Other
Pressure retaining fittings which are not made to approved standards, as e.g. ASME B16.9,
ASME B16.5 and BS EN 1092-1, shall be type approved or alternatively design approved.
ISO 15590-1:2001 Induction bends, fittings and flanges for pipeline transportation systems -
Part 1: Induction bends
The pipe material shall be compatible with the abutting pipe in accordance with the appropriate
Piping Class as specified.
The bends shall be manufactured by inductive heating and bending.
The bends manufactured from longitudinal welded pipe shall have the weld seam placed in the
tensile zone between 10 and 45 degrees from the neutral axis.
The bends manufactured from spiral welded pipe shall not contain skelp end welds.
The welding ends shall be delivered bevelled to match abutting pipe.
Each end of the bend shall have a straight tangential length not less than the nominal diameter.
The deviation from the stated bend angle shall not exceed 0.5 degree.
The end faces shall be perpendicular to pipe axis.
Minor defects may be removed by grinding provided that the minimum wall thickness is
maintained and the grinding does not exceed 300 mm in any direction.
NDE
The wall thickness shall be verified measured along the longest arc together with any area where
defects have been ground out.
The finished bends shall be examined by magnetic particle or dye penetrant for cracks.
General
Isolating couplings shall be installed at the interfaces between buried piping and piping
installations in buildings.
Functional requirements and materials
Coupling type
Design
The isolating coupling shall be designed in accordance with ASME VIII Div. 1 or PD 5500.
Construction
Bolted or threaded joints are not permitted. The design of welds joining coupling element and
pipe pup-pieces shall permit radiographic examination of joining welds.
Seals shall be made from continuously moulded precision "O" rings of dielectric material.
Bore shall be not less than 90% of abutting pipe internal diameter.
Welding ends shall match abutting pipe
Materials
Materials shall be fully killed fine grain carbon steel conforming to specified standards as
indicated in this Specification.
Pipe pup-pieces may be free issued to the Supplier by the Contractor. If this is not the case, pup-
piece material shall be in accordance with the relevant Piping Class Specification, and shall be
the same diameter and wall thickness as the line into which it will be installed.
Seals and dielectrics shall be inert and resistant to any blend of organic or inorganic corrosion
inhibitors and biocide microbiological growth inhibitors.
The isolating coupling Supplier shall obtain from the Contractor necessary information regarding
inhibitors to ensure appropriate selection of seal and dielectric material.
Surface treatment
The bore of the isolation coupling assemblies shall be lined with a coating as specified or to be
approved by the Engineer, with minimum DFT of 300 microns, having electrical and abrasion
resistance properties to prevent a decrease in electrical resistance across the isolation coupling
such as caused by debris bridging the isolating ring.
NDE
Hydrostatic testing
Each coupling shall be hydrostatically pressure tested to 1.5 times the system design pressure.
Initially, each coupling shall be subjected to 3 pressure cycles between 10% and 85% of the test
pressure.
The pressure test is accepted with the full test pressure applied for a minimum 1 hour.
Electrical test
The strength test shall be by 5000 V AC, 50 Hz shall be applied for a period of not less than one
minute during which no puncture of coating or formation of sparks may occur, and the leak
current differential shall not exceed 2 mA.
The resistance test shall be by application of 500 V DC with a measured electrical resistance
greater than 1 MΩ.
For piping materials with certificate, the charge number shall be transferred by permanent marker
to the pipe section so as to be able to identify the charge number of the pipe after welding.
These markings shall be removed after completed, approved and documented control of the
system.
Weld bevels for butt weld of pipes and fittings shall be in accordance with the relevant Welding
Procedure Specification (WPS).
Welding processes
Tungsten inert gas arc welding (TIG welding) for use in draught-free workshops.
Other welding processes are not acceptable unless agreed with the Engineer prior to fabrication.
Welding consumables
All consumables shall be low hydrogen type with maximum 5 ml hydrogen/100 g weld metal
(mercury method in accordance with BS EN ISO 3690).
Other consumables are not acceptable unless approved by the Engineer prior to qualification of
welding procedures or fabrication.
The chemical composition of the deposited weld metal shall be selected to ensure adequate
resistance to degradation under the intended operating condition.
All welding materials shall be delivered in hermetically sealed containers and stored in a clean,
dry, indoor area until used.
Wet or damaged electrodes, contaminated flux, and rusty filler wire shall be rejected.
Before commencing the work, the Contractor shall submit detailed welding procedure
specification (WPS) complying with BS EN 288-2. Specification and approval of welding
procedures for metallic materials - Part 2: "Welding procedure specification for arc welding".
The Contractor shall confirm compliance of each welding procedure according to BS EN 288-3.
"Specification and approval of welding procedures for metallic materials. Part 3: Welding
procedure tests for arc welding of steels" and undertake qualification tests.
The qualification tests shall be performed on the same material as stated in the relevant piping
class specification.
All welding procedures together with qualification documents - Welding Procedure Qualification
Records (WPQR) must be handed to the Engineer for approval.
The documentation for WPQR and production tests shall ensure traceability between material
including welding consumables and the material certificate.
The WPS shall only refer to one WPQR which shall include both the low and high heat input
level.
Welders' Qualification
Prior to the performance of any production welding, welders and welding operators shall qualify
for the relevant welding procedures according to BS EN 287-1. Approval testing of welders -
Fusion welding. Part 1: Steel or alternatively in accordance with ASME IX, BPVC, Welding and
Brazing Qualifications.
The welder's performance qualification shall be carried out in accordance with an approved
qualified welding procedure.
Identification of welders
Welder's Performance Qualification (WPQ) certificates with photograph shall be used unless
otherwise agreed prior to fabrication.
Each qualified welder or operator shall be assigned a symbol, which shall always be visible
during welding.
The welder or operator shall mark his welds with his symbol.
A record shall be kept of the welder's or operator's work during the latest 12 months and be
available for the Engineer at all times.
General
The Contractor shall establish shielding to protect each welding site from rain and wind.
Preparation and welding of materials shall be in accordance with the specifications and qualified
procedures and approved by the Engineer.
All welds shall be marked with a weld number and welder's designation.
These marks may be removed after completion and approval of the weld.
Welded connections
Adjacent sections of welded pipe that are joined by butt welding shall have the longitudinal
seams positioned so that they are at least 15 degrees apart.
Wherever possible the longitudinal weld seam shall be positioned so that branch connections
such as couplings, o'lets etc. is clear of the weld seam.
Butt welds between materials of different wall thicknesses shall be tapered by scarping the parent
material at a taper of 1:4.
Should the strikes occur, they shall be repaired in accordance with the procedures approved by
Contractor's QA department and Engineer's approved welding repair procedure.
Tack welds
Tack welds shall be of a minimum length of four times the base metal thickness or 50 mm, which
is the lesser, and shall be carried out in accordance with an approved welding procedure.
Tack welds that form part of the completed weld shall be ground to a feather edge, and
completely fused with the root run.
Cracked tack welds shall be completely removed by grinding and shall not be incorporated into
the finished weld.
After removal, the parent material shall be examined by magnetic particle or liquid penetrant to
ensure that crack propagation from the tack weld into the parent plate has not occurred.
Weld interruption
Welding shall not be discontinued until 25% of the weld thickness or 3 passes are complete,
whichever is more stringent.
At this stage, the weld profile should be con- cave, particularly at the weld material/parent plate
interface.
Weld repairs
All corrective work consisting of removal of defects and deposition of repair welds shall be
carried out in accordance with the qualified repair welding procedure or, alternatively, the
deposition of repair weld shall be in accordance with a welding procedure qualified for the
original weld.
The removal of defective areas shall be carried out by machining, grinding, chipping or arc/air
The resulting cavity shall be clean, free from scale and have a contour to permit ease in repair
welding.
If the Engineer has reasonable doubts of the welding quality, for example if during the periodical
parameter checks it is observed that the welding is not performed in accordance with the relevant
approved WPS, the Engineer may require production tests to be performed.
The production tests shall be taken directly from the production welds when it is technically
possible and the Engineer reserves the right to select the test welds.
All costs related to the production tests shall be to the Contractor’s account.
If the production test does not fulfil the requirements, the cause of failing shall immediately be
established and brought to the attention of the Employer.
The PAEW or his representative may specify further testing or the rejection of the represented
production welding.
The importance of cleanliness has been addressed in the context of materials handling and
storage. It is even more important during welding. Further recommendations are contained in BS
EN 1011-3.
Prior to welding, the weld zone and Heat Affected Zone shall be free from oil, grease, other
surface contamination and excessive oxidation.
Contamination of weld zone, particularly by iron, copper, zinc, lead, shall be minimised to extent
possible. Tooling shall chosen and used accordingly, e.g. iron-free slitting wheels and grinding
disk, stainless steel brushes shall be used.
An inert backing gas or mixture shall be used to protect the penetration bead of single-sided, full
penetration welds from oxidation, including tack welds. The shielding shall be maintained for
sufficient duration to ensure that the finished weld surface and HAZ oxidation is contractually
acceptable. These requirements are essential for optimum corrosion performance where there
will be no access for subsequent cleaning of weld surface. Where the use of inert backing gas is
impractical, then a shielding paste or tape may be used as an alternative, after submitting a
suitable qualified procedure and obtaining Engineer's approval. The paste or tape shall be
completely removed after welding. Where access does not permit full removal, then mechanical
joint shall be used instead of welded.
Post-weld cleaning
The slag left by welding must be removed by careful hammering, care being taken to avoid
denting the adjacent metal surface
In order to achieve the optimum corrosion performance of stainless steel welded joints
contamination and discoloration deeper than Sample 4 in accordance with ANSI/AWS 18.2 shall
be removed. The method of removal shall be by mechanical dressing followed by acid pickling
of the joint. Electro polishing or sand blasting may be used as an alternative to acid pickling.
For mechanical cleaning, grinding and polishing, all abrasive media shall be iron-free and wire
brushes shall be made of a suitable grade of stainless steel wire, be stored in clean conditions and
not be used for any other purpose, to avoid contamination.
The physical properties of stainless steels require care during mechanical cleaning to prevent
overheating and associated heat discoloration. This phenomenon occurs when the surface
temperature exceeds 200°C. The pressure exerted by the disk or belt must be adjusted to the
minimum level allowing satisfactory polishing without overheating.
The chemical treatment for removal of oxide film shall be by immersion in pickling bath
followed by abundantly rinsing with chlorine-free water. Alternatively pickling paste or gel can
be employed thus limiting the treatment to the weld zones, followed by rinsing with chlorine-free
water.
After pickling the metal surface is unprotected and new passive layer must be formed to restore
its corrosion resistance. The parts shall be immersed in passivating bath for required period of
time followed by rinsing with chlorine-free water. Alternatively passivating paste/gel shall be
used locally on weld zones followed by brushing and rinsing with chlorine-free water for
complete removal of passivating media.
The chemical treatment, pickling and passivation, shall be performed in accordance with
procedures prior approved by Engineer and samples of welded material, both prior and after
chemical treatment shall be retained through the contract as reference. These procedures may be
stand-alone or be a part of welding procedure.
Other examination methods may be acceptable upon agreement with the Engineer.
If, for any reasons, the Engineer or other parties have reason to believe that a weld contains
unacceptable defects, the Contractor shall use any of the above or alternative methods to
determine the acceptability of the weld with agreement with Engineer.
Qualification Requirements
The execution of all types of examination methods intended to be employed during fabrication
shall be qualified in accordance with relevant standard.
Examination Organization
Examinations carried out on behalf of the Employer shall be performed by personnel from an
inspection organization accredited in accordance with EN 45001.
The Engineer shall approve prior to commencing any testing procedures other examination
organizations if so required.
The organization shall employ minimum one level 3 person certified according to BS EN 473.
Examination Personnel
All personnel shall be certified in accordance with BS EN 473 or in accordance with ASME V:
BPVC Section V Nondestructive Examination.
Other qualifications shall be agreed by the Engineer, who reserves the right to require re-
examination or rejection of NDE personnel.
Visual Examination: The personnel performing visual examination shall be qualified based on
participation in relevant courses and practical experience.
Certification of the personnel performing visual examination is not required, but documentation
The visual perceptiveness of the personnel shall be checked annually according to BS EN 473 or
ASME V
Procedures
All NDE shall be performed in accordance with procedures which have been approved by the
responsible Level 3 personnel and the Employer in accordance with the requirements of the
applicable standards.
The procedures shall be referred to in relevant documents such as weld check lists.
Reporting
The Contractor shall document the examinations in reports in accordance with the requirements
of the applicable standard with regard to examination technique and results.
The reports shall include the parameters required for reproducing the examination.
Fabrication
All NDE shall be performed after final post weld heat treatment, if applicable.
Before final NDE, the following resting periods shall have elapsed after welding:
The following procedure can be used as an alternative for C-Mn steel to the 16-hour hold
between completing a weld and performing the final NDE for approval:
• After completion, the welding and its surroundings are heated up to minimum 200°C.
• The 200°C is maintained for 2 hours per 50 mm in thickness, minimum 2 hours.
• The weld is allowed to cool freely.
• NDE is performed after cooling to the temperature required for performance of the
examination.
Sequence of Examination
When examinations for detection of internal as well as external defects are required for the same
weld, the examination for external defects shall be performed prior to the examination for
internal defects.
Surface Conditions
The surface and the adjacent area to be examined shall be clean and free of all dirt, grease, paint,
spatter, heavy oxidation etc. that may interfere with the examination.
The weld shall be prepared by grinding if necessary to assure that the examination can be carried
out thoroughly and that the surface condition of the weld is not causing misleading
interpretations of the results.
Random Examination
The lot is defined as welds for piping for the given system.
Where practical, the selection shall ensure that the work product of each welder or welding
operator carrying out the production welding is included.
Where welding repair is required, the repair area including 100 mm on either side shall be re-
examined for external defects prior to welding.
Welding repairs (or replaced welds) shall be examined with the methods prescribed for the
original weld.
If NDE carried out at random reveals unacceptable indications, the following precautions shall be
taken:
a) Two additional welds made by the same welder or welding operator and welded in
accordance with the same welding procedure specification (WPS) shall be examined with
the same examination method.
b) If the results of the examination according to a) are acceptable, the defective welds shall
be repaired and re-examined, and all welds in the lot are considered acceptable.
c) If the results of the examination according to a) are unacceptable, all welds made by the
same welder or welding operator and welded in accordance with the same welding
procedure specification (WPS) shall be examined.
If the results of the examination according to c) are acceptable, the defective welds shall be
repaired and re-examined and all welds in the lot are considered acceptable.
If the results of the examination according to c) are unacceptable, all unacceptable welds welded
by the same welder or welding operator in accordance with the same welding procedure
specification (WPS) shall be:
The examination methods shall be selected in accordance with Table J4442-1 for detection of
internal defects, which are defects not located at accessible surfaces and Table J4442-2 for
detection of external defects, which are defects located at accessible surfaces.
In case of doubt or suspicion on defects, the Engineer reserves the right to require supplementary
examinations.
If black suspended powder is used, the examination surface shall be covered by a thin layer of
contrast paint.
Radiographic Examination
The Employer shall approve lower thickness prior to examination. Acceptance level: BS EN
12517 Level 1.
Ultrasonic Examination
Visual examination
Acceptance level: All areas with indications exceeding the signal from a 1 mm deep notch shall
be further investigated with MT or PT
b) Plate: Charpy tests shall be conducted on each plate as required in ASTM A20.
c) Coils: Charpy tests shall be conducted on the first 500 tons of steel by testing each coil as
follows:
• Tests shall include representative sampling of all steel thicknesses required for the
Work.
• Each coil shall be tested by taking coupons from the outer, middle, and inner wrap of
the coil. Middle coil coupons may be taken from the ends of full-length pipes that are
closest to the middle of the coil.
• Coils that do not meet the above Charpy acceptance criteria shall not be used in
production of pipe.
• After the initial 500 tons, conduct one test per heat of coil on the outer wrap only.
d) The Contractor shall increase the Charpy testing to include more steel than
indicated above (Le., beyond the first 500 tons and the single coupon per coil
thereafter) if directed by the Engineer.
a) To ensure that lap joints may be fully assembled and that excessive annular space between
spigots and bells does not exist, and that the pipe meets the requirements of AWWA
C200, the pipe fabricator shall perform a shop fit test on a minimum of five joints of
each size. The joints to be tested shall be selected by the Engineer based on pipe
measurements.
b) The shop fit test shall join the pipe ends in the shop with the proposed adjacent pipe end.
c) Record the actual annular space, with the data to include as a minimum:
J4.4.4.3 General
Ductile iron pipes and fittings shall be procured from a supplier acceptable to the Employer.
Draw cords shall be provided in all ducts. The draw cord shall be a polypropylene cord having a
breaking load of not less than 5kN. Joints in the draw cord shall be kept to a minimum; they shall
be at least as strong as the cord and shall be so made as not to cause any jamming in use.
Where detailed on the drawings spigot and socket joints to fittings shall be the mechanical
(bolted gland) type supplied with rubber gasket and bolts. Glands should be ductile iron of the
same quality as the fitting and shall be supplied with a bituminous coating of thickness not less
then 100 microns. On a fixed spot on the outside of each gland the manufacturers name or
identification mark, date of manufacture and nominal diameter shall be marked. Bolts for use
with bolted gland joints shall be spheroidal graphite in accordance with BS EN 1563 Grade EN-
GJS-500-7.
Where shown on the Drawings ductile iron pipes passing through concrete walls or other similar
structures shall incorporate a puddle flange of the same dimensions as flanges for the size and
class of pipe to which they are attached. A rubber strip or gasket shall be used to seal split puddle
flanges to the pipe if required by the design of puddle flange. Where pipes will be transferring a
thrust from the pipe to the wall an integral thrust flange shall be incorporated in the pipework.
Unless otherwise specified, each item shall be checked for holidays over all of the external
surfaces on delivery to the site and when being lowered into the trench.
No pipes with significant damage to the external coating will be accepted. Where, in the opinion
of the Engineer damage to the coating is minor, it shall be repaired in accordance with the
procedures specified by the supplier of the original coating system, subject to the approval of the
Engineer.
J4.4.5.3 External protection of ductile iron pipes and fittings by polyurethane coating
Where specified the external zinc coating and finishing shall be replaced by a two part solvent
free urethane coating applied to a minimum 1 mm dry film thickness. Preparation of the pipe
outer surface shall be strictly in accordance with the coating supplier’s specifications.
All other requirements of clause J4.4.5.1 shall remain applicable.
Fittings may alternatively be supplied with a fusion bonded epoxy coating applied to all internal
and external surfaces.
No pipes or fittings with significant damage to the internal lining will be accepted. Where, in the
opinion of the Engineer damage to the lining is minor, it shall be repaired in accordance with the
procedures specified by the supplier of the original lining system, subject to the approval of the
Engineer.
J4.4.5.8 Primer
The wrapping system for pipes shall, unless otherwise approved by the Engineer, include a
bituminous based quick drying surface primer which shall be compatible with the wrapping tape
and external pipe coating. The primer shall be as recommended by the tape manufacturer and be
fast drying and suitable for cold application by brushing and spraying and be compatible with the
factory applied pipe coating.
• Any pre-treatment prior to coating shall not be permitted without the written approval
of the Engineer
• The shot-blasted surface shall have a roughness RZ between 40µm and 80µm
inclusive.
The minimum and maximum thickness of coatings for pipes and fittings shall be as in the table
below:
Location Minimum Maximum
Pipe walls 300 microns 1.6mm
Fittings including flanges 300 microns 2.0mm
Inside bolt holes 300 microns 2.0mm
All thickness-critical surfaces shall be coated to the thickness specified and within the tolerances
identified. Raised flange faces shall be dressed after coating to remove coating runs.
Unless otherwise specified, each item shall be checked for holidays over all of the coated
surfaces. A fitting with two or more holidays per 3m2 of surface area or a pipe with thirty or more
holidays per pipe length shall be rejected for subsequent stripping and recoating. All holidays
detected shall be repaired and on completion the item shall be re-examined for holidays. After
repair the coating shall be holiday free to Class A.
All coatings on pipes and fittings shall be treated with a UV-inhibitor to prevent chalking or loss
of colour.
External protection to pipes to be surrounded in concrete over part of their length shall extend at
least 150mm within the concrete.
• The surface temperature of the exposed metal shall be raised to at least 3oC above
dew point and the coating shall then be applied in stages, as recommended by the
manufacturer, so as to achieve a total thickness in accordance with Clause J4.4.5.11;
• All repairs shall be checked with a holiday detector and any holidays shall be
repaired, after which the repairs shall rechecked.
J4.4.5.13 Painting new ductile iron pipes and fittings installed above ground
All damaged areas of shop applied coatings shall be degreased, wire brushed and painted with
one coat of zinc rich paint and one coat of two part solvent free epoxy or polyurethane as the
original coating.
After 3 days (minimum) the Contractor shall apply three coats of an approved oil based
aluminium paint by airless spray/brush/roller to a minimum dry film thickness of 25 microns per
coat. Over-coating times should be as indicated in the paint manufacturer's instructions. Prior to
over-coating the surfaces shall be sweep blasted to remove surface gloss and obtain an adequate
key to the paint system to be applied.
The aluminium paint should be suitable for application on the epoxy or polyurethane surfaces.
The paint shall have a metallic aluminium coloured finish.
J4.4.6 Valves
J4.4.6.1 General
Valves shall be manufactured to the requirements specified hereunder. All valves shall be
suitable for use with water at the temperatures and pressures specified or detailed on the
Drawings.
Where the Contractor proposes to use dissimilar metals either in contact or close enough for the
gap between them to be bridged by an electrolyte the Contractor’s design shall include provisions
to prevent corrosion.
Gate valves (sluice valves) and butterfly valves shall be suitable for flow in either direction.
Valves shall be suitable for frequent operation as well as for operation after long periods of
idleness in any position.
Rubber used in valves shall be ethylene propylene rubber (EPDM or EPM) or styrene butadiene
rubber (SBR). It shall be suitable for making a long-term flexible seal and be resistant to
mechanical, chemical or bacteriological attack leading to deterioration of the flexible seal.
Valve components shall be of materials not inferior in strength or resistance to corrosion to those
listed below:
Component Material
Bodies, covers, cowls and plungers Spheroidal graphite iron to BS EN 1563 Grade
EN-GJS-500-7 or EN-GJS-450-10
Pistons, sleeves, liners, guides, bushes, Gunmetal to BS EN 1982 Number CC491K
seats, seat rings and seal holders
Hinge bushes and pins Bronze to BS EN 12163 Number CW451K
Component Material
Valve stems, spindles other than extension Stainless steel to BS 970: Part 4, grade 431 S29
spindles and pins or 316S13 (BS EN 10088-1, X19 CrNi 17-2 or
X2-CrNiMo 17-12-2)
Aluminium Bronze to BS EN 12163/12167
Number CW307G
Extension spindles (plain ends) Galvanised mild steel to BS 970: Part 1,
grade 230 MO7 (BS EN 10087, 11 SMn 30)
Except where otherwise specified all valves shall be suitable for continuous use in the range -
0ºC to +50ºC.
The pressure rating of all valves, including gates, bodies and flanges, shall not be less than the
maximum working and test pressure of the pipeline in which the valve is to be installed.
Valves shall be supplied with all necessary accessories such as hand wheel, extension shaft,
couplings, caps, bolts, nuts, washers and 3mm cotton reinforced rubber gaskets for each flange.
Valves shall close clockwise.
All copper alloys which may come into contact with raw, treated or potable water shall contain
not more than 4% zinc.
The shot-basted surface shall have a roughness RZ between 40µm and 80µm inclusive.
Raised flange faces shall be dressed after coating to remove coating runs.
Unless otherwise specified, each item shall be checked for holidays over all of the coated
surfaces. A valve with two or more holidays per 3m2 of surface area shall be rejected for
subsequent stripping and re-coating. All holidays detected shall be repaired and on completion
the item shall be re-examined for holidays. After repair the coating shall be holiday free to
Class A.
All coatings shall be treated with a UV-inhibitor to prevent chalking or loss of colour.
Materials and instructions shall be supplied for repair of coating damaged in transit and on site.
Repair materials shall be compatible with the coating in colour and adhesion and shall be suitable
for site application.
Gaskets shall be suitable for use with both flanges with raised faces and between flanges with
fully machined faces. Gaskets shall be inside bolt circle type to BS EN 1514-1 of materials
complying with BS EN 681.
Gaskets shall comply with the relevant sections of BS 5292 and their dimensions shall be in
compliance with BS EN 1514-1.
Gaskets shall be one piece EPDM rubber of hardness 80, of minimum thickness 3mm and of
such physical properties as to be capable of forming permanent watertight joints against
pressures up to the maximum test pressure. The use of jointing paste, adhesive tape or grease on
gaskets will not be permitted.
Line valves and washout valves shall be installed with extension spindles, spindle caps, spindle
supports, protection tubes and surface boxes to permit operation of the valve from outside of the
chamber. The Contractor shall prepare shop drawings, supply and install suitable extension
spindles for all line and washout valve installations.
Disc edges shall be machined with rounded corners and shall be polished to a smooth finish. The
valve disc shall rotate through an angle of 90 degrees from the fully opened to the fully closed
position and the seat shall be designed so as to close at an angle normal to the axis of the pipe.
Hollow discs and any other castings with voids shall be fitted with watertight threaded plugs.
Discs shall be capable of maintaining their fully open and fully closed positions with the gearbox
removed. Limit stops shall be capable of absorbing full operating torque with a minimum design
safety factor of 5.
Shafts shall be fabricated of stainless steel grade X2-CrNiMo 17-12-2 to BS EN 10088-1. Body-
seats shall be fabricated of stainless steel grade X2-CrNiMo 17-12-2 to BS EN 10088-1 or made
of back-up welded nickel face (nickel weld overlay).
The shaft and disc fixing shall be capable of absorbing the full operating torque with a minimum
design safety factor of 5 and will safely sustained maximum differential pressure across the
closed valve. Shaft seals, when used, shall be of the resilient O-ring type. Packing shall be either
of the resilient 0-ring or of the self-adjusting chevron type.
The sealing ring shall be replaceable without the need to remove the valve body from the
pipework in which it is fitted.
The valve body and disk shall be of ductile cast iron of quality not less than BS EN 1563
Grade EN-GJS-500-7. In general the materials chosen shall be corrosion resistant to the source
water referred to in the Specification. All bolts, nuts and other fixings, which will be in contact
with the flow or with the ground shall be of stainless steel type X2-CrNiMo 17-12-2.
Bolts retaining the removable seal cover and the body seat ring shall be of stainless steel
type X2-CrNiMo 17-12-2.
Valves shall be suitable for submergence below water.
The valves shall be capable of being seated and unseated under the most adverse conditions
appropriate to its rating.
The gearbox spindle for hand wheel/tee key or for connecting with the extension spindle shall be
vertical when the valve is installed.
Valves greater than 600mm diameter shall be provided with suitable support feet.
The face-to-face dimensions of butterfly valves shall be as detailed for Series 14 valves in Table
4 of BS EN 558-1.
Each valve shall be tested in accordance with the requirements of BS EN593, for body test, seat
test and disc strength test. Seat tests shall be carried out in each direction and the valve shall be
drop tight. Disc strength tests shall also be carried out in each direction.
The seal and its retention members shall be adjustable to ensure water tightness and to minimise
the seating and unseating friction forces. When all the seal retention members are in place the
finished edges of the seal shall fit closely and the surface shall be smooth with all fastenings set
flush in the water passage so as to offer the least resistance possible to the flow of water through
the valve.
Valve seats which extend over the face of the flanges to secure the seat in place, or which require
surface grinding and/or hand fitting of the disc, or designs which require the adjoining pipe
flange to retain the seat in place and resist line pressure, are not acceptable.
Actuators shall be rated at not less than 20 percent in excess of the power required to operate the
valve under maximum working conditions.
Actuators shall be suitable for use with a nominal 400 volt 3 phase 50 Hz power supply and shall
incorporate a motor, integral reversing contactor starter local control facilities and terminals for
remote control and indication connection.
The gearbox shall be of the totally enclosed oil bath lubricated type suitable for operation at any
angle.
A handwheel shall be provided for manual operation engaged when the motor is declutched by a
lever.
Actuators shall be provided with open and close torque and/or position limit switches as required
by the type of valve or penstock plus two additional limit switches at each end of travel for
remote indication and interlocking.
The reversing contactor starter and local controls shall be integral with the valve actuator housed
to prevent breathing and condensation build up. The starter shall be suitable for 60 starts per hour
and shall comprise mechanically and electrically interlocked reversing contactors of appropriate
rating to the motor size with coils fed from a 12 volt control transformer of 40 VA minimum
rating.
Local controls shall comprise a switch for open close and stop and a Local/Remote selector
switch.
The actuator enclosure shall be watertight to NEMA 6, IEC 144-IP67.
The actuator starter shall be integrally housed with the actuator in a robustly constructed totally
enclosed weather proof housing. The motor starter shall be capable of starting under the most
severe conditions.
To enable the valve position to be remotely controlled from a telemetry system the actuator shall
be provided complete with equipment such that when “Remote” control is selected the actuator
can control the position of the valve in proportion to a continuous 4-20 mA current signal
(analogue).
For each actuator a control unit shall be provided for installation near to the actuator. The control
unit shall be arranged such that when “Remote” control mode is selected on the actuator then the
actuator may be controlled either from the local control unit or from a telemetry system.
Conditions a) and b) shall be met by using an orifice capable of handling large volumes of air at a
high-flow rate in either direction. Condition c) shall be met by using a small orifice capable of
discharging small volumes of air as they accumulate.
Valves shall have approved screens to prevent the ingress of foreign matter.
Air valves shall be of one of the following types;-
a) Double valves shall combine both large and small orifices in one valve. The large
orifice shall be sealed by a float and the valve shall be designed to avoid premature
closing of the valve by the discharging air. The small orifice shall be sealed by a float
at all pressures above atmospheric, except when air accumulates in the valve body.
b) Single large orifice type for automatic ventilation or exhaust of pipework.
c) Single small orifice type for automatic release of air under normal working pressure.
Large orifice air valves, including those incorporated in double air valves, shall be constructed so
that the air flow holds the valve open during discharge of air at all flows possible in service.
When coupled to their respective isolating valves, they shall be capable of admitting or
exhausting the required quantities of free air without the pressure differential across the
combined air valve and isolating valve exceeding 0.5 bar.
Small orifice air valves, including those incorporated in double air valves, shall be capable of
discharging not less than 0.5 m³/min of free air when the pressure in the pipeline is at the
maximum working pressure.
Balls or floats shall be of ABS, vulcanite, rubber-covered metal, stainless steel, or other approved
materials, and shall operate automatically at all pressures up to the test pressure. Orifices shall be
bronze or stainless steel.
Air valves shall be designed so that each float seats against its orifice or causes the orifice to be
closed without leakage at all pressures between 0.2 bar g. and the specified test pressure. Balls
and seats shall be designed to minimise adhesion of the ball to the seat. They shall be of a type
proven to be suitable for the specified duties.
Each air valve shall be provided with an isolating valve, which shall be an integral lever-operated
isolating ball valve.
Each small orifice or double air valve shall be fitted with a test cock in the valve body for
verification that the small orifice air valve is operating properly.
Body ends shall be flanged with raised faces and drilled to BS 4504 for the nominal pressure
specified.
The materials for valves shall be not inferior to the following:
• body cover and cowl: cast iron;
• small orifice: cast iron with gunmetal seat;
• small orifice ball: rubber-covered or other approved;
• large orifice: cast iron with rubber seat;
• large ball: Vulcanite covered or other approved.
J4.4.6.17 Non-slam air valves
Non-slam air valves shall be double air valves as specified above except that the air valve shall
be fitted with a vented non-return valve or other device which permits air to enter the pipeline
freely on low pressures caused by surges within the pipeline, but which controls the expulsion of
any air drawn into the pipeline under surge conditions in order to minimise ‘slam’ as the air is
finally expelled from the pipe.
The non-slam air release & vacuum break valve shall be of the compact single chamber design
with solid cylindrical HDPE. control floats housed in a tubular stainless steel body with epoxy
powder coated cast iron or steel ends secured by means of stainless steel tie rods. The valve shall
have an integral ‘Anti-Shock’ Orifice mechanism which shall operate automatically to limit
transient pressure rise or shock induced by closure.
J4.4.7 Ancillaries
J4.5 WORKMANSHIP
J4.5.9 Jointing
Before making any joint the Contractor shall ensure that the interior of each pipe or fitting is
clean and shall prepare the ends for jointing as necessary. All mechanical joints shall have their
coating made good before assembly in accordance with the coating manufacturer’s
recommendations.
Only the proper jointing parts as specified and obtained from the suppliers of pipes or fittings
shall be used.
Joints shall be made in accordance with the manufacturer’s instructions.
Unless otherwise specified or detailed in the Drawings the deflection of a flexible joint shall not
exceed 50% of the maximum value specified by the manufacturer.
Bolts for flanged and other mechanical joints shall show two threads clear of the nut after
tightening.
Stainless steel nuts and bolts shall be lubricated before assembly with an anti-galling lubricant.
Nuts shall be tightened to the torques recommended by the joint manufacturer. Torques shall not
exceed values at which there is risk of galling.
After completing the joint any protective or other coating shall be made good and the joint
protection and sleeving completed without delay.
concrete face and secured to the pipe barrel with PVC tape such that the end of the sleeving
overlaps the tape previously placed around the pipe and so that no part of the pipe remains
exposed. The termination of the sleeving shall be completed by placing a further run of adhesive
PVC tape around the pipe, spanning between the end of the sleeving and the face of the concrete.
Sleeving shall be continuous around fittings (bends and tees) at thrust blocks.
A double polyethylene sleeve shall be applied to all ductile iron pipes.
J4.5.15 Tape wrapping with outer wrap for ductile iron pipelines
Pipes shall be tape wrapped at locations shown on the Drawings or as directed by the Engineer.
Buried wrapped pipes shall be additionally protected by polyethylene sleeving to Clause J4.4.5.9.
The Contractor shall submit to the Engineer for his approval the details of the proposed methods
of cleaning, priming, application of mastic putty, tape wrapping and the equipment to be used for
wrapping before commencing work.
Primer, mastic putty and wrapping tapes shall be obtained from the same manufacturer and be
compatible.
Prior to wrapping all surfaces shall be cleaned and primed with primer complying with Clause
J4.4.5.8.
Pipes of 400 mm diameter and above shall be machine wrapped on site with tape complying with
Clause J4.4.5.6 using a wrapping machine supplied by the Contractor. The wrapping tape shall
be applied in a spiral manner under tension to ensure conformability and adhesion to the barrel of
the pipe or fitting. The wrapping shall have a minimum 55% overlap and shall be wrinkle and
bubble free. A length of 200 mm at the spigot shall be left unwrapped until after jointing.
When a new roll of tape is started, the end lap shall be overlapped on the roll a minimum of
150 mm, measured circumferentially and shall be smooth and placed so as to maintain the
continuity of the wrapping.
The Contractor shall prove the wrapping to be holiday free using a holiday detection meter and
voltages to the approval of the Engineer.
On completion of wrapping with protective tape an outer wrap of tape complying with Clause
J4.4.5.7 shall be applied over the protective tape using the same type of mechanical equipment as
used to apply the protective tape. The overlap of the outer wrap shall not coincide with the
overlap of the protective tape. The outer wrap may be applied at the same time as the protective
tape and shall have a minimum 50 mm overlap.
The minimum end lap of two rolls shall be 150 mm measured circumferentially. The outer wrap
shall be applied such as to initially leave 300 mm at the spigot unwrapped.
After the wrapped pipes are laid and jointed mastic putty shall be applied at the joint to smooth
out the external pipeline profile. The putty shall be applied as a fillet with an angle to the pipe
axis not exceeding thirty degrees.
Tape wrapping and outer wrap shall then be made continuous over the joint by hand wrapping.
Prior to backfilling the Contractor shall prove the joint wrapping and exposed pipe wrapping to
be holiday free using a holiday detection meter and voltages to the approval of the Engineer.
The aluminium paint should be suitable for application on the epoxy surfaces limiting any bleed
through the first finishing coat to a minimum and totally inhibiting bleed through the subsequent
coating. The paint shall have a metallic aluminium coloured finish.
All preparation and painting at works shall be carried out under cover at ambient temperature
controlled between 16°C and 21°C and relative humidity below 85%,
Site painting shall not under any circumstances proceed in an ambient temperature less than 5°C
for epoxy coat applications or on surfaces which are other than completely dry.
All paint shall be obtained from an approved manufacturer and shall be applied strictly in
accordance with this Specification. The Contractor shall issue a copy of this Specification to any
Sub-Contractor involved and also to the manufacturer of the paint.
The paint manufacturer shall spot check the preparation and painting and submit to the
Contractor a written report of his observations for forwarding to the Engineer.
Butterfly valves shall be fixed with the disc spindle horizontal and installed so that when the
valve is opening the lower portion of the disc moves in the direction of the main or normal flow.
Except where shown otherwise in the Drawings gate valves shall be fixed with their spindles
vertical.
J4.5.26 Drawpits
The Contractor shall submit details for drawpits which shall be either precast or insitu concrete
Class A1, or HDPE. The roof slab shall be precast concrete with lifting hooks to enable it to be
removed.
The cover shall be bedded and sealed against ingress of water.
The external faces of buried concrete walls shall be painted with 2 coats of bitumen paint.
Where ducts are built into the walls the openings shall be sealed and made good.
The drawpits shall incorporate anchor eyes for the pulling of the cables. Drawpits shall be spaced
at no more than 200metres centre to centre.
Where pipe fittings are cast into in-situ concrete walls and where a puddle flange is not required
to resist forces rubber sealing rings shall be installed.
Pipe clips shall be plastic and shall be correctly aligned to provide a flat smooth surface for
contact with the pipe. No sharp edges shall be present on supports. Valves and other such items
shall be properly supported.
Pipe shall be continuously supported or on fixings such as pipe clips, brackets, etc., which shall
be used at approximately the following spacings. Values are for use in temperatures up to 20 °C.
Spacings shall be reduced by 25% between 20-30°C. Pipes shall be continuously supported
where temperatures are above 40°C.
Nominal Size Spacing(m) Nominal size Spacing(m)
16 0.45 50 0.7
20 0.6 63 0.85
25 0.6 90 0.85
32 0.6 110 0.9
40 0.7 140 1.1
160 1.3
Support distances may be doubled for vertical pipes
J4.6.1 Scope
Where required by the Royal Oman Police and instructed by the Engineer the installation of
pipelines and cable ducts at road crossings shall be by trenchless construction methods.
The Contractor will at all times provide and maintain instrumentation which will accurately
locate the pilot hole and measure drilling fluid flow discharge rate and pressure. The Engineer
will have access to these instruments and readings at all times.
J4.6.1.3 Design
The Contractor shall design the permanent and temporary works covered by this section of the
Specification.
The design shall comply with the requirements of the Contract and shall be submitted to the
Engineer for his approval. The Contractor shall be responsible for his design and shall obtain all
necessary approvals from the Muscat Municipality, Royal Oman Police and any other relevant
authorities.
J4.6.2.3 Approvals
The design and construction of road crossings by trenchless construction shall be the sole
responsibility of the Contractor. Approval and/or comments by the Engineer shall not relieve the
Contractor of his obligations and responsibilities to complete the works in a satisfactory manner
to the approval of all concerned authorities.
a) Concrete pipes which shall be designed to give a reliable service life of at least 60
years. Concrete jacking pipes shall be butt-jointed reinforced concrete with an
external collar and shall comply with BS5911; Part 120. The pipes shall be
manufactured using Sulphate Resisting Portland cement. The 28-day characteristic
cube strength of the concrete shall be not less than 50 N/mm2. Both the internal and
external face of the sleeve shall be protected with two coats of bitumen paint;
or,
b) Polyester Resin Concrete pipes which shall be butt jointed with an external collar.
The minimum design compressive strength of for design purposes relative to design
jacking load shall not be less than 80 N/mm2;
or,
c) Welded steel pipe conforming to the requirements of ASTM A53 Grade B or
AWWA C200, having a minimum yield strength of 250 N/mm2 of minimum
thickness 10 mm for 900 mm diameter and smaller and 15 mm for 1050 mm
diameter and larger.
The strength of the pipes shall be selected to suit the installation loads, imposed loads and the
design life.
Joints which shall be used in conjunction with resilient packing shall be capable of accepting
repeated angular deflections of up to 0.5o without:
- Loss of structural strength;
- The ingress of water or bentonite.
Joint materials shall be suitable for the local ground conditions.
J4.6.3.4 Bentonite
The material used for lubrication of pipe jacked sleeves shall be calcium bentonite or other
approved material stored and mixed in a manner recommended by the supplier.
J4.6.3.7 Bulkheads
Bulkheads around the ductile iron carrier pipe at each end of the crossing shall be fabricated from
steel with grout inlet/outlet pipes.
J4.6.4.1 Approval
The Contractor shall obtain the approval of all concerned authorities. No construction shall
commence until written approvals have been submitted to the Engineer and the Engineer has
stated in writing that the work may commence.
J4.6.4.3 Monitoring
The Contractor shall be responsible for taking all precautions necessary to protect existing
infrastructure and existing utilities and structures and road surfaces from settlement or damage.
Under no account shall settlement be allowed to exceed 9 mm.
The Contractor shall survey all areas that may be affected by the works prior to commencement
and shall monitor surface levels during the progress of the works.
The Contractor shall submit results of surveys to the Engineer within 12 hours of taking the
levels.
The Contractor shall immediately inform the Engineer of any surface settlement that exceeds the
predicted value.
J4.6.4.11 Settlement
The Contractor shall continuously monitor settlement of the ground surface, adjacent structures
and buried utilities and shall limit settlement to an absolute minimum by controlling the
tunnelling activities such as rate of excavation, progress of jacking, design of bentonite slurry
mixes etc.
All work and any stoppages or modifications to materials, equipment or methods of working to
reduce settlement to the Engineer’s satisfaction shall be at the cost of the Contractor.
Any void between the soil face used to provide a reaction to the jacking force and the thrust wall
shall be filled completely with cement based grout.
The Contractor shall take any measures necessary to prevent damage or deterioration of the soil
reaction face during the construction of the temporary and permanent works from whatever
possible cause, such as ingress of water softening a cohesive soil or loss of fines from a granular
soil.
X- - mm
Y+ - mm
Y- - mm
t) Roll:
left - mm
right - mm
u) Lead:
left - mm
right - mm
v) Inclinometer - deg
J4.7.1 General
All water pipelines shall be cleaned, pressure tested and disinfected.
Cable ducts shall be cleaned and left stoppered with draw cords.
All chambers and draw pits shall be cleaned of all debris silt and sand, any mortar droppings on
pipework or metalwork shall be removed and any damaged coatings made good. Valves shall be
tested for operation, valve spindles shall be adjusted for correct alignment and chamber covers
shall be cleaned and properly seated.
Records of all cleaning, testing and disinfection operations shall be submitted to the Engineer
weekly.
J4.7.3 Valves
All valves shall be tested on completion of installation. Each installation shall be checked for
water tightness. Valves shall be demonstrated to function satisfactorily under design maximum
differential head conditions.
The Contractor shall carry out a final test and inspection of valves and associated equipment
immediately before pressure testing the pipeline.
Where directed by the Engineer valves shall be internally inspected after testing to verify that the
seals remain in a satisfactory condition.
J4.7.4.1 General
The Contractor shall submit for the approval of the Engineer details of his proposed methods and
programme for pipeline testing, swabbing, disinfection and cleaning (including details of test and
cleaning equipment).
All parts of pipeline systems shall be subjected to hydraulic pressure testing. Pipelines shall be
tested to the piezometric pressure (head) shown on the Drawings.
Testing shall be undertaken in sections as the work proceeds but the whole system shall be
subjected to a final test.
Pipelines at road crossings and in other locations as may be directed by the Engineer shall be
subjected to a hydrostatic pressure test immediately the section has been completed.
For the purposes of this final test, the pipeline system shall be divided into suitable sections as
agreed with the Engineer. The length of pipeline tested at one time shall not exceed 10 km
without the approval of the Engineer.
Testing shall not be carried out against closed valves, other than for testing of limited closure
sections to the working pressure indicated on the Drawings.
All testing shall be witnessed and approved by the Engineer.
J4.7.4.3 Anchors
The Contractor shall provide and install all necessary stop ends and temporary thrust restraints to
carry out the tests. Pressure tests shall not be made against closed valves.
The Contractor shall satisfy himself and the Engineer that all temporary and permanent structures
and thrust blocks are capable of withstanding the forces exerted from hydraulic tests with a
sufficient factor of safety. Calculations shall be submitted to the Engineer for approval.
Thrusts from hydraulic test pressures shall not be exerted on any permanent structure that is
located in saturated ground where the standing water level is above the lowest level of the
foundation without the approval of the Engineer.
The Contractor shall provide any additional support or kentledge to structures as necessary to
withstand the test pressures.
No loadings from testing shall be imposed on any structure without the approval of the Engineer.
Notwithstanding any approval given by the Engineer, the Contractor shall be fully responsible for
any consequences arising from the testing.
Where more than one pipe is laid in a common trench only one pipeline shall be pressurised at
any one time.
J4.7.4.4 Preparation for site pressure testing pipelines for water supply
Before filling pipelines for pressure testing, the Contractor shall re-check pipes and valves for
cleanliness and shall re-check the operation of all valves.
The ‘open’ ends of the pipeline (or sections thereof) shall be stopped off by blank flanges or cap
ends secured by temporary struts, wedges and thrust blocks.
All permanent thrust blocks and valve chambers shall have been completed and backfilled and
the concrete shall have attained its specified 28-day strength
All pipe straps and other devices intended to prevent the movement of pipes shall be securely
fastened.
J4.7.4.5 Procedure and standards for site pressure testing ductile iron water supply
pipelines
Testing of installed pipelines shall be carried out according to Clause 11.3 of EN 805:2000.
Joints including spigot and socket joints shall be left exposed for inspection during pressure
testing and trenches between pipe joints shall be backfilled to the extent necessary to prevent
movement of the pipeline.
The test section shall be filled with water and all air removed.
As a preliminary test the pipeline shall stand full of water for at least 24 hours at the working
pressure and all joints and restraints shall be inspected for leakage and movements.
The pressure shall then be raised by pumping in water until the specified test pressure is reached.
The pressure shall be maintained at the test pressure by further pumping for a period of not less
than 1 hour during which time the pipeline shall be again inspected for leakage or movement.
Pumping shall then cease and the time (T) for the pressure head to fall by 10 m shall be recorded.
If the pressure head has not fallen by 10m within three hours, then the fall in head at 3 hours shall
be recorded. Pumping from calibrated container(s) shall then be resumed to restore the pipeline
pressure to the test pressure. The quantity of water (Q) pumped into the pipeline shall be
recorded.
The rate of loss shall be calculated as being the quantity (Q) pumped into the pipeline divided by
the time (T).
The allowable rate of loss shall be less than 0.2 litres per 24 hours per mm of nominal internal
bore per kilometre of pipe for each 10 m head of pressure applied.
J4.7.4.6 Procedure and standards for site pressure testing HDPE pipelines
Joints including but welds shall as far as possible be left exposed for inspection during pressure
testing and trenches between pipe joints shall be backfilled to the extent necessary to prevent
movement of the pipeline.
The test section shall be filled with water and all air removed.
As a preliminary phase the pipeline shall stand full of water for at least 24 hours at the working
pressure and all joints and restraints shall be inspected for leakage and movements. The pipeline
shall then be de-pressurised to atmospheric pressure and allowed to stand for one hour, taking
care to avoid any air entry to the pipeline. After one hour quickly and continuously raise the
pressure to the system Test Pressure (STP) in less than 10 minutes. Maintain the pipeline at the
STP for thirty minutes by controlled continuous pumping, or by intermittent pumping. Inspect
the line for leakage during this period. After thirty minutes cease pumping and leave line under
pressure for one hour. Measure the pressure drop from the beginning to the end of this period. If
the pressure drop is less than 30% of the STP value the preliminary phase may be considered
acceptable and the main test may start. If the pressure drop exceeds 30% of the STP, de-
pressurise the line and rectify potential reasons for the drop.
If the preliminary phase was acceptable undertake an integrated pressure drop test to determine
that air content is acceptably low. Reduce rapidly the remaining pressure in the line to produce a
further pressure drop of 10 – 15% of STP by bleeding off water and measuring precisely the
volume withdrawn, ∆V. Calculate the allowable water loss, ∆Vmax from equation:
∆Vmax = 1.2 x V x ∆p x { 1/EW + D/(e x ER )}
Where:
∆Vmax = Allowable loss of water in litres;
V = Volume of test line in litres;
∆p = measured pressure drop in kilopoascals;
EW = bulk modulus of water in kilopascals
D = internal pipe diameter in metres
e = wall thickness of pipe in metres
ER = modulus of elasticity of pipe wall in the circumferential direction in kilopascals
Should ∆V exceed ∆Vmax then further removal of air from the line is necessary before the main
test.
During the 30 minutes immediately following completion of the integrated pressure drop test the
pressures should be monitored closely. If the pressure steadily rises during this period as a result
of pipe contraction following pressure reduction and at no time, falls the test is satisfactory.
In case of doubt from results over the 30 minute period the measurement should continue to a
total of 90 minutes. Should the pressure drop not exceed 25 kilopascals over this period then the
test may be considered satisfactory.
Any repetition of the Main test must be preceded by the test procedure including the full
preliminary phase.
After final flushing samples shall be collected from a sampling cock with a copper tube
gooseneck located at the end of the pipeline which is remote from the source of supply and tested
for bacteriological quality. The sampling cock shall remain in place upon completion of the test.
The samples shall show the absence of coliform organisms.
Samples shall be collected directly from the sampling cock in sterile bottles treated with sodium
thiosulphate. No hose or fire hydrant shall be used in the collection of the samples.
If the initial disinfection fails to produce satisfactory samples, disinfection shall be repeated until
satisfactory samples have been obtained.
J4.9 COMMISSIONING
Commissioning, putting into service and the full operation during the specified Contract period
and for the first three months of the Period of Maintenance of the Scheme will be undertaken by
the Contractor. The Contractor shall be fully responsible for all activities required to properly
commission the whole of the Works to transfer and treat water as specified.
J5.1 SCOPE
This Section covers the supply and installation of engineering metalwork and GRP fabrications.
J5.4 MATERIALS
J5.4.1 General
The Contractor shall supply and install the items of metalwork and GRP shown in the Drawings
or specified herein, together with all fixings, mounting brackets, locking screws, lifting keys and
other accessories normally required for erection, permanent fixing and operation.
No orders for engineering metalwork and GRP shall be placed by the Contractor until he has
submitted his detailed drawings, and where applicable supporting design calculations, to the
Engineer and received the Engineer’s consent.
Where the Contractor proposes to use dissimilar metals either in contact or close enough for the
gap between them to be bridged by an electrolyte, he shall satisfy the Engineer that adequate anti-
corrosion provision is included in the design.
Covers and frames detailed as sealed shall incorporate suitable neoprene or other approved
synthetic rubber sealing rings, or shall seal by another approved sealing method.
Access covers outside of enclosed sites shall be of a concrete infill pattern.
J5.4.11 Handrailing
Handrailing shall comply with the relevant recommendations of BS 6180. Except where
otherwise specified or shown in the Drawings, handrailing shall consist of standards at regular
intervals not exceeding 1.5m, and two rails. The upper rail shall be 1.1m above the adjacent
finished floor level, and 0.9m above the nosing line on stairways. The lower rail shall be midway
between floor or nosing line and the upper rail. Rails shall be fabricated from 32mm-bore mild
steel tube and standards from 38mm diameter solid mild steel bar, or pultruded GRP sized to
provide same deflection limits..
Handrailing shall be ball-jointed. Handrailing terminating against a wall shall either have a
suitable wall-fixing flange or shall terminate at a standard or a loop with a gap between the
standard or loop and the wall not exceeding 75mm. Where the shape of the floor or platform
structure does not incorporate an upstand at the edge of walkways, toe plates not less than 5mm
thick and not less than 100mm high shall be fixed to the handrail standards. The bottom edge of
such toe plates shall be not more than 25mm above the surface of the walkway.
The handrail standards for stairways and for landings and walkways of width less than 1.2m shall
have palm fittings for bolting to the sides of the structures. Elsewhere the standards shall be
designed for fixing 100mm (minimum) inside the edge of concrete structures, or at the
supporting edge girder of flooring, or have palm fittings. Standards either side of openings shall
be equipped with eyes for attaching safety chains at top and middle rail level.
Safety chains shall be of mild steel of 10mm nominal size, short link, smooth welded chain in
accordance with BS 4942, Part 2. Each length of chain shall be fitted with a shackle at one end
and a snap fastening at the other.
The Contractor shall submit details of his proposed fixings for the approval of the Engineer.
Where required by the Engineer, the Contractor shall demonstrate the effectiveness of the fixings
by suitable tests.
Other bolts and nuts used in fabrication or erection shall be in accordance with BS 4190.
Bolts, nuts, screws, washers and other fixings shall be stainless galvanised, sherardised or
electro-plated steel. All fixings within water or within damp and splash areas shall be of AISI
316L stainless steel.
J5.5 WORKMANSHIP
J5.5.1 Tolerances
Metalwork and GRP equivaents shall be constructed and installed within the following
tolerances:
− for work at floor level (such as joints between flooring sections and between steel/GRP
flooring and adjacent concrete):
− difference in level at joints: 3mm
− joint gap: 3mm
− dimensions shown in the Drawings: 5mm
− levels shown in the Drawings: 5mm
J5.5.2 Installation
Where metalworkor GRP equivalent is to be founded on and/or fastened to concrete, the
Contractor shall use one of the following methods:
l. Bolting or screwing the work to plates or angle section having anchors cast into the
concrete structure or set into pockets left in the concrete structure.
2. Setting the metalwork into pockets left in the concrete structure.
3. Bolting the work to anchor bolts (studs) cast into the concrete structure or set into pockets
left in the concrete structure.
4. Bolting the work to anchor bolts (studs) as specified, in holes drilled into concrete
structure.
5. Bedding the work on cement mortar placed on the concrete surface.
Cement mortar of 3 parts of sand to l part of cement shall be used for bedding access covers and
the like and for filling around metalwork or bolts set into pockets smaller than 100mm square or
equivalent. For larger holes, concrete of the same grade as the structure shall be used instead of
mortar. The installation methods permitted for various types of metalwork are specified below.
Metalwork and GRP items Permissible methods of installation
Stairs, ladders and flooring 1, 3 and 4
Step irons, sockets for removable items 2
Handrailing 2, 3 and 4
Access covers, surface boxes and gully 2 and 5
gratings
During installation each item of metalwork shall be temporarily braced as necessary to resist all
forces which are likely to be applied to it during installation, fixing and building in. Any bolted
connections required as part of the installation operation shall be fitted and tightened before
fixing bolts are tightened or pockets are grouted. The nuts of grouted or resin-fixed bolts shall
not be tightened until the grout or resin has fully cured.
Where approved by the Engineer, small or lightly loaded items may be fixed using screws and
plugs set in drilled holes.
J6.1 GENERAL
J6.1.1 Scope
This Section includes requirements for the construction of roads, drainage for roads, the
preparation of the sub-grade and the construction of sub-bases, bases and pavements for those
roads (including hardstandings) and footpaths which form part of the Permanent Works. All
clauses pertaining to roadworks shall also be applicable to parking areas.
BS 1377-1:1990 Methods of test for soils for civil engineering purposes. General
requirements and sample preparation
BS 1377-2:1990 Methods of test for soils for civil engineering purposes.
Classification tests
BS 812-111:1990 Testing aggregates. Methods for determination of ten per cent fines
value (TFV)
BS EN 1097-2:1998 Tests for mechanical and physical properties of aggregates. Methods
for the determination of resistance to fragmentation
BS 410-1:2000, ISO Test sieves. Technical requirements and testing. Test sieves of metal
3310-1:2000 wire cloth
BS 410-2:2000, ISO Test sieves. Technical requirements and testing. Test sieves of
3310-2:1999 perforated metal plate
BS 812-105.2:1990 Testing aggregates. Methods for determination of particle shape.
Elongation index of coarse aggregate
BS 5835-1:1980 Recommendations for testing of aggregates. Compactibility test for
graded aggregates
BS 8500-1:2002 Concrete. Complementary British Standard to BS EN 206-1. Method
of specifying and guidance for the specifier
BS EN 12620:2002 Aggregates for concrete
BS 4987-1:2003 Coated macadam (asphalt concrete) for roads and other paved areas.
Specification for constituent materials and for mixtures
BS 4987-2:2003 Coated macadam (asphalt concrete) for roads and other paved areas.
Specification for transport, laying and compaction
BS 434-1:1984 Bitumen road emulsions (anionic and cationic). Specification for
bitumen road emulsions
BS 434-2:1984 Bitumen road emulsions (anionic and cationic). Code of practice for
use of bitumen road emulsions
BS 594-1:2003 Hot rolled asphalt for roads and other paved areas. Specification for
constituent materials and asphalt mixtures
BS 594-2:2003 Hot rolled asphalt for roads and other paved areas. Specification for
transport, laying and compaction of hot rolled asphalt
BS EN ISO 591- Titanium dioxide pigments for paints. Specifications and methods of
1:2000 test
BS 4660:2000 Thermoplastics ancillary fittings of nominal sizes 110 and 160 for
below ground gravity drainage and sewerage
BS EN 13598- Plastics piping systems for non-pressure underground drainage and
1:2003 sewerage. Unplasticized poly vinyl chloride (PVC-U), polypropylene
(PP) and polyethylene (PE). Specifications for ancillary fittings
including shallow inspection chambers
BS 5481:1977 Specification for unplasticized PVC pipe and fittings for gravity
sewers
BS EN 1401-1:1998 Plastics piping systems for non-pressure underground drainage and
sewerage. Unplasticized poly vinyl chloride (PVC-U). Specifications
for pipes, fittings and the system
BS 4962:1989 Specification for plastics pipes and fittings for use as subsoil field
drains
BS 5911-3:2002 Precast concrete pipes, fittings and ancillary products. Specification
for unreinforced and reinforced concrete manholes and soakaways
(complementary to BS EN 1917:2002)
J6.3.1.3 Certificates
• Suppliers' certificates of compliance with specified requirements for the above.
J6.4 MATERIALS
J6.4.3 Sub-base
Material to be used as sub-base shall be Type 1 as specified and shall meet the following
requirements. Type 2 shall not be used for construction of carriageways.
Sub-base Type 1 shall be crushed rock or crushed concrete.
Sub-base Type 2 shall be natural sand or gravel, crushed rock or crushed concrete.
Grading (Clause 9.2 of BS 1377-2) Percentage by mass passing
Sieve size BS 410 (mm) Sub-base Type 1 Sub-base Type 2
75 100 100
37.5 85-100 85-100
10 40-70 45-100
5 22-45 25-85
0.600 8-22 8-45
0.075 0-10 010
10% fines value BS 812-111 50kN minimum 50kN minimum
Plasticity index (material passing 0.425mm Non-plastic 6 maximum
sieve) Clause 5 of BS 1377-2
California bearing ratio(material passing Test not required 30% minimum
20mm sieve) Clause 7 of BS 1377-4
The Contractor shall provide copies of current test certificates for each of the foregoing tests.
Flexible surfacing for footpaths shall comply with the requirements of BS 4987-1, and shall be as
specified under the Particular Requirements section of this Specification.
J6.5 WORKMANSHIP
J6.5.1 Earthworks
Excavations and embankments for roads shall be carried out to the lines and levels shown on the
Drawings or as directed by the Engineer and in accordance with the relevant provisions of the
Specification for Earthworks.
them from the stockpiles shall be such that no detrimental degradation of the particles will result
and no appreciable amount of foreign material will be incorporated into the materials.
The Contractor shall be responsible for taking all necessary steps to prevent damage to the
previously completed layer or layers by excessive wetting or drying due to weather conditions or
by traffic or any other cause. If the Contractor considers it advisable or if so ordered by the
Engineer the completed layers shall be sealed using bitumen road emulsions as specified
following the procedure set out in Section 8 of BS 434-2.
If instructed by the Engineer, the completed surface of the roadbase shall be sealed as specified
above immediately it has been completed and checked for compliance with the specified
tolerances.
The Contractor shall ensure that the bituminous emulsion does not come into contact with any
material other than that which is to be sealed.
Once compaction of the concrete is completed the surface shall be regulated by at least 2 passes
of a scraping straight edge with blade length greater than the bay width. If owing to irregularities,
the surface is torn significantly by the straight edge a further pass of the vibratory beam shall be
made and the scraping process shall be repeated.
After the final scraping with the straight edge the surfaces of concrete roads, hardstandings and
the like shall be brushed in a direction at right angles to the normal direction of travel with a wire
broom. The broom shall contain 2 rows of tufts spaced 20mm apart with tufts in each row 10mm
apart. The broom shall be at least 500mm wide and shall produce grooves at least 2mm deep.
Where the texture depth obtained by brushing is unsatisfactory the Engineer may require
mechanical grooving of the surface.
Surface levels and smoothness shall be in accordance with the specified tolerances.
Where the road channel is a drainage channel then the channel shall be steel trowel finished to
form a 250mm wide smooth drainage channel.
Immediately before the construction of any layer, the surface on which it is to be laid shall be
tested for accuracy of formation and smoothness, and if any areas are found to be outside the
specified tolerances such areas shall be scarified, reshaped, recompacted, broken out and
replaced, or otherwise treated until the specified smoothness and accuracy are obtained.
Notwithstanding the above requirements, no layer of road construction shall have a thickness less
than the thickness specified and the surface of the wearing course shall have no backfall from any
drainage point.
Kerbs shall be bedded on a layer of 2:1 sand-cement mortar 13mm thick laid on a concrete
foundation and shall be backed with concrete shaped up to the required cross-section, all as
detailed on the Drawings. Specially cast radius kerbs shall be used on curves of 12m radius or
less.
Kerb off-shoots (other than kerb weirs for catch pits) shall be of pre-cast concrete, positioned as
directed by the Engineer.
Kerbs shall be jointed with cement mortar except at expansion joints which shall be made with
preformed joint filler 13mm thick. Expansion joints shall be carried through the concrete backing
and foundation.
J6.5.15 Footpaths
The formation and subgrade for footpaths shall be prepared as specified for roads, except that
proof-rolling will not be required.
Edging to footpaths shall be bedded in a concrete foundation.
The sub-base, basecourse and wearing course shall be constructed as shown on the drawings.
Compaction shall be carried out in accordance with the requirements for granular materials.
Where a flexible final surface is specified, the base course shall be sealed with a coat of cold
bituminous emulsion sprayed on at the rate of 1.8l/m2 and shall be covered by a wearing course.
Where concrete flags are specified as the final surface, they shall be bedded on 1:10 cement/sand
mortar 30mm thick, laid on to sub-base. Joints shall be made with 1:3 cement/sand dry mix or
mortar.
the level of water at the vertical feed pipe shall be made up to produce the required 1.2m
minimum test head. The loss of water over a 30 minute period shall be measured by adding water
at regular 10 minute intervals to maintain the original water level and recording the amounts so
added. The drain will have passed the test if the volume of water added does not exceed 1l/hr per
30m of drain per 25mm of nominal internal diameter. Drains exceeding 750mm in diameter shall
be tested by means of an air test. The air pressure shall give 100mm head of water on a
manometer tube, and the loss shall not exceed 25mm over a period of five minutes. The drain
shall be tested in convenient lengths and all necessary tester junctions, expanding rubber plugs,
testing equipment etc. shall be provided by the Contractor. Drains failing to pass the test
(whether water or air) shall be retested after all defects have been made good.
Soakaways, where provided, shall be tested by subjecting them to an overflow equivalent in
volume to the design rainfall intensity on the area draining to the soakaway. If the soakaway
backs up under these conditions, it shall have failed the test. In this case the soakaway shall be
retested after all necessary remedial work has been carried out.
The manufacturer of precast concrete paving blocks shall carry out the tests specified in BS
6717-1 and test certificates shall be submitted to the Engineer.
Precast concrete kerbs and edgings shall be tested by the supplier for compliance with BS 7263
and test certificates shall be submitted to the Engineer before the materials are incorporated into
the Works.
Precast concrete flags shall be tested by the supplier for compliance with BS 7263 and test
certificates shall be submitted to the Engineer before the materials are incorporated into the
Works.
In-situ concrete shall be tested in accordance with the Specification for Concrete
SECTION J7 BUILDINGS
J7.1 SCOPE
This Section contains requirements which, where relevant to the Contract, shall apply to building
and associated works.
BS EN 1329-1:2000 Plastics piping systems for soil and waste discharge (low and
high temperature) within the building structure. Unplasticized
polyvinyl chloride (PVC-U). Specifications for pipes, fittings
and the system
BS 1521:1972 Specification for waterproof building papersBS EN
12020:2001 Aluminium and aluminium alloys. Extruded
precision profiles in alloys EN AW-6060 and EN AW-6063.
BS EN 515:1993 Aluminium and aluminium alloys. Wrought products.
Temper designations
BS 6925:1988 Specification for mastic asphalt for building and civil
engineering (limestone aggregate
BS 1282:1999 Wood preservatives. Guidance on choice, use and application
BS 6465:1994 Sanitary installations.
BS EN 12056-2:2000 Gravity drainage systems inside buildings. Sanitary pipework,
layout and calculation
BS 1336:1971 Specification for knotting
BS 1387:1985 Specification for screwed and socketed steel tubes and
tubulars and for plain end steel tubes suitable for welding or
for screwing to BS 21 pipe threads
BS 4987-1:2003 Coated macadam (asphalt concrete) for roads and other paved
areas. Specification for constituent materials and for mixtures
J7.4 MATERIALS
J7.4.2 Adhesives
Unless otherwise specified herein, or recommended by the manufacturer of items to be fixed by
adhesives and approved by the Engineer, adhesives shall be selected in accordance with the
recommendations in BS 5442 where relevant and shall be suitable for high ambient temperatures.
strength or appearance. The dimensions of stones shall be appropriate for proper coursing and
bonding.
Materials for external rendering, including cement, lime, aggregates, water, admixtures, pigments
and reinforcement, shall comply with BS 5262. External rendering to blockwork shall be cement
mortar No.3. An approved plasticiser may be added to the mortar mix to improve its workability.
The plasticiser must be approved by the Engineer and shall be used in the mortar mix strictly in
accordance with the manufacturer's instructions.
J7.4.16 Timber
All timber used for the Permanent Works shall be well seasoned and free from excess of wave or
discoloured sapwood, injurious open shakes, large loose or dead knots, decay and insect attack.
Materials for structural timber shall comply with the recommendations of BS 5268: Parts 2
and 5.
The quality of timber in joinery shall comply with BS EN 942 Class J40 timber or, where a clear
finish is specified, for Class J10 timber.
Tolerances on timber sizes shall be in accordance with BS EN 1313.
Location Type
Horizontal work surfaces in laboratories and workshops HDF
Other horizontal work surface HGF
Vertical surfaces and undersides of horizontal surfaces normally
exposed to view VGF
Vertical surfaces not normally exposed to view including inside
faces of cupboards and under sides of horizontal surfaces VLS
J7.4.19 Doors
Except where otherwise specified, wood panelled and flush doors shall be constructed in
accordance with the recommendations of CP 151 to the sizes specified in BS 4787.
Matchboarded doors shall be constructed in accordance with BS 459 and shall be framed, ledged
and braced. Fire doors, steel doors, roller shutter doors, folding doors and the like shall be of
galvanised mild steel and to the approval of the Engineer and full details of their design,
materials, testing and manufacturer's finish shall be submitted by the Contractor including
provisions for dust tightness.
Where steel door frames are specified or approved by the Engineer, they shall comply with BS
1245, otherwise frames and linings to wood doors shall be of wood and shall comply generally
with BS 1567.
J7.4.20 Windows
All windows in external walls shall be double glazed.
Windows for offices, conference rooms and the like shall be double glazed, tinted, horizontal
centre hung with friction hinges and provided with safety stays to limit normal opening to
150mm. For cleaning purposes the windows shall rotate through 180° and be lockable at 180° for
safety while being cleaned. Windows shall be of a size and shape compatible with the building
elevation. Frames shall be to a colour approved by the Engineer and of materials suitable for the
environment. Each window shall be fitted with closeable trickle ventilator, provisions for dust
tightness and with a venetian blind equipped with a rigid manual operating system to raise and/or
tilt the slats.
All other windows shall be of matching size and appearance but shall be fixed.
All windows, when tested in accordance with BS 5368, BS EN 1027 and BS EN 12211, shall
have classifications for weather tightness in accordance with BS 6375 of not less than:
air permeability; 200 Pa
watertightness 100 Pa
wind resistance 1200 Pa
except where other classifications for weather tightness are specified.
In addition, except where otherwise specified, steel windows shall comply with BS 6510 and
aluminium alloy windows shall comply with BS 4873.
Roof lights shall be horizontal fixed lights mounted on an aluminium alloy frame and GRP curb
and provided with means of ventilation as specified on the Drawings. Any ventilation openings
provided shall be fitted with insect screens. The roof lights shall be bedded on butyl-mastic and
screwed down to timber plugs cast into concrete up stands.
J7.4.22 Hardware
Hinges for doors shall be selected from types complying with BS EN 1935 and shall be of cast
iron, brass or aluminium except for outward opening exterior doors where the hinges shall be of
steel. Hinges shall be not less than 100mm long. Doors fitted with thief resistant locks shall have
each leaf hung on three hinges.
All locks on entrance doors to buildings and where thief resistant locks are specified shall
conform to BS 3621. Other locks and latches shall be in accordance with BS EN 12209. Letter
plates, where used, shall be to BS EN 13724.
Fire check doors shall be fitted with hydraulic or floor mounted spring door closers.
Door handles, finger plates, window stays and latches shall generally be in similar matching
materials and finish throughout areas of buildings used for the same purpose. These items shall
also match hinges, other hardware, furniture and light fittings. The Contractor shall submit
details of proposed hardware with samples for approval. Where not otherwise specified or
approved, items shall be of either brass with BMA finish or anodised aluminium. Visible screws
and fastenings shall have a matching finish.
J7.4.23 Glazing
Glass, spacing blocks, putty, mastic, fixing clips and the like shall be as recommended in BS
6262 and glass thicknesses shall be selected for wind loadings of 600N/m² or such greater
loadings as are specified or indicated on the Drawings. Before ordering glass, the Contractor
shall submit his calculations of the thickness required to the Engineer for approval and provide
samples of the glass which it is proposed to use.
Double glazing shall either have an air space in excess of 75mm with provision to allow
occasional cleaning of the inner glass faces, or shall consist of hermetically sealed units
complying with BS 5713 and having air spaces of not less than 10mm. In the latter case the
rebate of windows shall be sufficiently large to mask from view the sealing at the edge of the
units.
J7.4.24 Partitions
Except where otherwise specified, non-loadbearing partitioning, including relocatable partitions,
shall comply with the recommendations of BS 5234.
J7.5 WORKMANSHIP
and all newly erected walling shall be kept wet for at least 3 days by methods to be approved by
the Engineer.
All blockwork shall be laid and jointed with cement mortar No.3.
J7.5.5 Stonework
Unless otherwise specified, all masonry of natural stone or cast stone shall be constructed in
accordance with the recommendations of BS 5628.
J7.5.6 Brickwork
Joints in external or internal facing brickwork, shall be pointed with a 5 mm deep square
recessed joint before the mortar has set.
Except where directed otherwise by the Engineer, facing bricks shall start from 225 mm below
final ground level, the remaining brickwork down to the foundations being in common brick.
Brickwork in commons which is not to be rendered, plastered or tiled shall be finished with flush
joints, any surplus mortar being carefully wiped off to leave the brickwork plain and clean.
The finished rendering shall be protected and cured as specified for concrete.
J7.5.10 Flooring-general
Before the construction of any floor to which a finish is to be applied, the details of the proposed
finish shall be submitted to the Engineer for approval. Any damp proof course or screed required
for the installation of the floor finish as specified, or as required by the Reference Standards or
the manufacturer or installer of the floor finish, shall be incorporated in the floor in accordance
with the proposals approved by the Engineer.
not be delivered to Site for any purpose unless the Engineer has approved the Contractor's
proposals for ensuring that untreated timber is not incorporated in the Permanent Works.
J7.5.19 Carpentry
Workmanship for carpentry shall be in accordance with the recommendations of BS 5268: Part 2.
Wood chipboard for suspended flooring shall be laid in accordance with BS 5669.
J7.5.20 Joinery
Except as otherwise specified, joinery shall be carried out in accordance with BS 1186: Part 2.
Joinery of softwood shall be knotted, stopped and primed before leaving the joiner's shop. All
exposed faces of joinery shall be wrought and sanded to a standard where no defect is apparent
after the application of any specified finish.
Where timber is fixed with nails or pins which may be exposed to view in normal usage, the nails
or pins shall be punched in and the holes stopped with approved stopping. Where timber is fixed
with screws which may be exposed to view in normal usage, the screws shall be sunk in
countersunk holes covered by matching timber pellets. Where timber usually fixed by screws is
required to be removable, it shall be fixed with countersunk screws set in cups.
J7.5.22 Glazing
Glazing shall be carried out in conformity with BS 6262 and other Reference Standards where
applicable. Glazing of any portion of the Works shall not commence until the calculations of
glass thicknesses have been approved by the Engineer.
Immediately before completion of the Contract, all glass shall be cleaned inside and out, and any
defective, cracked or scratched panes shall be replaced. All glazing shall be watertight on
completion.
J7.5.23 Partitions
Except where otherwise specified, non-loadbearing partitioning including relocatable partitions
shall be erected and installed in accordance with the recommendations of BS 5234.
The Contractor shall submit drawings for the Engineer's approval showing details of the ceiling
supports and any light wells and semi-recessed light fittings to be incorporated.
J7.5.34 Painting
Surfaces to be painted shall be painted in accordance with the system specified in the “Painting
Schedule” at the end of this clause.
Paints to be used in the Works shall comply with the requirements detailed in the following table
and shall, in so far as it is practicable, be obtained from one manufacturer.
Any paint surface which after a reasonable curing period is considered by the Engineer to be
more sensitive to solvent-rub than a standard cured sample of the same material shall be
completely removed and a further coat of paint applied.
The Contractor shall regard the preparation of all surfaces to be painted as work of fundamental
importance and he shall provide surfaces which are sound clean smooth and dry. The preparation
shall have no detrimental effect on the sub-strata to be painted nor shall it be prejudicial to
subsequent operations.
Generally all timber iron and steel will be in a primed condition before delivery to site and will
not require further priming except to make good the damaged areas. Such work shall comprise
the preparation and primary procedures as described herein.
Where surfaces are suspected of being infected with mould they shall be thoroughly washed with
a fungicide.
Prior to the applications of any primer and between subsequent coats the surface shall be clean
dry and free from grease and other deposits.
Any knots or resinous runs in timber shall be scraped down and treated with knotting varnish. All
knotholes shall be plugged with timber. Minor holes cracks and crevices shall be filled with an
approved stopping compound.
Where soldered welded or brazed joints occur care shall be taken to remove fluxing material and
other debris before painting.
Painting shall not be undertaken in unfavourable weather or where the ambient temperature is
less than 5°C or the relative humidity is higher than 80% or when such conditions may arise
before the paint work has dried.
Surfaces shall not be painted when they are or are likely to be exposed to direct hot sunshine.
Where dirt or dust has been trapped in the paint film it shall be removed with fine abrasive paper.
Paint shall be applied uniformly. Adequate time shall be left for drying between successive coats.
Exposure of intermediate coats of paint for periods in excess of a few days shall not be permitted
except in the case of work delivered to site in a primed condition. Any work that has been subject
to deterioration from exposure shall be treated as described for remedial work.
Priming paints shall be applied by brush unless otherwise authorized by the Engineer.
Paints shall be well stirred before and during application. A wet edge to the paint surface shall be
maintained throughout all painting operations.
PAINTING SCHEDULE
Softwood primed Interior Gloss Sand down, treat knots 1 coat pink primer Alkyd undercoat
or unprimed Alkyd topcoat
Exterior Gloss Sand down treat knots 1 coat pink primer Alkyd undercoat
Alkyd topcoat(2 coats)
Plaster (including Interior Flat Degrease Sand down Emulsion thinned to 2 coats emulsion
plaster board) manufacturer's instructions
Interior Gloss Ditto 1 coat alkali-resistant Alkyd undercoat
primer Alkyd topcoat
Interior Multi-colour Ditto 1 coat primer Multi-colour wall finish
Blockwork Interior Gloss -1 coat alkali-resistant 2 coats approved alkyd masonry paint
Cement rendering primer
Concrete *Exterior Textured Stiff Brush -Stabilising solution
(fair-faced)
Hardboard Interior Flat Zinc chromate spot 1 coat emulsion 2 coats emulsion
primer to screw & nail
Interior Gloss heads 1 coat hardboard primer Alkyd undercoat
Alkyd topcoat
J7.5.35 Galvanising
Where steel or wrought iron is specified to be galvanised the galvanising shall be executed after
all fabrication has been completed. The articles shall be pickled in dilute sulphuric or
hydrochloric acid followed by rinsing in water and pickling in phosphoric acid. They shall be
thoroughly washed stoved and dipped in molten zinc and brushed so that the whole of the metal
shall be evenly covered and the additional weight thereof after dipping shall not be less than
610g/m2 of surface galvanised except in the case of tubes to BS 1387 when it shall be 460g/m2.
Edges shall be clean and surfaces bright.
J8.1 SCOPE
This Section contains requirements which, where relevant to this Contract, shall apply to the
provision and installation of furniture, furnishings, hand held fire extinguishers and other fittings.
The work shall include interior design, co-ordination of colours, finishes and materials,
procurement and installation of furnishings.
BS 4875-1:2001 Strength and stability of furniture. Requirements for the strength and
durability of the structure of domestic and contract seating
The furniture and fittings shall comply with all relevant rules and regulations of the Ministry of
Regional Municipalities and Water Resources and shall be of equal or higher quality to the
furniture with which the Directorate of Dams offices are equipped.
J8.3.1 Data
• Complete interior colour schemes;
• Manufacturers' catalogues, data sheets and specifications;
• Colour cards;
J8.3.2 Certificates
• Certificates showing compliance with British Standards.
J8.3.3 Samples
• Full size samples of typical items of furniture;
• Samples of basics.
J8.4 MATERIALS
J8.4.1 General
Office furniture shall comply with BS 5459 and any other seating including lounge chairs or
settees shall have performance ratings to BS 4875 of not less than grade 4. Upholstered seating
shall conform to BS 6261. The design and manufacture of materials used in upholstered furniture
shall be such as will pass the fire tests in BS 5852:1 and 2.
Hardware for furniture shall be resistant to corrosion and be of robust construction.
Unless otherwise specified, desks, worktables and chairs for use therewith shall have dimensions
and other properties in accordance with BS 5940. Furniture shall be selected from manufacturers'
standard lines intended for the high quality range of commercial and institutional use and
designed for the specified purpose. Where furniture in a room, a suite of rooms or a building is to
be used for similar purposes, it shall, wherever practicable, be provided from one design range
from one manufacturer to ensure compatibility of styling and allow future interchange and re-
arrangement. Furniture shall be from a modular range of desks and storage units to assemble
appropriate workstations for the nature of the offices. Furniture supplied shall be of equal or
better quality than the furniture with which the Directorate of Dams offices of the Ministry of
Regional Municipalities and Water Resources are equipped.
Furniture shall be in contemporary style in scale with the size and use of the buildings. Colours
shall be generally in the clear lighter range, with accents applied to smaller surface areas such as
chair seat and backs and draperies. Plastic laminate table and desk tops shall be in wood grain or
solid tone. Steel furniture and frames for work tables shall be finished in baked-on acrylic
enamel. Tubular aluminium frames shall be satin anodized finish. Legs, frames and surface
hardware shall be brushed stainless steel or dull chrome finish. Alternatively wood grained
casework may have blending colour toned hardware.
Colour schemes for furniture and furnishings shall be designed taking into account specified
ceiling, wall and floor finishes, light fittings, door furniture etc, and including details of all
colours and finishes which are not specified. Colour schemes and furniture and furnishing details
shall be submitted as fully developed proposals to the Engineer for approval.
All drawer slides shall be on nylon block or nylon rollers. All filing drawers, including desk
units, shall be equipped with heavy duty full-suspension ball bearing tracks.
All wood core casework, including cabinet assemblies shall be of rigid fabrication and design.
Exposed sides, drawer fronts and tops shall be finished with textured plastic laminate. Natural
wood furniture shall be solid hardwood stock with high temperature and high humidity resistant
glues with dowel or mortise and tenon joints.
Hardwood shall be carefully matched for type and grain and be free from blemish and of even
colour. Timber shall be finished to a high standard in acrylic lacquer clear coat matt finish.
Plastic laminated panels shall have balancing veneer on the reverse side and thick matching
plastic veneer edgings.
Locker units, desks, cupboards and filing cabinets shall be equipped with locks with three keys to
each fitting.
J8.5 WORKMANSHIP
J8.5.2 Installation
Furniture and furnishings shall not be placed in position until all construction work has been
completed and thoroughly cleaned and the Permanent Works are ready for final inspection.
Packing shall not be removed until items are finally placed in position.
The Contractor shall place in position all loose furniture in accordance with the schedules. All
wall and soffit mounted fittings shall be adequately mechanically fixed into position with
corrosion resistant fastenings compatible with the background materials and approved by the
Engineer.
J9.1 SCOPE
This Section includes requirements for building services equipment for use on the Contract
Works.
BS EN 671-2:2001 Fixed fire fighting systems. Hose systems. Hose systems with lay-flat
hose
BS EN 671-3:2000 Fixed fire fighting systems. Hose systems. Maintenance of hose reels
with semi-rigid hose and hose systems with lay-flat hose
BS 21:1985 Specification for pipe threads for tubes and fittings where pressure-
tight joints are made on the threads (metric dimensions)
BS EN 10226-1:2004 Pipe threads where pressure tight joins are made on the threads.
Taper external threads and parallel internal threads. Dimensions,
tolerances and designation
BS 5292:1980 Specification for jointing materials and compounds for installations
using water, low-pressure steam or 1st, 2nd and 3rd family gases
BS EN 751-2:1997 Sealing materials for metallic threaded joints in contact with 1st, 2nd
and 3rd family gases and hot water. Non-hardening jointing
compounds
BS EN 751-1:1997 Sealing materials for metallic threaded joints in contact with 1st, 2nd
and 3rd family gases and hot water. Anaerobic jointing compounds
BS 6956-1:1988 Jointing materials and compounds. Specification for corrugated metal
joint rings
BS 6956-5:1992 Jointing materials and compounds. Specification for jointing
compounds for use with water, low pressure saturated steam, 1st
family gases (excluding coal gas) and 2nd family gases
BS 143 and 1256 Threaded pipe fittings in malleable cast iron and cast copper alloy
BS 1387:1985 Specification for screwed and socketed steel tubes and tubulars and
for plain end steel tubes suitable for welding or for screwing to BS 21
pipe threads
BS EN 10216-1:2002 Seamless steel tubes for pressure purposes. Technical delivery
conditions. Non-alloy steel tubes with specified room temperature
properties
BS EN 10217-1:2002 Welded steel tubes for pressure purposes. Technical delivery
conditions. Non-alloy steel tubes with specified room temperature
properties
BS 2971:1991 Specification for class II arc welding of carbon steel pipework for
carrying fluids
BS 2640:1982 Specification for Class II oxy-acetylene welding of carbon steel
pipework for carrying fluids
BS EN 970:1997 Non-destructive examination of fusion welds. Visual examination
BS EN 1044:1999 Brazing. Filler metals
BS 417-2:1987 Specification for galvanized low carbon steel cisterns, cistern lids,
tanks and cylinders. Metric units
BS 4213:2004 Cisterns for domestic use. Cold water storage and combined feed and
expansion (thermoplastic) cisterns up to 500 l. Specification
J9.4.4.1 General
Values of the resistance to fluid flow of items of equipment, pipework and/or the total
distribution system where indicated in the contract documents are approximate. It shall be the
responsibility of the Contractor to verify these values and provide pumps capable of delivering
the required volume when operating against the actual total system resistance.
Pumps shall comply with the requirements of BS EN 1151, BS 4082 - 1 and 2 and BS 5257, as
applicable.
Pumps shall be `type' tested in accordance with the requirements of BS EN ISO 9906 and shall
be selected to give the correct fluid flow rate. Test certificates and performance curves shall be
submitted.
Pumps and their drives shall be segregated such that failure of pump seals shall not result in
damage to drive motors.
J9.4.5.1 General
Unless otherwise indicated, steel and copper pipework systems shall be in accordance with BS
EN 13480 or BS 1306 as relevant.
Where any of the services referred to in this section require the connection of differently sized
items, the Contractor shall be responsible for providing and installing the necessary adaptors.
Joints shall not be made in the thickness of any wall, floor or ceiling, and pipework shall not be
embedded in the structure of floors unless approved by the Engineer. Where pipework passes
through walls, floors or ceiling, sleeves shall be provided. Pipework passing through floors shall
be provided with approved floor and ceiling plates fastened securely to the pipe. Where a piped
service perforates a structure which is a fire barrier with a designated fire delay characteristic to
BS 476-20, the sleeve shall act as a fire stop complying with the local Building Regulations.
Fittings shall be of the same size as the tubes and pipes to which they are connected.
Exceptionally where a fitting having the required outlet is not of standard manufacture, the
necessary size reduction may be accomplished by the use of one bush for each connection.
Galvanised fittings shall be used only on galvanised pipework.
Pipework shall follow the contours of walls. The clearance between pipework, fittings, lagging or
flanges, and the wall or any other fixtures, shall be not less than 25mm.
Purpose made bends or springs may be used where it is necessary to deviate from a straight run
in un-galvanised pipework. In galvanised pipework deviations shall be formed from standard
fittings.
Bends or springs in tubes of DN50 and above shall be hot pulled and the tubes shall remain
circular after setting.
Eccentric reducing sockets shall be used where changes of bore are made in runs of nominally
horizontal pipework to facilitate air venting and draining.
Before pipework is assembled, the Contractor shall ensure that tubes and tube ends are free from
burrs and cutting dross. Tube ends shall be cleaned thoroughly of deleterious materials such as
rust, scale, paint, oil etc. Open ends left during the progress of work shall be closed temporarily
with purpose made metal, plastics or wood plugs or caps, or blank metal flanges.
Entry and exit holes for pipework services from buildings shall be sealed and plugged. For
service conditions below 60oC the sealant shall be mastic compound; above this temperature
sealants shall be silicone rubber. Where pipework enters a building through a duct or hole which
is considered by the Engineer to be too large for such treatment, a mild steel blanking plate not
less than 6mm thick shall be built into the walls of the duct or hole. The service pipes shall pass
through clearance sockets (not less than 4 diameters in length) welded into the blanking plate,
and the spaces between pipes and sockets shall be sealed and plugged as above.
Return headers, where indicated, shall be welded with flanged connections and ends. Each circuit
isolating valve shall be connected direct to a vertical flanged outlet on the top of the return
header. On the circuit side of the isolating valve a tee shall be fitted with a vertical thermometer
in the top reduced outlet. Each circuit return shall be taken horizontally towards the wall behind
the header to another tee, with a reduced outlet in a downward direction, into which the circuit
emptying pipe shall be connected and extended to a drain cock or valve below the level of the
header. The circuit return shall be connected into the vertical full-bore outlet of this second tee.
Headers shall be horizontal and thermometers, drain valves and circuit isolating valves shall be
arranged at common horizontal levels.
Flow headers where indicated shall be welded with flanged connections and ends, and installed
to prevent undue stresses on the boilers and their connections.
Unless otherwise indicated, both flow and return headers shall be provided with one spare
flanged connection. These connections shall be of sizes not less than the largest circuit
connections to the headers and they shall be sealed with blank flanges.
Metallic pipework systems shall be bonded in accordance with BS 7671 and all pipework
installations shall be electrically continuous.
(iv) Flanges for copper pipework shall be of composite type complying with BS EN 1092-3
comprising copper alloy inserts brazed to the tube with loose steel rocking rings. Flange
connections shall comply with items (v) and (vi) as appropriate.
(vi) Flanged joints shall be made with gaskets to BS EN 1514-1 or BS 3063 as appropriate.
They shall be of a grade and thickness suitable for the temperature, pressure and
operating conditions.
(vii) Pipework shall be arranged to allow easy dismantling. Dismantling points in copper
pipework up to and including DN50 shall be unions, otherwise they shall be flanged.
(viii) Where cold water services inside buildings do not form part of the Works, the DHWS
system shall terminate within 450mm of each sanitary fitting or range of appliances.
(iv) Proprietary grooved pipe jointing systems using elastomeric seal rings may be used with
the approval of the Engineer up to a maximum temperature of 95oC and a maximum
pressure of 9.5 bar. They shall be suitable for the temperature, pressure and operating
conditions of the service. Manufacturer's recommendations on pipe wall thickness,
methods of groove forming (cut or rolled), groove dimensions, seal materials and
limiting operational loads shall be followed. Piping ends shall be within the
recommended tolerances and shall be free from burrs and distortion.
J9.4.5.6 Welding
Unless otherwise indicated steel pipework complying with BS 1387 or BS EN 10216 and BS EN
10217 with diameters and wall thicknesses not exceeding DN 200 and 20mm respectively shall
be welded in accordance with a method of working to be submitted by the Contractor and
approved by the Engineer. Steel pipes of larger diameters and greater thicknesses shall be welded
in accordance with BS 2971, BS 2640 or other specifications as indicated or approved by the
Engineer.
Joint designs, welding procedures, welder certification and production weld quality shall comply
with the requirements the Engineer.
Unless otherwise indicated, joint designs, welding procedures and welders' competency tests
shall be submitted by the Contractor and approval by the Engineer. Prior approval shall be
obtained to the installation of gusseted bends.
Welds in fire protection system pipework shall be visually inspected in accordance with the
recommendations of BS EN 970, and copies of the records shall be given to the Engineer. Welds
will be checked by the Engineer at the time the pipework is pressure tested. Where the Engineer
is unsatisfied, the welds shall be subjected to non-destructive testing procedures.
J9.4.5.7 Brazing
Copper pipework up to DN200 with wall thicknesses up to 4.5mm shall be brazed in accordance
with a method of working to be submitted by the Contractor and approved by the Engineer. For
other pipe sizes and thicknesses, brazing shall be carried out in accordance with BS 1723, or
other specification as indicated or approved by the Engineer.
Joint designs, brazing procedures, brazer certification and production joint quality shall comply
with the requirements as interpreted by the Engineer.
Unless otherwise indicated or approved, filler metal shall be AG303 as specified in BS EN 1044.
Mild steel cisterns shall comply with BS 417 Grade A galvanised after manufacture, sacrificial
anodes being provided where indicated. Pressed steel sectional tanks shall be approved. Thermo-
plastics cisterns shall comply with BS 4213. Glass reinforced plastics and butyl rubber lined
cisterns shall be approved by the Engineer.
Each cistern shall be provided with a loose cover formed in sections not exceeding 2m long and
1m wide. Covers for steel cisterns shall be formed with 1.6 mm thick galvanised mild steel with
flanged edges to the sections. Covers for plastics and butyl rubber lined cisterns and tanks shall
be of the same material as the cistern or tank body. The termination of vent pipes into cisterns
and tanks shall permit the easy removal of the covers.
Pressed steel tanks shall be of the externally flanged type and complete with purpose made
covers and all necessary tie rods. Galvanised mild steel cisterns and pressed steel tanks shall be
painted internally with two coats of an approved bituminous solution.
Each cistern or tank shall be fitted with a ball-float valve. Ball-float valves shall be of the sizes
indicated and suited to the pressure available. The cistern or tank shall be installed in a position
that allows easy access for maintenance of the ball-float valve.
Float operated valves shall be to BS 1212 of a size and type to suit the cistern and duty and those
for use with feed/expansion and spill tanks shall be of the long-arm type arranged to shut off
when the tank contains 150 mm depth of water. Where a water meter, measuring the make-up
water quantity is indicated, the ball-float valve shall be of the delayed action type. The floats of
the valves shall be of heavy copper to BS 1968 Class C, or may be of heavy plastics to BS 2456
for cold water cisterns.
Warning and/or overflow pipes shall be twice the bore of the ball-float valve fitted or 32mm size,
whichever is the greater. Warning and/or overflow pipes shall be run to discharge outside the
building.
Connections to mild steel cisterns and tanks shall be made by means of bosses, screwed flanges
or pads and studs. Connections on mild steel cisterns shall be welded before galvanising.
Openings for connections to other tanks may be cut on site and the connections made with back-
nuts and plastics washers. For thermo-plastics and butyl rubber lined cisterns and tanks,
connections shall be fitted in accordance with the manufacturer's recommendations. Flanged
connections may be used on modular glass reinforced plastics tanks and cisterns.
Cisterns and tanks shall be labelled.
Pressed steel tanks shall be of the externally flanged type and complete with purpose made
covers and all necessary tie rods. Galvanised mild steel cisterns and pressed steel tanks shall be
painted internally with two coats of an approved bituminous solution.
Each cistern or tank shall be fitted with a ball-float valve. Ball-float valves shall be of the sizes
indicated and suited to the pressure available. The cistern or tank shall be installed in a position
that allows easy access for maintenance of the ball-float valve.
Float operated valves shall be to BS 1212 of a size and type to suit the cistern and duty and those
for use with feed/expansion and spill tanks shall be of the long-arm type arranged to shut off
when the tank contains 150mm depth of water. Where a water meter, measuring the make-up
water quantity is indicated, the ball-float valve shall be of the delayed action type. The floats of
the valves shall be of heavy copper to BS 1968 Class C.
Warning and/or overflow pipes shall be twice the bore of the ball-float valve fitted or 32mm size,
whichever is the greater. Warning and/or overflow pipes shall be run to discharge outside the
building.
Connections to mild steel cisterns and tanks shall be made by means of bosses, screwed flanges
or pads and studs. Connections on mild steel cisterns shall be welded before galvanising.
Openings for connections to other tanks may be cut on site and the connections made with back-
nuts and plastics washers. For thermo-plastics and butyl rubber lined cisterns and tanks,
connections shall be fitted in accordance with the manufacturer's recommendations. Flanged
connections may be used on modular glass reinforced plastics tanks and cisterns.
Cisterns and tanks shall be labelled.
J9.4.9.1 General
Unless otherwise indicated, copper alloy shall mean gun-metal grade CC491K to BS EN 1982.
Gland packing, plug lubricants etc shall be suitable for the application. For potable water
systems, materials shall comply with the requirements of the Water Undertaking. Graphite
packing will not be accepted in valves for hot systems.
Valves shall be easily accessible. Valves fitted in horizontal pipework or to equipment with
horizontal connections, shall be installed with the valve spindle vertically upwards unless
otherwise agreed by the Engineer. Check valves shall be installed in accordance with the
manufacturer's recommendations.
Where indicated, valves or cocks shall be lockable, with purpose made locking devices which do
not impede the fast closure of the valve where that is necessary. The locking device shall remain
attached to the valve in both 'open' and `closed' position.
Where modifications or extensions to existing services are to be carried out, all valves which are
to be removed and re-fixed shall be overhauled thoroughly, with glands and seals renewed, all to
the satisfaction of the Engineer.
Copper alloy valves shall be resistant to dezincification where recommended by the Water
Undertaking and approved by the Engineer.
J9.4.10 Fans
J9.4.10.1 General
Values of the resistance to air flow of items of equipment, ductwork and/or the total distribution
system where indicated in the contract documents are approximate. It shall be the responsibility
of the Contractor to verify these values based on the equipment offered and provide fans capable
of delivering the required air volume when operating against the actual total system resistance.
Fans shall be type' tested in accordance with the requirements of BS 848 and shall be selected to
give the air volume flow rate and sound power level specified in the contract documents.
Unless otherwise indicated, the requirements of this Section shall not apply to individual fans
having a duty air flow rate of 0.7m3/s or less.
All fans should be constructed to a fully developed design and shall be capable of withstanding
the pressures and stresses developed during continuous operation at the selected duty.
Additionally, all belt driven fans shall be capable of running continuously at ten per cent in
excess of the selected duty speed.
Fan drives shall be as detailed elsewhere in this Specification.
Fans shall be installed using bolts, nuts and washers with all `as cast' bearing surfaces for bolt
heads and washers counter faced. Holding-down bolts for fans and motors shall be provided with
means to prevent the bolts turning when the nuts are tightened. Anti-vibration mountings shall be
as detailed elsewhere in this Specification. Fans heavier than 20kg shall be provided with
eyebolts or other purpose made lifting facilities.
Where indicated or as necessary, fans shall be fitted with variable inlet vanes which shall be
matched to the fan performance to give stable control. Vanes shall be closely interlocked to
ensure movement in unison and operation shall be manual or automatic as indicated. Where
manual control is indicated, the operating device shall facilitate positive locking in at least five
different positions.
Vane blades shall not vibrate or flutter throughout their movement and the construction of the
linkage system shall minimise friction and lost motion.
The shaft and impeller assembly of all centrifugal, axial flow and mixed flow fans shall be
statically and dynamically balanced. All propeller fans shall be statically and dynamically
balanced where the impeller diameter is 750mm or greater. Limits of vibration severity shall be
in accordance with BS 7854.
Fan bearings shall be of a type suitable for the installed attitude of the fan. They shall be grease/
oil ball and/or roller type or alternatively oil lubricated sleeve type. All bearing housings shall be
precision located in position and arranged so that bearings may be replaced without the need for
realignment. Bearing housings shall be protected against the ingress of dust and, where fitted
with greasing points, they shall be designed to prevent damage from over-greasing. For grease
lubricated systems the bearings shall be provided with grease in amount and quality
recommended by the bearing manufacturer. For oil lubricated systems the housings shall provide
an adequate reservoir of oil and shall include a filling plug and be oil tight and dust proof.
Systems other than total loss types shall include an accessible drain plug. All bearing lubricators
shall be located to facilitate maintenance.
Impellers shall be of mild steel or aluminium alloy of riveted, welded or other approved
construction, with spiders or hubs of robust design.
J9.4.10.6 Protectively coated fans and fans for corrosive or hazardous applications
Where fans are required to handle toxic, corrosive, flammable, explosive or high temperature
gases the materials of construction shall be as indicated and all relevant safety regulations shall
apply. Bearings and lubrication arrangements shall be suitable for the conditions. Protectively
coated fans shall meet the appropriate requirements of the preceding clauses relating to fans
generally and to particular types of fans; the form of protection shall be as indicated. Where a
protective coating is required for use with corrosive gases the coating shall cover all parts of the
complete fan, motor and casing assembly which will be in contact with the corrosive gases. No
fan shall be installed if the protective coating has been damaged in any way. Impellers shall be of
coated steel, stainless steel or aluminium or plastics as indicated. Where fans are installed in a
potentially flammable explosive atmosphere requirements are to be as indicated and the electrical
installation and motor shall be suitable for the hazardous area zone classification in which it is
installed in accordance with BS 5345.
J9.4.11.1 General
Automatic sand filters shall be based upon the principle of inertial separation of sand from air by
virtue of a relatively circuitous flow path for air compared with a straight flow path for sand.
Each sand filter shall consist of housing, bleed air manifold, cell bodies, blade packs, bullnoses,
and inlet screen. All finished components shall be hot dip galvanized finished with a 2 pack
epoxy resin paint.
J9.4.11.2 Housing
Housings shall be constructed of not less than 11 gauge steel. The housing shall be of all welded
construction and equipped with continuous standing flanges around the periphery of both air
entering and air exiting sides. Flanges shall have pre-drilled bolt holes to facilitate field
installation.
J9.4.11.8 Efficiency
The sand filter efficiency shall not be less than 93% at a clean airflow rate of 1700m3/h per single
cell using a bleed rate equalling 10% of inlet flow. Inlet to clean air outlet resistance shall not
exceed 0.30kPa at 1700m3/h clean airflow.
J9.4.12.1 General
Filter assemblies shall operate with at least the efficiencies specified in this Section, or as
indicated elsewhere in the Specification or on the drawings.
Filter material or wetting agent shall not be carried over. Filters shall be complete with robust
purpose made holding frames which shall not distort in operation and all filters shall be arranged
to facilitate access for cleaning, removal and refitting. Purpose made seals shall be provided to
minimise air leakage around filters and the effectiveness of the seals shall not be impaired by
periodic removal and refitting of the filter cells.
A differential pressure gauge of the inclined manometer type shall be provided for each filter
bank and the gauge shall be fixed in such a position, outside the casing that it is accessible and
easily read. The gauge shall incorporate a graduated scale on which the reading of maximum
pressure drop shall occur in not less than 75% of the total scale length.
m/s. Bag filters shall inflate fully, shall not sag or flutter or be obstructed by contact with other
filter faces or duct surfaces.
At the design air volume flow rate the initial (clean) resistance shall not exceed 90 Pa for filters
of grade EU3 and 125 Pa for filters of a higher grade.
Sufficient spare filter medium shall be provided to replace the complete filter bank.
Unless otherwise indicated, filters shall be selected from the following range of preferred
nominal sizes:
(a) 600mm x 600mm
(b) 500mm x 500mm
Unless otherwise indicated, the initial (clean) resistance of the filter shall not exceed 65Pa and a
mean of 125Pa under design operating conditions. The air velocity through the filter medium
shall not exceed 2.5m/s unless otherwise indicated. Unless otherwise indicated filters of this type
shall be of a grade not less than EU2 in accordance with Eurovent 4/5 standard.
The motor and drive, the electrical insulation and lubricants shall be suitable for the conditions
indicated. The motor, drive and associated control equipment shall be accessible for maintenance
without disturbing the filter medium or roll. The medium shall be provided with an effective seal
to minimise air leakage around it.
A spare roll of filter medium shall be provided for each unit.
J9.4.13.1 General
Casings shall be of galvanised sheet steel not less than 1.2mm thick with angle framing at each
end drilled ready to receive the counter flanges on the connecting ductwork. Heaters shall be
supported so that their weight is not transmitted to ductwork and so that they can be removed
without disturbing adjacent ductwork. Inspection doors shall be provided on both the upstream
and the downstream sides of the heater.
The control of electric air heaters, except for remote boosters, shall be interlocked with the fan
motor starters and an air flow control of the pressure type so that the heaters cannot operate
unless the fan is running.
Electric air heaters which are installed as boosters in branch ducts remote from the fans shall
have an air flow control of the vane or pressure type which shall isolate the heating elements
from the electricity supply in the event of the failure of air flow.
The number of elements in the heater shall be the same as or a multiple of the number of steps in
the controller. All heaters and heater sections of more than 3 kW loading shall be balanced over 3
phases and the complete heater bank shall be arranged for balanced operation on a 3-phase 4-
wire system.
The connections form each element shall be taken to a readily accessible terminal box arranged
for conduit entry. Each heater section shall be separately fused and the neutral point of all 3-
phase star-connected sections shall be brought out to a link in the terminal box. Near hot areas
the wiring insulation shall be of a quality suitable for the maximum temperature.
The total resistance of the heater to air flow shall not exceed 25Pa and the face velocity shall not
exceed 6m/s.
J9.4.14.1 General
Split air conditioning units shall each comprise an indoor evaporator unit and either a roof-
mounted, air-cooled condensing unit, or an internally mounted centrifugal air-cooled condensing
unit ducted to outside air, together with all interconnecting refrigerant pipework. Split units shall
comply with the requirements of BS EN 378-2.
The evaporator shall be a single-pass copper coil with light gauge aluminium fins mechanically
bonded to it and with an automatic thermostat to prevent excessive frosting.
Each unit shall be provided with a wall mounted isolation switch grouped with lighting switches,
together with a hand held remote control. Units shall have facilities for varying the fan speed and
air flow direction. Units shall be capable of thermostatic control to a pre-set temperature between
18 and 26° C
J9.4.15.1 General
Air cooler casings shall be of galvanised sheet steel not less than 1.2mm thick with flanged ends
drilled to receive counter flanges on connecting ductwork or other associated equipment. The
bottoms of casings shall be made in the form of a watertight drip tray from sheet steel galvanised
after manufacture, or be otherwise equally corrosion resistant. Water shall not be carried over
from a cooler battery into the system and an eliminator section shall be provided, where
indicated, to prevent such carry over. The drip tray serving the cooler shall be extended or a
separate tray shall be provided to collect water from the eliminator. Drip trays shall be sloped
toward a drain connection and pipework shall be installed from each connection to the nearest
sump or gully. The drain pipework shall include a water seal of adequate depth to prevent entry
or exit of air to or from the system. A separate drip tray shall be provided for each 1.2m depth of
coil. Sealing devices shall be provided at tops and bottoms of coils to minimise air bypass and
water carry over.
Particular care shall be taken to avoid the use of dissimilar metals in the construction of tubes
and extended surfaces and to avoid contact between dissimilar metals in the presence of free
moisture.
Sprayed coil tubes and extended surfaces shall always be of the same material. The secondary
extended surfaces shall be in firm and continuous mechanical contact with the primary tubes to
ensure maximum heat transfer.
The resistance to air flow through a cooler battery shall not exceed 125Pa and the face velocity
shall not exceed 2.5m/s.
Air coolers shall be supported such that their weight is not transmitted to ductwork and they can
be removed without disturbing adjacent ductwork. Readily removable access panels with air
seals shall be provided upstream and downstream of the cooler battery. Access panels shall be
sized for the full height of the connecting ductwork but need not exceed 1800mm.
Before leaving the maker's works cooler batteries shall be tested with air under water to 1.5 times
the working pressure or to 700kPa whichever is the greater.
J9.4.16.1 General
All ductwork enclosing humidifying plant shall be watertight. Ductwork and plant shall be
protected from corrosion either by choice of materials or by an approved protective finish.
Particular care shall be taken in the design of plant and the choice of materials to minimise
electro-chemical corrosion between dissimilar metals.
J9.4.17 Ductwork
J9.4.17.1.1 General
Ductwork shall comply with the HVCA publications DW/144 and DW/143 with additions or
amendments as required by this specification and elsewhere in the contract documents.
Internal roughness and obstructions to air flow (other than dampers, splitters, vanes etc) will not
be accepted for ductwork constructed from sheet materials. Sharp edges or corners on the outside
of ductwork, fittings and supports will not be accepted. Where the use of other fastenings is
impractical self-tapping screws may be used subject to the approval of the Engineer.
At each point where a duct passes through a roof or external wall a weather cravat or other
purpose made arrangement shall ensure weatherproof fixing.
Duct connections between individual components of an air handling assembly and connections
between an assembly and a ductwork system shall be made with angle flanged joints.
Spring actuated pivoted single blade or multi-bladed dampers may be used for vertical or
horizontal duct applications. Multi-bladed dampers shall be provided with a means to ensure that
all the blades close simultaneously.
Gravity operated multi-bladed fire dampers shall not be used in vertical ducts.
Gravity operated single blade dampers may be used for both vertical and horizontal ducts
providing means are incorporated which ensure reliable and positive closure when operating in
maximum air flow rate conditions.
Where gravity acting off-centre pivoted dampers incorporate spindle bearings long term
corrosion effects shall be minimised by choice of materials and bearings shall be sealed or
capped to exclude dirt and dust. Damper blades shall close to comply with the stability and
integrity requirements of BS 476-8.
For high velocity air systems fire dampers shall be of the type where damper blades, in the open
position, give minimum interference with the air flow.
Unless otherwise indicated, each fire damper shall be held in the open position by a corrosion
resistant retaining device incorporating a fusible element which shall operate at a temperature of
72oC, unless otherwise indicated.
Fire dampers shall be located in such a position and be of types which facilitate periodic manual
release and re-setting for test purposes.
J9.4.18.1 General
The testing and rating of air terminal devices and the definition of terms used concerning such
devices shall be in accordance with BS EN ISO 5135.
The sizes of all air terminal devices shall be based on the dimensions indicated and shall be
suitable for the air volume flow rate, air diffusion and noise rating indicated.
The materials of construction shall be steel, aluminium or plastics as indicated. All items shall be
protected against corrosion and be provided in fully finished condition.
The perimeters of all air terminal devices shall be provided with positive seals with the exception
of those mounted on exposed ductwork.
J9.4.18.3 Diffusers
Diffusers shall be of steel, aluminium or plastics as indicated. Steel diffusers shall be protected
against corrosion and shall be stove enamelled. Diffusers mounted on ceilings shall have anti-
smudge surrounds. Pan type diffusers may be provided except where cone type diffusers are
indicated.
Each diffuser shall be provided with an air flow rate controller. Where a diffuser is directly
connected to a stub duct which has a straight length of less than two diameters or equivalent
diameters then an equalising deflector shall be used.
Casings shall be lined with material to act as both thermal and acoustic insulation. Fan and motor
assemblies shall be complete with anti-vibration mountings. Noise data shall be provided and
shall be based on the tests in accordance with the appropriate British Standard Specification; full
details of the testing technique and procedure shall be given. The data shall include an octave
band analysis of the sound power level of the unit when operating at its design speed.
J9.4.19.1 General
Testing and rating of terminal units shall meet the requirements of BS 4954 and BS 4857.
closed positions the air leakage across the device at the indicated pressure shall not exceed 2% of
the maximum air volume flow rate for which the unit is designed. If a flow rate controller is
mounted within a box means shall be provided to facilitate access.
All units shall be supplied to comply with the sound levels indicated. Acoustic lining shall be
securely fixed and shall be proofed against erosion by the airflow.
J9.4.20.1 General
Individual components forming part of packaged air handling plant shall, in addition to this
section, comply with the appropriate sections contained elsewhere in this Specification.
J9.4.20.2 Construction
Air handling assemblies shall be of rigid construction corrosion resistant and strengthened as
necessary to prevent distortion and drumming in operation. All individual components and
sections shall be assembled using proprietary and approved fastening techniques. Locking
devices shall be used with all fastenings which are subject to vibration. Material thicknesses and
methods of strengthening and fastening shall ensure that air handling assemblies are no less rigid
in operation than the distribution ductwork to which they connect.
Readily removable panels with air seals shall be provided to facilitate access to be made to
upstream and downstream faces and internal parts of all sections in the air handling plant. The
access panels shall be secured with a minimum number of fastenings consistent with effective air
sealing. The access panels shall be sized for the full height of the unit or section but need not
exceed 1800mm.
Sections of packaged units shall be arranged with adequate separation to avoid evaporation of
condensate from the cooler by the heating battery and to generally promote even air distribution
across the face of all components.
Where units incorporate humidifying plant and/or cooler batteries the internal surfaces of the
units liable to be affected by any moisture shall be protected by at least two coats of anti-
corrosion paint or a similar finish. All such units shall have corrosion resistant drain trays of
adequate size to collect water. The drain traps shall be extended, or other means of collection
shall be provided, to drain away any water deposited or condensed in adjacent sections. Trays
collecting cooled water shall be insulated to prevent condensation on the outer surfaces. All trays
shall be inclined toward the drain connection and a water sealed trap of adequate depth shall be
fitted in the rain pipework.
J9.4.20.4 Dampers
Dampers used in sections of packaged plant shall be of the multi-leaf type. The damper blades
shall be constructed to ensure rigidity and prevent distortion and jamming in operation. The
blades shall be securely fixed to their operating spindles so that differential movement between
them cannot occur. Spindles shall be carried in non-ferrous, nylon or ball bearings and air seals
shall be provided at all casing penetration points.
Manually and automatically operated dampers shall include a means for indicating externally the
position of damper blades. Manual dampers shall include a device for positioning and locking the
damper blades. The positions of all manual dampers, as set after final regulation, shall be
indelibly marked at the adjusting devices.
Damper actuators shall be kept to an essential minimum number and all actuators shall be
provided with mounting brackets.
Unless otherwise indicated, air leakage through dampers when in the closed position shall not
exceed 5% of maximum design air volume flow rate at the maximum design air total pressure.
J9.4.20.5 Fans
Centrifugal fans shall be backward or forward curved type, as indicated, except for high velocity
high pressure systems where backward curved fans shall be used. Fans for installation within
packaged air handling assemblies shall have fan total efficiencies of not less than 75% and 64%
for backward and forward curved impellers respectively at the operating point of the installation.
The method of testing shall be in accordance with BS 848.
Fan total efficiencies shall not be less than 55% and 45% for packaged assemblies using
backward and forward curved fans respectively. The fan total efficiency shall be related to the
motor drive shaft output power and to the complete fan section within the assembled packaged
air handling unit.
Where a fan and its drive motor are contained within a common casing they shall be mounted on
a frame or support base and the complete assembly shall be isolated from the casing to prevent
the transmission of vibration.
Where the fan and drive motor are directly coupled to the fan section casing, the casing shall be
isolated to prevent the transmission of vibration, and flexible joints shall be provided to couple to
adjacent sections of the complete packaged air handling assembly.
If a drive motor is mounted external to the fan section casing the fan impeller shaft shall extend
through the casing. Flexible joints and vibration isolators shall be used to minimise the
transmission of vibration and noise.
All external drive and mechanical power transmission systems shall be guarded and as detailed
elsewhere in this Specification.
Fan shaft bearings shall be self-aligning, grease lubricated ball/spherical roller type according to
load/speed requirements. Bearings shall be charged with grease and seals shall be provided to
prevent ingress of dust and minimise air leakage.
correctly aligned and the Contractor shall ensure that any holding down bolts or fixings he
provides that are positioned by others ensure correct alignment. Provision shall be made for
adjustment of the tension in belt drives and also for their alignment.
J9.4.22 Guards
Guards shall comply with PD 5304. Guards shall be provided at all open intakes and exhausts
from fans, all forms of open power transmission systems including belt drives and drive
couplings, and where indicated.
Fixed guards shall be used and they shall be installed to prevent access to dangerous parts of
machinery. Construction and installation of guards shall ensure strength and rigidity and it shall
not be possible to remove any guard or access panel without the aid of a tool.
For fans, the guards shall be manufactured by the fan maker or be to the fan makers approval and
they shall be constructed from galvanised steel wire.
For belt drives, the guards shall be of galvanised steel wire not less than 2.5mm diameter
attached to a rigid galvanised steel rod or angle framework. The mesh size and/or the location of
the guard shall prevent finger contact with any enclosed danger point. Alternative construction
may be from galvanised sheet steel not less than 0.8mm thick stiffened as necessary to ensure a
rigid enclosure. Removable access panels shall be provided in guards to allow tachometer
readings to be taken on both driving and driven shafts and also belt tension to be tested. The sizes
of guards including the dimensions and locations of access panels shall allow for the limits of
motor position.
Where duplicate motors are provided and fixed, the spare motor shall be complete with its
adjusting device to ensure belt tensioning and be in all respects ready for operation. The centre to
centre dimensions between the common driven pulley and the duplicate driving pulleys shall be
the same. The guard provided shall be either a double guard or single unit which can be arranged
to protect both drives. All fixings and mountings for both positions shall be supplied and
installed to facilitate change over of the drive and guard.
J9.4.24.1 General
The refrigeration plant shall be of the mechanical, vapour compression type using halogenated
hydrocarbon (halocarbon) refrigerants. The requirements of this section are not intended to apply
to through-the-wall and free standing (unitary or split system) room air conditioning units.
The refrigeration compressors may be of the reciprocating, centrifugal or screw type. The plant
shall include any accessories necessary to ensure continuous and reliable automatic operation.
The design maximum cooling rate shall be achieved at the maximum ambient conditions
indicated. Each unit shall be capable of running continuously at the lowest step of cooling
capacity provided without any adverse effect. The necessary charge of refrigerant and lubricating
oil shall be supplied by the Contractor.
J9.4.25 Condensers
J9.4.25.2 Evaporative
The condenser coils shall be of plain steel (galvanised after manufacture) or copper pipe. Each
condenser shall be complete with water circulating pump (as specified elsewhere in this
Specification) pump suction strainer, water tank complete with make-up connection, ball float
valve, overflow, drain and bleed connections, a cleanable water distribution system and a water
drift eliminator section. Any part of the distribution system open to atmosphere must be fitted
with a leaf or rubbish grid. The structure and casing of the unit shall be either constructed of
material which is corrosion resistant or proofed against corrosion after manufacture. Any pre-
galvanised steel sheet used shall have all cut edges sealed. The tank interior shall be coated with
bituminous or other corrosion resistant paint. The fan bearings and motor, the water pump and
motor, the water strainer and the ball float make-up valve shall all be readily accessible. Where
indicated, a thermostat controlled water sump heater shall be provided. Provision shall be made
for the purging of non-condensables from the condenser.
Fans shall be as specified elsewhere in this Specification, particular attention being given to
limitations on permitted noise levels indicated. Fan motors of induced draught condensers shall
have a suitable protective treatment if mounted in the moist air stream. Fan casings and impellers
shall be made either of corrosion resistant materials or proofed against corrosion after
manufacture.
Unless otherwise indicated, automatic control of the condensing pressure above a pre-determined
minimum shall be incorporated.
Where dampers are used, each fan motor shall be selected for the application and arranged so that
it is de-energised on complete closure of the dampers.
The condenser coil block shall be pressure tested after completion at the manufacturer's works in
accordance with the Pressure Testing section.
Methods of application for duct lining materials shall be in accordance with the Thermal
Insulation - Method of Application section.
All materials used shall have adequate strength and cohesion to resist erosion and shall not
produce dust.
Purpose-made silencers shall be tested in accordance with BS EN ISO 7235and the insertion loss
and generated noise level for each octave band and the pressure loss of the silencers shall be
provided by the Contractor.
J9.4.31.1 General
The instruments, gauges and devices detailed in this Section shall be provided in addition to
those associated with specific items of plant and indicated elsewhere. All instruments, gauges
and devices which have indicating scales shall be mounted such that they are accessible and can
be easily read without the need for portable or temporary means of access.
Scale ranges shall be appropriate within the extremes which will be indicated when the plant is
running and at rest. The design maximum operating condition shall be indicated at not less than
75% of the total scale length. Unless otherwise indicated, pressure gauges and dial thermometers
shall be accurate to 1% of total scale reading
shall be of steel except for copper installations where they shall be brass. Pockets shall be filled
with an approved heat-conducting medium.
An isolating valve and strainer shall be provided on the hot and on the cold supply to each
mixing valve.
Each shower shall be provided with an isolating valve on the riser pipe of type as indicated. Each
shower or group of showers shall be provided with an automatic drain valve which empties the
system when flow is turned off.
Manually operated mixing valves where indicated shall incorporate anti-scald devices and be
suitable for the working conditions.
Unless otherwise indicated, showers shall be stainless, robust and vandal resistant installations
with fixed spray nozzle terminals.
J9.4.31.10 Types of insulant to heating and piped water services - within buildings
Thermal insulation shall be applied to:
(a) All pipework flanges and valves carrying fluids at temperatures above 50oC and other
pipework as indicated;
(b) Cold water cisterns, feed and expansion cisterns and vent pipework as indicated.
The insulation referred to in item (a) above shall be preformed rigid sections and/or an approved
pre-insulated pipework system as indicated. Valves and flanges shall be insulated as specified
elsewhere in this Specification.
The insulation referred to in item (a) above shall be as indicated.
J9.4.31.11 Types of insulant to heating and piped water services - external to buildings
Preformed insulation shall be applied to:
(a) Cold water pipework run above ground external to buildings and run in ducts, chases,
roof spaces and as indicated;
(b) Expansion devices, as indicated.
The insulation referred to in item (b) above shall be as indicated on drawings, or elsewhere in
this Specification.
(b) Within sealed parts of the building structure which, in the event of fire, would isolate
smoke, noxious or toxic fumes from habitable spaces. Glass cloth facings applied to the
insulation and secured on site with adhesive and bands, or finishing material as item (a) above or
approved pre-insulated and clad as indicated. The finish shall be left unpainted.
(c) In all accessible ducts, voids, chases, false ceilings etc, finishing material shall be as item
(a) above with fabricated aluminium or galvanised steel or plastic casings applied to the
insulation at access points which could be subjected to mechanical damage, or approved pre-
insulated and clad pipework systems as indicated.
For visible pipework the finishes shall be in accordance with the following as indicated:
(a) Cotton canvas not less than 100g/m2 to BS 3958 Part 4, factory applied to preformed
sections, lapped and sealed on site with adhesive, and additionally secured with bands
and painted;
(b) Bends and tees shall be finished with preformed fittings.
(c) White lacquered aluminium foil/kraft paper laminate, factory applied to preformed pipe
insulation, overlaps to be sealed with adhesive and circumferential joints to be sealed
with 100mm wide matching tape.
J9.4.31.15 Thermal insulation finishes to heating & piped water services - external to
buildings in open air or in ducts
The outer covering to the insulation shall be a weatherproof finish which passes continuously
without being punctured through pipework supports and over flanges, expansion joints and
anchor points.
The weatherproof finish to the insulation of pipework carrying fluids at temperatures above
ambient shall be one of the following as indicated:
(a) Waterproof vapour permeable plastic coating systems, brush or spray applied and
reinforced with canvas or glass fibre cloth;
(b) Roofing felt, sealed with adhesive with overlaps of at least 50mm wrapped with 25mm
mesh by 1mm thick galvanised wire netting, laced with 1mm thick galvanised wire and
painted two coats of bituminous paint to BS 3416 Type 1 Class A.
(c) Bitumen impregnated fabric systems sealed by the application of heat or by cold
welding;
(d) Other proprietary weatherproof finishes of the type as indicated;
(e) Pre-insulated pipework systems, of the type as indicated.
The finishes specified in items (b) and (c) above shall be perforated on the underside of all
horizontal runs with 6mm diameter holes at approximately 150mm centres. The horizontally
lapped joints shall lie to one side of the bottom centre line exposed edge downwards, so that the
perforations are made in one thickness of the material, with the underlying preformed insulation
open to atmosphere at these points.
The weatherproof finish to the insulation of cold water pipework shall be as items (b), (c), (d) or
(e) above without the requirement for perforation on the underside as indicated.
Thermal insulation to air distribution ductwork and air handling plant
Thermal insulation shall be applied to air distribution ductwork and to components within
distribution systems such as fans, heater and cooler casings which convey conditioned air within
plant rooms and to ductwork (including recirculation air ductwork) conveying warmed or chilled
air through unconditioned spaces or the open air. Unless otherwise indicated, distribution
systems conveying conditioned, warmed or chilled air through conditioned spaces shall not be
insulated. Distribution systems conveying fresh air and exhaust air shall be insulated where
indicated.
The thicknesses of insulation for air distribution services shall be determined from the Thermal
Insulation Tables section.
J9.4.31.16 Thermal insulation to ductwork & air handling plant - materials & finish
All thermal insulating materials and finishes shall be subject to the requirements of fire
properties and vapour barriers mentioned elsewhere in the Specification. The vapour permeance
shall not exceed 0.05g/(sMN) unless otherwise indicated. Thermal insulation applied to packaged
air handling units shall be in accordance with Clause 2.19 of this Specification.
Within buildings, services concealed from view and not readily accessible; the following shall be
provided as indicated:
(a) Preformed slab (or flexible material having a bulk density at least 1 kg/m3) with a facing
of factory-applied aluminium foil or plastics film; secured by adhesive and piercing
fasteners or enclosed within galvanised wire netting of 25mm mesh.
(b) Preformed slab material, secured by adhesive and piercing fasteners, enclosed in
aluminium foil with all laps sealed with matching self-adhesive tape.
(c) As item (b) above but enclosure to be polyisobutylene sheet adhered to the insulating
material and bonded to itself at all laps.
(d) Preformed slab material secured by adhesive and piercing fasteners, covered or enclosed
in 136 g/m2 cotton fabric adhered to the insulating material; painted two coats of
appropriate vapour sealing compound.
Within buildings, services exposed to view but not readily accessible; the following shall be
provided as indicated:
(a) As items (b), (c) or (d) but painted to match decoration of surroundings.
Services in plant rooms and elsewhere, where indicated, to avoid possible damage; the following
shall be provided as indicated:
(i) As items (a) or (b) above but enclosed in 0.8mm thick aluminium sheet or 0.5mm
galvanised steel sheet.
(ii) Preformed slab material, covered with galvanised wire-netting of 25mm mesh, and
supercoated with 10mm thickness of self-setting cement primed and finally painted.
Outside buildings, services exposed to the weather; the following shall be provided as indicated:
(i) As items (a), (b) or (c) above but enclosed in 0.8mm thick aluminium sheet with all
joints sealed and arranged to shed water.
(ii) As items (a) or (b) above but covered in roofing felt and galvanised wire netting of
25 mm mesh and finally treated with two coats of bituminous weatherproofing
compound.
(iii) As items (a) or (b) above but enclosure to be polyisobutylene sheet bonded to itself at all
laps.
Particular care shall be taken to ensure that the edges of all internal insulating materials, whether
exposed or butted against similar edges, are sealed and secured to the internal surfaces of the
duct. They shall be protected with channel sheet metal of not less than 0.8mm thickness and
13mm width or be provided with other approved means of protection to prevent erosion and
peeling. All materials shall have adequate strength and cohesion to resist erosion at the maximum
design air velocity and shall not produce dust.
triangles shall be spaced and located to permit ready identification of the services particularly
adjacent to equipment positions, at service junctions and wall penetrations.
In addition to colour bands or triangles all pipework and ductwork in plant rooms and service
areas, whether insulated or not, shall be legibly marked with black or white letters and triangles
to show the type of service and the direction of fluid flow. The letters F and R shall be added to
piped distribution to show flow and return respectively.
J9.4.32 Controllers
to enable the leading machine to be selected manually (e.g. in sequence 1-2-3, 2-3-1 or 3-1-2).
For each compressor of more than 35kW capacity an hours-run meter shall be provided.
Sequence control shall be provided for boiler plant where relevant.
J9.4.35.1 General
Unless otherwise indicated the Contractor shall provide and install all electrical equipment
necessary for the complete installation and carry out all wiring from point(s) of supply as
required or as indicated on the drawings or elsewhere in this Specification.
The Contractor shall be responsible for the accuracy of all wiring diagrams provided by him and
for the correct internal wiring of all pre-wired equipment supplied for the contract.
Unless otherwise indicated all electrical equipment shall be suitable for use in ambient
temperatures up to 40oC and relative humidities up to 90%.
The electrical cabling and wiring installation for the air conditioning and ventilation systems
shall be combatable with and fully integrated with other cabling and wiring systems within the
buildings and shall fully comply with the Section 4.5 of the Specification.
insulation, class of temperature rise maximum number of starts per hour, type and serial number
of motor.
Unless otherwise specified the motors shall be capable of starting at least 5 times, equally
disposed in any one hour at maximum ambient temperature. Motor insulation shall be rated to
thermal class F and temperature rise shall not exceed the limits of class B.
The degree of protection of the motor enclosure as described by BS EN 60034-5 shall be as
follows:
- outdoors IPW 55
- indoors where hosing down may take place IP 55
- indoors general locations IP 54
All motors shall be provided with a frame earth terminal of sufficient size to take full fault
current.
All motors rated over 11kW or operated on variable speed controls shall have their stator
windings equipped with six embedded thermistor temperature detectors (3 for use, 3 spare) wired
to a motor mounted auxiliary terminal box. Connections shall be taken to a thermistor control
unit to BS 4999 part III external device to monitor continuously three temperature detectors in a
particular motor. The monitoring units shall be complete with trip contacts which shall operate
when any single detector exceeds prescribed limits.
Each motor circuit shall be provided with an isolator or switch or circuit breaker in the motor
starter.
Where a motor is not visible from the motor starter position, or where the Engineer decides it is
otherwise necessary to prevent danger, an isolator or switch or push-button shall be provided
adjacent to or mounted on the motor.
Motors arranged for automatic starting shall have a label of durable material fixed permanently
to them in a prominent position and, having, in clearly inscribed black characters on a yellow
background, the legend:
Each single-phase heater shall incorporate an adjustable thermostat having a range of adjustment
between 50oC and 80oC.
Each poly-phase immersion heater shall be controlled by an adjustable thermostat having a range
of adjustment between 50oC and 80oC installed in an immersed pocket and operating through an
electrical contactor.
J9.4.35.4 Bonding
The Contractor shall ensure that all the metallic installations he provides which constitute
'Extraneous conductive paths' shall be electrically bonded in accordance with BS 7671.
Metallic gas pipework shall be electrically continuous. Flanged, grooved or compression type
fittings in gas pipes shall be electrically bonded. Gas pipework shall be electrically bonded to the
electrical earth terminal in accordance with BS 7671.
J9.4.36 Testing
J9.4.36.1 General
All mechanical services plant and the complete installations shall be subject to Off - Site and On
- Site inspection and testing and commissioning.
The Contractor’s obligations and the requirements for inspection and testing and testing
procedures shall fully comply with the requirements of Section 4.1.
Additional specific requirements pertaining to the mechanical services installations are as
follows:
J10.1 SCOPE
This Section covers the requirements for the design, supply and erection of structural steelwork.
J10.3.1 General
The Contractor shall submit the following:
J10.3.3 Drawings
• general arrangements;
• general assembly, detailed shop and erection drawings;
• detailed manufacturing drawings.
J10.3.4 Certificates
• material tests;
• Inspection certificates;
• qualification certificates.
J10.4 DESIGN
the steel members, the other structural elements, the foundations and the connections between
each component, shall be such as to produce a strong and stable structure.
The structure shall be checked for the effects of all possible vertical and horizontal loads, acting
both in conjunction and separately as appropriate, using factored loads when checking strength
and stability to a limit state analysis and unfactored loads when checking deflections or strength
and stability using a working stress approach.
The structures shall be designed to be capable of accepting without overstress 10% extra loading
due to any cause including extra services, heavier cladding, or other appurtenances that may
reasonably be added during the life of the structure.
Structures shall be designed such that undue reliance is not placed on 'key' elements (a key
element is one whose removal tends to prejudice the ability of the whole structure to survive).
The removal or damage of such elements shall not entail collapse of more than a limited part of
the structure. The design of structures will not be considered to be adequate if an accident could
cause damage to the structure out of proportion to the magnitude of the event.
The design shall take account of the need for stability of both the framework and the individual
elements at all stages of erection. Where temporary bracing is required it shall be checked for the
effects of all loadings that may arise during erection including those due to erection equipment
and its operation. Such bracing shall be clearly indicated on the drawings together with clear
instructions as to the appropriate stage of removal.
The design of crane beams shall take due account of all factors relevant to the provision of
effective support to the crane under all conditions of loading including but not limited to:
(a) Underslung cranes and monorail runway beams:
(i) combined flange stresses resulting from overall bending and local flange bending
due to wheel loads causing transverse stresses;
(ii) lateral instability;
(iii) torsional restraint;
(iv) deflection limitations;
(v) joints, particularly local force concentrations due to loads passing across joints.
(b) Overhead, over slung cranes and gantry girders:
(i) as above but related to coincident lifting, slewing, traversing actions of the crane.
All crane-supporting structures shall be designed for the worst combination of all other design
loads with the crane under test.
Deflections of members listed in the table below shall not exceed the tabulated limits, unless the
Contractor can demonstrate to the Engineer's satisfaction that greater values would not be
detrimental to the performance of the structure.
The relative lateral deflection of adjacent frames (including the end frames) of sheeting clad
structure shall be limited generally to frame centres/250 unless greater values can be shown to
have no detrimental effect on the structural performance of the sheeting.
J10.5 MATERIALS
J10.6 WORKMANSHIP
J10.6.1 Detailing
The detailing and fabrication of structural steelwork shall be such as to minimise the need for site
welding. Structures and components such as trusses, combined columns and beams shall be shop
fabricated so as to form sub-assemblies of the largest practical size suitable for transportation,
handling and erection. Connections between members at the erection stage shall generally be
bolted.
Structural steelwork shall be so detailed and fabricated as to minimise the formation of pockets
to hold condensation, water or dirt. Where such pockets are unavoidable, suitable drainage shall
be provided.
Detailing shall be in accordance with BS 5950.
Erection drawings shall detail all connections, showing bolt types and sizes and site weld details
as applicable.
Shop and erection drawings shall show all marks necessary to facilitate erection and the marks
shown in the drawings shall be identical with those shown on the fabrications.
J10.6.3 Welding
All welding carried out during fabrication or erection shall be in accordance with the
requirements of BS 5135 and as shown in the approved detail drawings. Details of the proposed
weld procedures shall be submitted to the Engineer for approval at the same time as the detail
drawings. All connections shall be welded in such a manner as to make the finished connections
neat and smooth in appearance and suitable for painting. All slag shall be removed and any sharp
projections shall be ground smooth.
Before welding is commenced either in the fabrication shop or on Site, weld procedure tests shall
be carried out in accordance with BS EN 1011 where directed by the Engineer.
All welders employed either in the fabrication shop or on Site shall pass qualification tests
relevant to the weld procedures in use in accordance with BS 4871. Welders shall have
satisfactory evidence of having been engaged in welding for at least 9 months in the preceding
12-month period. If the work of any welders employed on the Contract is unsatisfactory, the
Contractor shall carry out such further welder qualification tests as are necessary to demonstrate
that the welders are proficient.
Welds shall be subjected to non-destructive testing by processes which may include but shall not
necessarily be limited to radiographic, ultrasonic, magnetic-particle or dye-penetrant methods,
depending on the type of weld and its position in the structure. The standards of acceptance shall
be as defined in PD 5500: Table 5.7, unless otherwise agreed with the Engineer.
If any work shows defects or fails to comply with the requirements of the Drawings or
Specification for any reason it shall be repaired or rejected, even though it may have been carried
out by qualified welders using approved procedures.
Where two steel surfaces are required to be in contact to effect a bearing or frictional contact, the
surfaces shall be prepared so that at least 90% of the area is touching before any clamping force
is applied.
J10.6.8 Storage
All structural elements and other materials shall be stored (whether at the place of fabrication or
on Site) clear of the ground and shall be protected against deterioration from any cause. The
Contractor shall agree the storage areas on the Site with the Engineer before any structural
steelwork is delivered.
J10.6.9 Erection
All erection processes shall be carried out in accordance with the recommendations of BS 5531.
The plant used for handling and erection shall be suitable and safe. The Contractor shall supply,
maintain and afterwards remove temporary protection to workmen and materials below any
structural steel under erection and shall provide walkways and ladders so that inspection of any
part of the completed structure may be safely carried out.
Anchor bolts shall be properly located by the use of templates or other approved method. After
building in the anchor bolts, a sufficient time shall be allowed for concrete strength to develop
before finally pulling down to shims and grouting.
Every part of the structural steelwork shall be positioned accurately in accordance with the
dimensions on the approved drawings with a maximum tolerance of !5 mm except where the
steelwork supports metal flooring, when the finished tolerances shall be such that differences in
level between adjacent flooring sections or between flooring sections and adjacent building
floors do not exceed 3 mm. Gaps between flooring sections shall not exceed 3 mm.
Where structural steelwork is to be grouted on or against a concrete or other similar surface and
the design requires a uniform contact area under the base plate, or where directed by the
Engineer, the Contractor shall remove all steel shims or wedges and replace these with grout of
the same constituents and consistency as the main grout. Such steel shims shall be initially
positioned so as to aid removal. In the case of baseplates with large overhangs or with heavy
bearing loads the positions of shims shall be agreed with the Engineer before the structure is
erected on them.
During erection, the work shall be securely bolted or otherwise fastened, and if necessary
temporarily braced, so as to make adequate provision for all erection stresses and conditions,
including those due to erection plant and its operation. No permanent bolting shall be done until
proper alignment has been achieved.
The Contractor shall immediately report to the Engineer any errors in shop fabrication, and any
deformations resulting from handling or transportation, which prevent proper assembly and
fitting of parts. Methods to be used to correct such errors or deformations shall be agreed with
the Engineer prior to beginning of any corrections.
The Contractor may use drift pins to bring several parts together but shall not use them in such a
way as to cause distortion or damage.
after first tightening. The bolts shall then be re-tightened to the initial load, all to the approval of
the Engineer.
J10.8.2 Paints
Primer shall be a shop applied zinc rich mix to 100 micron Dry Film Thickness (DFT). Paint
coating shall be three coats of catalyst-cured straight epoxy to 450 micron total DFT.
J10.8.3 Application
Paint shall be applied only when the ambient temperature is above 5°C, and when the relative
humidity is below 90%. Surfaces to which the paint is applied shall be dry and shall remain free
from moisture until the coating has dried or cured sufficiently to avoid effects harmful to the
subsequent appearance or satisfactory protective behaviour of the paint.
All paints shall be prepared and applied in accordance with the manufacturer’s instructions.
Copies of appropriate data sheets and of the relevant parts of this Specification shall be issued to
all the supervisors and foremen concerned with surface preparation and coating. Where a
manufacturer’s instructions conflict with this Specification, a ruling shall be sought from the
Engineer.
No thinners or cleaners shall be employed other than those recommended by the paint
manufacturer.
Except where otherwise specified or approved by the Engineer all priming paints shall be applied
by brush.
Exposure of intermediate coats of paint for periods in excess of a few days shall not be permitted
except in the case of work delivered to Site in a primed condition.
The dried films of the specified paints shall be free from bloom, sinkage, sheeriness, wrinkling,
sagging, curtaining, discolouration and extraneous matter.
No exterior or exposed paintwork shall be carried out under adverse weather conditions.
Painting shall insofar as is practicable be shaded from direct sunlight to prevent wrinkling and
blistering. Whenever possible, exterior painting during the day shall be so programmed as to be
carried out in shadow.
Painting of surfaces shall not be carried out when the relative humidity of the atmosphere is such
that condensation is present on such surfaces or the application and/or drying of the paints is
likely in the opinion of the Engineer to be affected.
J10.8.4 Repairs
Areas of paint on steelwork which have been damaged shall be cleaned to sound material and the
edges of the undamaged paint shall be smoothed with sandpaper to a gentle bevel. The specified
paint system shall then be applied to bring the damaged area up to the same state of protection as
the surrounding paintwork, with each coat of new paint overlapping the corresponding existing
coat of paint by at least 50mm.
J10.8.5 Inspection
The following tests shall be carried out:-
(a) Checking wet-film thickness:
Wet-film thickness gauges of an approved type shall be provided for each painter to
check the rate of paint application.
(b) Checking dry-film thickness:
The thickness of the built-up dry film after each paint coat applied to steel or other
magnetic surfaces shall be measured systematically, with a dry-film thickness gauge.
(c) Holiday detection on steel and iron surfaces:
The Contractor shall use a suitable method of detecting pinholes in the coating system
after trials on test plates. The sweep voltage on high-voltage direct-current equipment
shall not exceed half the voltage required to spark through the complete paint system
specified.
Any coating which does not meet specified requirements shall be removed and re-applied at no
extra cost to the Employer.