L3 Gym room near Entrance Lobby 2- Installation of horizontal Granite soffit stone

Completed .( left & right wings )

L3 External wall Lobby 3 –Installation of horizontal granite soffit stone unit/ vertical stone
units at top of the glass wall completed.
Tower no.1 , L5 Café Area, removal of bamboo scaffold completed.
(view from level L1)

Link Bridge No.1 – Installation of all of the horizontal granite soffit stone/ vertical stone units
to the concrete structure completed.
]
Link Bridge No.3 – Installation of all horizontal granite soffit stones completed