Ho Man Tin Station Package 2

Foundation Works

April 2020

1
1. Agenda
Items Content

2. Team Introduction

3. Communication Channel and Submission Sequence


Co-Ordinator Representative

4. Presentation – Works Overview

5. Upcoming Works - Scheduled Method Statement and


Precautionary Measures

i. Hoarding

ii. Monitoring Check Point Installation

iii. Fir – Log Platform

iv. Predrill + King Post (Steel Platform)


5. Q&A

2
2. Team Introduction

Project Team Company Name

Employer: Grace Castle Corporation Limited

Architect : Andrew Lee King Fun & Associates


Architects Limited

Structural /Geotechnical AECOM Asia Company Limited


Engineer/ Sustainability
Consultant :

Quantity Surveyor : Rider Levett Bucknall Limited


M&E Consultant Meinhardt (M&E) Limited

Safety and Risk Consultant WSP (Asia) Ltd.

Foundation Work Sunley Engineering & Construction Co. Ltd.


Contractor :
3
3. Communication Channel and Submission
Sequence

MTRC
(RP&LS)

Project Co-ordinator
AECOM – Associate
Director
Jeremy Lam (94338628)
For
Ap
AECOM ALKF (AP) WSP (Safety pro
(RSE) & Risk) val

Sunley
(contractor)
4
4. Site Works Overview

5
1. Major Scope and Programme of Works

Presented by Sunley Engineering &


6
Construction Co. Ltd.
1. Major Scope of Works

UN ND
L
E T OU
NE
SITE A2
Chung Hau Street

KT GR
R
DE
UN

EPIW
EPIW(Sub
ZONE 1

(Subwa
ZONE 2

way)
y)
3m
MT MTR
Ho R P Pro
Ma rot tec
ecti tio
nT on n Z
in S Zon one
tati e
on
(Ho
M)

7 Site
Boundary
1. Major Scope of Works
(Con’t)

UN ND
L
E T OU
NE
SITE A2

KT GR
R
DE
Erection of Hoarding

UN
Chung Hau Street

ZONE 1 ZONE 2

EPIW
EPIW(Sub
(Subwa
way)
y)
3m
MT MTR
Ho R P Pro
Ma rot tec
ecti tio
nT on n Z
in S Zon one
tati e
Open Up Existing Stub Column on
(Ho
M)

Pre-drilling and Temporary Steel Platform

Bored Piles Construction Socketed H-Piles Construction

8 Site
ELS Works Boundary
2. General Arrangement
and Site Layout of Facilities

9
2. General Arrangement and Site Layout of
Facilities
Vehicular Dangerous Goods, Tools
Vehicular Pedestrian Dangerous Goods, Tools
Entrance Guard and Equipment Storage
Entrance Guard House
House and
and Staff
Staff Pedestrian
Entrance
Entrance
and Equipment Storage
Registration Point
Registration Point
Hoarding Covered
Hoarding Covered

UN ND
Walkway
SITE A2 Container Muster Walkway

L
E T OU
NE
Container
Office Area Point

KT GR
Office Area

R
DE
UN
Major
Haul
Route to
30
ZONE 1 Pro m MT
Site A
tec R

EPIW (Su
Entrance
Zon tion
e ZONE 2 /Exit
Once Possession of Site

EPIW
bwa(Su
A2, Chain Link Fence will

y) bway)
be erected
Ho
Ma 3m
nT
in S MT MTR
tati R P Pro
on rot tec
ecti tio
(Ho on n Z
M) Zon one
e

EVACUATION Site
ROUTE Boundary
Plastic
Plastic
10 Barrier
Barrier
3. Major Site Activities in
Coming
Three months

11
3. Major Site Activities in Coming 3
months
Site Activities Location
General Site Clearance - Within 3-10m RP Zone
(Eradicate Shrubs and - Within 10m-30m RP Zone
Unplanned Vegetation) - Outside 30m
Erection of Site Offices and Site - Within 10m-30m RP Zone
Accommodation - Outside 30m

Erection of Hoarding - Within 3-10m RP Zone


- Within 10m-30m RP Zone
- Outside 30m
Installation of Monitoring Check - Within 3-10m RP Zone
Points - Within 10m-30m RP Zone
- Outside 30m
Construct Temporary Surface - Within 3-10m RP Zone
Water Drainage System with - Within 10m-30m RP Zone
Provision of Desilting Facilities - Outside 30m
Predrilling Works and King Post - Within 3-10m RP Zone
Installation for Temporary - Within 10m-30m RP Zone
Platform - Outside 30m
12
3. Major Site Activities in Coming 3 months
Site Activity - Erection of Site Offices and Site Accommodation

UN ND
SITE A2

L
E T OU
NE
KT GR
Chung Hau Street

R
DE
UN

ZONE 1 30
Pro m MT
tec R

EPIW (Su
Zon tion
e

EPIW
bwa(Su
y) bway)
ZONE 2

Ho 3m
Ma
nT MT MTR
in S R P Pro
tati rot tec
on ecti tio
(Ho on n Z
Zon one
M) e

Site
Boundary

13
3. Major Site Activities in Coming 3 months
(Con’t)
Erection of Hoarding

Erection of Hoarding

UN ND
SITE A2

L
E T OU
NE
KT GR
R
DE
UN
Chung Hau Street

ZONE 1 30
Pro m MT
tec R

EPIW (Su
Zon tion ZONE 2
e

EPIW
bwa(Su
y) bway)
HHoo 3m
MMaa
nnTT MT MTR
iinnS R P Pro
Sttaati rot tec
ecti tio
tioon on n Z
n((H Zon one
HooM
M)) e

Site
Boundary

14
3. Major Site Activities in Coming 3 months
(Con’t)
Site Activity - Construct Temporary Surface Water Drainage System with Provision of
Desilting Facilities

ZONE 1
ZONE 2

15
3. Major Site Activities in Coming 3 months (Con’t)
Site Activity - Installation of Monitoring Check Points

TE
GS1

DK
UN
SITE A2

EL RO
IN1
TM1 GS2

NN G
TU DER
BS1
VCP1 Chung Hau Street

UN
USM1
SP1
GS3 GS5 GS6 USM2
GS4
IN3
IN2 SP3
VCP4
IN6

VCP3 VCP5 SP5


MS GS7
3
ZONE 1 30
Pro m MT

EPIW
tec R

EPIW(Sub
TM3
BS5 Zon tion
TM5 e M

(Subwa
BS3 S2

way)
VCP6 GS9

y)
BS4 BS6
ZONE 2
TM4 TM6
VCP9 MS
1
IN
BS7 TM7 3m
MT MTR
Ho VCP11 R P Pro
Ma rot tec
ecti tio
nT on n Z VCP13
in S BS8
TM8 Zon one
GS1 Ground Settlement Marker tati e
on VCP12
TM1 Tilting Marker ( Ho
M) BS9
TM9
BS4
Building Settlement Marker
USM2
Utility Settlement Marker
Vibration Checkpoint
VCP1
SP1
Piezometer/Standpipe

16 IN1 Inclinometer
Magnetic Probe Extensometer Site
MS1
Boundary
3. Major Site Activities in Coming 3 months
(Con’t)
Site Activity - Predrilling Works

UN ND
SITE A2

L
E T OU
NE
KT GR
R
DE
UN
Chung Hau Street

30
Pro m MT
ZONE 1 tec R

EPIW (Su
Zon tion
e

EPIW
bwa(Su
y) bway)
ZONE 2

3m
MT MTR
R P Pro
Ho rot tec
Ma ecti tio
nT on n Z
in S Zon one
tati e
on
( Ho
M)
Site
Boundary

17
4. High Risk Activities and
Associated Precautionary
Measures

18
4. High Risk Activities and Associated Precautionary
Measures (Con’t)
Risks Control Measures
General 1. All method statements shall
be submitted to RP and seek
their comment/approval

2. MTRC approval on MS shall


be obtained at least 7 days
in advance of
commencement

3. 3m MTRC protection zone


will be demarcated by
physical barrier

4. Assessment Report for


existing MTR structure will
be provided

5. Alert, Alarm and Action level


19 monitoring will be checked
to ensure site works have no
4. High Risk Activities and Associated Precautionary
Measures (Con’t)
Risks Control Measures
Fire Prevention 1. Adequate fire extinguishers
shall be provided on-site

2. Dangerous goods will be


deployed on site. Prohibited
storage of dangerous goods
within 6m from MTR station
structure

3. Smoking will be prohibited in


entire site area

4. Corrosive and flammable


substances will not be
discharged into the Station
drainage system

20
4. High Risk Activities and Associated Precautionary
Measures (Con’t)
Risks Control Measures
Flooding 1. Routine surface channel
maintenance will be
conducted regularly and
report will be submitted to
MTRC

2. Flooding barrier will be


placed at the bottom of the
site along the Ho Man Tin
Station Building to prevent
water from affecting the
operation of Station

3. Temporary drainage system


will be set up on site,
sufficient water pumps will
be provided to avoid flooding

21 4. During site close security


guards will take routine
4. High Risk Activities and Associated Precautionary
Measures (Con’t)
Risks Control Measures
Lifting Operation 1. Lifting gear and appliances
will be examined by RPE

2. Colour coding system of


Lifting Gear

3. Permit-to-Lift system shall be


implemented

4. Lifting supervisor and


banksman will be provided
during lifting operation

5. Allow max. of 80% of safe


lifting load capacity during
lifting operation

6. Method statements will have


22 separate lifting plans to
cover all lifting activities
4. High Risk Activities and Associated Precautionary
Measures
Activities Control Measures
Drilling Works / Excavation 1. Permit-to-drill, Permit-to-dig,
and within RP Zone shall be
implemented

2. From 4 will be signed by


Competent Person weekly

3. Adequate temporary surface


channel will be provided to
prevent surface run-off
getting into excavated area

4. Pumps will be provided in


excavated areas

5. For pile lies within 10m


zone, verticality check shall
be conducted at interval of
23 depth<5m
5. Upcoming Works

24
Upcoming Site Activities
- Erection of Hoarding

Sprinkler Inlets
B2 Entrance of
HoM Station Typical Section
of Hoarding

Works Extent
`
Chung Hau Street

Works Extent

HoM Station

25
Upcoming Site Activities
- Erection of Hoarding

Sprinkler Inlets
Pre-fabricate major components off site
Erection to be Portion by Portion
Erection by using Crane Lorry TTM
Arrangement of TTM Works Extent
` to Lift” and
Lifting supervisor to issue the “Permit
Crane
checked with SO and RSS before any lifting Chung Hau Street
operation Lorry
Assign at least 2 personnel to fence off both ends
of Works Extent to ensure no pedestrian get in
during the lifting operation
Lifting supervisor shall supervise the entire lifting
operation to ensure all the operation are in order Portion by
-During the welding operation, Shelter to be Ho
provided to protect the pedestrian MS Portion
tati
- Repeat the above procedures to complete the on
remaining portions

Proposed Steel
Hoarding

26
Upcoming Site Activities – Installation of Fir Log
Platform

TE
A

DK
UN
SITE A2

EL RO
Chung Hau Street

NN G
TU DER
UN
B
A IN6

ZONE 1 ZONE 2

EPIW
EPIW(Sub
Ramp

(Subwa
way)
y)
B Ram p

IN
3m
MT MTR
Ho R P Pro
Ma rot tec
ecti tio
nT on n Z
in S Zon one
tati e
on
( Ho
M)

27
Site
Boundary
Upcoming Site Activities – Erection of Fir Log Platform

28
Upcoming Site Activities – Erection of Fir Log Platform

29
Upcoming Site Activities – Erection of Fir Log Platform

• Form 5 will be signed by Competent Person before use for first time and at
regular intervals not exceeding 14 days

• Supporting calculation for the stability and integrity of the platform shall be
provided and be certified by ICE

• Regular inspection by RSS and T4 of the condition of the scaffolding in weekly


interval. Particular attention shall be paid in the course of inspection to ensure
the scaffolding shall not pose any adverse effect of the scaffolding to the
stability of the existing slope.

30
Upcoming Site Activities – Predrilling Works
Precaution Measures for drilling works for monitoring check points are also
applied for predrilling works

TE
DK
A

UN
EL RO
SITE A2

NN G
TU DER
UN
Chung Hau Street
B
A IN6

ZONE 1 ZONE 2

EPIW
EPIW(Sub
Ramp

(Subwa
way)
y)
B Ram p

IN
3m
MTR Nos. of Ho
MT MTR
R P Pro
Ma rot tec
Protection Prdrilled nT
in S
ecti tio
on n Z
Zon one
Zone Hole tati
on
(
e
Ho
M)
0-3m None
3m – 10m 9 nos.
10m – 30m 15 nos.
31 Outside 30m 4 nos. Site
Boundary
Upcoming Site Activities – Installation of Monitoring
Checkpoint

TE
GS1

DK
UN
SITE A2

EL RO
IN1
TM1 GS2

NN G
TU DER
BS1
VCP1 Chung Hau Street

UN
USM1
SP1
GS3 GS5 GS6 USM2
GS4
IN3
IN2 SP3
VCP4
IN6

VCP3 VCP5 SP5


MS GS7
ZONE 1 30
3
ZONE 2
Pro m MT

EPIW
tec R

EPIW(Sub
TM3
BS5 Zon tion
TM5 e M

(Subwa
BS3 S2

way)
VCP6 GS9

y)
BS4 BS6

TM4 TM6
VCP9 MS
1
IN
BS7 TM7 3m
MT MTR
Ho VCP11 R P Pro
Ma rot tec
MTR Monitorin nT
in S BS8
ecti tio
on n Z VCP13
Zon one
Protection
Involved Drilling Works:
g Point. tati
on
TM8
e
VCP12
( Ho
Zone
(A) 3 nos. of Inclinometer M) BS9
TM9

0-3m
IN1, IN2 and IN3 None
(B) 3 nos. of Magnetic Extensometer
3m
MS1,–MS2
10m and MS3IN2, MS1
32 10m – 30m MS2,IN1
Site
Outside 30m IN3, MS3 Boundary
Upcoming Site Activities – Installation of Monitoring
Checkpoints

For drilling works within 3-10m RP Zone (i.e. IN2 and MS1)
• Arrange joint survey with MTR survey team for setting out of drillholes with
the presentation of RSS representative
• Implementation of “Permit to Drill” System
- checked by RSS Representative
• Forming a Whatapps Group for communication and reporting the status of
critical activities with the participation of Sunley, RPE, RPI, RSS and PPD
representatives
• Verticality check by using inclinometer to be conducted at interval of depth
<5m.
“AAA” Criteria to be 13mm (Alert), 20mm (Alarm) & 25mm (Action)

For remaining drilling works within 10-30m RP Zone (i.e. MS2 and IN1) and
outside 30m RP Zone (i.e. IN3 and MS3)
• Checking and inspection of setting out to be conducted by RSS representative
• Implementation of “Permit to Drill” System
- checked by RSS Representative in order prior to drilling
Checkpoint
Remaining Monitoring Checkpoints

TE
GS1

DK
UN
SITE A2

EL RO
IN1 GS2
TM1

NN G
TU DER
BS1
VCP1
Chung Hau Street

UN
USM1

GS3 GS5 GS6 USM2


GS4
IN3
IN2
VCP4
IN6

VCP3 VCP5
GS7
ZONE 1 30
Pro m MT ZONE 2

EPIW
tec R

EPIW(Sub
TM3
BS5 Zon tion
TM5 e

(Subwa
BS3

way)
VCP6 GS9

y)
BS4 BS6

TM4 TM6
VCP9
6mIN
M
TM7 3m TR
BS7
MT MTR Prote
Ho VCP11 R P Pro cti
Ma rot tec on
nT ecti tio Zon VCP13
in S BS8 on n Z e
tati TM8 Zon one
e
on VCP12
( Ho
GS1
M) BS9
TM9
Ground Settlement Marker
TM1
Tilting Marker
BS4
Building Settlement Marker
USM2
Utility Settlement Marker

VCP1
Vibration Checkpoint
34 IN1 Inclinometer
Site
Boundary
Upcoming Site Activities – Installation of Monitoring
Checkpoints

MTR RP Ground Utility Building Tilting Inclinome Vibration


Settleme Settlemen Settlement Marker ter Check Point
Zone nt t Marker Marker
Marker
0-3m 1n GS 1no USM 7 BS3 7 TM3 - - 6 VCP3
o. 3 . 1 nos to nos to nos VCP4
BS9 TM9 VCP6
VCP9
VCP1
1
VCP1
2
3m–10m 2n GS - - - - - - 1 IN2 1 VCP5
os. 2 no. no.
GS
4
10m- 3n GS 1no USM 1 BS1 1 TM1 1 IN1 1no VCP1
30m os. 5 . 3 no. no. no. .
GS
8
GS
9
Outside 2n GS - - - - - - 1 IN3 - -
30m os. 6 no.
GS
7
Upcoming Site Activities – Installation of Monitoring
Checkpoints

For installation of Settlement Marker and Utility Settlement Marker within 3-10m
RP Zone
• Arrange joint inspection with MTR survey team for setting out of pit location
before excavation with the presentation of RSS representative
• Implementation of “Permit to Dig” System
- checked by RSS Representative
• Forming a Whatapps Group for communication and reporting the status of
critical activities of installation with the participation of Sunley, RPE, RPI, RSS and
PPD representatives
Upcoming Site Activities – Installation of Monitoring
Checkpoints
Tiltmeter Marker Tiltmeter Marker
• Tilt Plates with 150mm diameter to be employed
• Tilt Plates shall be installed on sound concrete of
HoM Station
• Tilt Plates fixed to the sound concrete surface of
HoM Station by epoxy resin and further bolted into
the sound concrete

Building Settlement Marker


• Retro reflective survey tape targets to be installed on
sound concrete of HoM Station

Building Settlement Marker


Proposed Major Lifting Plants situated on existing
slope crest 11000-1 Crane and Sunward SWTD80
- Manitowoc
Piling Rig

Manitowoc 11000-
1

38
Proposed Major Lifting Plants situated on existing
slope crest
- Manitowoc
11000-1 - Sunward SWTD80
行架
Piling Rig
度長
27.
4
m

39
Proposed Measures for Major
Lifting Plants situated on existing
slope crest

• Excavate 300mm topsoil to expose founding soil


• Conduct sand replacement test to confirm the founding
stratum to be firm ground
• Construct 350mm thick concrete slab with 2 layers of A252
Wire Mesh
• Display banners on both sides of jib showing the boom
length
• 3m MTRC protection zone will be demarcated by physical
barrier
• 6m MTRC protection zone will be demarcated by flag
• 1.0m high crash barrier to be installed along the outer edge
of the concrete slab

40
Proposed Major Lifting Plants situated on existing
slope crest
- Manitowoc 11000-1 Crawler Crane
- Sunward SWTD80 Piling RigProposed Grade
30/20 Concrete
350

2 Layers of A252
Wire Mesh
Proposed 350tk Concrete Slab for Operation of
Machineries on Existing Slope Crest

Outside Inside

Proposed 1.2m High Crash Barrier


41 (Same as Temporary Steel Platform Approval Drawing)
5. Emergency Contact List

42
THE END