Entrance Lobby 3 (near EVA) –Vertical Granite Stone (at side face of existing vertical stone)

installation completed.

Entrance lobby 3 (facing swimming pool) – Demolition of vertical Granite stone unit at top of the
metal louvre is in progress.
Entrance lobby 3 (facing swimming pool) – Installation of horizontal Granite soffit stone unit at
top of the metal louvre is underway.

Swimming Pool – Installation of horizontal Granite soffit stone unit at top of the glass wall
Straight section completed.
Swimming Pool – Demolition of vertical Granite stone unit at top of the glass wall
(straight section left wing ) completed..

Swimming Pool – Demolition of vertical Granite stone unit at top of the glass wall
(straight section right wing ) completed..
Swimming Pool – Installation of protective sheeting & demolition of vertical stone panel
completed ( curved section)

Swimming Pool – Last section of right wing, Demolition of vertical Granite stone is underway.
L5 Club House (Under Tower 11) – Erection of Bamboo scaffold is underway.

L5 Club House (Under Tower 11) – Erection of Bamboo scaffold is in progress


L3 Internal EVA – Erection of Bamboo scaffold for horizontal soffit stone
Installation works. Is in progress.

L3 Internal EVA – Horizontal Granite soffit stone at top of louver not yet commenced.
EVA – Installation of Granite soffit stone units completed..