2 Spreading and leveling of filling materials (Area 3) 7-Jan-22 7-Jan-22 8:00 AM 5:00 PM
4 Concrete pouring for construction of Grouted Rockwall (Area 2) 7-Jan-22 7-Jan-22 8:00 AM 5:00 PM
10
11
12
13
14
EQUIPMENTS
Qty.
11 Dump Truck Total Volume Backfilled: 520 cu.m.
1 Payloader
1 Road Roller
MANPOWER
Qty.
1 Site Engineer
1 Site Foreman
20 Labors
2 Heavy Equipment Operators
12 Truck Drivers
FDT completed
(for 4th and 5th layer)
FDT completed
(for 4th layer)
Constructing Rockwall
(ongoing)
Excavated
(for rockwall)