Daily Drilling Report

DANAN OILFIELD DEVELOPMENT


General Data
Country/ Province Iran / Ilam Well Type Deevelopment W.S.S. Day/ Night H.Parvivzi / M.Onagh Report No. 149
Field/ Well No. DANAN-DA-13 Spud Date/ Time 09/15/2020(99/06/25)/02:00 Operations / Area Manager M.Amini / M.Aliabadi Report Date 02/10/2021 (99/11/22)
Rig Name NOOR 1 Est. Rig Days 139 Geologist M.Ghasemi / Actual Rig Days 148 Days + 22 Hrs.
EPD Contractor MAPNA Hole Section 5 7/8" ICOFC Rep K.Ghodsi
Act Rig Days less NPT 111 Days + 8.5 Hrs.
Client ICOFC Section Start Date (99/11/12) / 21:00 Senior/ Night Toolpusher A.Mortazavian / A.Sohrabi

Well Data Bit Data Mud Data


N (m) 1,182,043.48 Bit No. Mud Type S.S. Polymer
Location (UTM):
E (m) 1,736,309.47 Bit Size TCI/ MT/ PDC 5 3/4" Taper Mill MW Min / Max (pcf) 78
Project TD (m): 3536.5 Bit Manufacture Flow Line Temp. (deg F) N/A
R.T.E (m) G.L.E (m) 294.7 284.2 Bit Type Funnel Vis (sec/qrt) 41
Morning Depth (m) 3512 Bit Serial No. 4071977 Fann 600 44
Mid Night Depth (m) 3512 IADC Code Fann 300 31
Previous Depth (m) 3512 Nozzle Number * Size ( /32 in) Fann 200/ 100 26 / 20
Drilled Interval (m) 0.0 W.O.B (klb) 0-2 Fann 6/ 3 4/3
Drilling Time (hr) 0.0 RPM / Total bit RPM 50-60/ PV (cp) 13
Average ROP (m/hr) #DIV/0! Torque (klb.ft) 2-5 YP (lb/100ft^2) 18
Cum. DRLG Time (hr) 1006.0 Pump Type KLF1600 GEL 10 s/ 10 min/ 30 min 3/5
Estimated / Actual Rig Days 139 148 Days + 22 Hrs. Pump Liner Size (in) 6+6+6 API Fluid Loss (cc/30 min) 2.0
KOP (m) - Flow Rate (gpm) 205 Mud Cake Thickness (1/32") 1
Last Formation MD TVD (m) Sarvak 3411 Standpipe Pressure (psi) 1220 Oil % 1
Lithology Lst TFA (in2) Water % 85
Last casing/ liner shoe 7" @ 3420.5 m Jet Velocity (ft/s) Solid/ Sand Content (%) 14 /
Last liner lap (m) 7"@2375 Bit Daily Drilled (m) Salinity(ppm)/Chlorides (mg/l) / 100000
Last FIT TVD (m) EMW (pcf) 2460 85 Bit On BTM Hours PH / MBT 9.2 /
Costs Today Well's Total Cum Drill Out CMT/ Ream (m) Total Hardness/Calcium (mg/l) 1120 / 1000
Day rate Cum Drill Out CMT/ Ream (hr) KCl (%WT)/ Glycol (%Vol) -
Mud & Cement Bit Cum. Drilled (m) Vol. in Hole (bbl) 630
Bit Bit Cum. Hours Vol. in Pits (bbl) 880
Cas/Tub W/H Bit In / Bit Out(m) 3512/ Mud Sys./ Daily Made (bbl) 812 / 0
Service Bit Dull Condition Form. Loss/ Mud Pump Repair 0/0
Total Weight Below Jar in mud (klb) Evap./ Shaker / Pit Cleaning 0/0/0
Mud Materials & Chemicals BHA# 48 Dump/ Trip/ Centrifuge/ Other 0 / 36 / 0 / 0
Material Type Unit Rec/ Sent Used STK Item Description Length (m) OD (in) ID (in) Cum. L. (m) Total Loss 36
BARITE 1.5 MT 0 5 3/4" Taper Mill 0.73 5 3/4" 1 1/2" 0.73 POB
BENTONITE 1 MT 0 4 9/16" B.Sub 0.91 4 9/16" 2 3/4" 1.64 MDCO 4
SODA ASH 50 Kg 11 8 STD 4 3/4" DC 224.07 4 3/4" 2 1/4" 225.71 ICOFC 4
SALT (NaCl) 1 MT 36 4 3/4" D.Jar 4.41 4 3/4" 2" 230.12 Services Catering 12 14
CaCO3 (Weight agent) 1 MT 43 1 STD 4 3/4" DC 27.83 4 3/4" 2 1/4" 257.95 Rig crew Guests 38 13
CAUSTIC SODA 25 kg 17 42 STD 3 1/2" DP 1215.23 3 1/2" 2 3/8" 1473.18 Casual labors 5
CITRIC ACID 25 kg 0 XOS 0.97 4 3/4" 2 1/4" 1474.15 Drivers 8
Xanthan Gum 25 kg 29 Security 4
Starch,Potato 25 kg 200 Total 102
KCL 1 MT 0 HSE
Wallnut Shell F 1 MT 0 HSE Cases Daily Cum
CaCO3 (F/M/C) 1 MT / 25 kg 2 / 80 / 0 LTI free days 1 149
MICA M/ C 25 kg 0/0 Man-hours 1356 204348
MICA M 1MT 1 BHA # 47 LTI Accidents 0 0
MICA F 25 kg 41 Description length(m) OD (in) ID (in) Cum. L. (m) Non LTI Accidents 4 529
Shell Fish F/C 25 kg 0/0 Logging tools 20.25 5 20.25 BOP Drill 0 5
Shell Fish C 1 MT 2 42 STD 3 1/2" DP 1215.23 3 1/2" 2 3/8" 1235.48 H2S Drill 0 0
Shell Fish M 25 kg 212 XOS 0.97 4 3/4" 2 1/4" 1236.45 Fire Drill 0 0
Shell Fish M 1 MT 0 Medevac Drill 0 0
PAC-LV/R 25 kg 0/0 Stop Card 4 714
Fiber Lock 25 kg 13 PJSM 1 526
SODIUM BICARB 50 kg 22 Toolbox Meeting 2 524
PIPELAX DR 4
Defoamer 55 gal 4
PHPA 25 kg 15 BOP Test
Cement & Cement Additive LAST BOP TEST Date 99.11.05
Mat. Type Unit Rec/ Sent Used STK Days Since Last BOP Test 17
CMT "G" sxs /100 525 Pumps Data
CMT "G" W/Hi-dense sxs Pump # 1 Pump # 2 Pump # 3
NaCl-Salt (1ton) bb Make BOMCO BOMCO BOMCO

Antifaom Agent AA-01 can DP, HWDP & DC Data Type KLF1600 KLF1600 KLF1600

Dispersant FR-02 sxs Size (in) Grade Nominal Weight (ppf) Power (hp) 1600 1600 1600

GMC-01 dr DP 5/5 3.5 G/S G 19.5/19.5 13.3 Liner Size (in) 6 6 6

FLC 03/02 dr/sxs HWDP Stroke (in) 12 12 12

chemical wash, CW-01 can DC 4 3/4 47 Max Press (psi) 3200 3200 3200

Mutual solvent SLV-01 sxs Down Hole Equipment


Magneset thinner sxs Equipment (Quantity, OD and Description) ID (in) Serial Number Cum Drlg (hr) Cum W&R/ D/O (hr)
1771100051-13-31-50-21-14-32-18-04-43-52-48-60-55-47-34-05-49-28-03-02-33-46-53-
Cement Equipment 4 3/4" DC 2 1/4" 11-16-57 53.0 74/ 17
Equipment Unit Rec Send STK 4 3/4" D.Jar 2 5060038 53.0 74/ 3
Cement Unit no 1 1
Solution Tank no
CMT Silo no 5 Solid Control Equipment
Hook Load Data
Air Compressor no Equipment Working Time (hr) Remarks
Surfactant drum Shakers 1 / 2 / 3 Mesh Size: 4*140/1*180+1*140+ 2*170/4*180 H.L (Klb) Pump On Pump Off
Fuel & Water Desilter / Desander / Degasser Pick Up
Fluid Type Unit Rec. Used STK Mud Cleaner Mesh Size: 4*320 Slack-Off
DIESEL Liter 3,000 68700 Centrifuge #1 / #2 Rotation
Drill Water bbl 1700 Super Clone TDS & Block Weight 58
KOP : Survey Casing Data
No. MD (m) INC (deg) AZ (deg) TVD (m) NS EW DLS Remark Shoe Depth Liner Lap
Casing Size (in) Grade Weight (ppf) Thread Length (m)
1 56.0 0.0 Totco m) (m)
2 302.0 0.5 Totco 20 K-55 106.5 WSP-BIG 57.5 57.5
3 598.0 1.5 Totco 13 3/8 N-80 68.0 BTC 1415.5 1415.5
4 902.0 2.0 Totco 9 5/8 HC95SS & T-95 53.50 WSP-3T 2455.5 2455.5
5 1218.0 3.0 Totco 7 L-80 29 PJE 1045.0 3420.5 2375
6 1412.0 4.0 Totco 5
7
8
Daily Drilling Report

DANAN OILFIELD DEVELOPMENT

Formation Data Well Control (SCR)

Forecasted Top MW (pcf)/ FV


Formation Name Actual Top (m) Lithology Pump # SPM# 1 SPP 1 (psi) SPM# 2 SPP 2 (psi) Depth (m) Time
(m) (s/qrt)

Aghajari Surface Rd. Ml + Gy.Ml + S.st 1

Gachsaran 7- 5 1600 1385.0 Anhy + Rd. Ml + Gy.Ml+ Salt 2

Gachsaran 4 - 2 1990.5 1874.0 Anhy + Rd. Ml + Gy.Ml+ Salt 3

Gachsaran 1 (Cap Rock) 2482.5 2426.5 Anhy + Salt + Shale Wellhead BOP Test Record
Asmari 2556.5 2491.0 Lst + Anhy Component Top FLG (Size/ WP) BTM FLG (Size/ WP) Component Type and Size Test Pressure

Kalhur 2626.8 2566.0 Lst+ Anhy+ Shale+ Cyst+Salt Xmas Tree Annular 13 5/8"-5K 2500

Pabdeh 2860.6 2837.0 Lst + Gy.Ml THS 11" 5K 13 5/8" 3K Top Rams 13 5/8"-10K 4500

Gurpi 3311 3293.0 Lst DSA Pack off - - - - Blind Rams 13 5/8"-10K 4500

Ilam 3356.5 3332.0 Lst CHS 13 5/8" 3K 21 1/4" 2K Bottom Rams 13 5/8"-10K 4500

Sarvak 3440.5 3411.0 Lst + Cyst CHH 21 1/4" 2K - - Choke Manif. 5k 4500

Well TD 3536.5 Wear Bushing Size: 11" IN/ OUT: IN Accumulator 3k Function test

Received

To/ N#2: 100sxs Net "G" Cement


Sent

5" Liner Program + 5" liner 18#, L-80, WSP-4T (as required) + HGR Man + Casing crew & running equip+ 5" Liner HGR, 18#, L-80, VFJ & Acc.+ 4 1/8" Bit & Mill
Request
5" XOS, VFJ Pin * WSP-4T Box (2Jts) + 5" LDC, 18#,L-80, WSP-4T (3Jts) + 5" XOS, WSP-4T Pin * VFJ Box (2Jts) + 5" XOS, WSP-4T Pin * 3 1/2" IF Box

Outstanding

Detail of Operations within Last 24 hours


Code /Activity Hrs From To Hrs Code Remarks
1. Rigging and Moving 00:00 02:30 2.5 10A Cont. Unlatch PWCH from DWCH & pull out same to Surf. L/D CSES & R/D Logging Equipment W/NL-NG.
2. Drilling 02:30 12:00 9.5 10B Cont. POOH with TLC#1 string (MSFL/DLL/CDR/GR) F/2698m to surface W/NL-NG (Obs. the well on BHA "static" ).
3. Hole Conditioning 12:00 13:00 1.0 10A L/D logging tools & install Wear Bushing.
4. Coring 13:00 RIH with 5 3/4" Used Taper Mill (1/8" UG, S/N: 4071977) & BHA#48 from surface to 2795m W/NL-NG. soft W&R F/2795m
5. Mud Condition & Circ. to 2800m.
6. Trips 24:00 11.0 22N W&R Parameters: WOM: 0-2 klb, RPM: 50-60, FR: 205 gpm, SPP: 1220 psi, Torq.: 2-5 Klb.ft
7. Rig Services

8. Slip and Cut DRLG Line

9. Deviation Survey

10. Logging 13.0


11. Running Casing/ Liner

12. Cementing

13. Nipple up/ down

14. BOP Test >>>Note : Operation Crew Shortage (Night Shift Derrickman & Camp Motorman).
15. Formation Testing >>>Note : Released Homai Logging Crew at 13:00 O'clock.
16. Directional Drilling >>>Note : Rec. 1No. MDCO pump truck & CMT crew at 14:00 O'clock.
17. Well Completion

18. Perforation

19. Stimulation

20. Production & Well Testing

21. Suspension/Abandonment

22. NPT 11.0


23. Other Time 8:00 13:00 19:00
Pool Level (m) full full 0.1

Rig Shortage: ###


1- Some caravans facilities are not completed.

24.0
From To Hrs Code Morning Report
00:00 06:00 6.0 22N Cont. soft W&R F/2800m to 2907m (RIH F/2802m to 2813m normally) W/NL-NG.

Total (Hrs) 6.0

Operations Summary

POOH with TLC#1 string from 2698m to surface. RIH W/5 3/4" Used Taper Mill (1/8" UG) to 2795m. Soft W&R F/2795m to 2800m.

Next Operations

Continue RIH to 7" Liner Shoe depth. POOH to surface.


Operations Reference Code
MAPNA Drilling Co.
Code/
Main Activity Details
Subcode
1 Rigging & Moving
2 Drilling
3 Hole Conditioning
4 Coring
5 Mud Conditiong & Circulation
6 Trips
7 Rig Services
8 Slip & Cut Drilling Line
9 Deviation Survey
10 Wireline Logging
11 Running Casing/ Liner
12 Cementing
13 Nipple up/ down
14 BOP Test
15 Formation Testing
16 Directional Drilling
17 Well Completion
18 Perforation
19 Stimulation
20 Production & Well Testing
21 Suspension/ Abandonment
22 NPT
22A Waiting on Client
22B Waiting on EPD Contractor
22C Waiting on Service Company
22D Waiting on Rig Contractor
22E Stuck
22F Fishing and milling All preparing, assembling of fishing equipment to recover of junks or fish from a wellbore
22G Side-Tracking All operations related to Sidetracking Original Hole to Bypass a Fish (using cement plug or whipstock)
22H Well Control Issue
22I Washout Including trip out and trip in until reaching previous depth
22J String Plug Including trip out and trip in until reaching previous depth
22K Rig Repair
22L Wait On Weather
22M Force Majeure Other Force Majeures out of Client and Operator's Control
22N Other Down Hole Problem NPTs which is not within the above mentioned Categories
23 Others