Rig Name: NOOR 1 Location: E010 Drilling Supervisor: H.Parvizi / M.T.Ashtiani Date: 99.12.30 20-Mar-21
Well NO: 13 Rig Manager Asst. Drilling Supervisor: Released: 99.05.24 14-Aug-20
Field DANAN Rig Supt.: M.AKBARI Geologist: S.Hosseini / S.Kiamarzi Spud: 99.06.25 15-Sep-20
Client: I.C.O.F.C D.Toolpusher: A.SAEEDI Operator Area Manager: M.Amini / I.Birgani Act . Rig Days: 187
Well Type: PG N.Tourpusher: A.SOHRABI Completion/Drilling ENG: Monfared Rig Planned Days: 139
Planned TD(m) : 3536.5 Rotating TIME: Mid Night Depth (m): 3512 6:00 Hrs Morninig Depth (m): 2610
R.T.A (m): 294.7 Sliding TIME: Previous Depth (m): 3512 6:00 Hrs Morning Bit Depth (m): 2610
Cumulative TIME: 1006 Drilling TIME: 0 Actual Progress MD/TVD (m): 0.0 DAILY AVG ROP (m/hr): #DIV/0!
BHA TALLY BIT RECORD MUD REPORT MUD PUMP DRILLING INFORMATION
BHA No. / RIH DTAE #65 99/12/20 Bit No. Mud Type WBM Pump #1 #2 #3 WOB (Klbs)
No. ITEM OD Qty Length (m) Bit Type: Mud WT (pcf) 80 Liner ID (in) 6 6 6 Surface RPM
1 H.W.S 7" 1 5.75 Bit Size (in) Viscosity (sec) 42 Efficiency % 95 95 95 Motor RPM
2 T.MILL 6" 1 2.92 Serial No PV (cp) 17 SPM Apparent String Wt (Klbs)
3 R.TOOL 4 4/5 1 1.35 Type YP (lb/100 ft^2) 16 GPM 0 0 0 Pick Up Wt (Klbs)
4 H.D.P 3 1/2 1 9.17 IADC Code Gels 10'' / 10' 3-Jan 4.6 SLOW CIRC. RATE (SCR) Slack off Wt (Klbs)
5 G.SUB 4 3/4 1 0.4 Manufacturer FL Loss (cc) 2 2.6 MD/TVD (m): TIME: Drag Up (Klbs)
6 D.C 4 3/4" 18 169.51 TFA ( in²) 0.000 PH/Alk 9.4 Pump #1 #2 #3 Drag Down (Klbs)
7 DP 3 1/2" 24 231.46 Nozzle Velocity #DIV/0! Stability (volt) SPM #1 Off Btm torque (K ft.lbs)
8 XOS 6 1/2 1 0.97 Depth in (m) Hardness 1000 PSI On Btm torque (K ft.lbs)
9 Depth out (m) Solid% 15% SPM #2 Total Flow Rate (GPM) 0
10 Total Drill (m) 0 0 Water% 84% PSI Stand Pipe Press (PSI )
11 Total Hrs Oil% 1 MUD PITS INFORMATION LIQUIDS & MUD ADDCITIVES
12 AVG ROP #DIV/0! #DIV/0! Chlorides 100000 PIT CAP bbl VOL bbl MW pcf Item USED On Hand
13 (mph)
Hydro.Static Pre (PSI) 6406 Solid Cont Loss Suction 181 80 Diesel (Liter) RIG 4000 79200
14 IADC Dull Grading Surface Loss Middle 35 78 Diesel (Liter) CAMP 400 11900
15 Inner R. Wears Downhole Loss Desilter 17 78 Drill Water (BBL) 1600
16 Outer R. Wears HYDRUALICS Desander 17 78 FRESH WATER (Liter)
TOTAL BHA Length (m) 421.53 Dull Charact. DC_Ann Vel (fpm) #N/A Degaser 18 78 Lime (SX 25 KG)
DRILLIN-LINE TON-MILE 1795 Location HSI #DIV/0! Total Active 268 Barite ( BIG BAT 1.5 TON)
Drilling Line Reserve (Ft) 4276 Bearing Seals Impact Force Lb #DIV/0! Reserve 1 134 80 SALT (BIG BAG 1 TON)
JAR Gauge Bit Press Drop #DIV/0! Reserve 2 Limstone (BIG BSG 1 TON)
Type Size: Other Dull Bit HHP #DIV/0! Reserve 3 CaCl2
S/N: Hrs: Reason Pulled Pumps HHP 0.0 Reserve 4 48 80
Current Bit Nozzle Size (1/32") :
8 RIG REPAIR No. Of Drills Run Today 20 K55 106.5 WSP-Big 57.5 57.5
N-80 & T-
9 SLIP & CUT First Aid Cases 13 3/8 68 BTC 1415.5 1415.5
95
HC-95SS
10 DEVIATION SURVEY Last LTI Date 11-May-20 9 5/8 53.5 WSP-3T 2455.5 2455.5
& T-95
11 WIRELINE LOGS DAYS SINCE LAST 7 L-80 29 PJE 3420 1045 2375
12 RUN CASING & CEMENTING LTI 313 5
13 WAIT ON CEMENT (WOC) INSPECTION VISIT BOP DATA
14 NIPPLE UP/DOWN BOP SPILL BOP TYPE ANNULA TOP BLIND BOTTOM LAST BOP TEST 06-Mar-21
15 BOP TEST MEDIVAC SIZE R RAMS ELAPSED DAY 14
13 5/8 13 5/8 13 5/8 13 5/8
16 DRILL STEM TEST (DST) PRESSURE 5K 10K 10K 10K NEXT BOP TEST DATE 20-Mar-21
17 PLUG BACK
GEOLOGY
18 SQUEEZ CEMENT
19 FISHING FORECAST ACTUAL
FORMATION LITHOLOGY
20 DIRCETIONAL DRILLING Top MD (m) TopTVD (m) Top MD(m) Top TVD (m)
21 COILD TUBING Gurpi 3311 3293 Lst
22 DOWN HOLE TEST Ilam 3356.5 3332 Lst
23 PERFORATION Sarvak 3440.5 3411 Lst + Cyst
24 WELL CONTROL Well TD 3536.5
25 COMPLEATION
SAFETY
26 TREATING
27 STUCK PIPE & JARRING /WASHOUT No.of Incident No.of Accident Short Description of Incident / Accident
28 DOWN HOLE PROBLEM 23
29 RIG CONTRACTOR
Day Shift
30 SERVICE COMPANY
Wait On
PJSM Subject:
31 WEATHER
Night Shift
32 EPD CONTRACTOR
33 WAITING ON RIG CONTRACTOR Operational Meeting Subject:
Training Subject at Site:
Total Hours 24
FOP 01 (1)
Daily Drilling Report کد فرم: FO-TO-086-03
FIELD: DANAN Mid Night Depth (m): 3512 Rig Planned Days: 139
CLIENT I.C.O.F.C Morning Depth (m): 2610 Act . Rig Days: 187
Duration Operation
From To Hours Code RIG TIME DESCRIPTION
00:00 16:00 16 33 Continue RIH with 7" hydraulic whipstock assembly from 75 m to 1600 m with drifted DPs (F/U the string with HVP at 215m).
16:00 17:00 1 7 Work on koomy unit (pressure switch & KR valve leakage).
17:00 00:00 7 33 Continue RIH with 7" hydraulic whipstock assembly from 1600 m to 2500 m with drifted DPs.
00:00 00:00
00:00 00:00
00:00 00:00
00:00 00:00
00:00 00:00
00:00 00:00
00:00 00:00
00:00 00:00
00:00 00:00
00:00 00:00
00:00 00:00
00:00 00:00
00:00 00:00
00:00 00:00
00:00 00:00
00:00 00:00
00:00 00:00 Rig Shortage:
00:00 00:00
00:00 00:00
00:00 00:00
DIRECTIONAL INFORMATION
Sliding Hours: 0 Sliding
Intervals:
Rotating Hours: 0 Rotating
Intervals:
SURVEY DATA Ref. Azimuth:
No. Tool MD - m INC ° Azimuth ° TVD - m N/S (+/-) E/W (+/-) V. Section D/L °/30 ft D/L °/100 ft
SAP RESERVE/
NO DESCRIPTION QTY UNIT DATE PR/NO COMMENTS
ORDER
1
PIN FOR RIG TONG TYPE H 6 EA 42314 1399/07/30 ایوب مرتضویان
2
PIN FOR RIG TONG TYPE AAX 6 EA 42314 1399/07/30 ایوب مرتضویان
3
ELECTROD HOLDER 550A 2 EA 42318 1399/07/30 ایوب مرتضویان
4
گریس خور واش پایپ 10 EA 42319 1399/07/30 ایوب مرتضویان
5
کلمس پانی راد 3 عدد 47725 99.08.24 علی افروزی
6
دمپنر 1 عدد 41359 99.08.24 علی افروزی
7
RING GASKET RX24 5 عدد 58713 99/10/06 علی افروزی
8
INSERT FOR SLIPS 5" 108 EA 66399 99.10.04 علی افروزی
9
INSERT FOR SLIPS 3-1/2" 60 EA 66399 99.10.04 علی افروزی
10
TOTCO OIL 6 L 66399 99.10.04 علی افروزی
11
BUFFEL 5F6R 2 EA 66402 99.10.04 علی افروزی
12
LINER7" 12 EA 66405 99.11.04 علی افروزی
13
RUBBRE 7" 25 EA 66405 99.11.04 علی افروزی
14
SPRING 8 EA 66405 99.11.04 علی افروزی
15
متری30 متر 1 عدد 64473 99.10.27 ایوب مرتضویان
16
WASH PIPE PACKING 1 EA 79505 99.12.24 ایوب مرتضویان
17
WASH PIPE BARREL 2 EA 79505 99.12.24 ایوب مرتضویان
18
DOPE 40 KG 79505 99.12.24 ایوب مرتضویان
19
CYLINDER COVER SEAL 20 EA 79506 99.12.24 ایوب مرتضویان
20
LINR SEAL 20 EA 79506 99.12.24 ایوب مرتضویان
21
TOTCO OIL 5 L 80252 99.12.27 اافشین سعیدی
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
TOOLS AND MATERIAL SENT کد فرم: FO-TO-086-03
SAP RESERVE
NO DESCRIPTION QTY UNIT NUMBER DATE REMARKS
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
TOOLS AND MATERIAL RECEIVED کد فرم: FO-TO-086-03
SAP RESERVE
NO DESCRIPTION QTY UNIT PART NO NUMBER
DATE REMARKS
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
TOOLS AND MATERIAL SENT کد فرم: FO-TO-086-03
SAP RESERVE
NO DESCRIPTION QTY UNIT PART NO DATE REMARKS
NUMBER
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
CODE MAIN OPERATION ACTIVITY
02 DRILLING
03 REAMING
04 CORING
06 TRIPS
07 SERVICE RIG
08 REPAIR RIG
10 DEVIATION SURVEY
11 WIRELINE LOGS
12 RUN CASING & CEMENT
13 WAIT ON CEMENT
15 TEST BOP
17 PLUG BACK
17 PLUG BACK
18 SQUEEZE CEMENT
19 FISHING
21 COILED TUBING
22 DOWNHOLE TEST
22 DOWNHOLE TEST
23 PERFORATION
24 WELL CONTROL
25 COMPLEATION
26 TREATING
28 CHANGE RAMS
31 WAIT ON WEATHER
D- Milling
A - Back Ream
B - Down Ream
A - Cut Core
A - Circulatioin In Hole
B - Displace Mud
C - Mud Conditioning
A - Trip in (RIH)
A- Rig-up Wireline
B - Rig-Down Wireline
C - Run Wireline
A - Rig-up/down Casing Handling Equipment
B - Run Casing
C - Run Liner
D - Set Casing
E - Rig-up/down Cement Job
F - Pressure Test Cement Line
G - Cement Job
A - Cut Casing
B - Instal Casing Head
B - Pressure Test
A - Rig-up/Down Coil Tubing
C - N2 liftting
D - Acidizing
A - Perform FIT
B -Perform LOT
B - Perforating On Wireline
A - Flow Check
B- BOP Drill
C - Shut in Well
F - Well Kill
G - Bullheading
H - Divertring
B - Compleation Test
A - Stuck
B - Jar up
C - Jar down
Drilling is boring a hole into the earth with the purpose of finding an
drilling out shoe tracks and dressing off cement plugs. Time starts o
Replacing drill line begins when the drawworks is removed from ser
activity involves spooling in a new supply line and moving worn lin
This operation refers to dry BOP stacks, i.e., BOPs that are not subse
begins assembling the unit. Rig up ceases when the complete BOP s
BOP testing begins when the process of checking the device for func
The drill stem test begins with picking up temporary packers used to
Plugging back begins when the plug or cement head is run into the h
Plugging back begins when the plug or cement head is run into the h
Specialized directional work begins when the drill bit and assembly
assembly and drill bit have been rigged down. Otherwise, this catego