Daily Drilling Report

DANAN OILFIELD DEVELOPMENT


General Data
Country/ Province Iran / Ilam Well Type Development W.S.S. Day/ Night H.Ahmadi / B.Hemati Report No. 256
Field/ Well No. DANAN-DA-14 Spud Date/ Time 1399/07/09 / 23:00 Operations / Area Manager M.Amini / I.Birgani Report Date 06/12/2021 (1400/03/22)
Rig Name NOOR 2 Est. Rig Days 138 Geologist H.Omidi Actual Rig Days 256
EPD Contractor MAPNA Hole Section 5 7/8" ICOFC Rep M.Baghaee / M.Khanalizadeh
Act Rig Days less
100 Days + 9 Hrs
Client ICOFC Section Start Date 1399/10/17- 10:00 Senior/ Night Toolpusher P.Parsi / Gh.Shojaee NPT

Well Data Bit Data Mud Data


N (m) 3,612,265.00 Bit No. Mud Type Salt Polymer Mud
Location (UTM):
E (m) 734,134.00 Bit Size TCI/ MT/ PDC MW Min / Max (pcf) 71
Project TD (m): 3509 Bit Manufacture Flow Line Temp. (deg F) P.CH
R.T.E (m) G.L.E (m) 261 252 Bit Type Funnel Vis (sec/qrt) 31
Morning Depth (m) 3484 Bit Serial No. Fann 600 25
Mid Night Depth (m) 3484 IADC Code Fann 300 17
Previous Depth (m) 3484 Nozzle Number * Size ( /32 in) Fann 200/ 100 13 / 9
Drilled Interval (m) 0.0 W.O.B (klb) Fann 6/ 3 3/2
Drilling Time (hr) 0.0 RPM / Total bit RPM PV (cp) 8
Average ROP (m/hr) #DIV/0! Torque (klb.ft) YP (lb/100ft^2) 9
Cum. DRLG Time (hr) 759.0 Pump Type KLF1600 GEL 10 s/ 10 min/ 30 min 2/3/-
Estimated / Actual Rig Days 138 256 Pump Liner Size (in) 6/6/7 API Fluid Loss (cc/30 min) 10.0
KOP (m) - Flow Rate (gpm) Mud Cake Thickness (1/32") 1
Last Formation MD TVD (m) Sarvak 3386 Standpipe Pressure (psi) Oil % 2.5
Lithology Lst TFA (in2) Water % 89.5
Last casing/ liner shoe 5" / 2829 m Jet Velocity (ft/s) Solid/ Sand Content (%) 8/-
Last liner lap (m) 5" L.Lap @ 2634 m Bit Daily Drilled (m) Salinity(ppm)/Chlorides (mg/l) - / 90000
Last FIT TVD (m) EMW (pcf) 2469 85 Bit On BTM Hours PH / MBT 10.5 / -
Costs Today Well's Total Cum Drill Out CMT/ Ream (m) Total Hardness/Calcium (mg/l) 2400 / 2000
Day rate Cum Drill Out CMT/ Ream (hr) KCl (%WT)/ Glycol (%Vol) -
Mud & Cement Bit Cum. Drilled (m) Vol. in Hole (bbl) 643
Bit Bit Cum. Hours Vol. in Pits (bbl) 1269
Cas/Tub W/H Bit In / Bit Out(m) Mud Sys./ Daily Made (bbl) 908 / 878
Service Bit Dull Condition Form. Loss/ Mud Pump Repair 0/0
Total Weight Below Jar in mud (klb) Evap./ Shaker / Pit Cleaning 0 / 0 / 21
Mud Materials & Chemicals BHA# Dump/ Trip/ Centrifuge/ Other 60 / 0 / 0 / 0
Material Type Unit Rec/ Sent Used STK Item Description Length (m) OD (in) ID (in) Cum. L. (m) Total Loss 81
BARITE 1.5 MT 0 POB
BENTONITE 1 MT 0 MDCO 5
SODA ASH 25 kg 12 ICOFC 5
SALT (NaCl) 1 MT 30 Services Catering 29 15
CaCO3 (weight agent) 1 MT 11 Rig crew Guests 39 4
CAUSTIC SODA 25 kg 12 Casual labors 7
CITRIC ACID 25 kg 0 Drivers 11
Xanthan Gum 25 kg 0 Security 13
G.Starch 25 kg 65 Total 128
Drilling Detergent 55 Gal 0 HSE
NUT PLUG F/M/C 25 kg / 1 MT 0 HSE Cases Daily Cum
Starch HT 25 kg 0 LTI free days 1 256
KCl 1MT 0 Man-hours 1536 706368
LIME 25 kg 5 25 BHA# LTI Accidents 0
CaCO3 (F/M/C) 25 kg / 1 MT 0 Description length(m) OD (in) ID (in) Cum. L. (m) Non LTI Accidents 4
MICA F/ M/ C 25 kg / 1 MT 0 BOP Drill 1400/02/19 6
SHELL Fish F-M-C 25 kg / 1 MT 0 H2S Drill 99/09/23 1
PAC-LV/R 25 kg 0 Fire Drill
BIOCIDE 55 Gal 0 Medevac Drill
SODIUM BICARB 25 kg 2 Stop Card 3 1160
SPERSENT CF 25 kg PJSM 3 908
PIPELAX 55 gal 4 Toolbox Meeting 1 769
Defoamer 55 gal 4
OYSTER SHELL COARSE 25 kg
Fiber lock 25 kg 0
CORROSION INHIBITOR 55 gal 4

BOP Test
Cement & Cement Additive LAST BOP TEST Date 1400.03.08
Mat. Type Unit Rec/ Sent Used STK Days Since Last BOP Test 14
CMT "G" Delijan sx 0 Pumps Data
CMT "G" Kerman sx 0 Pump # 1 Pump # 2 Pump # 3
Chemical wash can 0 Make KLF KLF KLF
Defoamer (5gal) can 0 DP, HWDP & DC Data Type F1600 F1600 F1600
Dispersant FR-01 sx 0 Size (in) Grade Nominal Weight (ppf) Power (hp) 1600 1600 1600
Spacer SPC-01 sx 0 DP Liner Size (in) 6 6 7
Mutual solvent Dr 0 HWDP Stroke (in) 12 12 12
Accelerator S-01 sx 0 DC Max Press (psi) 4500 4500 3500
Light WT Add. LWA-01 Dr 0 Down Hole Equipment
Heavy WT Add LWA-01 B.Bag 0 Equipment (Quantity, OD and Description) ID (in) Serial Number Cum Drlg (hr) Cum W&R/ D/O (hr)
Cement Equipment
Equipment Unit Rec Send STK
Cement Unit no 0
Solution Tank no 0
CMT Silo no 5 Solid Control Equipment
Hook Load Data
Air Compressor no 0 Equipment Working Time (hr) Remarks
Surfactant drum 0 Shakers 1 / 2 / 3 0 0 0 170-170-140 / 170-140-140 / 170-14H.L (Klb) Pump On Pump Off
Fuel & Water Desilter / Desander / Degasser 0/0/0 Pick Up
Fluid Type Unit Rec. Used STK Mud Cleaner 320-320-320 (API) Slack-Off
DIESEL Liter 3100+1000 57100 Centrifuge #1 / #2 0 0 Rotation
Drill Water bbl 1000 Super Clone TDS & Block Weight 58 Klb
KOP : Survey Casing Data
No. MD (m) INC (deg) AZ (deg) TVD (m) NS EW DLS Remark Shoe Liner Lap
Casing Size (in) Grade Weight (ppf) Thread Length (m)
1 57.0 0.0 TOTCO Depth m) (m)
2 85.0 0.0 TOTCO 20 K-55 106.5 WSP-Big 57.0 57.0
3 940.0 0.5 TOTCO 13 3/8 N-80 & T-95 68 & 72 BTC 1970.0 1970.0
4 1570.0 2.5 TOTCO 9 5/8 HC-95SS & T-95 & L-80 53.5 & 43.5 & 47 WSP-3T & PJE 2469.0 2469.0
5 1884.0 2.5 TOTCO 7 L-80 29 PJE 1007.0 3388.5 2381
6 5 L-80 18 WSP-FJ 189.00 2829 2640
7 5 Tie back L-80 18 VFJ 4.06 2637
8 5 Tie back #2 L-80 18 VFJ 4.48 2634
Daily Drilling Report

DANAN OILFIELD DEVELOPMENT

Formation Data Well Control (SCR)

Forecasted Top MW (pcf)/ FV


Formation Name Actual Top (m) Lithology Pump # SPM# 1 SPP 1 (psi) SPM# 2 SPP 2 (psi) Depth (m) Time
(m) (s/qrt)

Aghajari Surf. Surf. Rd Mrl + Sst + Gy Mrl + Anhy 1

Gachsaran 7- 5 1827 1938.0 Anhy + R.Mrl + G.Mrl 2

Gachsaran 4 - 2 2137 2252.0 Slt + Anhy + Mrl 3

Gachsaran 1 (Cap Rock) 2412 2426.0 Anhy + Mrl + Lime + Cly + Shale Wellhead BOP Test Record
Asmari 2474 2496.0 L.st.+Anhy+Dol L.st+Arg.L.st+ Cl.st. Component Top FLG (Size/ WP) BTM FLG (Size/ WP) Component Type and Size Test Pressure

Kalhur 2548 2573.0 Arg.L.st + Anhy + Cl.st. + Dol.L.st.+ L.st+ G.Mrl + Salt Xmas Tree Annular 5k - 13-5/8" 2500

Pabdeh 2813 2816.0 Arg. Lst THS 11" 5k 13-5/8" 3k Top Rams 10k- 4-1/2" *7" VBR 4500

Gurpi 3283 3262.0 Lst DSA Pack off Blind Rams 10k - 13-5/8" 4500

Ilam 3329 3305.0 Lst CHS 13-5/8" 3k 21-1/4" 2k Bottom Rams 5"fix, 10k - 13-5/8" 4500

Sarvak 3410 3386.0 Lst CHH 21-1/4" 2k welded Choke Manif. 10k 4500

Well TD 3509 3484.00 Lst Wear Bushing Size: 11" IN/ OUT: Out Accumulator 3K Function test

Received

Sent

Request

Outstanding

Detail of Operations within Last 24 hours


Code /Activity Hrs From To Hrs Code Remarks
1. Rigging and Moving 00:00 Cont Run Comp. Strg W/ 3 jts 7" TBG (29#, L-80, HSM1) (Totally: 5jts) F/ 2401 to 2438m while use C.Line Protector &
2. Drilling band-it strap to tight C.Line against TBG body. M/U 7” D.Pin (29#, L-80 13CR, N.Vam, Slotted, PED) + 11" x 9-5/8"x7"
3. Hole Conditioning TBG Hanger (N.VAM, Wetco), M/U 7" L.Joint (29#, L-80, HSM1) on TBG HGR, connect C.Line to TBG HGR & test
4. Coring W/5000 psi "Ok" , flush & clean T.H.Spool. Cont RIH to 2447m (1.5m Space out as T.H.Spool., PKR DEPTH: 2430m).
5. Mud Condition & Circ. 07:30 7.5 17C F/U string W/71pcf S.WTR & P/T inside Comp. string W/ 4500psi, "OK". Install Golp. Flange.
6. Trips 07:30 R/U MAX Co. Slick line lubricator & equipment and P/T all with 4500 psi, "Ok".
7. Rig Services As Slick line operation: Pull out 5.950" Dummy from SSSV L.Nip. and pull out Prong and Plug 3.688" from SSD. Set
8. Slip and Cut DRLG Line 19:30 12.0 17E 3.125" Plug & Prong in No-Go. Install Dummy. R/D Slick line lubricator, L/D Golp. FLG.
9. Deviation Survey 19:30 Chnge TDS links. Line up pump unit and test Line with 4500 psi, "Ok".
10. Logging Pressurizing inside string to 4500 psi step by step and Set packer at 2430m as program. hold pressure, "Ok".
11. Running Casing/ Liner Release pressure & test PKR W/20 KLB over pull "OK".
12. Cementing Land TBG HGR in T.H.Spool, shear T.Joint & obs back flow. P/T hanger W/1000 psi "OK", tighten Tie-
13. Nipple up/ down 24:00 4.5 17C Down screws. Close top rams & P/T hanger W/4500psi "ok".
14. BOP Test

15. Formation Testing

16. Directional Drilling

17. Well Completion 22.0


18. Perforation Note: 2hrs waiting for PED Co. (MAX Co. Slick line) due to delay in operation.
19. Stimulation Note: NO-GO Depth: 2446m PKR Depth: 2430m SSD Depth: 2415.8 3SV L.Nip. Depth: 72.3m.
20. Production & Well Testing

21. Suspension/Abandonment

22. NPT 2.0


23. Other

Note: Personnel Shortage On Board : 1 Roughneck + 2 Crane Operator + 1 Camp motor man.
TOTALLY 24.0 24.0
From To Hrs Code Morning Report
00:00 03:30 3.5 17C P/T string W/4500 psi "Ok". P/T Ann. to 2000 psi "Ok". B/O & L/D L.joint, install 6-5/16" two-way in TBG HGR & P/T W/4500 psi "Ok".
03:30 06:00 2.5 13A N/D BOP stack in progress.

Total (Hrs) 6.0


Operations Summary
Cont Run Comp. Strg W/3 jts 7" TBG (29#, L-80, HSM1) (Totally: 5jts) + D.Pin + TBG HGR + L.Jt. To 2447m while connect C.Line to TBG HGR & P/T, "Ok". R/U S.Line, Pull out 5.950" Dummy
from SSSV L.Nip. and pull out Prong and Plug 3.688" from SSD. Set 3.125" Plug & Prong in No-Go. Install Dummy. R/D Slick line, Set PKR @ 2430m as program, Land TBG HGR in T.H.Spool, P/T
hanger W/4500psi "Ok".
Next Operations

N/D BOP stack, N/U X-Mass tree & P/T it. Displace Ann. with Hi-PH Water (with Corrosion inhibitor).
Operations Reference Code
MAPNA Drilling Co.
Code/
Main Activity Details
Subcode
1 Rigging & Moving
2 Drilling
3 Hole Conditioning
4 Coring
5 Mud Conditiong & Circulation
6 Trips
7 Rig Services
8 Slip & Cut Drilling Line
9 Deviation Survey
10 Wireline Logging
11 Running Casing/ Liner
12 Cementing
13 Nipple up/ down
13A Nipple up/down BOP All activities related to Nippling up or nippling down the BOP

13B Nipple up/down Wellhead


All activities related to Nipple up or nipple down Wellhead (including rough cut, bevel, pressure test)

13C Nipple up/down Xmas Tree


All activities related to Nipple up or nipple down Xmas tree (including rough cut, bevel, pressure test)
14 BOP Test
15 Formation Testing
16 Directional Drilling
17 Well Completion
18 Perforation
19 Stimulation
20 Production & Well Testing
21 Suspension/ Abandonment
22 NPT
22A Waiting on Client
22B Waiting on EPD Contractor
22C Waiting on Service Company
22D Waiting on Rig Contractor
22E Stuck
22F Fishing and milling All preparing, assembling of fishing equipment to recover of junks or fish from a wellbore
22G Side-Tracking All operations related to Sidetracking Original Hole to Bypass a Fish (using cement plug or whipstock)
22H Well Control Issue
22I Washout Including trip out and trip in until reaching previous depth
22J String Plug Including trip out and trip in until reaching previous depth
22K Rig Repair
22L Wait On Weather
22M Force Majeure Other Force Majeures out of Client and Operator's Control
22N Other Down Hole Problem NPTs which is not within the above mentioned Categories
23 Others