SONATRACH
SUPERVISOR/SUPERINTENDENT: RIG NAME & No: FIELD: ACC. FREE: AFE (KD): DAILY (KD): CUM (KD): WELL OBJECTIVE:
A.AISSAOUI / M.B.GUECHOUT TP 202 HASSI MESSAOUD 1494 days 1 003 252 6 725 293 249 DEVELOPMENT
LAST CSG/LNR SHOE: LAST CSG/LNR TOP: LAST FM. TEST/EMW: L. BOP TEST: L.SAFETY MEETG: DAY DRL NPT: CUM DRL NPT: I.SERVICE:
24,000 in @ 238,00 m 0,00 m 05/09/2021 23,50 hr 36,15 days NONE
ACCIDENT / INCIDENT TOPICS:
NO ACCIDENT// NO INCIDENT // 04 STOP CARDS // 00 PTW // 00 JSA.
BIT DATA LAST BHA MUD CHECKS
BIT No./Re-Run(U) 5/U / NAME: SLICK BHA TYPE 1: WBM TIME/LOC 00:01/IN
BIT RUN No. 6 OD TOOL JTS LENGTH TYPE 2: TIME/LOC /
BIT SIZE (in) 22,000 (in) TYPE No (m) DENSITY (sg) 1,05 ECD (sg)
BIT MANUFACTURE NOV 5,000 HW 6 55,21 DEPTH (m) 395,0 SAND () 0,80
BIT TYPE T11CPT 8,000 XO 1 1,19 FL TEMP (°C) SOLIDS (%) 3,00
BIT IADC CODE 115 8,000 DC 9 81,47 FUN VIS (s/qt) 84 OIL (%)
BIT SERIAL No. D253635 9,500 XO 1 1,22 PV (cp) 12 H2O (%) 97,00
BIT JETS (32nd") 3X20 9,500 DC 2 18,35 YP (lbf/100ft²) 56 OIL/H2O / /
9,500 SS 1 3,60 GEL (10sec) (lbf/100ft²) 26,00 LGS (%) 2,30
BIT TFA (in²) 0,920 9,500 BS 1 0,98 GEL (10m) (lbf/100ft²) 32,00 HGS (%) 0,33
FUEL & WATER MUD LOSSES MOTOR&TURBINE (day/cum) SHOCK SUB 46,2
FUEL: 66,00 m³ SURF: MOTOR: / JAR
WATER: 180,00 m³ HOLE: 114,0 m³ TURBINE: / BHA
AV DP: DP/CSG: STRING: 0,0 ANNULUS: 0,0 TQ.on BTM: TQ.off BTM:
AV DC: Jets Vel ( m/s): PITS: 0,0 TOTAL 0,0 BELOW JAR: ABV. JAR:
SODA ASH TONNE 0,125 0,475 MICA ( M ) TONNE 2,400 3,200 3,850
NUT PLUG ( C ) TONNE 2,100 2,500 2,100 MICA ( F ) TONNE 2,400 2,400 2,400
SURVEY DATA
MD INC AZI TVD N/S (-) E/W (-) VS DLS MD INC AZI TVD N/S (-) E/W (-) VS DLS
(m) (°) (°) (m) (m) (m) (m) (°/30m) (m) (°) (°) (m) (m) (m) (m) (°/30m)
478,00 478,00 0,00 0,00 0,00 0,00
SUPERVISOR/SUPERINTENDENT: RIG NAME & No: FIELD: ACC. FREE: AFE (KD): DAILY (KD): CUM (KD): WELL OBJECTIVE:
A.AISSAOUI / M.B.GUECHOUT TP 202 HASSI MESSAOUD 1494 days 1 003 252 6 725 293 249 DEVELOPMENT
LAST CSG/LNR SHOE: LAST CSG/LNR TOP: LAST FM. TEST/EMW: L. BOP TEST: L.SAFETY MEETG: DAY DRL NPT: CUM DRL NPT: I.SERVICE:
24,000 in @ 238,00 m 0,00 m 05/09/2021 23,50 hr 36,15 days NONE
ACCIDENT / INCIDENT TOPICS:
NO ACCIDENT// NO INCIDENT // 04 STOP CARDS // 00 PTW // 00 JSA.
PERSONNEL DATA
COMPANY NO HOURS NAMES COMPANY NO HOURS NAMES
SONATRACH (SH/DDO) 2 0,00 Y.MENNAI+A.AISSAOUI MI SWACO (MUD ENGINEER) 2 0,00 K.ZEKRI + F.FRIEKH
MI SWACO (SOLID CONTROL) 1 0,00 H.MAKHLOUFI SH/DDO COMPAGNONNAGE 3 0,00 S.M.TELLI+C.HEDDAR, S.SAMI
MI SWACO (WASTE MANAGEMENT) 4 0,00 R.ZID HABICHE+H.MEKHLOUFI+Y.KARKABOU+I.GUERACHE+A/R.GUERACHE
ENSP MUD LOGGING 4 0,00 R.MESSAOUDI+M.BENAMEUR+M.BOUAZ+B.B
CIEPTAL 21 0,00 I. BENADDA SECURITY (PSG) 26 0,00 R. KHALFAOUI
ENTP 41 0,00 A.MAOUCHE SOFIALINE WATER WELL 3 0,00 F.RACHDI+B.BOUDINA+A.BOUDINA
SH/DDO CONFINEMENT 1 0,00 T.BENBAKRETI NPS (CEMENT CREW) 3 0,00 S/A.KERROUM+S.GUERRAS+L.CHOUAIB
OPERATIONS SUMMARY
FROM-TO HRS PHASE CODE SUB DESCRIPTION FROM-TO NPT NPT DETAIL NPT Co Op Co BILL
00:00-00:30 0,50 22" 21 P J CANRIG/TOP DRIVE SERVICE 225,0-225,0 ENTP T1
00:30-03:00 2,50 22" 06 X P CONT. MAKE UP AND RIH OEDP W/BULL NOSE 225,0-365,0 DPRB STAB SH/FOR ENTP T1
* Washing down to tag bottom@395m, Q=1000lpm, SPP=20Psi - 50% return -
* Ajust cement string@365m
03:00-04:30 1,50 22" 12 X V RIG UP CIRC.HEAD & NESR/CMT LINE AND TEST IT AT 3000PSI -Ok- 365,0-365,0 DPRB STAB SH/FOR NPS T2
04:30-05:00 0,50 22" 05 X J PUMP 25m3 LCM PLUG (650kg/m3) - 50% RETURN - 365,0-365,0 DPRB STAB SH/FOR ENTP T1
* Q=800lpm, SPP=20psi
05:00-06:30 1,50 22" 12 X K SET LOSSES CMT PLUG N°4 (NO RETURN) 365,0-365,0 DPRB STAB SH/FOR NPS T1
* Pump 06m3/fresh water
* 30m3/slurry 1.58sg
* Displace slurry with 1,5m3 of water
06:30-10:00 3,50 22" 06 X I POOH OEDP TO SURFACE (STATIC LEVEL AT SURFACE) 365,0-0,0 DPRB STAB SH/FOR ENTP T1
* Circulate @24" casing shoe (Q=1000lpm / SPP=30psi) - No return -
* Fill up the well with 10m3 WBM
10:00-16:00 6,00 22" 06 X F MAKE UP & RIH 22" SLICK BHA 0,0-380,0 DPRB STAB SH/FOR ENTP T1
* R-run Bit service type: T11CPT SN°D253635
* Washing f/234m to 380m, Q=1000lpm, SPP=580Psi -full return-
* Tag top of cement at 380m (Theorical top cement @243m)
16:00-17:30 1,50 22" 05 X C CIRCULATE AT DIFFERENT FLOW RATES & EVALUATE LOSSES 380,0-380,0 DPRB STAB SH/FOR ENTP T1
Q=1000lpm, SPP=200psi -full return-
Q=2000lpm, SPP=400psi -full return-
Q=2500lpm, SPP=600psi -full return-
17:30-17:45 0,25 22" 02 X B START DRILL OUT CEMENT 380,0-380,0 DPRB STAB SH/FOR ENTP T1
* Total loss @380m
17:45-21:00 3,25 22" 06 X I POOH 22" SLICK BHA FREELY TO SURFACE 380,0-0,0 DPRB STAB SH/FOR ENTP T1
* Lost volume while pulling out 40m3
* Bit dull grading: 1-1-WT-A-E-I-NO-BHA
21:00-00:00 3,00 22" 06 X P MAKE UP AND RIH OEDP W/BULL NOSE 0,0-360,0 DPRB STAB SH/FOR ENTP T1
* Washing down to tag TOC @380m (Q=1000lpm, SPP=60Psi) - No return -
* Ajust cement string@360m
REMARKS:
**************************** DRILLING WITH TOP DRIVE / CANRIG/500T *****************************************************************************
** TD @3494m PLANNED IN 45 DAYS/ACTUAL DAYS=39.25 DAYS
** NPT (DAILY/CUMUL)= 23.50hrs/36.15days (0.49+30.73+3.21=36.15days)
** ENTP T3 (daily // monthly // cumul) = (0.0 hrs // 11.75 hrs // 0.49days)
** ENTP NR (daily // monthly // cumul) = (0.0 hrs // 0.0 hrs // 00days)
** SH/DDO NPT (DAILY/CUMUL)=23.50hrs//32.42days,SLS/SIDE TRACK NPT (DAILY/CUMUL)=00hrs//3.21days
** Drilling 26" to csg pt : Planned in (4.69 days) -------------Real: (39.25 days) -in progress
****************************** SIDE TRACK DATA ***********************************************************************************************************
** Stuck pipe at 367m,back off,TOF at 150m,blind side track n°1 F/61m T/372m (totco measure:0.5°/92m,0.2°/102m,0.2°/ 111m,0.1°/122m,0.5°/152m,0.8°/180m,0.6°/307m,0.4°/350m)
** Stuck pipe at 359m,back off,TOF at 154m,blind side track n°2 F/70m T/239m (totco measure:0.5°/97m,1.5°/107m,1.5°/122m,1°/142m,1°/239m)
** While running 24'' csg column, got stuck @ 66m (6m below 30" csg shoe), unstuck & pooh,wiper trip w/two type of packed hole bha rih csg with drag to bottom
* Final well TD planned to be reached in (45 days)
***************************** WATER SUPPLY & FUEL STORAGE *****************
* WATER WELL: OMJH116 (27m3/h,2.5km PEHD line)
* BAYAT:water well pump and electrical connections/SOFIALINE:Generator,cabin and guardians
SUPERVISOR/SUPERINTENDENT: RIG NAME & No: FIELD: ACC. FREE: AFE (KD): DAILY (KD): CUM (KD): WELL OBJECTIVE:
A.AISSAOUI / M.B.GUECHOUT TP 202 HASSI MESSAOUD 1494 days 1 003 252 6 725 293 249 DEVELOPMENT
LAST CSG/LNR SHOE: LAST CSG/LNR TOP: LAST FM. TEST/EMW: L. BOP TEST: L.SAFETY MEETG: DAY DRL NPT: CUM DRL NPT: I.SERVICE:
24,000 in @ 238,00 m 0,00 m 05/09/2021 23,50 hr 36,15 days NONE
ACCIDENT / INCIDENT TOPICS:
NO ACCIDENT// NO INCIDENT // 04 STOP CARDS // 00 PTW // 00 JSA.
* FUEL: (Rig= 66m3/Camp= 25m3), Water Storage:180m3
***************************** SH & SERVICE COMPANIES MATERIALS ON LOCATION *****************
** SH PROGRAM MATERIAL
** 63 CSG 18"5/8 87.5# J55 + 210 CSG 13"3/8 68# N80 BTC + 2 P. JT 9"5/8 47# BTC + 1 P.JT 13"3/8 68# BTC + 06 CSG 24" API5L GR X52 PSL2 (QUICK LOCK) + 10 CSG 24"
(WELDING TYPE)
** NESR (150tons cmt G,1500kgs Cacl2, 100kgs NR1,50 litres DAF-1, 600litres CTX15 and all eqpts), MI (mud cabin&pdts/wast management), ENSP/MLU,SECURITY/PSG
(guardians&vigils camp)
** BAKER (CARGO BOX - 8' x 4' + ELEVATOR SIDE DOOR VARCO SLX 250T 24" + HANDLING SLIPS CASING UC3 200T 24" + BOWL SPIDER 200T 24" )
** BAKER's BOX contains 04 Radioactive sources (4702NK -4703NT-4717NF-4718XB)
**************************** RENTAL EQPT ******************************************
** G-ENERGY 9"1/2 SHOCK TOOL SN°: ST950-0004 + 03 X 21"15/16 STRING STABILIZERS SN°:(OGID-18627 , OGID-18628 , OGID-18633)
**************************** RECEPTION, BACKLOAD & REQUIREMENT **************************
***************************** MISSING EQPTS & PERSONNEL ENTP *****************
* ENTP Must Urgently Bring and install New Main Camp Kitchen with all Accomodations ***(Very bad condition)***
* ENTP to install & fix Air Conditionors in Rooms
* SH/SV's Office and Rooms on Rig site Camp in Bad condition : Must be changed in Next Rig Move
***************************** REMARK *****************
* A Lot of Dust spread arround the Rig site area due to Bad Platform Compaction