Daily Drilling Report

DANAN OILFIELD DEVELOPMENT


General Data
Country/ Province Iran / Ilam Well Type Development W.S.S. Day/ Night H.Ahmadi / B.Hemati Report No. 227
Field/ Well No. DANAN-DA-14 Spud Date/ Time 1399/07/09 / 23:00 Operations / Area Manager M.Amini / I.Birgani Report Date 05/14/2021 (1400/02/24)
Rig Name NOOR 2 Est. Rig Days 138 Geologist R.Kashanian / - Actual Rig Days 227
EPD Contractor MAPNA Hole Section 5 7/8" ICOFC Rep M.Baghaee / A.Skandari
Act Rig Days less
93 Days + 6 Hrs
Client ICOFC Section Start Date 1399/10/17- 10:00 Senior/ Night Toolpusher A.Afroozi / Gh.Shojaee NPT

Well Data Bit Data Mud Data


N (m) 3,612,265.00 Bit No. Mud Type F.WTR
Location (UTM):
E (m) 734,134.00 Bit Size TCI/ MT/ PDC MW Min / Max (pcf) 63
Project TD (m): 3509 Bit Manufacture Flow Line Temp. (deg F) P.CH.
R.T.E (m) G.L.E (m) 261 252 Bit Type Funnel Vis (sec/qrt) 27
Morning Depth (m) 3484 Bit Serial No. Fann 600 -
Mid Night Depth (m) 3484 IADC Code Fann 300 -
Previous Depth (m) 3484 Nozzle Number * Size ( /32 in) Fann 200/ 100 -
Drilled Interval (m) 0.0 W.O.B (klb) Fann 6/ 3 -
Drilling Time (hr) 0.0 RPM / Total bit RPM PV (cp) -
Average ROP (m/hr) #DIV/0! Torque (klb.ft) YP (lb/100ft^2) -
Cum. DRLG Time (hr) 759.0 Pump Type GEL 10 s/ 10 min/ 30 min -
Estimated / Actual Rig Days 138 227 Pump Liner Size (in) API Fluid Loss (cc/30 min) N.C
KOP (m) - Flow Rate (gpm) Mud Cake Thickness (1/32") -
Last Formation MD TVD (m) Sarvak 3386 Standpipe Pressure (psi) Oil % -
Lithology Lst TFA (in2) Water % -
Last casing/ liner shoe 5" / 2829 m Jet Velocity (ft/s) Solid/ Sand Content (%) -
Last liner lap (m) 5" L.Lap @ 2634 m Bit Daily Drilled (m) Salinity(ppm)/Chlorides (mg/l) / 8000
Last FIT TVD (m) EMW (pcf) 2469 85 Bit On BTM Hours PH / MBT 12 /
Costs Today Well's Total Cum Drill Out CMT/ Ream (m) Total Hardness/Calcium (mg/l) 800 / 700
Day rate Cum Drill Out CMT/ Ream (hr) KCl (%WT)/ Glycol (%Vol) -
Mud & Cement Bit Cum. Drilled (m) Vol. in Hole (bbl) 609
Bit Bit Cum. Hours Vol. in Pits (bbl) 1166
Cas/Tub W/H Bit In / Bit Out(m) Mud Sys./ Daily Made (bbl) 834 / 0
Service Bit Dull Condition Form. Loss/ Mud Pump Repair 0/0
Total Weight Below Jar in mud (klb) Evap./ Shaker / Pit Cleaning 5/0/0
Mud Materials & Chemicals BHA# Dump/ Trip/ Centrifuge/ Other 0 / 12 / 0 / 0
Material Type Unit Rec/ Sent Used STK Item Description Length (m) OD (in) ID (in) Cum. L. (m) Total Loss 17
BARITE 1.5 MT 0 POB
BENTONITE 1 MT 0 MDCO 4
SODA ASH 25 kg 23 ICOFC 6
SALT (NaCl) 1 MT 39 Services Catering 16 14
CaCO3 (weight agent) 1 MT 14 Rig crew Guests 40 3
CAUSTIC SODA 25 kg 19 Casual labors 7
CITRIC ACID 25 kg Drivers 10
Xanthan Gum 25 kg 14 Security 14
G.Starch 25 kg 104 Total 114
Drilling Detergent 55 Gal 0 HSE
NUT PLUG F/M/C 25 kg / 1 MT 0 HSE Cases Daily Cum
Starch HT 25 kg LTI free days 1 227
KCl 1MT Man-hours 1368 666696
LIME 25 kg 40 BHA #81 LTI Accidents 0
CaCO3 (F/M/C) 25 kg / 1 MT 0 Description length(m) OD (in) ID (in) Cum. L. (m) Non LTI Accidents 0 3
MICA F/ M/ C 25 kg / 1 MT 0 Mule Shoe 1.70 5" 2.25" 1.70 BOP Drill 1400/02/19 6
SHELL Fish F-M-C 25 kg / 1 MT 0 7" RTTS Packer (BTM To Center) 0.80 5.77" 2.25" 2.50 H2S Drill 99/09/23 1
PAC-LV/R 25 kg 0 7" RTTS Packer (Center To Top) 0.40 5.77" 2.31" 2.90 Fire Drill
BIOCIDE 55 Gal RTTS Safety Jt 1.23 5" 2.31" 4.13 Medevac Drill
SODIUM BICARB 25 kg 8 Big John Jar 1.59 5" 2 1/4" 5.72 Stop Card 3 1050
SPERSENT CF 25 kg Hydraulic By Pass (Full Close) 2.11 5" 2 1/4" 7.83 PJSM 0 859
PIPELAX 55 gal 4 Gauge carrier 2.13 5" 2 1/4" 9.96 Toolbox Meeting 2 720
Defoamer 55 gal 4 LPR-N Tester Valve 4.84 5" 2 1/4" 14.80
OYSTER SHELL COARSE 25 kg Sleeve Type Drain Valve 1.05 5" 2 1/4" 15.85
Fiber lock 25 kg 0 RD Safety Circulating Valve 6 kpsi 1.74 5" 2 1/4" 17.59
CORROSION INHIBITOR 55 gal 4 RD Circulating Valve 6.5 kpsi 1.11 5" 2 1/4" 18.70
XOS 0.28 5" 2 1/4" 18.98
15 STD 3 1/2" DPs 432.83 3.5" 2.764" 451.81 BOP Test
Cement & Cement Additive XOS 0.95 6.5" 2-3/8" 452.76 LAST BOP TEST Date 1400.02.06
Mat. Type Unit Rec/ Sent Used STK Days Since Last BOP Test 18
CMT "G" Delijan sx 1000 Pumps Data
CMT "G" Kerman sx 0 Pump # 1 Pump # 2 Pump # 3
Chemical wash can 0 Make KLF KLF KLF
Defoamer (5gal) can 0 DP, HWDP & DC Data Type F1600 F1600 F1600
Dispersant FR-01 sx 0 Size (in) Grade Nominal Weight (ppf) Power (hp) 1600 1600 1600
Spacer SPC-01 sx 0 DP 5 3-1/2 G-105 / S-135 G-105 19.5 13.3 Liner Size (in) 6 6 7
Mutual solvent Dr 0 HWDP Stroke (in) 12 12 12
Accelerator S-01 sx 0 DC 3-1/8 4 3/4 20 47 Max Press (psi) 4500 4500 3500
Light WT Add. LWA-01 Dr 0 Down Hole Equipment
Heavy WT Add LWA-01 B.Bag 0 Equipment (Quantity, OD and Description) ID (in) Serial Number Cum Drlg (hr) Cum W&R/ D/O (hr)
Cement Equipment 4 3/4" D.Jar 2 5060036 0.0 0 / 31.5
1771150009-1771100025-1771100027-177150001-1771100014-
Equipment Unit Rec Send STK 26 Jts 3 1/8" DC 1 1/2 1771150017-1771100003-1771150010-1771150002-1771100009 0.0 0 / 39
1771100030-1771100048-1771100055-1771100002-1771100023-
Cement Unit no 0 12Jts 4-3/4" DC 2 , 2-1/4 1771100015-1771100044-1771100057-1771100011-1771100031- 0.0 0 / 30
1771100038-1771100022
Solution Tank no 0
CMT Silo no 5 Solid Control Equipment
Hook Load Data
Air Compressor no 0 Equipment Working Time (hr) Remarks
Surfactant drum 0 Shakers 1 / 2 / 3 0 0 0 170-170-140 / 170-140-140 / 170-14H.L (Klb) Pump On Pump Off
Fuel & Water Desilter / Desander / Degasser 0/0/0 Pick Up
Fluid Type Unit Rec. Used STK Mud Cleaner 320-320-320 (API) Slack-Off
DIESEL Liter 2,500 38100 Centrifuge #1 / #2 0 0 Rotation
Drill Water bbl 1700 Super Clone TDS & Block Weight 58 Klb
KOP : Survey Casing Data
No. MD (m) INC (deg) AZ (deg) TVD (m) NS EW DLS Remark Shoe Liner Lap
Casing Size (in) Grade Weight (ppf) Thread Length (m)
1 57.0 0.0 TOTCO Depth m) (m)
2 85.0 0.0 TOTCO 20 K-55 106.5 WSP-Big 57.0 57.0
3 940.0 0.5 TOTCO 13 3/8 N-80 & T-95 68 & 72 BTC 1970.0 1970.0
4 1570.0 2.5 TOTCO 9 5/8 HC-95SS & T-95 & L-80 53.5 & 43.5 & 47 WSP-3T & PJE 2469.0 2469.0
5 1884.0 2.5 TOTCO 7 L-80 29 PJE 1007.0 3388.5 2381
6 5 L-80 18 WSP-FJ 189.00 2829 2640
7 5 Tie back L-80 18 VFJ 4.06 2637
8 5 Tie back #2 L-80 18 VFJ 4.48 2634
Daily Drilling Report

DANAN OILFIELD DEVELOPMENT

Formation Data Well Control (SCR)

Forecasted Top MW (pcf)/ FV


Formation Name Actual Top (m) Lithology Pump # SPM# 1 SPP 1 (psi) SPM# 2 SPP 2 (psi) Depth (m) Time
(m) (s/qrt)

Aghajari Surf. Surf. Rd Mrl + Sst + Gy Mrl + Anhy 1

Gachsaran 7- 5 1827 1938.0 Anhy + R.Mrl + G.Mrl 2

Gachsaran 4 - 2 2137 2252.0 Slt + Anhy + Mrl 3

Gachsaran 1 (Cap Rock) 2412 2426.0 Anhy + Mrl + Lime + Cly + Shale Wellhead BOP Test Record
Asmari 2474 2496.0 L.st.+Anhy+Dol L.st+Arg.L.st+ Cl.st. Component Top FLG (Size/ WP) BTM FLG (Size/ WP) Component Type and Size Test Pressure

Kalhur 2548 2573.0 Arg.L.st + Anhy + Cl.st. + Dol.L.st.+ L.st+ G.Mrl + Salt Xmas Tree Annular 5k - 13-5/8" 2500

Pabdeh 2813 2816.0 Arg. Lst THS 11" 5k 13-5/8" 3k Top Rams 10k- 2-7/8" * 5" VBR 4500

Gurpi 3283 3262.0 Lst DSA Pack off Blind Rams 10k - 13-5/8" 4500

Ilam 3329 3305.0 Lst CHS 13-5/8" 3k 21-1/4" 2k Bottom Rams 5"fix, 10k - 13-5/8" 4500

Sarvak 3410 3386.0 Lst CHH 21-1/4" 2k welded Choke Manif. 10k 4500

Well TD 3509 3484.00 Lst Wear Bushing Size: 11" IN/ OUT: OUT Accumulator 3K Function test

Received

Sent

Request 6" Metal muncher junk mill (2No.) + 6" R.Bit.

Outstanding 1 Jt 7" Long flow coupling (29#, L-80 13CR, N.VAM) as spare part.

Detail of Operations within Last 24 hours


Code /Activity Hrs From To Hrs Code Remarks
1. Rigging and Moving 00:00 Cont. RIH 7" Hydro-Mechanical Bridge Plug (Exxon Dena Co.) W/5" drifted DPs F/520 to 2588m W/NL-NG.
2. Drilling Set brigde plug at 2588m (14m above top of CMT plug) & check it, "ok". Release running tools, POOH to surface while
3. Hole Conditioning 16:30 16.5 22N OBS. The well @ 7"L.Lap, "static" & C.C.W.H. W/NL-NG, L/D running tools.
4. Coring 16:30 Prepare DST tools, RIH W/7" DST tools (full bore- MDCo) as BHA#81 followed by 5" DPs to 880m while F/U string
5. Mud Condition & Circ. 24:00 7.5 22N W/ 63pcf F.WTR as cushion fluid every 5 STDs W/NL-NG.
6. Trips

7. Rig Services

8. Slip and Cut DRLG Line

9. Deviation Survey

10. Logging

11. Running Casing/ Liner Note: Release Exxon Dena Co. crew @ 1400.02.24 on 17:00 O'clock.
12. Cementing

13. Nipple up/ down

14. BOP Test

15. Formation Testing

16. Directional Drilling

17. Well Completion

18. Perforation

19. Stimulation

20. Production & Well Testing

21. Suspension/Abandonment

22. NPT 24.0


23. Other

Note: Personnel Shortage On Board : 1 Derrickman + 1 Roughneck + 2 Crane Operator + 1 Mud logger (M.L.Crew).
TOTALLY 24.0 24.0
From To Hrs Code Morning Report
00:00 Cont. RIH 7" DST Tools (full bore- MDCo) F/880 to 1620m while F/U 1500m of string W/ 63pcf F.WTR as cushion fluid every 5 STDs
06:00 6.0 22N W/NL-NG. (Cushion fluid height: 1500 m).

Total (Hrs) 6.0


Operations Summary

Cont. RIH 7" Hydro-Mechanical Bridge Plug (Exxon Dena Co.) to 2588m, Set brigde plug at 2588m (14m above top of CMT plug) & check it, "ok". Release running tools, POOH to surface, L/D
running tools. RIH W/7" DST Tools (full bore- MDCo) to 880m while F/U string W/ 63pcf F.WTR as cushion fluid every 5 STDs W/NL-NG.

Next Operations
RIH W/7" DST tools (full bore) to 2570m, perform 7" LNR aginst 7" B.Plug dry test, POOH to surface.
Operations Reference Code
MAPNA Drilling Co.
Code/
Main Activity Details
Subcode
1 Rigging & Moving
2 Drilling
3 Hole Conditioning
4 Coring
5 Mud Conditiong & Circulation
5A Preparing Mud Making Mud
5B Displacing the Hole Displacing the well with new mud
5C Mud Circulation Circulation of mud to clean the hole, allow cuttings to reach to surface, etc.
5D Mud Condition Circulation of mud in order to treat the mud condition working on mud properties
5E Loss Control All Activities Associated With Circulate and Condition due to lost circulation
5F Pit Management Cleaning pits, Transferring mud between pits (if cannot be done while doing other operations)
6 Trips
6A Trip in the Hole Run in hole on Drill pipes with drilling or other BHA's
6B Trip out of the Hole Pull out of hole on Drill pipes with drilling or other BHA's
6C Short Trip (in) RIH with bit to condition the drilled hole section
6D Short Trip (Out) POOH with bit to condition the drilled hole section
6E Make up BHA Preparing, Picking up and Making up the BHA (except directinal drilling BHA)
6F Lay Down BHA Breaking out and Laying Down BHA (except directinal drilling BHA)
6G Pick up Drill Pipe Picking up and Making up Drill Pipes joint by joint, making stand and rack back them
6H Lay Down Drill Pipe Breaking out and Laying down Drill Pipe s joint by joint
6I Pump POOH POOH with Pumping (no reaming)
6J Wash Down RIH with Pumping (no reaming)
6K Wear Bushing Putting/ Retrieving Wear Bushing
6L Flow Check Observing the well for any flow while tripping (at BHA and shoe)
7 Rig Services

7A Rig Services Service or lubricate of TDS in limited time according to the contract
8 Slip & Cut Drilling Line
9 Deviation Survey
10 Wireline Logging
11 Running Casing/ Liner
12 Cementing
13 Nipple up/ down
14 BOP Test
15 Formation Testing
16 Directional Drilling
17 Well Completion
18 Perforation
19 Stimulation
20 Production & Well Testing
21 Suspension/ Abandonment
22 NPT
22A Waiting on Client
22B Waiting on EPD Contractor
22C Waiting on Service Company
22D Waiting on Rig Contractor
22E Stuck
22F Fishing and milling All preparing, assembling of fishing equipment to recover of junks or fish from a wellbore
22G Side-Tracking All operations related to Sidetracking Original Hole to Bypass a Fish (using cement plug or whipstock)
22H Well Control Issue
22I Washout Including trip out and trip in until reaching previous depth
22J String Plug Including trip out and trip in until reaching previous depth
22K Rig Repair
22L Wait On Weather
22M Force Majeure Other Force Majeures out of Client and Operator's Control
22N Other Down Hole Problem NPTs which is not within the above mentioned Categories
23 Others