GRTA TIE IN SCOPE- NDT PLAN

RT LAMINATIO Exposure Total Minutes


TIE-IN TIE-IN NO. OF Welding Completion NDT Source Total Minutes
Sl.No TIE-IN TYPE JOINT CONFIGURATION LOCATION Planned N CHECK Source Type Time/joint (Exposure+Set up RT Crew REMARKS
NUMBER PERIOD JOINTS Time METHOD Strength
Date STATUS (Minutes) Time)/Joint

Film D4 .
198-FLANGE TO PIPE Single exp time - 3 mints
TP- IR192 with SCAR
1 GRTA 8" Welded, Sch 20 2 FW37-ELBOW TO PIPE New Unit-51/52 1/30/22 1:00 PM 31-Jan-22 Completed RT 20Curi 9 60 120 RT Crew-01 No of exp - 03
026A/027/198 Shielding
The site prepataion time
approximate 45 mints
FW-36-PIPE TO EBOW
TP- FW20-ELBOW TO PIPE IR192 with SCAR
2 GRTA 8" Welded, Sch 20 3 New Unit-51/52 2/1/22 6:00 AM 2-Feb-22 Completed RT 20Curi 9 60 120 RT Crew-01
026A/027/198 FW-17-TEE TO PIPE Shielding
FW-5-ELBOW TO PIPE
SFD 16 inches
1 1/2" Welded, Sch 80 151A-TEE TO PIPE IR192 with SCAR Film D4
3 TP-151A/B GRTA 2 Unit-22 1/30/22 9:30 PM 31-Jan-22 Completed RT 20Curi 27 75 150 RT Crew-02
151B-PIPE TO PIPE Shielding Considered 03 exp per jt

IR192 with SCAR


4 TP-130A/B GRTA 8" Welded, Sch 20 2 FLANGE TO PIPE Unit-51 1/30/22 6:30 AM 31-Jan-22 Completed RT 20Curi 9 60 120 RT Crew-01
Shielding

57A-PIPE TO PIPE
5 TP-057A/B GRTA 8" Welded, Sch 20 2 Unit-51 1/30/22 7:30 AM 31-Jan-22 Completed RT Selinium 75 50Curi 11.5 30 60 RT Crew-03
57B-TEE TO PIPE

57A-TEE TO PIPE IR192 with SCAR


6 TP-060A/B GRTA 2" Welded, Sch 80 2 Unit-51 1/31/22 12:00 AM 2-Feb-22 Completed RT 20Curi 33 80 160 RT Crew-01
57B-PIPE TO PIPE Shielding

112A-REDUCER TO PIPE Unit-51 Pipe


7 TP-112A/B GRTA 6" Welded, Sch 40 2 1/30/22 8:00 AM 31-Jan-22 Completed RT Selinium 75 50Curi 8 30 60 RT Crew-03
112B-PIPE TO PIPE rack

Unit-51 Pipe
8 TP-113A/B GRTA 6" Welded, Sch 40 2 FLANGE TO PIPE 1/30/22 11:00 PM 31-Jan-22 Completed RT Selinium 75 50Curi 8 30 60 RT Crew-03
rack

Unit-51 Pipe
9 TP-182A/B GRTA 10" Welded, Sch 20 2 FLANGE TO PIPE 1/30/22 8:30 AM 31-Jan-22 Completed RT Selinium 75 50Curi 15 35 70 RT Crew-03
rack

Unit-51 Pipe IR192 with SCAR


10 TP-114A/B GRTA 4" Welded, Sch 40 2 FLANGE TO PIPE 1/31/22 5:30 AM 1-Feb-22 Completed RT 20Curi 3 40 80 RT Crew-01
rack Shielding

Unit-51 Pipe IR192 with SCAR


11 TP-115A/B GRTA 4" Welded, Sch 40 2 FLANGE TO PIPE 1/31/22 11:00 PM 1-Feb-22 Completed RT 20Curi 3 40 80 RT Crew-01
rack Shielding

Unit-51 Pipe IR192 with SCAR


12 TP-039A/B GRTA 2" Welded, Sch 80 2 PIPE TO FLANGE 1/31/22 2:00 PM 2-Feb-22 Completed RT 20Curi 33 80 160 RT Crew-02
rack Shielding
132A-PIPE TO TEE Unit-51 Pipe IR192 with SCAR
13 TP-132A/B GRTA 1" Welded, Sch 80 2 1/31/22 4:00 PM 2-Feb-22 Completed RT 20Curi 28 70 140 RT Crew-02
132B-FLANGE TO PIPE rack Shielding
133A-PIPE TO PIPE Unit-51 Pipe IR192 with SCAR
14 TP-133A/B GRTA 1" Welded, Sch 80 2 1/31/22 6:00 PM 3-Feb-22 Completed RT 20Curi 28 70 140 RT Crew-01
133B-FLANGE TO PIPE rack Shielding
Unit-51 Pipe IR192 with SCAR
15 TP-131A/B GRTA 8" Welded, Sch 20 2 FLANGE TO PIPE 1/30/22 6:30 PM 1-Feb-22 Completed RT 20Curi 9 35 70 RT Crew-02
Rack B/L Shielding
Unit-51 Pipe IR192 with SCAR
16 TP-105 A/B GRTA 6" Welded, Sch 40 2 FLANGE TO PIPE 1/31/22 4:30 AM 1-Feb-22 Completed RT 20Curi 6 45 90 RT Crew-02
Rack B/L Shielding
Unit-51 Pipe IR192 with SCAR
17 TP-129A/B GRTA 6" Welded, Sch 40 2 FLANGE TO PIPE 1/31/22 6:30 AM 1-Feb-22 Completed RT 20Curi 6 45 90 RT Crew-02
Rack B/L Shielding
Unit-51 Pipe IR192 with SCAR
18 TP-127A/B GRTA 8" Welded, Sch 20 2 FLANGE TO PIPE 1/30/22 9:30 AM 1-Feb-22 Completed RT 20Curi 9 60 120 RT Crew-01
Rack B/L Shielding
Unit-53 Pipe
19 TP-047A/B GRTA 10" Welded, Sch 20 2 TEE to PIPE 1/30/22 7:00 AM 1-Feb-22 Completed RT Selinium 75 50Curi 15 35 70 RT Crew-03
rack
Unit-53 Pipe
20 TP-062A/B GRTA 8" Welded, Sch 80 2 TEE to PIPE 1/30/22 8:30 PM 1-Feb-22 Completed RT Selinium 75 50Curi 24 50 100 RT Crew-03
rack
181A-TEE TO PIPE Unit-53 Pipe
21 TP-181A/B GRTA 8" Welded, Sch 20 2 1/30/22 9:30 AM 1-Feb-22 Completed RT Selinium 75 50Curi 9 35 70 RT Crew-03
181B-FLANGE TO PIPE rack
Unit-53 Pipe IR192 with SCAR
22 TP-071 GRTA 2" Welded, Sch 80 1 FLANGE TO PIPE 1/30/22 9:00 PM 3-Feb-22 Completed RT 20Curi 33 80 80 RT Crew-01
rack Shielding

IR192 with SCAR


23 TP-051 CRUDE 3" Welded, Sch 80 2 FLANGE TO PIPE Unit-51 1/20/22 4:30 PM 21-Jan-22 Completed RT 20Curi 3 60 120 RT Crew-01
Shielding

IR192 with SCAR


24 TP-045 CRUDE 3/4" Welded, Sch80 2 FLANGE TO PIPE Unit-51 1/20/22 4:30 PM 21-Jan-22 Completed RT 20Curi 20 50 100 RT Crew-03
Shielding
IR192 with SCAR
25 TP-220A/B RFCC 1 1/2" Welded, Sch 80 2 FLANGE TO PIPE Unit-53 1/21/22 4:30 PM 22-Jan-22 Completed RT 20Curi 27 75 150 RT Crew-02
Shielding
Unit-53 Pipe
26 TP-007A/B GRTA 16" Welded, Sch 40 2 TEE to PIPE 1/30/22 7:30 PM 31-Jan-22 Completed PAUT+TOFD - - - 60 150 PAUT Crew-01
rack

27 TP-148A/B GRTA 16" Welded, Sch 40 2 TEE to PIPE Unit-22 1/31/22 6:00 AM 1-Feb-22 Completed PAUT+TOFD - - - 60 150 PAUT Crew-01

28 TP-147A/B GRTA 24" Welded, Sch STD 2 TEE to PIPE Unit-22 1/31/22 7:00 PM 1-Feb-22 Completed PAUT+TOFD - - - 60 150 PAUT Crew-01

TOTAL 56 TOTAL Time 3030 50.5


GRTA TIE IN SCOPE- NDT PLAN

RT LAMINATIO Exposure Total Minutes


TIE-IN TIE-IN NO. OF Welding Completion NDT Source Total Minutes
Sl.No TIE-IN TYPE JOINT CONFIGURATION LOCATION Planned N CHECK Source Type Time/joint (Exposure+Set up RT Crew REMARKS
NUMBER PERIOD JOINTS Time METHOD Strength
Date STATUS (Minutes) Time)/Joint

TOTAL RT Time 2580 43

TOTAL PAUT Time 450 7.5

Hours
GRTA RT Time 2210 36.83