SUNLEY ENGINEERING & CONSTRUCTION CO., LTD.

Foundation Works for Ho Man Tin Station Package Two Property Development at KIL No. 11264

Master Programme (Rev.3)


ID Task Name Duration Start Finish

Mar '20Apr '20May '20Jun '20Jul '20Aug '20Sep '20Oct '20Nov '20Dec '20Jan '21Feb '21Mar '21Apr '21May '21Jun '21Jul '21Aug '21Sep '21Oct '21Nov '21Dec '21Jan '22Feb '22
1 Key Date 8 days Thu 19/3/20 Fri 27/3/20
2 Notification of Contract Award 7 days Thu 19/3/20 Wed 25/3/20 19/3 25/3
3 Date of possession of the site 0 days Fri 27/3/20 Fri 27/3/20 27/3
4
5 Total Contract Period 540 days Fri 27/3/20 Fri 17/9/21
6
7 Preliminaries 66 days Tue 14/4/20 Thu 18/6/20
8 Carry out condition survey for existing structures 42 days Tue 14/4/20 Mon 25/5/20 14/4 25/5
9 Prepare & submit condition survey report 7 days Fri 24/4/20 Tue 19/5/20 24/4 19/5
10 Carry out CCTV for existing drainage 7 days Mon 27/4/20 Sun 3/5/20 27/4 3/5
11 Prepare & submit CCTV survey report 7 days Mon 4/5/20 Sun 10/5/20 4/5 10/5
12 Set up site office 14 days Fri 17/4/20 Thu 30/4/20 17/4 30/4
13 General site clearance 14 days Wed 22/4/20 Tue 5/5/20 22/4 5/5
14 Installation of monitoring checkpoints 30 days Wed 20/5/20 Thu 18/6/20 20/5 18/6
15
16 Consent & Design Submission 218 days Fri 27/3/20 Fri 30/10/20
17 Section 1 Temporary steel platform design amendment submission 9 days Tue 5/5/20 Wed 13/5/20 5/5 13/5
18 Section 1 Temporary steel platform design review by consultants 5 days Thu 14/5/20 Mon 18/5/20 14/5 18/5
19 Section 1 Approval and consent application for temporary steel platform design plan 90 days Tue 19/5/20 Sun 16/8/20 19/5 16/8
20 Section 2 Temporary steel platform design amendment submission 15 days Fri 27/3/20 Fri 10/4/20 27/3 10/4
21 Section 2 Temporary steel platform design review by consultants 7 days Sat 11/4/20 Fri 17/4/20 11/4 17/4
22 Section 2 Approval and consent application for temporary steel platform design plan 30 days Sat 18/4/20 Sun 17/5/20 18/4 17/5
23 Hoarding Amendment 30 days Mon 27/4/20 Tue 26/5/20 27/4 26/5
24 Piling design amendment submission (section 1 & 2) 60 days Mon 27/4/20 Thu 25/6/20 27/4 25/6
25 Piling design review by consultants 7 days Fri 26/6/20 Thu 2/7/20 26/6 2/7
26 Approval of amendment for piling design plan (section 1 & 2) 30 days Fri 3/7/20 Sat 1/8/20 3/7 1/8
27 ELS design submission 30 days Mon 18/5/20 Tue 16/6/20 18/5 16/6
28 ELS design review by consultants 7 days Wed 17/6/20 Tue 23/6/20 17/6 23/6
29 Approval ELS design plan 60 days Wed 24/6/20 Sat 22/8/20 24/6 22/8
30 Consent for ELS 30 days Sun 23/8/20 Mon 21/9/20 23/8 21/9
31 Pile cap design submission (section 1 & 2) 60 days Fri 26/6/20 Mon 24/8/20 26/6 24/8
32 Pile cap design review by consultants 7 days Tue 25/8/20 Mon 31/8/20 25/8 31/8
33 Approval pile cap design plan (section 1 & 2) 60 days Tue 1/9/20 Fri 30/10/20 1/9 30/10
34
35 Method Statement Submission and Approval 125 days Fri 27/3/20 Wed 29/7/20
36 Material Handling Plan 16 days Wed 1/4/20 Thu 16/4/20 1/4 16/4
37 Railway Protection Plan 17 days Wed 1/4/20 Fri 17/4/20 1/4 17/4
38 Emergency Plan 20 days Wed 1/4/20 Mon 20/4/20 1/4 20/4
39 Project Safety Plan 16 days Wed 1/4/20 Thu 16/4/20 1/4 16/4
40 Fire Safety Plan 16 days Wed 1/4/20 Thu 16/4/20 1/4 16/4
41 5S Plan 16 days Wed 1/4/20 Thu 16/4/20 1/4 16/4
42 Site office set up 21 days Wed 1/4/20 Tue 21/4/20 1/4 21/4
43 Shrub Felling 21 days Wed 1/4/20 Tue 21/4/20 1/4 21/4
44 Installation of Monitoring checkpoints 47 days Fri 3/4/20 Tue 19/5/20 3/4 19/5
45 Lifting Plan 21 days Fri 27/3/20 Thu 16/4/20 27/3 16/4
46 Open up the existing stub columns 30 days Fri 15/5/20 Sat 13/6/20 15/5 13/6
47 Hoarding works 30 days Wed 1/4/20 Thu 30/4/20 1/4 30/4
48 Timber Scaffolding erection (30m away from MTR structure) 50 days Wed 1/4/20 Wed 20/5/20 1/4 20/5
49 Timber Scaffolding erection (10m away from MTR structure) 55 days Fri 27/3/20 Wed 20/5/20 27/3 20/5
50 Timber Scaffolding erection (within10m from MTR structure) 30 days Fri 8/5/20 Sat 6/6/20 8/5 6/6
51 Predrilling works (30m away from MTR structure) 50 days Wed 1/4/20 Wed 20/5/20 1/4 20/5
52 Predrilling works (10m away from MTR structure) 60 days Wed 15/4/20 Sat 13/6/20 15/4 13/6
53 Predrilling works (within 10m from MTR structure) 30 days Mon 4/5/20 Tue 2/6/20 4/5 2/6
54 Temporary Steel Platform Erection 30 days Fri 22/5/20 Sat 20/6/20 22/5 20/6
55 Piling works (30m away from MTR structure) 30 days Fri 29/5/20 Sat 27/6/20 29/5 27/6
56 Piliing works (10m away from MTR structure) 30 days Fri 5/6/20 Sat 4/7/20 5/6 4/7
57 Piling works (within 10m from MTR structure) 30 days Fri 12/6/20 Sat 11/7/20 12/6 11/7
58 ELS works 30 days Tue 30/6/20 Wed 29/7/20 30/6 29/7

Tender Programme Task Milestone Summary Critical Task

Page 1
SUNLEY ENGINEERING & CONSTRUCTION CO., LTD.
Foundation Works for Ho Man Tin Station Package Two Property Development at KIL No. 11264

Master Programme (Rev.3)


ID Task Name Duration Start Finish

Mar '20Apr '20May '20Jun '20Jul '20Aug '20Sep '20Oct '20Nov '20Dec '20Jan '21Feb '21Mar '21Apr '21May '21Jun '21Jul '21Aug '21Sep '21Oct '21Nov '21Dec '21Jan '22Feb '22
59
60 Hoarding 40 days Mon 11/5/20 Fri 19/6/20
61 Hoarding erection 40 days Mon 11/5/20 Fri 19/6/20 11/5 19/6
62 Completion of hoarding 0 days Fri 19/6/20 Fri 19/6/20 19/6
63
64 Section 1 450 days Fri 27/3/20 Sat 19/6/21
65 Date of comencement 0 days Fri 27/3/20 Fri 27/3/20 27/3
66 Stub Columns Investigation 401 days Fri 1/5/20 Sat 5/6/21
67 Erection of temporary access 14 days Fri 1/5/20 Thu 14/5/20 1/5 14/5
68 Open up the existing stub columns trial 21 days Mon 15/6/20 Sun 5/7/20 15/6 5/7
69 Open up the remaining existing stub columns 100 days Fri 22/1/21 Sat 1/5/21 22/1 1/5
70 Surveying the existing stub columns 14 days Sun 2/5/21 Sat 15/5/21 2/5 15/5
71 Surface protection for the existing stub colums 21 days Sun 16/5/21 Sat 5/6/21 16/5 5/6
72 Submission of investigation report 21 days Sun 16/5/21 Sat 5/6/21 16/5 5/6
73 Completion of stub columns investigation 0 days Sat 5/6/21 Sat 5/6/21 5/6
74
75 Temporary Steel Platform at Section 1 390 days Tue 26/5/20 Sat 19/6/21
76 Pre- Drilling 55 days Tue 26/5/20 Sun 19/7/20
77 Timber Scaffolding erection (30m away from MTR structure) 22 days Tue 26/5/20 Tue 16/6/20 26/5 16/6
78 Timber Scaffolding erection (10m away from MTR structure) 22 days Tue 26/5/20 Tue 16/6/20 26/5 16/6
79 Timber Scaffolding erection (within 10m from MTR structure) 13 days Sun 7/6/20 Fri 19/6/20 7/6 19/6
80 Predrilling Works 30 days Sat 20/6/20 Sun 19/7/20 20/6 19/7
81 Temporary Steel Platform at Section 1 307 days Mon 17/8/20 Sat 19/6/21
82 Mini Piles for Temporary Platform at Section 1 39 days Mon 17/8/20 Thu 24/9/20
83 Submission of BA10 7 days Mon 17/8/20 Sun 23/8/20 17/8 23/8
84 Mini pile works (46 nos) 32 days Mon 24/8/20 Thu 24/9/20 24/8 24/9
85 Construction of Temporary Steel Platform at Section 1 24 days Fri 25/9/20 Sun 18/10/20
86 Temporary steel platform installation 24 days Fri 25/9/20 Sun 18/10/20 25/9 18/10
87 Completion of temporary steel platform at section 1 0 days Sun 18/10/20 Sun 18/10/20 18/10
88
89 ELS and Stub Columns Investigation 249 days Tue 22/9/20 Fri 28/5/21
90 Submission of BA10 7 days Tue 22/9/20 Mon 28/9/20 22/9 28/9
91 Plant mobilization 14 days Mon 5/10/20 Sun 18/10/20 5/10 18/10
92 Installation of pipe pile (63 nos.) 110 days Mon 19/10/20 Fri 5/2/21 19/10 5/2
93 Installation of pipe pile (30 nos.) from lay-by 90 days Mon 19/10/20 Sat 16/1/21 19/10 16/1
94 Installation of pipe pile (26 nos.) from section 2 steel platform 46 days Tue 26/1/21 Fri 12/3/21 26/1 12/3
95 Grout curtain 50 days Tue 2/2/21 Tue 23/3/21 2/2 23/3
96 Submission of BA14 14 days Thu 11/3/21 Wed 24/3/21 11/3 24/3
97 Consent for excavation 28 days Fri 26/2/21 Thu 25/3/21 26/2 25/3
98 Submission of BA10 7 days Sat 20/3/21 Fri 26/3/21 20/3 26/3
99 Excavation and shoring installation including open up the existing stub columns 60 days Sat 27/3/21 Tue 25/5/21 27/3 25/5
100 Surveying the existing stub columns 5 days Sat 22/5/21 Wed 26/5/21 22/5 26/5
101 Surface protection for the existing stub colums 5 days Mon 24/5/21 Fri 28/5/21 24/5 28/5
102 Submission of investigation report 7 days Sat 22/5/21 Fri 28/5/21 22/5 28/5
103 Completion of ELS and stub columns investigation 0 days Fri 28/5/21 Fri 28/5/21 28/5
104
105 Bored Pile 142 days Fri 29/1/21 Sat 19/6/21
106 Submission of BA10 7 days Fri 29/1/21 Thu 4/2/21 29/1 4/2
107 Plant mobilization 7 days Sat 6/2/21 Fri 12/2/21 6/2 12/2
108 Bored pile construction (2 nos.) 56 days Wed 24/3/21 Tue 18/5/21 24/3 18/5
109 Interface & sonic test 14 days Wed 12/5/21 Tue 25/5/21 12/5 25/5
110 Submission of BA14 14 days Wed 19/5/21 Tue 1/6/21 19/5 1/6
111 Selection of piles for coring test 14 days Tue 1/6/21 Mon 14/6/21 1/6 14/6
112 Coring test 5 days Tue 15/6/21 Sat 19/6/21 15/6 19/6
113 Commpletion of bored pile 0 days Sat 19/6/21 Sat 19/6/21 19/6
114
115 Completion of section 1 0 days Sat 19/6/21 Sat 19/6/21 19/6
116

Tender Programme Task Milestone Summary Critical Task

Page 2
SUNLEY ENGINEERING & CONSTRUCTION CO., LTD.
Foundation Works for Ho Man Tin Station Package Two Property Development at KIL No. 11264

Master Programme (Rev.3)


ID Task Name Duration Start Finish

Mar '20Apr '20May '20Jun '20Jul '20Aug '20Sep '20Oct '20Nov '20Dec '20Jan '21Feb '21Mar '21Apr '21May '21Jun '21Jul '21Aug '21Sep '21Oct '21Nov '21Dec '21Jan '22Feb '22
117 Section 2 540 days Fri 27/3/20 Fri 17/9/21
118 Date of comencement 0 days Fri 27/3/20 Fri 27/3/20 27/3
119 Timber Scaffolding erection (30m away from MTR structure) 25 days Tue 26/5/20 Fri 19/6/20 26/5 19/6
120 Timber Scaffolding erection (10m away from MTR structure) 25 days Tue 26/5/20 Fri 19/6/20 26/5 19/6
121 Timber Scaffolding erection (within 10m from MTR structure) 14 days Sun 7/6/20 Sat 20/6/20 7/6 20/6
122 Predrilling works (30m away from MTR structure) 23 days Sat 20/6/20 Sun 12/7/20 20/6 12/7
123 Predrilling works (10m away from MTR structure) 23 days Sat 20/6/20 Sun 12/7/20 20/6 12/7
124 Predrilling works (within 10m from MTR structure) 21 days Mon 22/6/20 Sun 12/7/20 22/6 12/7
125 Temporary Steel Platform at Section 2 211 days Mon 13/7/20 Mon 8/2/21
126 Submission of BA10 7 days Mon 13/7/20 Sun 19/7/20 13/7 19/7
127 King Posts for Temporary Platform at Section 2 -Stage 1 39 days Mon 20/7/20 Thu 27/8/20
128 King Posts installation (8 nos. 305x305x180kg/m) 25 days Mon 20/7/20 Thu 13/8/20 20/7 13/8
129 Temporary steel platform installation 14 days Fri 14/8/20 Thu 27/8/20 14/8 27/8
130 Submission of ICE Cert 1 day Thu 27/8/20 Thu 27/8/20 27/8 27/8
131 King Posts for Temporary Platform at Section 2 -Stage 2 26 days Fri 28/8/20 Tue 22/9/20
132 King Posts installation (6 nos. 305x305x180kg/m) 19 days Fri 28/8/20 Tue 15/9/20 28/8 15/9
133 Temporary steel platform installation 14 days Wed 9/9/20 Tue 22/9/20 9/9 22/9
134 Submission of ICE Cert 1 day Tue 22/9/20 Tue 22/9/20 22/9 22/9
135 King Posts for Temporary Platform at Section 2 -Stage 3 36 days Wed 23/9/20 Wed 28/10/20
136 King Posts installation (7 nos. 305x305x180kg/m) 22 days Wed 23/9/20 Wed 14/10/20 23/9 14/10
137 Temporary steel platform installation 21 days Thu 8/10/20 Wed 28/10/20 8/10 28/10
138 Submission of ICE Cert 1 day Wed 28/10/20 Wed 28/10/20 28/10 28/10
139 King Posts for Temporary Platform at Section 2 -Stage 4 59 days Thu 29/10/20 Sat 26/12/20
140 King Posts installation (12 nos. 305x305x180kg/m) 38 days Thu 29/10/20 Sat 5/12/20 29/10 5/12
141 Temporary steel platform installation 28 days Sun 29/11/20 Sat 26/12/20 29/11 26/12
142 Submission of ICE Cert 1 day Sat 26/12/20 Sat 26/12/20 26/12 26/12
143 King Posts for Temporary Platform at Section 2 -Stage 5 44 days Sun 27/12/20 Mon 8/2/21
144 King Posts installation (5 nos. 305x305x180kg/m) 16 days Sun 27/12/20 Mon 11/1/21 27/12 11/1
145 Temporary steel platform installation 21 days Tue 5/1/21 Mon 25/1/21 5/1 25/1
146 Submission of ICE Cert 1 day Mon 25/1/21 Mon 25/1/21 25/1 25/1
147 BA14 submission 14 days Tue 26/1/21 Mon 8/2/21 26/1 8/2
148 ELS Works 88 days Tue 26/1/21 Fri 23/4/21
149 Installation of pipe pile (88 nos) 77 days Tue 26/1/21 Mon 12/4/21 26/1 12/4
150 Grout curtain 45 days Tue 9/3/21 Thu 22/4/21 9/3 22/4
151 Submission of BA14 14 days Sat 10/4/21 Fri 23/4/21 10/4 23/4
152 Completion of ELS works 0 days Fri 23/4/21 Fri 23/4/21 23/4
153 Socketed H-Piles 111 days Tue 26/1/21 Sun 16/5/21
154 Plant mobilization 4 days Tue 26/1/21 Fri 29/1/21 26/1 29/1
155 Test boring 5 days Sat 30/1/21 Wed 3/2/21 30/1 3/2
156 Socketed H-Pile installation (18 nos.) 42 days Wed 3/2/21 Tue 16/3/21 3/2 16/3
157 Post drill 5 days Wed 17/3/21 Sun 21/3/21 17/3 21/3
158 Submission of BA14 14 days Mon 22/3/21 Sun 4/4/21 22/3 4/4
159 Selection of piles for loading test 14 days Mon 5/4/21 Sun 18/4/21 5/4 18/4
160 Loading Test 28 days Mon 19/4/21 Sun 16/5/21 19/4 16/5
161 Completion of socketed H-pile 0 days Sun 16/5/21 Sun 16/5/21 16/5
162
163 Bored Pile 192 days Wed 10/3/21 Fri 17/9/21
164 Plant mobilization 7 days Wed 10/3/21 Tue 16/3/21 10/3 16/3
165 Bored pile construction (11 nos.) 154 days Wed 17/3/21 Tue 17/8/21 17/3 17/8
166 Interface & sonic test 14 days Wed 11/8/21 Tue 24/8/21 11/8 24/8
167 Submission of BA14 14 days Wed 18/8/21 Tue 31/8/21 18/8 31/8
168 Selection of piles for coring test 14 days Tue 31/8/21 Mon 13/9/21 31/8 13/9
169 Coring test 5 days Mon 13/9/21 Fri 17/9/21 13/9 17/9
170 Completion of bored pile 0 days Fri 17/9/21 Fri 17/9/21 17/9
171
172 Completion of section 2 0 days Fri 17/9/21 Fri 17/9/21 17/9
173
174 Contract completion 0 days Fri 17/9/21 Fri 17/9/21 17/9

Tender Programme Task Milestone Summary Critical Task