Professional Documents
Culture Documents
HAZAMA over 25 y e a r s at r e s e a r c h d i v i s i o n s . He w a s a m e m b e r
April 1996. He is a r e g i s t e r e d c o n s u l t i n g e n g i n e e r . H e is a c i v i l
r e s e a r c h d i v i s i o n s . He w a s also a m e m b e r of 2 n d m i s s i o n of E D O
for t e c h n i c a l e x c h a n g e w i t h N o r t h E u r o p e .
- 297 -
EPS TOKYO '96 Japan, 29·30 October 1996
ABSTRACT: A large embankment was planned to be placed near a structure supported by PHC piles ( ¢ 600
mm XL55m) in reclaimed soft ground. One of the concerns during the construction stages was the likelyhood of
large pile displacements resulting from lateral flow casued by weak subsoil itself.
Judging from the observed pile behavior and results of numerical analyses, it was anticipated that a higher
filling woud cause damage to piles. Therefore a light fill method (EPS Embankment Method) was adopted to
restrain the lateral displacement and about l l , 000m 3 EPS blocks were used for additional filling.
INTRODUCTION
At the site under disccusion, reclamation had barely been completed before the initiation of the construction of
the structure. At the site, the soil layer to a depth of 30m was very soft with N-values raging from 1 to 4. Piles
were driven into the ground and as a result of the excavation for the piles and the filling on top of the areas nearby
to the structure the difference in elevation of the piles and adjacent ground surface was expected to be about 10 m.
This is immediately lead to the concern of the possibility of severe damage to the piles resulting from a flow of
weak subsoil. Later plans called for a hill to be built around the structure, so the difference in elevation was going
to increase. In order to investigate the behavior of the ground and the piles, three inclinometers were set in the
ground and in a PHC Pile which was located near the embankment. The observations from those inclinometers
We also, performed two-dimensional elasto-viseoplastic FEM analyses to obtain accurate estimates of the lateral
displacement caused by the planned filling. In our analyses we estimated the distribution of pore water pressure
using a one-dimensional FEM Analysis for considering the effect of pumping during a 100-year period and
reclamation before running the two-dimensional FEM routine for calculating the displacements (Matsumoto et al.,
1989). Based on the computed results we reached conclusions similar to those from the in-situ observations,
namely that countermeasures are required to restrain the lateral displacement induced by the further filling.
GROUND CONDITIONS
The soil profile before the construction is shown in Fig-1. The reclamation of this site began about 15 years ago
and the ground elevation at the site was raised to AP. +5.5m before the start of construction, The soil profile is
made of a layer the so-called Yurakucyolayer (As, Ac), followed by a Nanago-layer (Nas, Nae) at the bottom of
which is a Tok-yo Gravel-layer (Tog) up to a depth of AP-55 m. The properties of the soil layers are sumarized in
Table-I.
Fig-2 shows the ground settlement and the water level in the obsevational well located just under Tog-layer near
the construction site (the measurement were made by the metropolitan office). The water level had been lowered
to a depth of 30m in 1972, and after restrictions were put in place the level had already risen to a depth of lOm and
was continuing to rise. The ground settlement caused by the changes in the water level was measured as 2.3m.
The effective stresses in the soil are influenced by the pore water pressure. As a result of the reclamation and
groundwater pumping the pore water pressure has undergone a lot of change so the task of estimating the
- 298 -
In this paper, we have evaluated the pore water pressure distribution by the means of a one-dimensional FEM
-50 50
-10.0- Clayey Silt with"
Tokyo Gravel-layer(Tog)
-60 �� Ac thin layer of sand.
60
0
�
20 ,oc m) -25.0
�= N-values l-4
-25.0- -_-_,7,
Fig-1 Soil profile - -, ,_ DHrk grey silty Clay
with layer of sand.
-49.0 -:::;�- Nae
_.,,_ - N-values 9-22
-38.0-
Dark grey Sand.
·//.:.\
Nas
N-values 5-50
-40.0
1920 1930 1940 1950 1960 1970 1980
O 1890 1900 1910 · · · · . · .
..
..
>
-10
· - · ---
-- ·-...... _ _ _ .. """"
1
..
..
:::
-49.0- ti> Tog
Sandy
N-values
clayey
25-50
Gravel.
-, o ·:. o
...
..
.... settlement �
..
:,,
-20 2 ::,
...
ground water level
-e
c measured at GL-70m
',I-
:, �
0 -30 3
t;.
Fig-3 shows the consolidation yield stresses and the unconfined compression strength obtained from
measurements made at and around the site. Also, the estimated effective overburden pressure before the
construction is shown by the dotted line. The OCR values were calculated based on the pore water pressure
distribution estimated from the one-dimensional FEM analyses. Fig.3 shows that the AP.-lOm to -25m
Yurakucho-layer is at normally consolidated state, the AP.-25m to -49m Nanago-layer is overeonsolidated with
OCR's lying in the range 2 to 3. The OCR values indicate that the Yurakucho-layer is easily deformed by loading.
..
-10
•I ..
'". .
:·•.
-20 ··�·!
. -: ;.
·. ', . .... ',}:·... ... a. ..
-30
·.• . . . . .
. ..
-40
. : . , . . .
. .
-so
(m) > Toe
- 299 -
OUTLINE OF CONSTRUCTION PROCEDURE AND FIELD OBSERVATIONS
Some of the construction stages shown on Table-2 together with field observations schedule. The plane of the
construction area is shown on Fig-4. Fig-5(a) and (b) shows field surface and its section at various stages of the
1) Preload,
3) Pile driving,
12 l 2 J 4 5 6 7 8 9 101112 l 2 J 4 5 6 7 8 9 101112 l 2 J
Pre load
+ Removal
the
Filling
of
preload
CJ
c:::J
Pile driving CJ
Excavating CJ
Building
Ga r de n around
t h e s true cure
c
G r o u nd
analytical section behavior
Settlement
Pile
behavior
embankment
£9
,, ... - ... ,
I I
I '
'--.,.lJ>s:,
Removal of Excavating
6) Gardening
AP.
0
( m )O I 1) Preload
3) Pile driviug
-20 piles
-20
-40
-40
-60
-60-'-�����������������-'- I
�-
structure
0 4) Excavating
O 2) Removal of the p r e Lo ad
and filling
-20 -20
piles
5) Building
-40 -40
6) Garden
-60-'-����������������_J,_ -60
- 300 -
FIELD OBSERVATIONS
Fig-4 shows measureing points and analytical section. Fig-6 shows plots of lateral displacement in the ground
and the deformation of one of the piles from inclinometer readings and the ground settlement as recorded by
settlememnt gages. The pile was a PHC half-closed end pile, whose inside diameter was 420 mm.
All observations exrept the deformation of the pile had been carried out since this project started and the pile
measurements were made from the time the pile was driven. The instrumented pile was located near the
Lateral displacement
(cm)
0 2 4 6 8 0 2 4 6 8
F -
AP (ground)
0
G--
-10 (pile)
-20
-30
o b s e rv a t i o n
-50
Cm)
Fig-6 Lateral deformation (comparison between a pile behavior and the ground)
According to the observational results, shown in Figs-6 and 7, the pattern of ground displacement can be divided
as;
1) A pile driving stage during which ground displacements were generated in a direction away from the pile
2) The excavating and filling stage during which the ground displacements occurred in the direction of the pile
driving area. The largest ground displacements was observed in the soft clay layer called Yurakucho-layer.
u
0
"'
.....
-2 1988 • .....
.., • 12 1989
0.
..
-e
"'
..... -4 • 6
�B {Ground) •
..
-6
6
• .Q ,,,. . .. ...••. : . .
..... A · - • • .- --....._
-8 • V" ;
� � 66
F (Ground)
�
"'
a,
-10
..., • AP.-16.Sm
• center of Ac-layer
..... -12
"' •
-14
- 301 -
OBSERVED BEHAVIOR OF THE PILE
As shown in figs-6 and 7, the pile deformation, indicated by G, and the ground deformation, indicated by F,
coinside with each other even though the measurements were made 20m apart from each other. It appears as if
the pile deformed suddenly at the boundary between the soft Yuraku-cho clay layer and the stiff Nanago clay
layer.
The height of the embankment was expected to rise in the future as a results of additinal filling, Based on the
observed data up to this stage it was anticipated that the piles would be damaged by the future filling. Therefore,
the incremental ground displacement resulting from filling in the future was estimated by using a numerical
procedure.
NUMERICAL ANALYSES
We used a finite element program called DACSAR (lizuka et al.,1987) to predict the ground deformation.
DACSAR is based on a elast-viscoplastic constitutive model proposed by Sekiguchi and Ohta(l977) for clayey
materials. This model incorporates induced anisotropy, creep and relaxation characteristics, and feature which
One-dimensional analyses were conducted to estimate the initial stress condition in the ground. The analytical
section for the two-dimensional analyses was made to corresponded with the observed data shown in Fig-4. The
finite element mesh and the boundary conditions are shown in Fig-8.
Two-dimensional analyses were performed from at "preload" to at "future filling for landscaping a garden". To
express faithfully the complex field works, the size of the mesh for adding and removing due to filling and
excavating was taken as 50cm. The effects of the piles supporting the structure were not taken in to consideration,
hence the ground deformation during the pile driving period was ignored.
�a
j
1 1 II i 1 1 1 1
inclinometer
rl 1 1 1 1 1 1 1
F
11 1 Fl
?OOm
11 1 I 1 1 I
t
I
ANALYTICAL RESULTS
The post excavation computed ground displacement is show in Fig-9 together with observed values. The
calculated values are slightly higher than the observed data in the Nanago-layer but are very comparable in the
Yurakucho-layer. Fig-10 show the lateral displacement at AP. +2.5m of F with the passage of time. The observed
values had a high of 17cm, which occurred during the pile driving period in a direction away from the pile driving
area. As the excavation progressed a lateral displacement of 15cm was recorded in the direction towards the pile
driving area. The numerically calculated values do not include the displacement during the pile driving because it
is not considered in the routine nonetheless as seen in Fig-10 the calculated values show a good agreement with
the measured values. The numerical routine predicted a lateral displacement of future filling and the observed
- 302 -
displacement ( cm) displacement (cm)
-40 -20 0 0 5 10 15 20
AP "'1'l - \ I
0
Before \ \
tile ucnatioa\�\
-10
Alter \ /
� 10 Excavation
e tile uuntio1 \ ....,
u
H calculated
"' I c
-20 "'
I .,
...
� ••• .:.-···--A EPS
"'
II � O""'r-���������_.,....a;.;....;:.�����--1
-30 x
c.
c:,
c:, ..
.., ....
.... "O
..
17 194
-so
(m)
. .... - -20-=-���-=-=-::--__._�_,...,!-=-�-'-���--'-�--'�---'
0 200 400 600 800
0 6. elapsetime(days)
COUNTERMEASURES
Several countermeasures such as light fill methods (EPS, air mortar), soil improvement methods, pile
foundation method etc., were considered to maintain the safety of the piles and these measures must all satisfy the
followings:
2) the lateral movement of the soft ground should not be increased by filling, and
The most obvious solution to overload problems is to reduce the load. The Expanded-Polystyrol (EPS) lightfill
method was adopted based on a comparison of the effect, cost, period etc,.
The density of the 2m x lm X0.5m EPS blocks was 18kg and ll,000rn3 of blocks were used. Fig-ll(a) shows the
plan of the EPS hill, and A-A section is shown in Fig-ll(b). The EPS area was extended over the top of the hill so
that these blocks are not subjected to any appreciable soil pressure. Under normal conditions cncrete slabs would
be installed at the top of the EPS layer to prevent traffic-induced deflections in the material but as this area was a
SOm
- 303 -
r"· 000 .L---�t;'-':."."'.."_ ��� _:'.,_�-- - - - _ /;'.000 r'"""T •." �
-·c
<"
1
I · �
�
- - - - - - _ !PS 2. 000 x I. 000 x 500 IT I,,
..... AP . 9 . 3 5 ( AP . 7 . 8 5 ��-------- �
1
AP . 8 . 35 1
. �
• ORAi H D I T C H AREA •
I
SECTION
Our aim was to optimize the loading capacity of the soft ground and therefore even before the filling started, the
base of the ground was excavated to a depth of lm so as not to increase the load on the soft ground. This resulted
in a sort of equilibration of the conditions before and after the construction of the embankment.
It was also important to prevent build-up of any water pressure against the EPS blocks. To reduce the buoyancy,
a layer of gravel approximately 35cm thick was placed at the bottom of the EPS hill and, also, a ditch was dug to
reduce the seepage of water by ensuring a smooth flow of water along the surface of the hill. The ditch was set up
by spacing lOm. Non-wovens fabric was placed surrounding the gravel to reduce the erosion. Thus, the inflow of
water was reduced as much as possible and any water that penetrated the EPS fill could easily drain off
Before the EPS blocks were laid a 5cm thick sand layer was spread to level the base of the ground. This work
was performed very carefully by a hand process because the horizontality of the base EPS blocks have a direct
effect on the next upper EPS blocks and so on. The blocks in the upper layer were placed perpendicularly to the
lower blocks and are connected to each other by two metal joints, see Phot-I, 2.
CONCLUSIONS
The experience of this project was good in all respects, technically, as well as practically. The easy handling
The EPS blocks, also, made it possible to achieve the originally planned height of the hill, which provided a nice
view of the Tokyo Bay. So far this enbankment has performed quite satisfactorily. Zero lateral displacement of the
soft clay layer has been observed during the period 3/1989 to 3/1991
- 304 -
ACKNOWLEDGEMENTS
The authors would like to thank metropolitan office for offering observation data. The support of Taniguchi
design office and Kimura structural engineers is gratefully acknowledged. The results of these analysis were
available under the guidance of Pro. Ohta and Dr. lizuka (Kanazawa Uni.)
REFERENCES
1) Mastumot.o,K,Kobayashi,A.; Deformation Analysis of Soft Ground under Excavation and Filling, Technical
3) Sekiguchi,H.,Ohta,H.; Induced Anisotropy and Time Dependency in Clay, Pro. Specialty Session 99th ICSMFE,
4) Mastumot.o,K,Ishihara,K,Kat.o,T.; Countermeasures for the Lateral Displacement of Piles in Soft Clay, Pro. of
- 305 -