AECOM +852 3922 9000 tel

20/F, Grand Central Plaza, Tower +852 3922 9797 fax


2, 138 Shatin Rural Committee
Road, Shatin, Hong Kong
香港新界沙田鄉事會路 138 號新城
市中央廣場第 2 座 20 樓
www.aecom.com
Site Memorandum
Date: 18 March 2021 Ref No: CHC/SM/005
To: Yau Lee Construction Co., Ltd (YL) (the Contractor) – Ms. Sammi CHAN
From: Mr. James SHI - Resident Engineer
Project: Design & Construction of A Community Health Centre Cum Social
Welfare Facilities at Pak Wo Road, North District
(Contract No. SS H501)
Subject: Approval to the Use of Steel H-Piles (Batch 4)
Distribution: √ ArchSD – Ms. Amie LAI, Ms. Joelle CHU, Mr. Jackson WAI,
Mr. Anfield CHIU, Mr. Alex TSOI, Mr. Ken SHUM, ,
Mr. Y.K. HSU, Mr. Roy YUEN
√ AECOM – Mr. K.L. WONG, Mr. Jimmy WU, Mr. Benton LI, Mr.
Adam SHUM
√ YL – Mr. Darren LEE, Mr. C.C. LEE, Mr. James IP, Mr
Samuel LO, Mr. Joshua YU, Mr. C.W. SIN

I refer to the following formal test reports for the 160 nos. Grade S450J0 305x305x223kg/m
steel H-piles (Batch 4) which were delivered to the site on 26/01/2021:-

1. Tensile test reports of structural steel sections (Castco Report No.: 210210-2073 to
210210-2078, 210210-2080 & 210210-2081) received on 18/03/2021.

Please be informed that these test results had been checked and found to satisfy the
relevant requirements of BS 10025-2:2004. As such, the use of these steel H-piles in the
construction works of the Project is now permitted.

Thank you for your attention.

Regards,

__________________
James Shi
Resident Engineer

Note: If the Contractor considers that the above instruction constitutes a change to the works information he
has to notify the Project Manager accordingly, as provided for by the Conditions of Contract.