You are on page 1of 19

Construction Management

and LEED
Glossary of Terms
Compliments of

zumBrunnen, Inc.
Construction Management and LEED
Glossary of Terms
Compliments
Of

zumBrunnen, Inc.
Atlanta, GA

This glossary of terms was created to assist those who desire to learn more
about the construction industry. We hope you enjoy this compilation of
construction management and consulting-related terms, and that it helps
to assist you in understanding the common terms and abbreviations used in
zumBrunnen’s construction monitoring reports.

John H. zumBrunnen
President

For additional terms or comments, please contact zumBrunnen


Construction Management and LEED Glossary of Terms
deliberation, it being understood that the results
-A- will be binding on the contending parties.

ACM – Additional Construction Management Arbitration (Non-Binding) – A method by


which processes for bringing about agreement
ADA - The Americans with Disabilities Act which or reconciliation between opponents in a dispute
gives civil rights protection to individuals with is designated. Arbitration involves a formal
disabilities similar to those provided to deliberation, it being understood that the results
individuals on the basis of race, color, sex, are not binding on the contending parties and
national origin, age, and religion. It guarantees relief in the court system is an additional remedy
equal opportunity for individuals with disabilities if desired.
in public accommodations, employment,
transportation, State and local government Architect - An individual or firm who designs
services, and telecommunications. and supervises the professional design for the
construction of buildings or other structures.
Addendum - (Addenda) Written information
adding to, clarifying or modifying the bidding Architect-Engineer (A/E) - An individual or firm
documents. An addendum is issued by the offering professional services as both architect
Owner to the Contractor during the bidding and engineer.
process and as such, addenda are intended to
become part of the contract documents when Architect’s Supplemental Instructions (ASI) A
the construction contract is executed. document written by the Architect containing
additional instructions regarding the Contract
A/E - Architect/Engineer; the design professional specifications or drawings. Generally, the
hired by the Owner to provide design and Architect uses an ASI when the information is
design-related services. not anticipated to cause a change to the
Contract. If the Contractor believes these
Agency CM (ACM) - (CM Without Risk). A instructions are a change to the Contract, he can
contractual form of the CM system exclusively write a COP.
performed in an agency relationship between
the Construction Manager and Owner. ACM is As-Built Drawings - Drawings marked up to
the form from which other CM forms and reflect changes made during the construction
variations are derived. process or after construction that amend the
contract drawings to show the exact location,
Agent - One authorized by a client (principal) to geometry, and dimensions of the constructed
act in his/her stead or behalf and owes the client project. It is good practice to make as-built
a "fiduciary duty" (Trust). Example: Construction drawings by marking the changes as the project
Manager for fee but classified as an unfolds. As-built drawings are not the same as
independent contractor for tax purposes. A Record Drawings.
construction manager for fee does not have any
financial responsibility whereas a construction
manager at-risk does have financial risk similar -B-
to a general contractor.
Bank Inspector – An independent consultant
AIA - American Institute of Architects engaged by a construction lender to provide
periodic site inspections, to opine on
Application for Payment - Contractor's written construction schedule and general compliance,
and to make recommendations for contractor
request for payment for completed portions of
the work and, for materials delivered or stored payment application. Inspections are made
and properly labeled for the respective project. during the construction phase of a project
development, expansion or renovation and are
(e.g., American Institute of Architects – AIA,
Forms G-702 and G-703) performed for the benefit of the bank. Bank
Inspector scope-of-services are not the same as
a Construction Monitor.
Arbitration (Binding) – A method by which
processes for bringing about agreement or
Baseline Building Performance - A
reconciliation between opponents in a dispute is
designated. Arbitration involves a formal term used in the LEED certification
process that describes the annual
Revised September 2010 1
energy cost for a building design intended for for discretionary change orders, unless
use as a baseline for rating above standard otherwise noted.
design as defined by ASHRAE 90.1.
Building Code - The legal requirements
Beneficial Occupancy – The point wherein the established by the various governing agencies
project is substantially complete in nature to covering the minimum acceptable requirements
allow the Owner to utilize the project for its for all types of construction. (See also Codes.)
intended use. The mechanical systems, life
safety systems, telecommunications systems Building Envelope - (1) The elements of a
and any other systems which are required to building which enclose conditioned spaces and
properly utilize the project are complete and in intended to keep water from entering. (2) The
good working order. The remaining items to be outer structure of the building. (sometimes
completed shall be such that the correction does referred to as "Building Shell")
not cause inconvenience to the Owner or
disruption to the Owner's normal operations. Building Inspector/Official - A government
representative authorized to inspect construction
Bid Bond - A written form of security executed for compliance with applicable building codes,
by the bidder as principal and by a surety for the regulations and ordinances. Courts have ruled
purpose of guaranteeing that the bidder will sign that government agencies’ building inspectors
the contract, if awarded the contract, for the are exempt from errors and omissions liabilities.
stated bid amount. The Surety is a third-party
that makes a pledge to pay damages to the Building Permit - A written document issued by
Owner if the bonded contractor declines an the appropriate governmental authority
award offered by the Owner.
permitting construction to begin on a specific
project.
Bid Documents - The documents distributed to
contractors by the Owner for bidding purposes. Budget Summary Table - A table summarizing
They include drawings, specifications, form of the hard cost budget funds and committed hard
contract, general and supplementary conditions,
cost contingency to date to determine the
proposal forms, and other information including remaining (balance) hard cost contingency. The
addenda. purpose of this table is to help provide the
earliest possible notice of a budget overrun.
Bond - A written form of security from a surety
company, on behalf of a prime contractor or
subcontractor, guaranteeing execution of the -C-
contract and all supplemental agreements
pertaining thereto and for the payment of all Certified Wood - A term used in the LEED
legal debts pertaining to the construction of the certification process that describes the use of
project. (See Bid Bond, Payment Bond, wood that is certified in accordance with the
Performance Bond, Labor and Material Payment Forest Stewardship Council (FSC) Principles
Bond, or Subcontractor Bond.) and Criteria for wood building components. This
is wood that originates from sources that
Bonding Company - A properly licensed surety practice environmentally responsible forest
willing to execute a surety bond, or bonds, management.
payable to the Owner, securing the performance
on a contract either in whole or in part; or Change Order - A written document between
securing payment for labor and materials. the Owner and the Contractor signed by the
Owner, Architect, and the Contractor authorizing
Budget Analysis - Budget analysis as to a change in the project documents, adjustment
sufficiency of funds takes into consideration in the contract sum and/or the contract time.
various factors. A cost-to-complete estimate Proper contract administration requires the
must be developed and compared to the contract terms, scope, sum and the contract
balance of funds. This analysis may include time to be changed only by change order. The
consideration for (i) contractor performance; (ii) recommended document for this is the AIA
percent completion and schedule status; (iii) Document G701.
status of contract buyout and contingency; (iii)
potential for shared savings; and (iv) various
Change Order Proposal (COP) - A
other risk factors as deemed pertinent. This
written change document before it has
estimate typically does not include projections
been approved by the Contractor,
Revised September 2010 2
Architect, and Owner. A change order proposal Codes - Prevailing regulations, ordinances or
can be issued by the Contractor, Architect, or statutory requirements set forth by governmental
the Owner. The change order proposal becomes agencies associated with building construction
a change order only after it has been approved practices and owner occupancy, adopted and
and by the Contractor, Owner, and Architect. administered for the protection of public health,
life safety and welfare. (See Building Code.)
Change Order Request (COR) - A written
document requesting an adjustment to the Commissioning - The process at or near
contract sum or an extension of the contract construction completion when various
time; issued by the Architect, Owner, or mechanical, electrical, and plumbing systems
Contractor. are tested and checked for compliance with the
design, and are operating properly.
Changed Conditions - Conditions or
circumstances, physical or otherwise, which Committed HC Contingency – See “HC
surface after a contract has been signed and Contingency Committed”
which alter the circumstances or conditions on
which the contract is based, i.e., Concealed Completion Schedule Analysis – See “Project
Conditions or Latent Conditions. Completion Graph (S-Curve)”

Chart of Accounts - An alpha/numeric Constructability - The optimizing of cost, time,


accounting system used by the Contractor to and quality factors with the material, equipment,
ensure that the project expenditures are properly construction means, methods, and techniques
debited/credited in the project budget as used on a project; accomplished by matching
payments are made in behalf of the project. owner values with available construction
industry practices.
Claim - A formal notice sent by a Contractor to
an Owner asserting the fact that the terms of the Construction Budget - The target cost figure
contract have changed and compensation is covering the construction phase of a project. It
being sought by the Contractor from the Owner. includes the cost of contracts with trade
contractors, construction support items other
Clerk-of-the-Works - An individual employed by purchased labor, material and equipment, and
an Owner to represent him on a project at the the construction manager's cost but not the cost
site of the work. The clerk-of-the-work's abilities, of land, A/E fees, or consultant fees.
credentials, and responsibilities vary at the
discretion of the Owner. Construction Change Directive (CCD) - A
construction change directive is a written order
CM - The abbreviation for Construction signed by the Owner and Architect directing the
Management and Construction Manager (a firm Contractor to make a change in the work and
that provides CM services or persons who work stating a proposed basis for any appropriate
for a CM firm). adjustment in the contract sum or the contract
time. This may result in a change order if an
CM Fee Plus Reimbursables - A form of agreement is reached between the Contractor
payment for CM services where the construction and the Owner. But even in the absence of total
manager is paid a fixed or percentage fee for agreement, the construction change directive by
CM expertise, plus pre-established hourly, daily, itself constitutes a change in the contract
weekly, or monthly costs for field personnel and documents, with determination of any
equipment. appropriate adjustment in contract sum or
contract time being handled in accordance with
specified detailed procedures at a later date.
CM Partnering - A contractual commitment by
the Owner, A/E, and CM to achieve a common
goal, and doing so without a stake holder’s Construction Documents - All drawings,
exposure to a potential for conflict of interest in specifications and addenda associated with a
pursuit of that goal. specific construction project. These documents
delineate and graphically represent the physical
CM Services - The scope of services provided construction requirements established by the
by a construction manager and available to A/E.
owners in whole or in part. CM services are not
consistent in scope or performance from one Construction Documents Phase - The
CM firm to another. third phase of the Architect's basic
Revised September 2010 3
services wherein the Architect prepares working construction portion of the project-delivery
drawings, specifications and bidding information. process, showing activities, durations, and
projected completion dates.
Construction Document Review - One party’s
review of another party’s construction Construction Waste Management - A term
documents for the purpose of confirming that used in the LEED certification process that
these documents and estimates are feasible and describes the diversion of construction and
are in accordance with the proposed loan or demolition debris from disposal in landfills and
project appraisal. incinerators. This process redirects recyclable
resources back to the manufacturing process
Construction IAQ Management Plan - A term and redirects reusable materials to appropriate
used in the LEED certification process that sites.
describes a document specific to a building
project that outlines measures to minimize Contingency - Line-item amounts in the project
contamination in the building during construction budget, or contractor’s schedule of values
and to flush the building of contaminants prior to intended to cover costs of unknown,
occupancy. unforeseeable, or missed cost items.
Contingency may be owner-controlled or
Construction Management (CM) – (1) A contractor-controlled.
project delivery system that uses a construction
manager to facilitate the design and construction Contingency within the GMP (GMP
of a project by organizing and directing men, Contingency) – Contractor-controlled
materials, and equipment to accomplish the contingency; see Contingency
purpose of the design. (2) A professional service
that applies effective management techniques to Contingency Graph – See Project HC
the planning, design, and construction of a Contingency Graph
project from inception to completion for the
purpose of controlling time, cost and quality, as Contract Administration - The contractual
defined by the Construction Management
duties and responsibilities of the A/E,
Association of America (CMAA). Contractor, or CM during the construction phase
of a project for servicing the interactive
Construction Management Contract - A provisions in the contract for construction.
written agreement wherein responsibilities for
coordination and accomplishment of overall
Contract Document Phase - The final phase of
project planning, design and construction are design on an architectural project when
given to a construction management firm. The
construction documents are completed and
building team generally consists of the Owner,
bidding documents are formulated. See also
Contractor, and Designer or Architect. "Construction Documents Phase".

Construction Manager - A business Contract Documents - A term used to


organization with the expertise and resources to
represent all documents (any general,
manage the design, contracting, and supplementary, or other contract conditions, the
construction aspects of project delivery. drawings and specifications, all bidding
Individuals who work for a CM Firm are also
documents, addenda issued prior to execution of
referred to as Construction Managers. the contract and post-award Change Orders,
and any other items specifically stipulated as
Construction Monitor – An independent being included in the contract documents) which
construction consultant engaged by a collectively form the contract between the
member(s) of the financial team to observe and Contractor and the Owner.
report pertaining to the current status of a
construction project schedule, project budget, Contract Performance Bond - A written form of
hard cost payment approvals, and contract
security from a surety company to the Owner, on
administration compliance, and tracks critical behalf of an acceptable prime or main contractor
action items. The Construction Monitor acts as or subcontractor, guaranteeing the completion of
an independent facilitator and reports all findings
the work in accordance with the terms of
in an objective manner. the contract.

Construction Schedule - A graphic, tabular or


Contract Substantial Completion –
CPM representation or depiction of the The project contract documents will
Revised September 2010 4
define substantial completion, which is the Cost-of-Work - All costs incurred by the
contract substantial completion requirement. Contractor in the proper performance of the
Contract substantial completion may or may not work required by the plans and specifications for
have additional requirements to be achieved a specific project. The term is more specifically
before a project is deemed substantially defined in all GMP contracts.
complete by the Architect and Owner. Typically,
substantial completion is achieved when the Cost-Plus Contract - A form of contract usually
facility is complete enough to be used for its between an Owner and Contractor, A/E design
intended use. The Architect will issue a professional, or CM, under which the Contractor,
certificate of Substantial Completion, which is A/E, or CM is reimbursed for direct and indirect
typically an AIA Document G704. costs plus a fee for services. The fee is usually
stated as a stipulated sum or as a percentage of
Contract Sum - The total dollar amount payable cost.
by the Owner to the Contractor for the
performance of the work under the contract Cost Plus Fee Agreement - A written
documents. agreement under which services are provided by
a Contractor, Architect, Engineer, or CM for the
Contract Time - The time period set forth and cost of work plus a specified fee.
established in the contract documents for
completing a specific project; usually stated in Cost-To-Complete - All costs remaining to
working days or calendar days. The contract complete construction of the project to obtain a
time can only be adjusted by valid time certificate of occupancy and occupy the project
extensions through change order. for its intended use. These costs can be further
defined as Contract, Owner, hard or soft cost-to-
Contractor's Option - A written provision in the complete.
contract documents giving the Contractor the
option of selecting certain specified materials, Critical Path – (1) The continuous chain of
methods or systems without changes in the activities from project-start to project-finish,
contract sum. whose durations cannot be exceeded if the
project is to be completed on time. (2) A
Contractor's Qualification Statement - A sequence of activities that collectively require
written statement of the Contractor's experience the longest duration to complete (the duration of
and qualifications submitted to the Owner during the sequence is the shortest possible time from
the Contractor selection process. The American the start event to the finish event). Activities on
Institute of Architects publishes a standard the critical path have no float time.
Contractor's Qualification Statement form for this
purpose. Critical Path Method (CPM) - A planning
scheduling and control line and symbol diagram
Cost Breakdown - A financial statement drawn to show the respective activities involved
furnished by the Contractor delineating the in constructing a specific project. A CPM
portions of the contract sum allotted for the schedule shows activity duration and inter-
various parts of the work and used as the basis dependence.
for reviewing the Contractor's applications for
progress payments. See also "Schedule of CSI - Abbreviation for the Construction
Values". Specification Institute

Cost Codes - A numbering system given to CSI Master Format - The CSI Master Format is
specific kinds of work for the purpose of a system of numbers and titles for organizing
organizing the cost control process of a specific construction information into a regular, standard
project. order or sequence. By establishing a master list
of titles and numbers Master Format promotes
Cost of Construction - The target cost figure standardization and thereby facilitates the
covering the construction phase of a project. It retrieval of information and improves
includes the cost of contracts with trade construction communication. It provides a
contractors, construction support items other uniform system for organizing information in
purchased labor, material and equipment, and project manuals, for organizing project
the construction manager's cost but not the cost cost data, and for filing product
of land, A/E fees, or consultant fees. information and other technical data.

Revised September 2010 5


implicitly conveyed through the assumption of
-D- project-specific design liability, via performance
specifications.
Daily Construction Report - A written
document and record that has two main Design Development Phase – (1) The second
purposes: (1) Furnish information to off-site phase of the Architect's basic services wherein
persons concerning important details of events the Architect prepares drawings and other
as they occur daily and hourly, and (2) Furnish presentation documents to fix and describe the
historical documentation that might later have a size and character of the entire project as to
legal bearing in cases of disputes. Daily reports architectural, structural, mechanical, and
should be as factual and impersonal as possible, electrical systems; materials; and other
free from the expression of personal opinions essentials as may be appropriate; and prepares
and feelings. Each report should be numbered a statement of probable construction cost. (2)
to correspond with the working days established The term used on architectural projects to
on the progress schedule. In the event of no- describe the transitional phase from the
work days, a daily report should still be made, Schematic Phase to the Contract Document
stating "no work today" (due to rain, strike, or Phase during design.
other causes). The report includes a description
of the weather; a record of the total number of
employees, subcontractors by name, work Design-XCM - A variation of the extended
started and completed today, equipment on the services form of CM, where the A/E also
job site, job progress today, names and titles of provides the CM function.
visitors, accidents and/or safety meetings, and a
remarks column for other job related information. Direct Costs - The costs directly attributed to a
work-scope, such as labor, material, equipment,
Date of Agreement - (1) Usually on the front and subcontracts but not the cost of operations
page of the agreement; (2) If not on front page it overhead and the labor, materials, equipment,
may be the date opposite the signatures when and subcontracts expended in support of the
the agreement was actually signed; (3) or when undertaking. Direct Costs, Hard Costs, and
it was recorded; (4) or the date the agreement Construction Costs are synonymous.
was actually awarded to the Contractor.
Discretionary Change Order – Owner directed
Date of Commencement of the Work - The change order not required for completion of the
date established in a written notice to proceed project for the projects’ intended use and in
from the Owner to the Contractor. accordance with the construction contract.

Date of Substantial Completion - The date Division of Work - A portion of the total project
certified by the Architect when the work or a reserved for contractors for bidding and
designated portion thereof is substantially performance purposes, i.e., Bid Division or
complete. The Architect will document this date Work-Scope.
on an AIA Document G704.
-E-
Daylighting - A term used in the LEED
certification process that describes the Engineer - A professional individual who is
controlled admission of natural light into a space
licensed by the state to practice a specific
through glazing with the intent of reducing or engineering discipline.
eliminating electric lighting.
Energy STAR Rating - is a government-backed
Demising Walls - The boundaries that separate
program helping businesses and individuals
your space from your neighbors' or from the
protect the environment through superior energy
public spaces. efficiency. It is also a term used in the LEED
certification process that describes the rating a
Design-Build (D-B) - A project delivery method building earns using the Energy STAR Portfolio
where a design-build contractor (contractor-led Manager to compare building energy
D-B), A/E design professional (design-led D-B) performance to similar buildings in similar
or CM (CM-led D-B) is directly responsible for climates. A score of 50 represents
both the total project design and construction of average performance.
the project. Design-Build liability can be explicitly
conveyed through the contract documents or

Revised September 2010 6


Enhanced/Fundamental Commissioning - A property rather than real property; (3) An
term used in the LEED certification process that abbreviation generally associated with interior
describes the verification that a building’s energy design and planning of retail stores or office
related systems are installed, calibrated and facilities.
perform according to the Owner’s project
requirements, basis of design and construction Field Order (FO) - A written order issued to a
documents. Contractor by the Owner, or Owner's
Representative, i.e., A/E design professional,
Escrow Account - (1) Money put into the effecting a minor change or clarification with
custody of the third party by the first party for instructions to perform work not included in the
disbursement to the second party. (2) A brief contract for construction. The work will
temporary depository for progress payments eventually become a Change Order. A Field
until authorized for release according to the Order is an expedient process used in an
depositor’s explicit instructions. emergency or need situation, which in many
cases does not involve an adjustment to the
Estimated Cost-to-Complete - An estimate of contract sum or an extension of the contract
the cost yet to be expended on a work-scope in time. See also "Construction Change Directive.”
order to complete it. The difference between the
Cost to Date and the Estimated Final Cost. Field Schedule - A graphic, tabular or narrative
representation or depiction of the construction
Estimated Final Cost - An estimate of the final portion of the project-delivery process, showing
cost of a work item based on its Cost-to-Date field activities and durations in sequential order.
and the estimated cost to complete it. The sum A short-interval, field-based schedule that plans
of the Cost-to-Date and the Estimated Cost-to- contractor and subcontractor activities on a
Complete. month-to-month, week-to-week, or day-to-day
basis from the project milestone schedule.
Estimate of Construction Cost - A calculation
of costs prepared on the basis of (1) A detailed Field Work Order (FWO) - A written request to
analysis of materials and labor for all items of a subcontractor or vendor, usually from the
work, or (2) On current area, volume, or similar general or main contractor, for services or
unit costs. materials.

Extended Services-CM - A form of CM where Final Acceptance - The action of the Owner
other services such as design, construction, and accepting the work from the Contractor when the
contracting are included with ACM services Owner deems the work completed in
provided by the construction manager. accordance with the contract requirements. Final
acceptance is confirmed by the Owner when
making the final payment to the Contractor.
-F-
Final Completion - The point at which both
Fast Track Construction - A method of parties to a contract declare the other has
construction management which involves a satisfactorily completed its responsibilities under
continuous design-construction operation. This the contract.
usually involves a prime or main contractor
starting the construction work before the plans Final Design Phase - The designation used by
and specifications are complete. engineers for the last portion of the design
process prior to bidding.
Feasibility Phase - The conceptual phase of a
project preceding the Design Phase used to Final Inspection - A final site review of the
determine from various perspectives whether a project by the Contractor, Owner or Owner’s
project should be constructed or not. Authorized Representative prior to issuing the
final certificate for payment.
Fee Enhancement - The awarding of an
additional fee, over and above the basic fee for Final Payment - The last payment from the
services, based on the performance quality of Owner to the Contractor of the entire
the party providing the basic service. unpaid balance of the contract sum as
adjusted by any approved change
FF&E - (1) An abbreviation for furniture, fixtures orders.
and equipment; (2) Items classified as personal
Revised September 2010 7
Financial and Management Control System - contract for construction, e.g., American Institute
A manual or computerized management control of Architects (AIA) Document A201.
system used by the project team to guide the
course of a project and record its status and General Contractor (GC) - A properly licensed
progress. individual or company having "primary"
responsibility for the work. A GC can perform
Fixed Fee - A set contract amount for all labor, work with its own contractors or can perform the
materials, equipment and services; and project work as an independent contractor,
contractors’ overhead and profit for all work providing services to owners through the use of
being performed for a specific scope of work. subcontractors when using the general
contracting system. In the latter case, the GC is
Fixed Limit of Construction Costs - A referred to as "Paper Contractor".
construction cost ceiling agreed to between the
Owner and Architect or Engineer for designing a GMP Contingency (Contingency within the
specific project. GMP) – Contractor-controlled contingency.

Float - A scheduling term indicating that an Green Roofs – A roof system that incorporates
activity or a sequence of activities does not vegetative cover on a roof membrane surface
necessarily have to start or end on the that both protects the roofing membrane and
scheduled date to maintain the schedule on the lowers the surface temperature of the roof to aid
critical path. The difference between the early in reducing the Heat Island Effect (see this
start and late finish of an activity, minus the definition below) and is a method used in LEED
activities duration. certified buildings to garner points toward this
LEED certification. Green roofs also minimize
Fundamental / Enhanced Refrigerant drainage run-off, which reduces the impact on
Management - A term used in the LEED local storm drainage systems.
certification process that describes the process
of using non-CFC based refrigerants or Greenfields - A term used in the LEED
refrigerants with low ozone depletion and global certification process that describes building sites
warming characteristics in air conditioning and that have not been previously developed or
refrigeration equipment to reduce ozone graded and remain in a natural state.
depletion in the earth’s atmosphere.
Guaranteed Maximum Price-Construction
Management (GMP-CM) - A form of the CM
-G- system where the construction manager
guarantees, in addition to providing ACM
General Conditions - A written portion of the services, a ceiling price to the Owner for the cost
contract documents set forth by the Owner of construction.
stipulating the Contractor’s minimum acceptable
performance requirements including the rights,
responsibilities and relationships of the parties -H-
involved in the performance of the contract.
General conditions are usually included in the Hard Costs - All items of expense directly
book of specifications but are sometimes found incurred by or attributable to a specific project,
in the architectural drawings. assignment or task. Direct Costs, Hard Costs,
and Construction Costs are synonymous.
General Condition Items - Purchases,
services, or materials required to facilitate Hard Cost Contingency ("HC Contingency") -
construction at the site. As part of the Owner-controlled contingency limited to project
construction budget, these are financial Hard Costs; see Contingency. Direct
obligations of the Owner and the logistic Contingency Costs and Construction
responsibility of the CM. Contingency Costs are synonymous.

General Conditions (of the Contract for HC Contingency Balance – Owner-controlled


Construction) - The part of the contract that contingency that has not been committed to an
prescribes the rights, responsibilities, and approved, pending, or potential project
relationships of the parties signing the change order; unencumbered or
agreement and outlines the administration of the remaining contingency.

Revised September 2010 8


HC Contingency Committed – Owner- Officials (IAPMO) and the National Fire
controlled contingency that has been committed Protection Association (NFPA), which have
to an approved, pending, or potential change similar goals as far as code publications are
order; committed or encumbered contingency. concerned. The IBC is designed to be
compatible with these other codes, as together
HC Contingency Graph – See Project HC they make up the enforcement tools of a
Contingency Graph jurisdiction. More and more governing
authorities are accepting the IBC (with edits) as
their standard, in most cases replacing the
Heat Island Effect – A term used in the LEED
certification process that describes the thermal Southern Building Code or Uniform Building
gradient between developed and undeveloped Code.
areas. These heat islands are typical in urban
development. Urban heat islands increase IRFP - The abbreviation for Initial Request for
overall electricity demand, as well as peak Proposal; The first request for uniform detailed
demand, which generally occurs on hot summer information from prospective CM practitioners
weekday afternoons, when offices and homes being screened for a project.
are running cooling systems, lights, and
appliances. During extreme heat events, which
are exacerbated by urban heat islands, the
-J-
resulting demand for cooling can overload
systems and require a utility to institute Job-Site Overhead - Supportive and necessary
controlled, rolling brownouts or blackouts to on-site construction expense, such as
avoid power outages. construction support costs, supervision, bonus
labor, field personnel, and office expense.
-I- Joint Venture Partner - A party that contracts
with another similar party on a project basis to
Independent Contractor - One free from the provide greater financial strength, improved
influence, guidance, or control of another or services or more acceptable performance
others and does not owe a "fiduciary duty". e.g., qualifications as a combined organization to
an architect, engineer, prime or main contractor, design, bid, and/or constructs a specific project.
construction manager at-risk.

Indirect Costs - Costs for items and activities -K-


other than those directly incorporated into the
building or structure but considered necessary to K - Used as an abbreviation for Contract or
complete the project. A contractor’s or Contracts in the legal sector.
consultant’s overhead expense; expenses
indirectly incurred and not chargeable to a
specific project or task. The terms indirect costs -L-
and soft costs are synonymous.
Labor and Material Payment Bond - (1) A
Indoor Environmental Quality – A term used in written form of security from a surety (bonding)
the LEED certification process that describes the company to the Owner, on behalf of an
measurement of the level of indoor pollutants acceptable prime or main contractor or
inside buildings that affect the health and well- subcontractor, guaranteeing payment to the
being of building occupants. The LEED Owner in the event the Contractor fails to pay for
certification process encourages the use of all labor, materials, equipment, or services in
higher levels of outside air in building HVAC accordance with the contract, and (2) to pay any
systems, the use of low volatile organic claims against the Owner from contractors and
compounds in paints, stains, adhesives and suppliers who have not been paid for labor,
coatings and the reduction of tobacco usage in material, and equipment incorporated into the
buildings. project.

International Building Code (IBC) -The IBC is LEED (Leadership in Energy and
one of the family of codes and related Environmental Design) - An internationally
publications published by the International recognized green building certification
Conference of Building Officials (ICBO) and system, providing third-party verification
other organizations, such as the International that a building or community was
Association of Plumbing and Mechanical designed and built using strategies
Revised September 2010 9
aimed at improving performance across all the the event that the agreement is violated. The
metrics that matter most: energy savings, water fixed amount (usually on a per-day basis) which
efficiency, CO2 emissions reduction, improved a party to an agreement promises to pay to the
indoor environmental quality, and stewardship of other in case one party does not fulfill some or
resources and sensitivity to their impacts. all portions of an agreement.

LEED-EBOM (LEED for Existing Buildings: Lump Sum Contract - A written contract
Operations & Maintenance) - Rating system between the Owner and Contractor wherein the
helps building owners and operators measure Owner agrees the pay the Contractor a specified
operations, improvements and maintenance on sum of money for completing a scope of work
a consistent scale, with the goal of maximizing consisting of a variety of unspecified items or
operational efficiency while minimizing work. (See also "Stipulated Sum Agreement".)
environmental impacts. LEED for Existing
Buildings addresses whole-building cleaning and
Lump Sum Fee - A fixed dollar amount which
maintenance issues (including chemical use), includes all costs of services including overhead
recycling programs, exterior maintenance and profit.
programs, and systems upgrades. It can be
applied both to existing buildings seeking LEED
certification for the first time and to projects -M-
previously certified under LEED for New
Construction, Schools, or Core & Shell.
Mandated Change Order – Change orders
required to complete the work as directed by
Letter of Intent - A notice from an Owner to a governing authorities or others to accomplish a
Contractor stating that a contract will be certificate of occupancy allowing the Owner to
awarded to the Contractor providing certain take occupancy of the Project and utilize it for its
events occur or specific conditions are met by intended use.
the Contractor. The letter can sometimes serve
as a formal Notice to Proceed on the project.
Materials Re-use - A term used in the LEED
certification process that describes the reuse of
Lien, Mechanic's or Material - The right to take materials and products in order to reduce
and hold or sell an Owner’s property to satisfy demand for virgin materials and to reduce
unpaid debts for labor, materials, equipment, or waste, thereby reducing impacts associated with
services to improve the property. the extraction and processing of virgin
resources.
Lien Release - A written document from the
Contractor to the Owner that releases the Lien, Mediation – The action of mediation between
Mechanic’s or Material following its satisfaction. parties to effect an agreement or reconciliation.
Mediation implies deliberation that results in
Lien Waiver - (1) A written document from a solutions that may or may not be accepted by
contractor, subcontractor, material supplier or the contending parties.
other construction professional, having lien
rights against an Owner’s property, relinquishing Mechanic’s Lien - A legal claim against an
all or part of those rights. (2) Lien waivers are Owner’s property by a project participant to the
generally used for processing progress value of monies earned but not paid for by the
payments to prime or main or subcontractors as Owner or an employing contractor.
follows: Conditional Lien Waiver, Unconditional
Lien Waiver, and Final Lien Waiver.
Meeting Attendance Form - A generic form
used to record presence of persons attending a
Light Pollution - A term used in the LEED specific meeting.
certification process that describes the light
trespass from a building and site to the
Meeting Notes - A written report consisting of a
surrounding areas. LEED certified buildings
project number, project name, meeting date and
attempt to minimize this light pollution to
time, meeting place, meeting subject, a list of
increase night sky access, improve visibility due
persons attending, and a list of actions taken
to glare reduction and reduce development
and/or discussed during the meeting. Generally,
impact on nocturnal environments.
this report is distributed to all persons
attending the meeting and any other
Liquidated Damages (LD’s) – An amount of
money specified in a contract to be awarded in
Revised September 2010 10
person having an interest in the meeting. Open Bid - A specific term used where any
qualified bidder or estimator is given access to
Milestone - An activity with a duration of zero the prescribed project information. Open bid
(0) and by which progress of the project is project information is not private.
measured. A milestone is an informational
marker only; it is used to delineate strategic Open Grid Pavement - A term used in the
events of signal importance to monitor progress LEED certification process that describes
on the construction milestone schedule. It pavement that is less than 50% impervious and
marks a specific point in time, which point may contains vegetation in open cells.
be contractual.
Owner-Architect Agreement - A written form of
Milestone Schedule - A schedule of milestones contract between Architect and Client for
spanning from the start of construction to professional architectural services.
occupancy, used as the main measure of
progress to keep the project on schedule. It is Owner-Builder - A term used to describe an
usually summary in nature. Owner who takes on the responsibilities of the
general contractor to build a specific project.
Minor Change in Work – A minor change in
work is a written order by the Architect to make Owner Contingency – Owner-controlled
a change that does not involve adjustment in the contingency; see Contingency
contract sum or extension of the contract time
and is not inconsistent with the intent of the Owner-CM Agreement - Contract between
contract documents.
construction manager and client for professional
services.
-N-
Owner-Construction Agreement - Contract
Notice of Award - A letter from an Owner to a between Owner and Contractor for a
Contractor stating that a contract has been construction project.
awarded to the Contractor and a contract will be
forthcoming. It may also function as a Notice to Owner's Representative (OR) – An "Agent" of
Proceed. the Owner engaged to provide project
management of design and construction
Notice to Proceed - A notice from an Owner activities. The OR acts in the absence of and/or
directing a Contractor to begin work on a interest of the Owner to facilitate the chosen
contract, subject to specific stated conditions. design and construction delivery method. Scope
of services sometimes includes management of
non-construction components, such as
-O- equipment procurement and low voltage
performance specification; refer to RA and RE.
OAC Meeting - Meeting of the Owner, Architect
and Contractor. -P-
Occupancy Phase - A stipulated length of time Payment Bond - A written form of security from
following the construction phase, during which a surety company to the Owner, on behalf of an
contractors are bonded to ensure that materials, acceptable prime or main contractor or
equipment, and workmanship meet the subcontractor, guaranteeing payment to all
requirements of their contracts, and that persons providing labor, materials, equipment,
supplier- and manufacturer-provided warranties or services in accordance with the contract.
and guarantees remain in force.
Pending and Potential Change Orders –
Occupancy Schedule - A schedule of the Unexecuted change order or items identified to
activities and events required to effect have a cost or time impact to the project which
occupancy or the use of a facility for its intended may result in a change order.
purpose. It is used to determine if construction
progress will meet the occupancy date.
Preliminary Drawings - (1) The
drawings that precede the final
On-Site Supervision - Site-based personnel approved drawings. (2) Usually these
with supervisory responsibilities. drawings are stamped or titled
Revised September 2010 11
"PRELIMINARY", or "PRELIMINARY/NOT FOR Program Schedule - A schedule that spans
CONSTRUCTION"; and the "PRELIMINARY" is from the start of design to occupancy; includes
removed from the drawings upon being the signal activities which control the progress of
reviewed and approved by the Architect and/or the project from start to finish.
Owner and/or code official.
Progress Meeting - A meeting dedicated
Preliminary Lien Notice - A written notice given essentially to contractor progress during the
to the Owner by the subcontractors, suppliers, construction phase.
etc. The notice states if bills are not paid for the
labor, services, equipment, or materials Progress Payment - Partial payments on a
furnished or to be furnished, a mechanic's lien Contractor’s contract amount, periodically paid
may be placed against the property even though by the Owner for work accomplished by the
the Owner has paid the prime contractor. The Contractor to date determined by calculating the
notice may explain how the Owner can protect difference between the completed work and
himself against this consequence by (1) materials stored and a predetermined schedule
requiring the prime contractor to furnish a of values or unit costs.
release by the person giving the Owner notice
before making payment to the prime contractor Progress Schedule - A line diagram showing
or (2) any other method or device which is
proposed and actual starting and completion
appropriate under the circumstances. Some times for the respective project activities.
states (known as "lien notice states") require lien
notices to be filed and some do not. Failure to
file a lien notice in a lien-notice state usually Project - A word used to represent the overall
results in forfeiture of one's lien rights. scope of work being performed to complete a
specific construction job.
Pre-qualification - A screening process of
prospective bidders wherein the Owner gathers Project Budget - The target cost of the project
background information from a contractor or established by the Owner and agreed to be
construction professional for selection purposes. achievable by the team. The Project Budget
Qualifying considerations include competence, usually includes the cost of construction and the
integrity, dependability, responsiveness, bonding CM fee, plus any other line-item costs (land,
rate, bonding capacity, work on hand, similar legal fees, interest, design fees, CM fees, etc.)
project experience, and other specific owner that the Owner wishes to have included in the
requirements. budget.

Prime Contractor - (1) Any contractor having a Project Completion Graph (S-Curve) - A
contract directly with the Owner. (2) Usually the Project Completion Graph, commonly referred to
main (general) contractor for a specific project. as an "S-Curve Graph;” The graph resembles an
“S” and projects the estimated cash flow through
project completion; exclusive of retainage. The
Professional Engineer – A designation graph is based on a direct relationship of cash
reserved, usually by law, for a person or flow to the percentage of project completion.
organization professional qualified and duly
For a typical single-phase construction project,
licensed to perform such engineering services the first and last stages of construction
as structural, mechanical, electrical, sanitary, represented by 15-20% each of the construction
civil, etc.
schedule, makes up less then an equal amount
of percentage of completion. This allows for
Professional Liability Insurance - Insurance ramping up and down of the construction
provided for design professionals and process. The remaining interim period,
construction managers that protect the Owner representing 60-80% of the schedule is
against the financial results and liability of generally a straight line, which connects the
negligent acts by the insured. Usually referred to ramping up and down sections of the schedule;
as Errors and Omissions (E&O) insurance. this straight-line portion of the S-curve will
normally pass through approximately 50%
Professional Services - Services provided by a completion at approximately 50% of the
professional, in the legal sense of the word, or construction schedule.
by an individual or firm whose competence can
be measured against an established standard of Project Contingency Graph – A graph
care. projecting the use of hard cost
contingency through project completion.
Revised September 2010 12
Each month the committed hard cost the Contractor’s home offices and the on-site
contingency is plotted as a percentage of total project team; sub-contractors may be included.
hard cost contingency against the project
schedule. The projected hard cost contingency Project Site - The place where a structure or
line provides a baseline for analysis. It is group of structures was, or is to be located, i.e.,
assumed for the typical project that up to 40% of a construction site.
the hard cost contingency will be committed
during the first 30% of the project schedule; the Project Team - Consists of the
remaining 60% is a straight-line projection to the
Architect/Engineer, Construction Manager, and
end of the project. The 40% allows for the high- Owner, represented by their Level 1, 2, and 3
risk period during project startup: completion Persons, plus the designated leaders of
and outstanding governing approvals of design
contracted constructors.
documents, earthwork, and foundations. Where
the total cost for mandated change orders falls
below the projected graph line, it may be Punch List - A list prepared by the Owner or
assumed, unless otherwise noted, that sufficient his/her Authorized Representative of items of
funds remain to complete the project, assuming work requiring immediate corrective or
no extraordinary event(s) occurs. completion action by the Contractor.

Project Cost - All costs for a specific project Pure CM - A contractual form of the CM system
including costs for land, professionals, exclusively performed in an agency relationship
construction, furnishings, fixtures, equipment, between the Construction Manager and Owner.
financing and any other project related costs (CM Without Risk). ACM is the form from which
other CM forms and variations are derived.
Project Directory - A written list of all parties
connected with a specific project. The list -Q-
usually includes a classification or description of
the party (i.e., Owner, Architect, Attorney,
Quality Assurance (QA) - The procedure
General Contractor, Civil Engineer, Structural
established by the Project Team to inject and
Engineer, etc.); name, address, e-mail,
extract the level of quality designated by the
telephone and FAX numbers opposite their
Owner.
respective classifications or description. It is
particularly important that the emergency or after
hour telephone numbers are included. These Quality Control (QC) - That part of the Quality
numbers should be kept confidential if requested Assurance procedure that determines if
by the respective parties. specified quality is attained.

Project Manager - A qualified individual or firm Quality Engineering - That part of the Quality
authorized by the Owner to be directly Assurance procedure where the required level of
responsible for the day-to-day management and quality is accurately inserted into the
administration, and for coordinating time, construction documents by the A/E.
equipment, money, tasks and people for all or
specified portions of a specific project. -R-
Project Manual - An organized book setting
Rapidly Renewable Materials - A term used in
forth the bidding requirements, conditions of the
the LEED certification process that describes the
contract and the technical work specifications for
use of materials and products in buildings that
a specific project that documents and augments
are made from plants typically harvested within
the drawings. The Project Manual contains the
a 10-year cycle or shorter to reduce the use and
General Conditions, Supplementary and Special
depletion of finite raw materials and long cycle
Conditions, the Form of Contract, Addenda,
materials.
Change Orders, Bidding Information and
Proposal Forms as appropriate, and the
Technical Specifications. Record Drawings - A set of contract document
drawings, marked up as construction proceeds
to reflect changes made during the construction
Project Meeting - A meeting dedicated
process, which show the exact location,
essentially to contractor performance and
geometry, and dimensions of all
progress payments, involving supervisors from
elements of the constructed project as
installed. It is good practice to make As-
Revised September 2010 13
Built Drawings by marking the changes on Resident Engineer (RE) (inspector) - An
reproducible drawings such a mylar, vellum or individual permanently assigned at a job site for
sepias for the duplication purposes later. the purpose of representing the Owner's
interests during the construction phase, i.e.,
Regional Materials - A term used in the LEED Owner's Rep.
certification process that describes the use of
materials and products in buildings that have
been extracted, harvested, recovered or
-S-
manufactured within 500 miles of a construction
site to reduce the environmental impact resulting S-Curve – See “Project Completion Graph”
from transportation of these materials to the
project site. Safety Report - The Occupational Safety and
Health Act (OSHA) of 1970 clearly states the
RFI - Request for Information. A written request, common goal of safe and healthful working
usually a form, from the Contractor addressed to conditions. A Safety Report is prepared following
the Architect requesting additional information a regularly scheduled project safety inspection
on an issue in the contract specification or of the specific project.
drawings. The answer to an RFI can result in a
COP if either the Architect or Contractor Schedule of Values - The breakdown of a
believes there is a change in the contract terms. contract price into sub-items and sub-costs for
identifiable construction elements, which can be
RFP - Request for Proposal. 1) A request for evaluated by examination for contractor
uniform detailed information from prospective progress payment purposes.
CM practitioners being screened for a project; 2)
A document generated by the Architect Schematic Design Phase - The first phase of
requesting a cost proposal for a potential the A/E design professional's basic services in
change to the Contract. Generally an RFP is which he consults with the Owner to ascertain
used when no determination has been made the requirements of the project and prepares
whether or not the change will be executed. schematic design studies consisting of drawings
and other documents showing the scale, project
Reimbursable Expense - Charges to the components, and delineates the Owner’s needs
Owner covering costs for services that could not in a general way for the Owner’s approval.
or intentionally were not quantified at the time
the fee arrangement was made. Scope of Work (SOW) - A written range of view
or action; outlook; hence, room for the exercise
Reimbursable Expenses (or Costs) - Amounts of faculties or function; capacity for
expended for or on account of the project which, achievement; all in connection with a designated
in accordance with the terms of the appropriate project.
agreement, are to be reimbursed by the Owner.
Shared Savings - Contractor controlled
Release of Lien - A written action properly contingency or buyout savings remaining after
executed by an individual or firm supplying all approved contract cost-of–work has been
labor, materials or professional services on a accounted for, from which a percentage of the
project which releases his mechanic's lien savings, as defined in the construction contract,
against the project property. is returned to the Owner.

Renewable Energy Systems – Energy systems Shop Drawings - Detailed information and/or
that include technologies designed to capture drawings provided by material/ equipment
solar, wind, geothermal, water or bio-based suppliers or subcontractors demonstrating that
energy to satisfy on-site electrical demand in the item provided meets the requirements of the
buildings. This is component of the LEED contract documents, or how it is to be installed.
certification process. Also referred to as “Green
Power”. Soft Cost - Cost items in addition to the direct
construction cost. Soft Costs generally include
Resident Architect (RA) - An architect architectural and engineering, legal, permits and
permanently assigned at a job site who fees, financing fees, construction
supervises the construction work for the purpose interest and operating expenses,
of protecting the Owner's interests during leasing and real estate commissions,
construction.
Revised September 2010 14
advertising and promotion, and supervision. Structural Systems - The load bearing frame
assembly of beams and columns on a
Soft Cost Contingency – Owner-controlled foundation; the most common materials are
contingency limited to project Soft Costs; see wood, cement block, re-enforced concrete, or
Contingency. Hard cost contingency plus the steel. Steel beams and columns are generally
soft cost contingency generally represent the fabricated off-site and assembled on site. Other
total Owner’s contingency for the Project, unless systems such as non-load bearing walls, floors,
specific contingency accounts are established ceilings and roofs are generally constructed
for unique budget items the Owner wishes to within and on the structural system.
track and report separate from the hard and soft
cost contingency accounts. Subcontractor - A qualified subordinate
contractor who has a contract with the prime or
Source and Use Budget – Budget detailing the main contractor.
funds for all project-related costs and how they
are to be expended. Subcontractor Bond - A written document from
a subcontractor given to the prime or main
Special Conditions - (1) Amendments to the contractor by the subcontractor guaranteeing
General Conditions that change standard performance of his/her contract and payment of
requirements to unique requirements, all labor, materials, equipment and service bills
appropriate for a specific project. (2) A section of associated with the subcontract agreement.
the conditions of the contract, other than the
General Conditions and Supplementary Substantial Completion - The stage in the
Conditions, which may be prepared for a progress of the work when the work, or
particular project. (3) Specific clauses setting designated portion of the work, is sufficiently
forth conditions or requirements peculiar to the complete in accordance with the contract
project under consideration, and covering work documents so that the Owner can occupy or
or materials involved in the proposal and utilize the work for its intended use. (See also
estimate, but not satisfactorily covered by the "Beneficial Occupancy"). This date is normally
General Conditions. documented by the Owner and Architect on an
AIA Document G704.
Specifications - A detailed statement of
particulars, especially statements prescribing Sub-surface Investigation - (1) A term used to
materials and methods, and quantitative represent an examination of soil conditions
information pertaining to material, products, and below the ground. (2) Investigations include soil
equipment to be incorporated into a specific borings and geotechnical laboratory tests for
project. The most common arrangement for structural design purposes.
specifications substantially parallels the
Construction Specification Institute (CSI) format. Superstructure The part of a building or other
structure above the foundation.
Standard Details - A drawing or illustration
sufficiently complete and detailed for use on Supplemental Conditions - Supplements or
other projects with minimum or no changes. modifies the standard clauses of the general
Non-project-specific details. conditions to accommodate specific project
requirements. (synonymous with Supplementary
Start Date - The date that an activity or project Conditions).
begins.
Surety Company or Surety - A properly
Statute of Limitations - The period of time in licensed firm or corporation willing to execute a
which legal action must be brought for an surety bond, or bonds, payable to the Owner,
alleged damage or injury. The period securing the performance on a contract either in
commences with the discovery of the alleged whole or in part; or securing payment for labor
damage or injury; or in construction industry and materials.
cases with completion of the work or services
performed. Legal advice should be obtained. Sustainable Sites – A term used in the LEED
certification process that establishes
Stipulated Sum Agreement - A written sustainable design objectives and
agreement in which a specific dollar amount is integrates building location and
set forth as the total payment for performing the sustainable features as a metric for
contract. (See also "Lump Sum Contracts") decision making that encourages
Revised September 2010 15
development and preservation or restoration
practices that limit the environmental impact of
-U-
buildings on local ecosystems.
U. S. Green Building Council – A non-profit
agency established in 1993 representing the
-T- building industry consisting of over 11,000
companies and organizations that oversees and
Technical Inspection - Matching technical implements the LEED certification process of the
specification criteria with visual or mechanical design, construction, and operation of high
tests on the project site, or in a remote location performance, healthful, durable, affordable, and
or laboratory, to ascertain conformance. environmentally sound commercial, institutional,
and high rise residential buildings.
Technical Review - The critique of design
solutions, or criteria used for design solutions, Underwriter's Laboratories (UL) Label - A
by a party other than the one providing the label on a product or manufactured item
solutions or criteria, to determine adequacy and showing the material is regularly tested by, and
suitability of purpose. complies with the minimum standards of the
Underwriter's Laboratories specification for
safety and quality.
T&M - (1) An abbreviation for a contracting
method called Time and Materials (2) A written
agreement between the Owner and the Uniform Building Code (UBC) - The Uniform
Contractor wherein payment is based on the Building Code is one of the family of codes and
Contractor's actual cost for labor, equipment, related publications published by the
materials, and services plus a fixed add-on International Conference of Building Officials
amount to cover the Contractor’s overhead and (ICBO) and other organizations, such as the
profit. International Association of Plumbing and
Mechanical Officials (IAPMO) and the National
Time is of the Essence - A provision in a Fire Protection Association (NFPA), which have
construction contract by the Owner that punctual similar goals as far as code publications are
concerned. The Uniform Building Code is
completion within the time limits or periods in the
contract is a vital part of the contract designed to be compatible with these other
performance and that failure to perform on time codes, as together they make up the
enforcement tools of a jurisdiction.
is a breach and the injured party is entitled to
damages in the amount of loss sustained. e.g.,
"time is of the essence in the completion of the Unit Prices - A predetermined price for a
construction contract". measurement or quantity of work to be
performed within a specific contract. The
designated unit price would include all labor
Total Project Budget - All costs, hard and soft,
necessary to achieve completion of a project. materials, equipment or services associated with
the measurement or quantity established.
Transmittal - A written document used to
identify information being sent to a receiving -V-
party. The transmittal is usually the cover sheet
for the information being sent and includes the Value Engineering - A technical review process
name, telephone/FAX number, e-mail, and whereby the design documents are reviewed in
address of the sending and receiving parties. an effort to reduce the overall construction cost
The sender may include a message or by implementing alternate materials, processes,
instructions in the transmittal. It is also important and/or equipment while maintaining the original
to include the names of other parties the design intent and overall quality of the Project.
information is being sent to on the transmittal
form.
Verbal Quotation - A written document used by
the Contractor to receive a subcontract or
Travel Time - Wages paid to workmen under material cost proposal over the telephone prior
certain union contracts and under certain job to the subcontractor or supplier sending their
conditions for the time spent in traveling from written proposal via mail, e-mail or
their place of residence to and from the job. facsimile.

Revised September 2010 16


-W- -X-
Warranty - Assurance by a providing party that XCM - An abbreviation for "Extended Services -
the work, material, and equipment under CM"; a form of Construction Management (CM)
warranty will perform as promised or as required where other services such as design,
by contract. construction, and contracting are included with
Additional Construction Management (ACM)
Warranty Phase - The time period during which services provided by the Construction Manager.
a warranty is in force.
-Z-
Water Efficiency - A term used in the LEED
certification process that describes the
procedures to minimize potable water usage in Zoning - Restrictions of areas or regions of land
buildings through the use of improved and within specific geographical areas based on
efficient plumbing fixtures, use of recycled water permitted building size, character, and uses as
and use of water efficient landscaping materials. established by governing urban authorities.

Working Drawing - A drawing sufficiently zumBrunnen Cost-to-Complete – An estimate


complete with plan and section views, provided to account for all committed costs and
dimensions, details, and notes so that whatever a reasonable allowance for projected future
is shown can be constructed and/or replicated. costs to complete construction of a Project. This
estimate includes the following specific costs

Work Order (WO) - A written order (directive), zumBrunnen, Inc. – The nation’s leading
signed by the Owner or his Representative, of a independent construction consultant providing
contractual status requiring performance by the construction monitoring, facility assessment, and
Contractor. capital replacement budget services to the
senior living and healthcare fields, and
commercial real estate industry.

Revised September 2010 17

You might also like