TUTORIAL WORKSHEET
PERT/CPM
1. What are some questions that can be answered with PERT and CPM?
2. Briefly discuss what is meant by critical path analysis. What are critical path activities, and
why are they important?
3. Construct a Gantt chart for the following set of activities and indicate the project
completion time:
1 ___ 3
2 ___ 7
3 1 2
4 2 5
5 2 6
6 4 1
7 5 4
4. Sam Spade is the Director of Gum Shoe Ltd a Private Eye (Investigator) Firm. He has just
hired some UTech graduates and needs to put them through a special training program
before sending them out on any job. Sam has listed a number of activities that must be
completed before a training program of this nature could be conducted. The activities,
immediate predecessors and activity times appear in the following table:
A __ 2
B __ 5
C ___ 1
D B 10
E A, D 3
1 | Page
F C 6
G E,F 8
b. Determine the total project completion time and the critical path.
5. The Utech Student Union Event Planner is planning the Freshers’ Fete for next weekend in
Negril. In applying techniques she learnt in Decision Sciences class, she has identified the
activities that are necessary to prepare for her trip down to Negril. The following table lists the
activities, the immediate predecessors, and the activity times for the project.
A -------- 3
B -------- 7
C A 4
D B 2
E C,D 5
F A 6
G E 3
B. Find the earliest, latest, and slack times for each activity. Then find the critical path.
6. Consider the following project network and activity times (in weeks)
2 | Page
Activity A B C D E F G H
3 | Page
8. Based on the table below:
The following represents a project with four activities. All times are in weeks.
Activity Immediate Optimistic Most Pessimistic
Time
A - 2 8 14
B - 8 8 8
C A 6 9 18
D B 5 11 17
9. The manager of the Oak Hills Swimming Club is planning the club’s swimming
team program. The first team practice is scheduled for May 1. The activities,
their immediate predecessors, and the activity time estimates (in weeks) are as
follows.
Immediate Time (weeks)
Activity Description Predecessor Optimistic Most Probable Pessimistic
A Meet the Board - 1 1 2
B Hire Coaches A 4 6 8
C Reserve pool A 2 4 6
D Announce Program B,C 1 2 3
E Meet with coaches B 2 3 4
F Order team suits A 1 2 3
G Register swimmers D 1 2 3
H Collect Fees G 1 2 3
I Plan first practice E,H 1 1 2
a. Draw the project network.
b. Develop an activity schedule
c. What are the critical activities?
d. What is the expected completion time for the project?
10. A small software development project has nine major activities. The times are
estimated and provided in the table below.
4 | Page
Activity Immediate m
Predecessor
A −
B Α
C A 10
D B 14
E D
F C 10
G E, F
H C 10 14
I G, H
11.
Activity Immediate Optimis Most Pessimistic
tic
Predecessor Likel
y
A - 2 3 4
B - 2 5 8
C A 1 2 9
D A 5 5 5
E B, C 6 7 8
F B 12 12 12
G D, E 1 5 9
H G, F 1 4 8
================================