You are on page 1of 5

6.36.

Optirnal Design of Distribution Networks using Network Configuration and Load


A.F. Hi11 Kasiiii (*) , C. S. ozvereii (**),B. Railsay (***),A. P. Birch(****)

:k1)irectrir of Works Office. Universiti Teknologi, Malaysia


**University of Ahertay-Duudee, Dundee, Scotland, U K
***University of Duodee, Dundee, Scotland, U K
****Scottish Hydro-Electric, Perth, Scotland, UK

A IISTKACT circuit were calculated with a program developed using


In eltxtrical distribution system planning, careful a standard spreadsheet package, and were based on the
scrutiny of design assumptions, and philosophies, when calculated fault levels of the 22 kV network. Finally
coinhilied with the use of modern computer aided possibilities of further reducing the operational costs,
design tools, can result in significant improvements in using various Load Management Options were also
operational costs and levels of security. Furthermore investigated. After a brief review of the most common
the corresponding increase in operational reliability as approaches, it is demonstrated that shifting of the air-
well the ease of operation and maintenance will result conditioning load of the campus is economically
in additional tangible benefits. This paper presents the feasible with minimum investment and interruption to
results of a planning approach that looks at both the services.
investment and operational costs. The application of In conclusion, the paper demonstrates the importance
this newly devised methodology, has incorporated a of a computer aided comprehensive approach to
loss minimisation algorithm with commercially electrical distribution system planning and presents
available load flow, fault analysis and spreadsheet results in support of this argument. Further, the paper
progatns. argues that given the present availability of commercial
software and the availability of cheap and effective
computing power this approach is within the realm of
every planner. The results of this work indicate that
(hrvicw optimal network configuration studies and the related
The planning and design of a public distribution supply operational costs should be incorporated and evaluated
system is a complex iterative process. This is mainly respectively at every design stage to ensure that the
because the designer has to meet the present power installation will be operated and maintained optimally
requirements, while ensuring that the network has a after its completion.
ccrtain degree of flexibility to meet future load growth
in thc area. Traditionally, distribution network A LOSS MINIMISING ALGORITHMIC (LMA)
planners try to overcome the uncertainty in forecasting, TECHNIQUE
the future load growth, by over sizing the elements;
such as cables and transformers. However, failure to Network Configuration Management
calculate the design and operational costs and the The existing network in UTM has been influenced
benefits of the network configuration management, partly by the philosophies and policies of earlier
during the design stage, will result in future financial planners and designers. As more than 50% of the
losses even for a for a medium sized network. substations have been built, the planned mesh
The expansion project for a 40 MVA, 22 kV arrangement of the UTM network would provide
Distribution Network of University Campus of increased security of supplies to the substations
Universiti Teknologi Malaysia (UTM) is presented as a distributed within the campus. Although this
case study to analyse the operational costs of the arrangement requires more substationkquipment, it is
present and planned network expansion. Firstly, the more efficient in terms of total circuit costs. This mesh
paper will explain the methodology used and report the arrangement is easier to extend and has a higher
results, that demonstrate the effect of a loss minimising utilisation of circuits when fully developed than a ring
algorithmic (LMA) technique , in reducing the system, although this can result in higher network
operational costs, through network reconfiguration. losses [2]. Under normal operating conditions, the
Security and fault analysis studies were also conducted network is operated as a number of radial feeders. On
to check the reliability of the optimal configuration. the occurrence of fault between the substation and the
An alternative design philosophy was used for sectionalising open point, the normally open point can
transformer sizing and placement. Load flow and be closed to provide back-up supplies once the faulted
economic return calculations were conducted to section has been isolated .
compare the results between the existing and the Configuration management deals with the change of
proposed projects. To complete this comprehensive network configuration by altering the status of the
design evaluation, potential fault levels of the LV sectionalising switches or normally open points (NOP).

ClRED 97,2-5 June 1997, Conference Publication No. 438, 0 IEE, 1997
6.36.2

NOP \ are used for effective co-ordination of protection network. Thus, it is necessary to simulate the LF again
so that ;i fault may be easily located and isolatcd by with the original values of R and X on the network to
eu\uring that each load is supplied by only one obtain the correct values of voltages and currents (and
transforincr [ 11. other network configurations).
I11 configuration m;inagement, switching is also used LMA Steps
to: Create two network program files of the network.
1. reduce system losses In one of the files, make the value of X of the line equal
2. load balancing to R.
3. restoration of supply after fault Using REX file, run Load Flow (LF)
Identify Summation Nodes in REX file.
Loss Miiiiniiser Algorithm (LMA) List down the currents entering each nodebus [group
LMA is c " k d out by running a load flow simulation 11. If there is more than one node, the lowest value of
on thc network to determine the optimum NOP. It is current from each node is then selected and listed into
based 011 the recursive solution of a full Newton- the second group [group 21.
Rnphson's AC load flow. In this method, the network is If there is only one node, take the line with the lowest
reconlignrecl by changing the status of the current as NOP. If there is more than one nodes,
sectionalising switches which will determine the identify the line which has the highest current in group
optimal NOP of the network. It is also used to help 2.
power engineers to identify an optimal network If there is no node, select the line element of the ring
configuration when a significant change of load is network with the lowest current as NOP.
detected or when recovering from a power interruption. Open this line in REX and RNX files.
The optimal NOP will result in the minimal resistive Run LF in RNX file and record the losses.
losses for the network. Return to REX and run LF again.
Network losses are nor~nallydetermined by network Repeat step d until the network is fully radialised.
parameters which are made up of line/cable resistance, When this is achieved, the losses obtained fi-om RNX
load distribution at the busses and network file is the optimum losses.
con tipration. Minimum losses could only be achieved If some part of the network is still in a ring
by hnving an optimal network configuration. For a configuration, run the LF in REX network to detcrmine
network fed from a single source, the NOP is the lowest current-carrying conductor.
tletermined from the position of current minima Remove this line and run LF on the RNX file.
tlowing in the line (cable or transmission line) between Record the final network losses parameters.
the nodes. The minimum brnnch current is determined
by solving krchoff-s Current atid Voltage Laws of a Operational Constraints
purely resistive network whose branch resistance is LMA is a tool used eo select or determine the optimal
cclual to the resistive .component of the branch operating conditions of a balanced network using load
impedance. This is made on the assumption that if all flows simulation. While running the LF, the normal
the lines of the network are made up of similar cable, operational (overload and voltage) constraints must be
thcti the current minima approach will produce a observed and all the circuits must be radialised.
reasonable approximation [3].
However, since the conductor shares current in inverse Phase I & II(1985 - 1989) The Present
proportion to their impedance which is dependent on X Network
and R, the method will only produce accurate results if The present network configuration is shown in Figure
the X/R ratios of the conductors are identical. 1. It was established in 1989 after the completion of
Therefore, the minimum loss position should be Phase 11. There are thirteen substations (including the
determined by a load flow that (while considering the Main Intake Substation) in service. The NOP between
whole load current) is governed by the resistive element SS03 and SSO4 was assigned by the consultant soon
of the line impedance. This load flow is similar in after the ring was completed in 1989.
principle to a dc load flow study [4]but must also
account for the variations in load power factor and any Phase III (1993) Planned Network Expansion
transfonners which are present. Figure 2 shows that there are seven substations
If the react" of each line is set equal to its resistance currently under construction in this phase. They are
value, the resulting impedance is directly proportional expected to be commissioned by the end of this year
to R, by a factor of 42. The resulting load flow will (1993). When completed, the network single-line
then he solely dependent on R with the current minima diagram will be as shown in Figure 3.
coinciding with the normal open position for minimum
loss. Since the cable/line parameters was modified by Phase N (1995)The Planned Network Expansion
making X = R, the voltage and current values obtained The planned network configuration with NOPs is
from LF simulation are not the actual values on the shown in Fig. 5.4. When phase IV is completed, there

ClRED 97, 2-5 June 1997, Conference Publication No. 438, 0 IEE, 1997
6.36.3

will he twenty-five substations in the ~ m p u s .With It has also been inferred that to overcome the
tliese 25 substations which will be fed via five feeders uncertainties due to the variation in short circuit
from SSOl (Main hit'ake Substation), five NOPs would current at various 22 kV and 415 V LV boards,
hc required during normal operations. These NOPs standardisation of the switch gear or circuit breaker
have alrendy been determined during the planning short circuit rating is the best solution to be adopted.
stage based on experience and approximation of total This will ensure the safety of the 0 & M personnel and
fcecier currents. prevent any accidental damage to the switch gear from
Summary of Results and Discussions for LMA analysis unexpected rise in fault current. From the simulations
Table 1 summarises the results obtained from and calculations carried out, the distribution system of
simulntions. The table shows that the losses on the the campus can generally be divided into three short
reconfigured network is lower than the losses of the circuit zones. This would be a useful reference for the
originally planned network. This clearly demonstrates 0 & M staff of the campus.
onc of the benefits of network reconfiguration.
Although the difference in losses is relatively small, the DISCUSSION
total costs of losses would be considerable over the life The analysis of the demand characteristic of the
span of the network. planned 22 kV campus network has indicated that there
It is also interesting to note that the simulated results is an element of over design during its planning stage.
have shown that tlie NOPs found in the earlier phase This could have been caused by the lack of concern on
of the project were not the same as the NOPs of the the part of the designers over the operational costs or
later project phase. This is clearly demonstrated in the failure of the university's management to stress its
Table 2. importance. This is evidenced from the value of
From the table it can be seen that the NOP at SSO4- utilisation factor (TJF) of only 25% in 1992 or 35% in
SSOS was maintained as the project progressed from the year 2005, 20 years after the first part of the
phase I&I1 to phase I11 with an additional NOP at network was commissioned. The need to re-evaluate the
SS12-SS13. Simulated result on Phase IV shows that effects of the network design is further enhanced by the
the NOP at SSO4-SSO5 was moved to SSO3-SSO4 while escalation of the campus electricity bill to > RM 4
thc second NOP during Phase 111 at SS12-SS13 was million in 1992 . This study has evaluated the
maintained. Three new NOPs were added to the system, performance of various network elements in the system
turning the network into a radial configuration for including their positive or negative contribution to the
normal operating condition. Thus, the location of the operational costs of the campus. Various options were
NOPs are not necessarily fixed throughout the life of studied and proposed as alternatives or improvements
the network. They may have to be reconfigured when to the existing parameters in an effort to solve the
necessary to keep the network losses to a minimum. above uncertainties.
Close monitoring of the network configuration by the 0 LF simulations carried out on the campus network
& M personnel is necessary especially when the configuration using SIMPOW with the LMA technique
network is still in the process of expansion. have produced some useful and encouraging results.
The use of an LMA technique to determine the NOP The simulations have shown that the NOPs on the
and optimal network configurations has indicated existing phase I&II and the planned network (phase I11
nctwork loss reduction could be achieved by & IV) were different from the NOPs obtained through
reconfiguring the existing part of the network which is the LMA technique. This finding is rather fortunate as
already in operation. It has also shown that the NOPs the next 50 percent of the network will be
on the existing network, the network that is currently commissioned within the end of this year and the next
under construction (phase 111) and the part that is going two years where the new configuration can be adopted.
to he built in phase N have to be reconfigured Although the difference in the present-worth cost of
according to the results obtained for optimal network cable losses between the planned and the optimal
operating condition. network is found to be only RM 7,120.64 (E 3,560),
there are other indirect benefits to be gained that cannot
Effect of Changing NOP on Fault Level be quantified. The optimal network configuration is
Fault levels and currents have been identified at the 22 expected to lengthen the life span of the network
kV and 415/240V voltage levels within the distribution equipment as the network is operated at its optimal
network. The assumption that ,. short circuit fault configuration. This will indirectly reduce the 0 & M
currents are 17 kA and 43 kA throughout the 22 kV expenditure.
and 415V sections respectively. The variation of short Security assessments carried out using the same
circuit currents at the 22 kV and 415 V switchboards package have proved that the distribution capability of
due to the changing of NOPs during N-1 security state the network is very secure. Even after losing the two
or substiition maintenance does not cause the fault level most heavily loaded feeders from the main intake
to exceed the ceiling values of 650 MVA and 31 MVA substation, the remaining network elements can still
respectively. sustain the load without any of the buses or lines
_I_

6.36.4

experiencing 'an under voltage or overloading chiller units during the day will significantly reduce the
respectively. Further simulations have shown that in peak MD of the campus. The proposed load-shifting is
the absence of inductive air-conditioning load and the expected to achieve a pay-back-period of about three
presence of highly capacitive charging of the 22 kV years on the additional capital spent after which about
underground cable during the night do not cause any RM 200,000 is expected to be saved annually. This is
inauked over-voltage 011 the network. The highest approximately 5% of the mnpus annual electricity bill
voltage recorded from the night load simulation was for 1992. Various other DSM techniques were also
22.0004 kV. proposed in trying to reduce the peak MD load of the
The study has showed that the sharp increase of campus.
electricity bill was partly contributed by the cost of Fault simulations and calculations carried out using
transformer losses. The total present-worth cost of SIMPOW and a standard spreadsheet package have
transformer losses has 'amounted to RM 297,846.40 provided a useful information on the fault level
(574,451.60) by the end of 1992. The study has shown distribution of the network. This knowledge is very
that this cost is still increasing as more transformers useful the to the 0 & M engineers as more transformers
are being added to the network which is expected to and circuit breakers are being added to the M Y and LV
reach its targeted completion in 1995. If no action is sections of the network respectively. The simulations
taken to modify the planned number and sizes of have also given an awareness that a fault level at a
transformers to be installed, by the year 2005 the substation can be affected by the position of the NOPs
present-worth cost of losses will amount to R M on the network particularly those which have more than
1,029,399.56 (&257,349.89). one routes of supply from the source. The knowledge
Three alternatives are proposed to reduce the cost of and awareness gained from the simulations will help in
transformer losses in the network. The fvst alternative some decision-making process to ensure safety in the
i h to shift some of the existing transformers to Phase IV daily operation and maintenance of the network.
which is expected to start in one or two years time. This To conclude, the six-month study has only managed to
could reduce the cost of losses by about 11% in 20 focus on a few elements present in the campus
years. The second alternative could reduce the cost of distribution network. The importance of the design
losscs by 29% by switching off one of the double stage in any project has been highlighted and must be
transformers available in seven substations within the realised by the designers and clients alike. With the
cmpus. Although this alternative seems quite advent of computers and the availability of power
promising, the effect of surges caused by the simulation packages today, network designers are able
tra1isformer switching, the practicality of switching-in to simulate and predict the behaviour of an installation
and out of the transformer and effect on the life span of well before it is built. Optimal network configuration
thc equipment are some of the factors to be thoroughly and operational costs should be incorporated and
considered. Stnndardisation of transformer sizes is the evaluated respectively while the design is still on the
third alternative proposed. On paper, standardisation drawing board to ensure that the installation will be
could save as much as 40% of the total transformer operated and maintained optimally after its completion.
losses by the y e s 2005. Basically it involves the
purchase of smaller transformers < 1 MVA and selling REFERENCES
off the existing large transformers > 1 MVA. 1) Muchayi, E, Birch, A. P., ozveren, C. S., " A Study of
Although <an initial additional capital is required, the Loss Accounting and Minimisation in Electrical
savings anticipated after standardisation is carried out Distribution Systems", 28th Universities Power
will be recovered just after three months. Engineering Conference KJE'EC 931, 21-23
Tariff structure shows that the Maximum Demand September, pp. 245-247.
(MD) of the campus load is a major contributing factor 2) Lakervi, E and Holmes E.J. (1980) Electricity
to electricity bill. Therefore, investigation on the Distribution Network Design. Peter Peregrinus Ltd,
opportunities to implement Demand-side Management Stevenage, UK. ISBN 0 86341 151 7
(DSM) to reduce and manage the electrical load of the 3) Merlin, A and Back, H, Search for a Minimal-Loss
cmnpus were made. h-conditioning ( N C ) load which Operating Spanning Tree Configuration for an Urban
Power Distribution System, Proc. of Power System
accounts for about 65(%of the total campus MD is the
Operation & Control (PSOC), Cambridge 1975, Paper
inain target in a11 attempt to reduce the peak MD of the 1.216
ciunpus which occurs during the day. Preliminary
result shows that it is possible to shift about 53% of the Phase Normal Open Point (NOP)
total cnmpus N C load from the day on-peak to the off-
I & II (1985-89) SSO4-SSO5
peak period.
The proposed DSM solution is by running the chiller
III (1993) sso4-sso5& ss12-ss13
IV (1995) sso3-sso4,ss12-ss13, SS15-
units at night to cool the water and store it in insulated
water wiks. The cold water is later used in the air- I I SS16,SS17-SS19&SS18-SS25 I
conditioning process during the day. Turning off the Table 1 Normal Open Points (NOP)
6.36.5

Exidng LMA % Difference


Network (2) Network (3) (4)
[(2)-(3)/(2)]xlOO%
I

Network Losses Pr(kW) Qr (kVAr) Pr OCW) QrOtVAr) % DPr % DQr


I & I1 ( 1985-89) 3.42 1.88 2.96 1.63 13.5 13.3
111 (1YY3) 1.23 3.99 . 6.69 3.69 7.5 7.5
IV (1995) 14.44 7.96 11.49 6.32 20.4 20.6
Table 2 Network Losses
~~~~~ -
PHASE I & II (1989)

I I I

Figure1 Phase I & II (1989)


PHASE lll(l993)

I
I-'

I - T
ss11

Figure 2 Phase III (1993)

~~ ~~ ~ ~

Figure 3 22KV Network by 1995

You might also like