You are on page 1of 48

Standard CT Operating Procedures

General Operating Procedures & Guidelines

Schlumberger Private
Revision History
Rev A – Nov 2006 Version for peer review
Rev B – Feb 2007 Final version
Rev C – Feb 2013 Added QHSE section; Removed "Tie off to CTU
and crane outriggers" from Figure 8 in H ≤ 40, per
InTouch ticket 6154225
Rev D – Dec 2013 Corrected bleed off step in section 4.1.2 PT2
Rev E – Sep 2014 Updated references to Standards from WS to WI

Copyright © 2014 Schlumberger


General Operating Procedures & Guidelines Page i of 45
Revision E September 2014

Table of Contents

1 Introduction ...................................................................................................... 1
2 QHSE................................................................................................................. 2
2.1 Standards .................................................................................................................................. 2

2.2 Safety ......................................................................................................................................... 2

3 Generalized Job Execution Process .............................................................. 3


3.1 Running into the Well ............................................................................................................... 4
3.1.1 Preparing to access the well .......................................................................................... 4
3.1.2 Running the CT String into the Well .............................................................................. 5

3.2 Executing the Treatment .......................................................................................................... 7


3.2.1 Prepare to execute the treatment .................................................................................. 7

Schlumberger Private
3.2.2 Executing the treatment ................................................................................................. 8

3.3 Pulling out of the well .............................................................................................................. 9


3.3.1 Retrieving the CT string ................................................................................................. 9
3.3.2 Completing the CT Operation ......................................................................................10

4 Pressure and Function Testing .................................................................... 11


4.1 Pressure Testing ....................................................................................................................11
4.1.1 Pressure Test One (PT-1) ...........................................................................................11
4.1.2 Pressure Test Two (PT-2) ...........................................................................................12
4.1.3 Pressure Testing Lubricator and Riser Connections ...................................................14

4.2 Slip and Shear Ram Function Testing ..................................................................................14


4.2.1 Slip Ram Testing .........................................................................................................14
4.2.2 Shear Ram Testing ......................................................................................................14

4.3 Accumulator System Function Testing ................................................................................15


4.3.1 Accumulator system testing .........................................................................................15

5 CT Equipment Rig Up and Operation ........................................................... 15


5.1 Stabbing the CT string ...........................................................................................................15
5.1.1 Conventional CT String Stabbing ................................................................................16
5.1.2 CT String Stabbing with a CT Snake ...........................................................................17

5.2 CT Connector Make Up and Testing .....................................................................................17

5.3 Flange Make-Up ......................................................................................................................19


5.3.1 General Flange Make Up.............................................................................................19
5.3.2 HP CT Flange Make Up ...............................................................................................20

5.4 Securing the Injector Head and Wellhead Equipment ........................................................24


5.4.1 Land Based Operations ...............................................................................................25

Copyright © 2014 Schlumberger


General Operating Procedures & Guidelines Page ii of 45
Revision E September 2014

5.4.2 Offshore Operations – Fixed Structure ........................................................................27


5.4.3 Offshore Operations - Floating Vessel ........................................................................27

6 CT String ......................................................................................................... 28
6.1 Cleaning the CT String ...........................................................................................................28
6.1.1 Pickling the CT String ..................................................................................................28
6.1.2 Neutralizing the CT string ............................................................................................29
6.1.3 Post-job Purging ..........................................................................................................29

6.2 Corrosion Mitigation ..............................................................................................................30


6.2.1 In-service Corrosion Protection ...................................................................................30
6.2.2 In-storage Corrosion Protection ...................................................................................30

7 Depth Control and Correlation...................................................................... 32


8 Reverse Circulation ....................................................................................... 33
9 Tool Deployment Systems ............................................................................ 34

Schlumberger Private
9.1 Bar Deployment Method ........................................................................................................34

9.2 CIRP Deployment Method......................................................................................................37

10 CT Operations in Extended Reach Wellbores ........................................... 38


10.1 Pipe Straightener ..................................................................................................................38
10.1.1 Pipe Straightener Operation ......................................................................................38

10.2 Metal-to-Metal Friction Reducers ........................................................................................39

11 Downhole Tools ........................................................................................... 40


11.1 CT Tool Threads ...................................................................................................................40

11.2 Tool String Make-up and Break-out ....................................................................................40


11.2.1 Thread Locking Compounds......................................................................................42

11.3 Function Testing Downhole Tools ......................................................................................42

12 Offshore CT Equipment ............................................................................... 43


12.1 Towers and Jacking Structures ..........................................................................................43

12.2 Lifting Frames .......................................................................................................................44

12.3 Boat Spooling .......................................................................................................................44

13 Nitrogen Services ........................................................................................ 45


13.1 Nitrogen Transfer .................................................................................................................45

Copyright © 2014 Schlumberger


General Operating Procedures & Guidelines Page 1 of 45
Revision E September 2014

1 Introduction

Schlumberger Private
Standard Operating Procedure

Title or Key Operational Phase

Copyright © 2014 Schlumberger


General Operating Procedures & Guidelines Page 2 of 45
Revision E September 2014

2 QHSE
2.1 Standards

2.2 Safety

Schlumberger Private

Copyright © 2014 Schlumberger


General Operating Procedures & Guidelines Page 3 of 45
Revision E September 2014

3 Generalized Job Execution Process

Before running in the well


• Prepare fishing diagram
• Observe/record wellhead
conditions
• Manage/confirm wellbore After completing the CT operation
returns • Observe/record wellhead
• Set and prepare monitoring conditions
and recording equipment
• Confirm equipment shutdown
settings

Schlumberger Private
Running the CT string into the well Pulling out of the well
• Manage speed • Confirm/prepare tool string for
• Observe restrictions retrieval
• Check and mange wellbore returns • Observe operating limits
• Conduct pull-tests • Observe CT string forces model
• Observe operating limits • Observe restrictions
• Observe CT string forces model • Manage fluid circulation
• Manage fluid circulation
• Observe tagging obstructions

Executing the treatment

Prepare to execute the treatment


• Manage/confirm wellbore fluid/hydraulics
• Manage/confirm CT string fluid/hydraulics
• Manage/confirm CT string depth and treatment
depth
Executing the treatment
• Manage fluid circulation
• Observe/manage wellbore returns
• Manage CT string speed and load on BHA
• Observe critical operating parameters
• Observe treatment responses
• Manage tool operation
• Determine/confirm end of treatment
• Implement treatment change to suit conditions

Figure 1. Generalized CT job execution process.

Copyright © 2014 Schlumberger


General Operating Procedures & Guidelines Page 4 of 45
Revision E September 2014

3.1 Running into the Well

3.1.1 Preparing to access the well


Confirm fishing diagram for toolstring has been prepared

Standard Operating Procedure


Requirements for fishing diagram

Schlumberger Private
Confirm status of sub-surface safety valve (SSSV) if applicable

Observe/record wellhead conditions

Copyright © 2014 Schlumberger


General Operating Procedures & Guidelines Page 5 of 45
Revision E September 2014

Arrange/confirm facilities for wellbore returns


Set and prepare the monitoring and recording equipment






Confirm equipment shutdown settings

Schlumberger Private

3.1.2 Running the CT String into the Well

Wellbore schematic diagram


Running through the surface equipment stack and wellhead


Running into a well


Copyright © 2014 Schlumberger


General Operating Procedures & Guidelines Page 6 of 45
Revision E September 2014

Passing through wellbore restrictions


Check and manage wellbore returns

Schlumberger Private

Conduct pull-tests

Observe operating limits


Copyright © 2014 Schlumberger


General Operating Procedures & Guidelines Page 7 of 45
Revision E September 2014

Compare weight indicator readings - model vs. actual


Manage fluid circulation


Tagging an obstruction

Schlumberger Private
3.2 Executing the Treatment

3.2.1 Prepare to execute the treatment


Manage/confirm wellbore fluid/hydraulics

Manage/confirm CT string fluid/hydraulics


Manage/confirm the CT string depth and treatment depth


Copyright © 2014 Schlumberger


General Operating Procedures & Guidelines Page 8 of 45
Revision E September 2014

3.2.2 Executing the treatment


Manage fluid circulation





Observe/manage wellbore returns

Schlumberger Private


Manage CT string speed and load on BHA




Observe critical operating parameters

Copyright © 2014 Schlumberger


General Operating Procedures & Guidelines Page 9 of 45
Revision E September 2014

Observe treatment responses


Manage tool operation


Determine/confirm end of treatment


Schlumberger Private
Implement treatment change to suit conditions

3.3 Pulling out of the well

3.3.1 Retrieving the CT string


Confirm/prepare tool string for pulling out of hole

Copyright © 2014 Schlumberger


General Operating Procedures & Guidelines Page 10 of 45
Revision E September 2014

Observe operating limits


Compare weight indicator readings - model vs. actual


Passing through wellbore restrictions


Schlumberger Private

Manage fluid circulation





3.3.2 Completing the CT Operation


Observe/record wellhead conditions

Copyright © 2014 Schlumberger


General Operating Procedures & Guidelines Page 11 of 45
Revision E September 2014

4 Pressure and Function Testing

4.1 Pressure Testing

Schlumberger Private
4.1.1 Pressure Test One (PT-1)

Standard Operating Procedure


Pressure Test One (PT-1)

Copyright © 2014 Schlumberger


General Operating Procedures & Guidelines Page 12 of 45
Revision E September 2014

Schlumberger Private
4.1.2 Pressure Test Two (PT-2)

Standard Operating Procedure


Pressure Test Two (PT-2)

Copyright © 2014 Schlumberger


General Operating Procedures & Guidelines Page 13 of 45
Revision E September 2014

Schlumberger Private

Copyright © 2014 Schlumberger


General Operating Procedures & Guidelines Page 14 of 45
Revision E September 2014

4.1.3 Pressure Testing Lubricator and Riser Connections

4.2 Slip and Shear Ram Function Testing

4.2.1 Slip Ram Testing

Schlumberger Private

4.2.2 Shear Ram Testing

Copyright © 2014 Schlumberger


General Operating Procedures & Guidelines Page 15 of 45
Revision E September 2014

4.3 Accumulator System Function Testing


4.3.1 Accumulator system testing

Schlumberger Private


5 CT Equipment Rig Up and Operation


5.1 Stabbing the CT string



Copyright © 2014 Schlumberger


General Operating Procedures & Guidelines Page 16 of 45
Revision E September 2014

5.1.1 Conventional CT String Stabbing

Schlumberger Private

Copyright © 2014 Schlumberger


General Operating Procedures & Guidelines Page 17 of 45
Revision E September 2014

5.1.2 CT String Stabbing with a CT Snake

Schlumberger Private
5.2 CT Connector Make Up and Testing
Check condition of seal and seal areas

Copyright © 2014 Schlumberger


General Operating Procedures & Guidelines Page 18 of 45
Revision E September 2014

Check condition of threads


Follow connector manufacturer’s make-up procedure


Perform pull test on assembled connector


Standard Operating Procedure


CT connector pull test

Schlumberger Private

Copyright © 2014 Schlumberger


General Operating Procedures & Guidelines Page 19 of 45
Revision E September 2014

5.3 Flange Make-Up

5.3.1 General Flange Make Up

Schlumberger Private
Standard Operating Procedure
General Flange Make Up

Copyright © 2014 Schlumberger


General Operating Procedures & Guidelines Page 20 of 45
Revision E September 2014

Schlumberger Private
Figure 2. Bolt tightening sequence.

5.3.2 HP CT Flange Make Up

Copyright © 2014 Schlumberger


General Operating Procedures & Guidelines Page 21 of 45
Revision E September 2014

Figure 3. Load-indicating washer and hardened back-up washer.

Schlumberger Private
Figure 4. Load-indicating washer assembly in place.

Copyright © 2014 Schlumberger


General Operating Procedures & Guidelines Page 22 of 45
Revision E September 2014

Schlumberger Private
Required Wrench
Equipment Size Bolt Size (in.) Nut Size (in.)
Capacity (ft-lbf)

2-9/16 10k 7/8 1-7/16 400


3-1/16 10k 1 1-5/8 600
4-1/16 10k 1-1/8 1-13/16 800
5-1/8 10k 1-1/8 1-13/16 800
2-9/16 15k 1 1-5/8 600
3-1/16 15k 1-1/8 1-13/16 800
4-1/16 15k 1-3/8 2-3/16 1600
7-1/16 15k 1-1/2 2-3/8 2200

Figure 5. Make-up wrench selection guide.

Copyright © 2014 Schlumberger


General Operating Procedures & Guidelines Page 23 of 45
Revision E September 2014

Standard Operating Procedure


HP CT Flange Make Up

Schlumberger Private

Figure 6. Bolt tightening sequence

Copyright © 2014 Schlumberger


General Operating Procedures & Guidelines Page 24 of 45
Revision E September 2014

5.4 Securing the Injector Head and Wellhead Equipment

Schlumberger Private

CT String OD (in.) Chain Type Wire Rope Type Guy Wire Preload

OD ≤ 1.75 3/8-in. transport 1/2-in. (6x19 or 6x37) 1500 to 2000lbf


OD > 1.75 5/8-in. transport 5/8-in. (6x19 or 6x37) 2250 to 2750lbf

Figure 7. Minimum specifications for support guy systems.

Copyright © 2014 Schlumberger


General Operating Procedures & Guidelines Page 25 of 45
Revision E September 2014

5.4.1 Land Based Operations

Stack Height (ft) Mitigating Conditions Key Components

Schlumberger Private
Four-point restraint from top of injector frame
WHP > 10,000psi
Anchors driven per site plan A
WHP ≤ 10000 psi
Three-point restraint from top of injector frame
H ≤ 40 Crane opposes CTU
Three-point restraint at top of injector
WHP ≤ 10000 psi
Anchors driven per site plan B
Crane does not oppose CTU
Tie off to CTU and anchors
Four-point restraint from top of injector frame
40 < H < 110 All Category Operations Four- point restraint from middle of stack
Anchors driven per site plan A
H ≥ 110 Contact InTouch CTS for Engineering Support

Figure 8. Pressure control stack support guidelines for land-based operations.

Copyright © 2014 Schlumberger


General Operating Procedures & Guidelines Page 26 of 45
Revision E September 2014

Schlumberger Private
Figure 9. Site plan A

Figure 10. Site plan B

Copyright © 2014 Schlumberger


General Operating Procedures & Guidelines Page 27 of 45
Revision E September 2014

5.4.2 Offshore Operations – Fixed Structure

Stack Height (ft) Mitigating Conditions Key Components

Four-point restraint from top of injector frame


H ≤ 40 All Category Operations
Sound structural tie off point

Schlumberger Private
Four-point restraint from top of injector frame
40 < H < 110 All Category Operations Four- point restraint from middle of stack
Sound structural tie off point
H ≥ 110 Contact Business Segment for Engineering
All Category Operations
Support

Figure 11. Pressure control stack support guidelines for offshore operations.

5.4.3 Offshore Operations - Floating Vessel

Copyright © 2014 Schlumberger


General Operating Procedures & Guidelines Page 28 of 45
Revision E September 2014

6 CT String
6.1 Cleaning the CT String

Schlumberger Private
6.1.1 Pickling the CT String



Pickling fluid composition

Copyright © 2014 Schlumberger


General Operating Procedures & Guidelines Page 29 of 45
Revision E September 2014




Pickling fluid volume

Pickling treatment rate

Disposal of used pickling fluid

6.1.2 Neutralizing the CT string

Schlumberger Private

6.1.3 Post-job Purging






Copyright © 2014 Schlumberger


General Operating Procedures & Guidelines Page 30 of 45
Revision E September 2014

6.2 Corrosion Mitigation

6.2.1 In-service Corrosion Protection

Schlumberger Private

6.2.2 In-storage Corrosion Protection


Copyright © 2014 Schlumberger


General Operating Procedures & Guidelines Page 31 of 45
Revision E September 2014

Internal CT String Protection

Schlumberger Private
External CT String Protection

Copyright © 2014 Schlumberger


General Operating Procedures & Guidelines Page 32 of 45
Revision E September 2014

7 Depth Control and Correlation



Schlumberger Private

Copyright © 2014 Schlumberger


General Operating Procedures & Guidelines Page 33 of 45
Revision E September 2014

8 Reverse Circulation

Schlumberger Private

Copyright © 2014 Schlumberger


General Operating Procedures & Guidelines Page 34 of 45
Revision E September 2014

9 Tool Deployment Systems

General considerations for tool deployment


Schlumberger Private

9.1 Bar Deployment Method

General considerations for bar deployment method







Copyright © 2014 Schlumberger


General Operating Procedures & Guidelines Page 35 of 45
Revision E September 2014

General Procedure – Conductor Deployment

Schlumberger Private

Copyright © 2014 Schlumberger


General Operating Procedures & Guidelines Page 36 of 45
Revision E September 2014

General Procedure – Fluid Deployment

Schlumberger Private

Copyright © 2014 Schlumberger


General Operating Procedures & Guidelines Page 37 of 45
Revision E September 2014

9.2 CIRP Deployment Method



Schlumberger Private

Copyright © 2014 Schlumberger


General Operating Procedures & Guidelines Page 38 of 45
Revision E September 2014

10 CT Operations in Extended Reach Wellbores

10.1 Pipe Straightener

Schlumberger Private

10.1.1 Pipe Straightener Operation

Copyright © 2014 Schlumberger


General Operating Procedures & Guidelines Page 39 of 45
Revision E September 2014

10.2 Metal-to-Metal Friction Reducers

Schlumberger Private


Copyright © 2014 Schlumberger


General Operating Procedures & Guidelines Page 40 of 45
Revision E September 2014

11 Downhole Tools

11.1 CT Tool Threads

11.2 Tool String Make-up and Break-out

Schlumberger Private

Copyright © 2014 Schlumberger


General Operating Procedures & Guidelines Page 41 of 45
Revision E September 2014

Tensile Torsion Make-up Bending Pressure


Connection Type Strength Strength Torque Strength Rating
(lbf) (ft/lbf) (ft/lbf) Ratio (psi)

1-in. Hydril CS/Enerpro RTS-8 - 1.80lb/ft 54000 1405(2) 400-500 N/A 19470

1-in. Hydril CS/Enerpro RTS-8 - 2.25lb/ft 70000 1699(2) 400-500 N/A 25010

1-1/4-in. Hydril CS/Enerpro RTS-8 - 2.40lb/ft 74000 2482(2) 600-750 N/A 16230

1-1/4-in. Hydril CS/Enerpro RTS-8 - 3.02lb/ft 97000 3082(2) 600-750 N/A 21140

1-1/2-in. Hydril CS/Enerpro RTS-8 - 2.90 lb/ft 100000 3451(2) 800-1000 N/A 21920

Schlumberger Private
1-in. American MT 57217 665 399 2.71 N/A

1-1/4-in. American MT 58424 758 455 2.93 N/A

1-1/2-in. American MT 77305 1119 672 2.8 N/A

NC10 52960 414 249 1.97 N/A

NC12 67334 711 427 2.1 N/A

NC13 91311 1085 651 2.05 N/A

NC16 137269 1896 1137 2 N/A

1-1/4-in. FJ Regular 152391 2248 1349 3.29 N/A

2-3/8-in. API Regular 382847 4847 2908 2.07 N/A

2-3/8-in. PAC 245931 4489 2693 1.9 N/A

2-7/8-in. PAC 279777 5879 3527 2.19 N/A

1-13/16-in. Wilson FJ OS 120149 1011 607 2.12 N/A

1-13/16-in. Wilson FJ NS 105069 1011 607 2.58 N/A

2-3/8-in. Wilson FJ 176020 3010 1806 2.58 N/A

AW Rod 100529 1491 895 N/A N/A

BW Rod 143956 2467 1480 N/A N/A

N Rod 159189 2780 1668 N/A N/A

1.50-in. OD DS Stub Acme 38459 493 296 N/A N/A

1.81-in. OD DS Stub Acme 89625 1330 798 N/A N/A

2.06-in. OD DS Stub Acme 154963 2537 1522 N/A N/A

1.125-in. Nowsco Modified Stub Acme 57020 566 340 N/A N/A

Copyright © 2014 Schlumberger


General Operating Procedures & Guidelines Page 42 of 45
Revision E September 2014

1.562"-in.Nowsco Modified Stub Acme 93999 1251 751 N/A N/A

2.080-in. Nowsco Modified Stub Acme 97193 1546 928 N/A N/A

Figure 12. Tool connection recommended make-up torque.

11.2.1 Thread Locking Compounds


Schlumberger Private
11.3 Function Testing Downhole Tools

Copyright © 2014 Schlumberger


General Operating Procedures & Guidelines Page 43 of 45
Revision E September 2014

12 Offshore CT Equipment

12.1 Towers and Jacking Structures


Schlumberger Private

Copyright © 2014 Schlumberger


General Operating Procedures & Guidelines Page 44 of 45
Revision E September 2014

12.2 Lifting Frames



Schlumberger Private

12.3 Boat Spooling

Copyright © 2014 Schlumberger


General Operating Procedures & Guidelines Page 45 of 45
Revision E September 2014

Summary of general conditions required for boat spooling







13 Nitrogen Services

Schlumberger Private
13.1 Nitrogen Transfer

Copyright © 2014 Schlumberger

You might also like