Professional Documents
Culture Documents
NEC 4 Alliance Contract Explained
NEC 4 Alliance Contract Explained
www.fenwickelliott.com
01 Insight Issue 81
What is alliancing? What types of construction works changing behaviour patterns. Alliances
tend to use alliancing? are also popular where there is an
extended supply chain and either
HM Treasury’s Alliancing Best Practice innovation of some form is required or
in Infrastructure Delivery defines Contracts using alliancing tend to be
direct customer access if through that
alliancing as: high value and are frequently for
supply chain.
longer-term projects. Alliancing was
first used in the UK for delivering
“… an arrangement where a investment in the North Sea oil fields As outlined above, alliancing is
collaborative and integrated team during the 1990s.5 In Australia and New generally perceived to be more
is brought together from across the Zealand alliancing is also widely used beneficial for long-term and high value
extended supply chain. The team for delivering high value infrastructure projects. This is essentially because the
shares a set of common goals investment such as for roads.6 costs of setting up an alliance are high
which meet client requirements and the benefits that alliancing may
and work under common bring will need to be discounted
incentives.”2 Examples of alliancing contracts within
against this cost. Obviously for higher
the UK include:
value projects the benefits are likely to
The key to alliancing is the alignment be more tangible from a cost/benefit
of the parties’ goals commercially so 1. Alliances entered into by British point of view.9 Time is also required to
that parties are financially motivated Gas with lead partners and build the relationships and trust
to focus on achieving agreed members of their onward supply required within the alliancing chain
outcomes. Typically in alliancing (as chain to deliver their brownfield and that means that alliancing is more
opposed to partnering), cost overruns investment programme; likely to suit longer-term projects.
and savings are shared between the 2. The Anglian Water @one alliance
parties regardless of how they came which describes itself as: “a What standard alliancing contract
about.3 The idea is that this results in collaborative organisation of options are already available?
the confrontational behaviour, consultants and contractors
sometimes associated with traditional working together to deliver more
construction contracts, being avoided. than half of Anglian Water’s For high value construction projects a
In particular, alliancing focuses on capital investment programme”; 7 bespoke alliancing contract may well
creating an integrated project team and be used. Indeed in the 2012
which is highly motivated to ensure the 3. Alliances entered into by Network Effectiveness of Frameworks Report, it
best overall project outcome as was found that the absence of a
Rail. For example, Network Rail
opposed to serving its own particular suitable standard form is impeding
entered into an alliance with
employer’s interests. Alliancing progress in the use of alliancing etc.10
Atkins, Laing O’Rourke and
arrangements often also extend down VolkerRail for the design and
the supply chain in order to try and construction of the East–West Rail Other standard form alliancing
encourage innovation and good value. phase 2.8 contracts do exist including the
recently published TAC-1 (Term Alliance
Some alliancing contracts take the Contract) published by the ACA11 in
What are the perceived benefits of
non-confrontation goal to its extreme alliancing? conjunction with King’s College
by including “no dispute” clauses which London.12 The same group also publish
essentially waive contractual and the FAC-1 or Framework Alliance
tortious claims against alliance Alliancing is perceived as particularly Contract which came out in 2016. The
members in advance with the beneficial where there is a complex FAC-1 can be set up between one or
exception of fraud or wilful default. It is environment with multiple more clients and other alliance
debatable whether such clauses are in stakeholders, interests and goals. The members. These alliance members can
fact enforceable, or what their likely idea is that creating an alliancing include contractors, consultants and
impact on insurance policies the contract will help collaboration and specialists as required. An Alliance
parties may have is likely to be, but enable better performance. Similarly, it Manager leads the agreed procedures
historically they have been widely used is viewed as a good tool for achieving and makes sure the FAC-1 is adhered to
in Australian alliancing contracts.4 performance improvement and by the parties.13
02 Insight Issue 81
• enables a client and its team to As such they have more detailed and
As can be seen from the above, the
obtain better results from any specific obligations to work together
options for standard form alliance
term contract than the woollier “good faith”
contracts are not very wide.15 In that
obligations seen in other forms of
• helps to integrate a team into an sense the arrival of the NEC4 Alliance
NEC4 contracts.
alliance Contract is a welcome one. The
• helps to obtain improved value contract also has familiar provisions,
through building information management processes and An Alliance Board is also set up, with
modelling terminology which are an advantage each member of the Alliance
for those who are used to working (including the Client) nominating
• is designed for use in any sector
with NEC form contracts. someone to sit on it.18 The Alliance
and in any jurisdiction.
Board is tasked with:
So how does the NEC4 Alliance
TAC-1 supports and integrates the
Contract work? • Setting the strategy for achieving
provision of any type or scale of
the Alliance’s objectives and the
works and/or services and/or
partner objectives;
supplies. It is endorsed by the The NEC4 Alliance Contract describes
Construction Industry Council and itself as a “true alliancing contract” • Agreeing the work within the
by Constructing Excellence. …… because all the parties involved sign Alliance;
up to the same single contract.16 If a • Making decisions as stated in the
subcontractor is a member of the contract;
TAC-1 sets out:
alliance then they become a partner • Appointing and instructing the
with the same standing as other Alliance Manager;
• the “Alliance Members” including members. If they are not a member
• Resolving any disputes between
the “Client”, the “Provider”, and then the Guidance Notes make it
the Alliance.19
an in-house or external “Alliance clear they will need to be contracted
Manager” with the facility to add to a member of the alliance in the
“Additional Alliance Members” ….. traditional way. However, the Alliance The Alliance Board also has the power
• why the term alliance is being Manager (see further below) would to alter the scope and add partners to
created, stating agreed have to approve the subcontractor the Alliance as required. If the Client’s
“Objectives, Success Measures, first. Requirements are changed then that
Targets” and “Incentives” …. is a Compensation Event as would be
expected. However, the Client is on
• mobilisation and handover The Alliance, Alliance Board and
the Alliance Board meaning their
procedures and improved Alliance Manager
requirements can’t be changed
engagement with Stakeholders ….
without their agreement.
• a clear “Order Procedure” for The Alliance itself consists of all of the
simple or complex “Orders”, parties who have joined together to
supported by “Template Order The Alliance Manager has a similar
deliver the project (potentially but not
Documents”…. role to the project manager in a
necessarily excluding subcontractors).
standard NEC contract save for in one
• what the Alliance Members will do The Alliance includes the Client.
crucial respect. This is, namely, that
to seek “Improved Value”, working Members of the Alliance have an
he or she is acting on behalf of the
together through “Supply Chain obligation to:
Alliance Board NOT the Client. The
Collaboration” and other agreed
Alliance Manager must act in
“Alliance Activities” in accordance
• Collaborate with each other to accordance with instructions from the
with an agreed “Timetable”….
achieve the objectives of the Alliance Board and also the
• how the Alliance Members will alliance as well as the objective of Implementation Plan more generally.20
manage risks and avoid disputes the individual “partners” to the The NEC Guidance Notes state that
using a shared “Risk Register”, alliance; for major projects the Alliance
“Core Group” governance and Manager will no doubt have staff to
• Work collectively to support the
“Early Warning” with options for assist them in carrying out their
delivery of the contract on a “best
an “Independent Adviser” and duties.21 This is perhaps to be expected
for project basis”;
alternative dispute resolution ….. given that projects using alliancing
• Develop and use common
• flexibility to include particular tend to be higher value.
systems and processes as set out
“Legal Requirements” and
03 Insight Issue 81
The Implementation Plan and the between the members of the considered.
Programme Alliance arising out of or in Additional Options
connection with the contract are
only resolved in accordance with
There are two key documents which As well as these core provisions, the
these conditions of contract.”
govern the project as a whole. These Contract also gives options for early
[Emphasis added]
are: alliance involvement (a two- stage
process) and Project Bank Accounts
There are broadly speaking four amongst others.
1. The Implementation Plan; and
categories of Client Liabilities. These
2. The Programme. are:
Conclusion
The Implementation Plan sets out the 1. An intention act or omission to
management structure for the not comply with an obligation The NEC4 Alliance Contract is a useful
Alliance, roles and responsibilities, (e.g. wilful default); addition to standard form alliance
delegation by the Alliance Board, the contracts and benefits from the fact
2. A liability which the Client takes
use of common systems and that NEC users will be familiar with its
on from takeover (and the
processes22 and (rather widely!) “any terminology. It also provides for a
guidance notes make a point of
other information which the Alliance range of tools to ensure that
emphasising that any liabilities for
Board requires to be included” which is collaboration can be integrated into
the Alliance are likely to be very
either in the documents referred to in the team from the offset. That said, as
small post-takeover and almost
the Contract Data or in an instruction. is ever the case with contracts aimed
disappear after the Defects
at integrating teams and fostering
Certificate is issued);26
collaboration, it is essential that
The provisions in respect of the 3. Loss or damage to property entrenched attitudes of “them and us”
Programme, as you might expect for owned and occupied by the Client; are tackled early on and the integrated
NEC contracts, require detailed
4. Any other categories listed in the team is educated as to how to use
provisions for float, time risks, health
Contract Data. these tools effectively. This may take
and safety requirements and
time and will undoubtedly require
procedures within the contract
additional costs and investment to set
generally. Access dates, information The Partners’ liabilities are similarly
up these processes at the beginning of
deadlines and breakdowns of limited and include (broadly speaking)
the contract, which is why its use is
operations are also required.23 If the wilful default, a breach of intellectual
likely to be confined to higher value
Programme is set up properly (and rights, death or bodily injury caused to
and longer-term contracts.
updated regularly as per the intervals an employee and any other liabilities
provided for in the Contract Data24) stated in the Contract Data.27
then it will obviously be a powerful Further, parties do need to take note
project management tool. of the dispute resolution provisions and
As such, very real limitations are
the limitations placed on the ability to
placed on what Alliance members can
dispute certain types of claims. Whilst
Dispute Resolution Provisions raise claims for.
the reasoning behind these limitations
is clear there is always a risk that these
As discussed above, alliancing In terms of Dispute Resolution options provisions are overlooked until such
contracts do sometimes restrict the provided for, the main options are claims arise.
extent to which parties can engage referring a dispute to an independent
the classic dispute resolution processes expert for “an opinion” (not a decision)
Claire King, Partner
should problems arise. Unlike the and referring the dispute to Senior
FAC-1, which contains relatively Representatives of each member of Fenwick Elliott
standard dispute escalation the Alliance. They in turn can decide to
provisions,25 the NEC4 Alliancing mediate. Adjudication is an additional Footnotes
Contract limits both what can option although there is a query as to 1. See the introduction to the NEC4 Alliance
constitute a “dispute” and also what how useful this would be to run given Contract dated June 2018.
methods of dispute resolution can be the limitations on what is a “dispute” 2. See Infrastructure Client Group, Improving
used to resolve them. in the first place. There is no provision Infrastructure Delivery: Alliancing Best
for the resolution of disputes by court Practice in Infrastructure Delivery, p. 5.
or arbitration. 3. See Julian Bailey, Construction Law, vol. I,
Clause 94 provides as follows: 2nd edn (Informa Law from Routledge), p. 39.
4. See Andrew Chew, “Some Practical and
It goes without saying that parties Legal Considerations when bidding and
“The members of the Alliance Agree
entering into the NEC4 Alliancing structuring alliancing projects” , Australian
that any failure by a member of the
Contract need to be aware that their Construction Law Newsletter, #106 January/
Alliance to comply with their February 2006.
rights to seek redress if disputes arise
obligations stated in these 5. See the Infrastructure Client Group,
are severely curtailed. They either need
conditions of contract does not “Preface”, in Improving Infrastructure
to take this on board or amend the
give rise to any enforceable right of Delivery: Alliancing Code of Practice (HM
dispute resolution provisions Treasury, 2015).
obligation at law except for an
accordingly to amend the risk profile 6. See Douglas D. Gransberg, Eric
event which is a Client’s or
being taken on. Their insurance Scheepbouwer and Michel C. Loulakis,
Partners’ liability. Any disputes
position also needs to be carefully Alliance Contracting Evolving Alternative
03 Insight Issue 81
Claire King
Partner
cking@fenwickelliott.com.
Tel +44 (0)20 7421 1986
www.fenwickelliott.com