JOINT VENTURE
Rm. 510 Malate Crown Plaza Adriatico St. Cor., San Andres
Malate, Manila
Contact No.: 5310-3493 / 8256-4006 / 0916-331-1227
Email Address: omicrontektonjv@gmail.com
Leveling Plate at middle of 4 anchor-bolts with the same level of bottom of column-base-
plate.
Checking the level of the baseplate in reference to the same bases in uniformity of
column height.
Grouting mortar for column base i.e. Sika - grout 212-11or any approved equal levelling
grout.
Phase 3
Step 1:
Step 2:
Step 3:
Repeat Step 1 and 2 along grid B from 8-5, erecting column and installation of beam
using mobile crane. Columns along grid B are 18 m length.
Provide temporary platform for welding works on columns and beams.
Inspection is necessary at all steps of erection process, from the times materials are first
received until the structure is completely installed. Inspection during the steel erection
process shall be continuous in order to prevent the occurrence of possible damage and
to require the maintenance of high standard workmanship. Inspection shall include
members, painting, connection, alignment, bracings, roofing and wall cladding,
equipment and false work.
Inspection of Members
After the first bay (braced bay) is erected, the columns shall be made plumb and the
rafters shall be straight.
After completing the erection of main frames the alignment check shall be done
again, before continuing the erection of the successive bays.
The tolerance of column plumb must be within the value of 1/500 of column height,
but can not be more than 25mm.
The tolerance of Rafter alignment (from straight rafter - line) must be within the value
of 1/300 of Span.
After completing the erection of main frames, the final check of alignment (plumbing
and straightness) for all the columns and rafters of whole building shall be done.
Adjustment of bracing
Adjustable diagonal bracing is fixed after all parts of the structure are in place. In bolted
structures having diagonal bracing, wall bracings are adjusted after the columns are
plumbed, and roof bracing are adjusted when rafters are in straight line.
After completing all trims and accessories, a final inspection of the building shall be
done:
All bracings in position and tightened.
All bolts in place and high strength bolts tightened to correct tension value(as
needed).
Check that roof and gutters are clear of debris and ferrous metals.
Check improper drilled screws.
Check opening for joinery.
Touch up any damaged paint.