"Q5. Which statement below about the TRIZ design methodology is incorrect?
1. TRIZ uses a table of ""technical contradictions"" to check which principles of design may
be applicable to improve one aspect of a design without making another aspect worse.
2. TRIZ uses a checklist of 40 design principles, which are ideas to think about.
3. One of the 40 principles of TRIZ is to consider ease of assembly.
4. One of the 40 principles of TRIZ is to consider use of asymmetry on purpose."
Jean and Bob are reviewing the status of a project schedule and find a variance on
the critical path.
This will have a direct impact on the number of stakeholders
the project end date
both answer 1 and answer 2
neither answer 1 or answer 2
A project manager is preparing the work breakdown structure for a new project.
The WBS is typically used for explaining the scope of the project relevent to the client.
a basis to organize and to define the total scope of the project.
showing the resource conflicts that exist in the project.
the logical relationship between tasks in the project.
A project manager meets with the project team to review lessons learned from
previous projects. In what activity is the team involved?
Scope specification
Performance management
Risk identification
Project team status meeting
"Spot the incorrect statement below about the scrum philosophy of project
management.
Workers in a team pick a work package to work on, often displayed on a ""scrum wall"".
There is a short planning meeting each day at which members of a team report on what they
are working on, and their progress.
The short planning meeting is the ""daily scrum"".
A sprint to achieve an intermediate goal could be up to a fortnight in length."
Questions to ask when assessing if team members will be motivated to get a task
done could include the following.
People looking at detailed requirements of a sub-system need not concern themselves with
the higher-level requirements of major stakeholders.
10. Which statement about negotiation below is incorrect?
A negotiator should peg the negotiation with an opening bid, being the upper limit of their
ZOPA.
18. Which is the incorrect completion of the statement below? Principles on which
project quality management described in ISO10006 is based include
19. Which of the following is an incorrect statement about the acronym DMAIC?
The cost of poor quality is only a small portion of a company's cost structure.
21. The ....... is a document which describes how the project management team
will implement the organization's quality policy.
A quality assessment.
23. The economic useful life of an asset determines the point at which an asset
should be disposed and/or replaced. It is calculated when
The total per unit owning and operating costs of an asset are minimised
All of the above: Labour costs, materials, energy, services, general and administrative
25. In real life, early replacement and mid-term replacement options may be
available for assets. What are the advantages of early replacement?
All of the above: reduced maintenance labour costs, higher equipment resale value, reduce
spare parts holdings.
The QANTAS trademark of a kangaroo jumping means that you cannot put a picture of a
kangaroo jumping on clothing
Copyright in Australia now applies for 50years after the death of the creator of work
34. What is the incorrect statement below about conflict within a team.
Conflict is unusual.
36. During a project, an earned value analysis gives the following numbers. EV
523000, PV 623000, AC 643000. Which of the conclusions below is correct?
CV = -120000, SV = -100000.
Investigate whether the statement of work given to suppliers was deficient or ambiguous
39. What is the estimated cost accuracy at the Concept stage of a project?
+/- 25%
41. If the capital cost of a project is $100000 and it results in a positive cash flow
each year of $30000 over 5 years, then the return on investment over the 5 years is
50%
Behind
45. In the context of supply chain management, what does BoM stand for?
Bill of Materials
47. When evaluating make or buy decisions, when should a company consider
making components?
Answers (a) and (b) above combined: When company expertise, resources and machinery
are available and underutilized, When internal costs are less than those of contractors
The rate at which a finished product needs to be completed to meet customer demand
53. Which of the following three elements will a court look for to determine a valid
contract?
Offer, acceptance and consideration
Costs are reimbursed to the contractor at a fixed rate plus profit margin
Agile management may be less appropriate when it is hard to foresee the scope of a project.
58. Spot the incorrect statement about the scrum philosophy of project
management.
59. You are the project manager for a project that has high visibility. Your
manager wants you to prepare a presentation for him to present at a conference.
Most of the material in the presentation will be facts that are the results of your
project. Your manager intends to present the material under his own name. Your
name will not appear. Which of the responses below is most consistent with
professional ethics expected?
60. Which of the following is the clearest and least debatable example of a conflict
of interest?
You are the owner of another company that is supplying parts to a project that you are
managing for your current company
61. The Project Management Institute (PMI) code of ethics distinguishes between
aspirational and mandatory standards of conduct. The difference is explained as
follows.
Aspirational standards are required but we cannot easily measure your performance at trying
to achieve them, while with mandatory standards compliance is assessable, and disciplinary
action will be taken for non-compliance.
62. A feature of the validate phase of the seven step design process is to
64. Which is the incorrect statement about the "capture" stage of the seven-
step design process?
It is the last stage not to be done until after the other six stages
65. A feature of the synthesis phase of the seven step design process is
66. Which statement below about the TRIZ design methodology is incorrect?
67. Physical asset management differs from asset maintenance in which of the
following aspects?
68. What are the four maintenance strategies that are commonly employed?
Asking why an asset is required and how it relates to the business plan
70. Which of the following best describes the four principal maintenance tactics?
71. Which of the following is correct? Good asset management starts by: