Summative assessment 1
Q5.
The technique of decomposition involves subdividing the project work packages into smaller,
more manageable components called schedule activities. Decomposition determines the
project components, identifies milestones and creates packages that can be individually
targeted. It is important to realise how much time spent in decomposition is correct for the
project, as it is possible to do excessive decomposition which may lead to more work without
much value in the time spent and decreased work efficiency. If over-decomposed, estimating
those work packages will not be possible and the effort put on for decomposition will be a
waste. Since this is known to be a teamwork activity, everyone on the project team is
requested to participate in bringing up the most efficient WBS of the project.
Activities are vital input in performing a work. The correct level of decomposition in time
management can produce an accurate estimate of the schedule and timely completion of the
project. It is important to always get in mind that the next level of decomposition is possible
only when we have a clear understanding of deliverables at a particular level.