Professional Documents
Culture Documents
Fullpaper COSYS Loume Final
Fullpaper COSYS Loume Final
___________________________________________________________________________
Abstract
A protection strategy for multi-terminal HVDC (MTDC) grids based on AC/DC converters
without fault blocking capability such as half-bridge MMC converters is presented in this paper.
The key components of the proposed strategy consist of DC breakers located at each converter
station DC side and at each transmission line end, all of them based on low-speed mechanical
DC breaker technology with no fault current limiting devices. A primary protection sequence
as well as a back-up sequence are developed and are presented. The proposed protection
strategy is compared to a protection strategy using the same philosophy and based on IGBT-
CBs and Fast DC switches. Off-line simulations of both protection strategies are performed in
EMTP-RV® and results are depicted and compared. Advantages and features of the proposed
protection strategy are described.
___________________________________________________________________________
I. Introduction
One of the main challenges of the development of multi-terminal HVDC grids concerns their
protection against DC short-circuit faults. Several protection strategy concepts have been
proposed in the literature and could be classified according to two main protection philosophies
based on priority considerations.
In the selective protection philosophy, priority is given to the selective isolation of the
fault in order to preserve as much as possible the DC grid integrity and to avoid power flow
interruption. The use of hybrid DC circuit breakers is generally needed as in [1], [2] and in [3].
Because of the high rate of rise of DC fault currents and the limited breaking capability of DC
breakers, they are usually combined to fault current limiters such as inductances.
In the non-selective protection philosophy, priority is given to the suppression of the
fault current by isolating AC grids from DC grid. In this case, the fault current is prevented
from rising to levels that will make impossible the isolation of the fault. The power flow on the
DC grid is thus interrupted and has to be restored after the selective isolation of the faulty line.
The “Open-grid protection strategy” based on hybrid DC breakers located at each transmission
line end have been proposed in [4] where all breakers are first opened for fault current
suppression and are reclosed, except those associated to the faulty line, for power flow
*
Institute of Engineering Univ. Grenoble Alpes.
COSYS-DC 2017 2
restoration. Protection strategies within this philosophy can also be based on fault blocking
capability of converters such as with full bridge MMC converters in [5]. In case AC/DC
converters have no fault blocking capability such as 2-level VSC or Half-bridge MMC, [6]
proposes isolation of AC grid from DC grid either from AC side by AC circuit-breakers opening
or from DC side by IGBT-CBs opening. Fast DC switches located at each transmission line end
will thereafter isolate the faulty line according to the handshaking method described in this
reference.
This paper presents a protection strategy for multi-terminal HVDC (MTDC) grids within the
non-selective protection philosophy developed in the SuperGrid Institute. The strategy is based
on low-speed mechanical DC breakers and no fault current limiting devices are used. In chapter
II, the protection strategy based on IGBT-CBs and Fast DC switches introduced in [6] is first
presented in order to highlight limitation of backup solutions for such protection strategy in
case of breaker failure. The proposed protection strategy is introduced on chapter III and
protection system composition as well as primary and back-up sequences are presented. In
chapter IV, the MTDC test grid on which the two protection strategies will be applied is
presented and results of electromagnetic transient simulations of each protection strategy are
provided. Finally, a conclusion on advantages of the proposed protection strategy is given.
2. Protection sequences
The primary protection sequence of the protection strategy, FAULT
detection
1. Fault
following steps of: SWs relays
Converters
blocking
1. Fault detection
2. AC sources contribution suppression
discrimination
2. AC sources
contribution
suppression
Fault
3. Fault
IGBT-CBs
3. Fault discrimination discrimination
at SWs relays
opening
4. Faulty line
isolation
When a DC short-circuit fault occurs in the MTDC grid, SWs opening
fault propagates along the grid and is detected at protective according to
handshaking
relays associated to each IGBT-CB and Fast-DC-Switches. method
5. Power flow
restoration
closing
contribution suppression from the DC side. SWs closing
After a time delay necessary to ensure the faulty line SWs relays
ACCBi opening
SWs opening
the AC side of the converter is open as highlighted on back- according to
handshaking
up sequence flowchart on Figure 2 . When the ACCB is method
closing
to be tripped once the inductance currents have been totally SWs closing
Each DC transmission line of the system is associated to two Line Breaking Modules
(LBMs), located at each end. The role of the LBMs is to isolate the faulty transmission line
in case of DC short-circuit fault. The current breaking capability of the breaker LDCCB
is required to be equivalent to the highest maximum short-circuit current contribution
of the converters of the grid, which is here assumed to be 20kA. This characteristic will
be helpful in case of back-up.
In order to avoid inrush current during the DC grid voltage restoration process, pre-insertion
resistances have to be used in series with the DC breakers.
COSYS-DC 2017 5
2. Protection sequences
The primary protection sequence of the proposed strategy Start
includes, as on the previous strategy, the following main steps Fault detection at
C_DCCB and L_DCCB
detection
1. Fault
of: relays
discrimination
2. AC sources
contribution
supression
Fault
3. Fault
C_DCCBs
4. Faulty line isolation discrimination
at L-DCCB relays
opening
4. Faulty line
capability level
The overall flowchart of the primary sequence of the proposed
isolation
verification
5. Power flow
restoration
converters. The converters are thus blocked and start behaving C_DCCBs closing
like uncontrolled diode Rectifier Bridges. CDCCBs are first open Grid voltage and
power restoration
for AC sources contributions suppression by isolating each
END
AC/DC converter from DC side. Once this opening is effective,
the control of the converters can be resumed setting DC power Figure 4: Flowchart of the
reference to zero and DC voltage reference to 1pu in order to primary protection sequence
be ready for grid voltage restoration. of the proposed strategy.
By that time, from fault detection at protective relays associated to LDCCBs, the faulty
transmission line discrimination process is started. Once the faulty line is discriminated, the two
associated LDCCBs are open as soon as the current flowing through them is reduced below their
current breaking capability. In other words, in the proposed protection strategy, the DC fault
currents only need to be reduced up to the fault breaking capability of the LDCCBs and the faulty
line can be isolated even if the fault current is not totally suppressed.
From fault detection, CDCCBs are reclosed for grid voltage restoration after a security delay
before reclosing. This delay is set such that the steps of AC sources contribution suppression
and faulty line isolation are completed. CDCCBs reclosing is performed through pre-insertion
resistances to limit inrush current. Power flow can finally be restored once nominal voltage is
resumed on the DC grid.
COSYS-DC 2017 6
Start
Considering N converter stations on the MTDC grid, In case
N-1 CDCCBs are open and 1 CDCCB fails while opening, the AC Fault detection at
C_DCCB and L_DCCB
detection
1. Fault
source connected to the associated converter still feeds the relays
discrimination
2. AC sources
contribution
supression
Fault N-1 C_DCCBs
3. Fault
of the LDCCBs. They thus can be tripped allowing isolation of discrimination
at L-DCCB relays
opening and
C_DCCBi failure
the faulty line as depicted on the flowchart of the back-up
sequence on Figure 5. The isolation of the fault will result in Current breaking
capability level
the interruption of the fault current flowing from converter verification
4. Faulty line
isolation
associated to the faulty CDCCB. L_DCCBs of faulty
line opening
This blocked converter is now connected to the healthy DC
Current cancellation
grid and will thus initiate grid voltage restoration up to 0.8pu at C_DCCBi
5. Power flow
restoration
reclosing delay has elapsed, CDCCBs previously open will N-1 C_DCCBs closing
reclose to complete grid voltage restoration. Power flow is Grid voltage and
power restoration
finally restored. The proposed back-up is thus able to act
without any delay in addition to the expected duration of END
SW23 LDCCB-23
a) System layout for strategy in [6] b) system layout for proposed strategy.
Figure 6: Positive pole representation of the three-terminal MTDC test grid in bipolar
configuration for both protection systems.
COSYS-DC 2017 7
AC Side
f Frequency 50 Hz
X/R AC grid ratio 10
SSC Short-circuit power 30 GVA
SAC Transformer rated power 500 MVA
MMC converter
as shown on Figure 8.b. from t=60ms, grid voltage restoration can be initiated by reclosing
CDCCB-1, CDCCB-2 and CDCCB-3 through pre-insertion resistances PIRs before restoring power
flow.
Fault isolated Fault isolated
- i1 - i1
- i2 - i2
- i3 a) - i3 a)
- v1 - v1
- v2 - v2
- v3 b) - v3 b)
Breaking capability
- i31
- i13
- i23 c) Trip LDCCB - i31
Trip Fast DC c)
SWitch - i13
Figure 7: Current and voltage waveforms Figure 8:Current and voltage waveforms
during primary protection sequence of during primary protection sequence of
protection strategy in [6]. proposed protection strategy.
faulty line is isolated. Current from MMC converter 3 is cleared as there is no more fault to
feed. As the converter is still connected to the DC grid, the cables of the remaining DC grid are
charged to the diode rectifier bridge voltage, which corresponds to around 0.8pu of the nominal
grid voltage as shown in Figure 10.b. As in the primary sequence, the faulty cable C13 is isolated
in less than 45ms and power flow restoration can be initiated from t=60ms.
Trip ACCB - i1
- i1 - i2
a) a)
- i2 - i3
- i3
- v1
- v2 - v1
- v3 b) b)
- v2
- v3
Figure 9:Current and Voltage waveforms Figure 10:Current and Voltage waveforms
during IGBTCB-3 opening failure. during CDCCB-3 opening failure.
Conclusion
A protection strategy for multi-terminal HVDC grids based on low-speed mechanical DC
Breakers has been proposed. The following are the features of the strategy:
Study results show that, compared to the protection strategy based on IGBT-CBs introduced in
[6], the proposed protection strategy has the following advantages:
COSYS-DC 2017 10
The protection strategy is based on low-speed mechanical DC breakers that are assumed
to be much cheaper than IGBT Circuit breakers;
The faulty line isolation duration is reduced;
In case the contribution from one AC source is still feeding the fault due to a switchgear
opening failure, the faulty line isolation is not extended in time and thus the associated
back-up sequence is carried out in the same time as the primary protection sequence.
Protection algorithms of the proposed protection strategy including primary and back-up
protection have be developed. Thereafter, the complete protection strategy including algorithms
will be applied and tested on RTS platform. The management of MMC stations during the fault
clearance and the grid reclosing process are key parts of the process and will be described in
further studies.
Acknowledgements
This work was carried out at the SuperGrid Institute, an institute for the energetic transition
(ITE). It is supported by the French government under the frame of “Investissements d’avenir”
program with grant reference number ANE-ITE-002-01.
References
[1] J. Descloux, “Protection contre les courts-circuits des réseaux à courant continu de forte puissance,”
PhD Thesis from Université de Grenoble, pp. 99 – 139, September 2013.
[2] J. Sneath and A. D. Rajapakse, “Fault detection and interruption in an earthed hvdc grid using rocov
and hybrid dc breakers,” IEEE Transactions on Power Delivery, vol. 31, no. 3, pp. 973–981, 2016.
[3] W. Leterme, J. Beerten, and D. V. Hertem, “Nonunit protection of HVDC grids with inductive DC
cable termination,” IEEE Transactions on Power Delivery, vol. 31, no. 2, pp. 820–828, April 2016.
[4] C. D. Barker and R. S. Whitehouse, “An alternative approach to HVDC grid protection,” in AC and DC
Power Transmission (ACDC 2012), 10th IET International Conference on, Dec 2012, pp. 1–6.
[5] C. Karawita, D. Suriyaarachchi, and M. Mohaddes, “A controlled dc fault clearance mechanism for
full-bridge mmc vsc converters,” Cigré symposium, Lund., 2015.
[6] L. Tang, “Control and protection of multi-terminal dc transmission systems based on voltage-source
converters,” Ph.D. dissertation, McGill University,Montreal,Canada, 2003.
[7] L. Tang and B.-T. Ooi, “Locating and isolating dc faults in multi-terminal dc systems,” Power Delivery,
IEEE Transactions on, vol. 22, no. 3, pp. 1877–1884, July 2007.
[8] T. Eriksson, M. Backman, and S. Halen, “A low loss mechanical hvdc breaker for hvdc grid
applications,” Cigré 2014, 2014.
[9] H. Saad, S. Dennetière, J. Mahseredjian, P. Delarue, X. Guillaud, J. Peralta, and S. Nguefeu, “Modular
multilevel converter models for electromagnetic transients,” IEEE Transactions on Power Delivery, vol. 29,
no. 3, pp. 1481–1489, June 2014.
[10] A. Morched, B. Gustavsen, and M. Tartibi, “A universal model for accurate calculation of
electromagnetic transients on overhead lines and underground cables,” IEEE Transactions on Power Delivery,
vol. 14, no. 3, pp. 1032–1038, Jul 1999.