You are on page 1of 6

A multi-vendor protection strategy for HVDC grids based on

low-speed DC circuit breakers


D S Loume*, A Bertinato*, B Raison*†, B Luscan*

*SuperGrid Institute, France, dieynaba.loume@supergrid-institute.com , †Grenoble Electrical Engineering laboratory


(G2Elab), France, bertrand.raison@univ-grenoble-alpes.fr

Keywords: HVDC grid, MMC, Protection, mechanical DC selective tripping of the breakers associated to the faulty
Breaker. transmission line. In [5], [6] and [7], protection strategies
using hybrid DC breakers combined with limiting inductances
Abstract located at each transmission line end are proposed. In [8] the
strategy presented is based on mechanical DC breakers
A protection strategy for Multi-terminal HVDC (MTDC) associated to even higher values of inductances at each
grids based on AC/DC converters without fault handling transmission line end because of the longer opening time of
capability such as half-bridge MMC converters is presented in these breakers compared to hybrid DC breakers. [9]
this paper. The key components of the proposed strategy introduces a selective strategy based on fault-tolerant
consist of DC breakers located at each converter station DC capabilities of the LCL-VSC converter for fault current
side and at each transmission line (overhead line or cable) reduction allowing a selective isolation of the faulty
end, all of them based on low-speed mechanical DC breaker transmission line by slow mechanical DC breakers.
technology with no fault current limiting devices. The In the non-selective protection philosophy, priority is given to
primary protection sequence includes steps of fault detection, the suppression of the fault current. Once the fault current has
AC sources contribution suppression, faulty transmission line been suppressed the faulty transmission line is selectively
discrimination and isolation, and power flow restoration. A isolated. In this protection philosophy, because the entire DC
back-up sequence is also proposed in case of breaker grid is impacted, grid voltage and power flow restoration are
operation failure which is able to be performed in the same necessary. In the so called open-grid protection strategy
time duration than the primary protection sequence. The proposed in [10], all line hybrid DC breakers of the system
design requirements of the DC breakers have been verified are first opened. Thereafter only breakers associated to
and are consistent with both the primary and back-up healthy transmission lines are reclosed to resume power flow.
sequences. The concept of the proposed strategy and its A non-selective strategy based on current blocking capability
associated key components are described in the paper and of the full-bridge MMC converters is presented in [11]. In
validated by off-line simulations performed in EMTP-RV®. [12], the total fault current suppression is performed by
opening AC breakers located at converter AC sides and in
1 Introduction [13] by IGBT breakers located at converter DC sides; in both
the faulty line is thereafter isolated by opening Fast DC
A main challenge related to the development of future Multi- switches according to the handshaking method [13].Moreover
terminal HVDC grids concerns their protection which is more in the latter, the opening of all IGBT breakers is necessary for
difficult than in AC systems because of the rapids a total fault current suppression because the Fast DC switches
propagation and increase to high values of fault currents. at transmission line ends have no current breaking capability.
Advances in HVDC breaker technologies have demonstrated Consequently, in case one IGBT breaker fails, the suppression
possibilities to clear DC fault currents up to 16kA using either of the fault current could only be achieved by opening the AC
ultra-fast hybrid DC breakers or mechanical DC breakers with breaker which would considerably extend the total fault
breaking times of respectively 2-3 ms [1] and 5-10 ms [2] [3]. clearing time.
When considering hybrid DC breakers, new ultra-fast This paper presents a non-selective protection strategy using
algorithms are required to rapidly detect and identify the low-speed mechanical DC breakers placed at each converter
faulty part of the grid. Consequently, algorithms based on DC output and at each line end without current limiting
signals exchanged between relays located at opposite sides of devices. The MTDC test grid used to illustrate the proposed
a long transmission line would not be acceptable because of concept is first briefly presented. Then, the location, the
the communication delays. In addition, limiting devices such arrangement and the composition of the so-called breaking
as inductances may be necessary for both hybrid and modules are explained. Afterwards, a focus on the main steps
mechanical DC breakers. Several protection strategies are of the primary protection sequence as well as a back-up
available in the literature and an initial classification has been protection sequence are made. Finally, the results obtained
proposed according to the objectives of the strategy and its from off-line simulation studies performed in EMTP-RV® are
impact on the system [4]. The strategies can also be classified shown and analyzed to validate the proposed concept and DC
according to protection philosophies based on priorities. In breakers requirements.
the selective protection philosophy, priority is given to the

1
2 MTDC Test Grid  a DC breaker (DCCB),
 an isolation Fast-Switch (FS),
The test grid is a three-terminal MTDC grid in bipolar  a protective relay,
configuration based on Half-Bridge MMC AC/DC converters  Voltage and current sensors.
interconnected through underground DC cables. In Figure 1,
only the positive pole of the test grid is depicted for simplicity
reasons. Half-Bridge MMC converter stations are connected Relay
on their AC side to AC sources modelled by ideal voltage
sources in series with a short circuit impedance. Each MMC i
station is solidly grounded at the neutral point of the bipole. A
Metallic return conductors are not considered. Main DCCB FS
V V
parameters of the MTDC test grid are listed on Table 1. Local data
Communication
N1 CBM : Converter Breaking Module
i 13 LBM : Line Breaking Module Breaking Module
MMC1 CBM-1 i LBM-13
1
C 13
Figure 2: Illustration of a breaking module arrangement.
vMMC1
v1
i 12
N3
LBM-12 i 31 Due to the relaxed fault current breaking time required by
F LBM-31 i 3 CBM-3 MMC3 the strategy, a technology based on mechanical DC circuit
C 12 v3 vMMC3
breakers can be used. In the simulations, the DCCB model
N2 i 32
consists of a mechanical breaker with forced current injection
i 21
LBM-32 method whose operation principle has been presented in [2].
MMC2 CBM-2 i LBM-21
2
C 23 The DC breakers will not require series inductances and in the
v2
vMMC2 i 23 simulation an opening time of 15ms has been used.
Isolation Fast-Switches are located in series to each
LBM-23
DCCB. Their role is to isolate the element associated to the
Figure 1: Positive pole representation of the 3 terminal breaking module in case of DC breaker failure. Isolation Fast-
MTDC test grid in bipolar configuration. switches could be based on standard AC breaker technology.
In order to avoid inrush current during the DC grid
Symbol Description Value Units voltage restoration process, pre-insertion resistances have to
VAC Rated voltage 400 kV be used in series with the DC breakers.
AC Side

f Frequency 50 Hz
X/R AC grid ratio 10 3.1 Converter Breaking Modules
SSC Short-circuit power 30 GVA
SAC Transformer rated power 500 MVA Converter breaking Modules (CBMs) are located at DC sides of
each MMC station. Each CBM aims, in case of DC short-
MMC converter

xT Transformer reactance 0.18 pu


circuit fault, at suppressing the contribution to the DC fault
VDC Rated voltage ±320 kV
current of the AC source connected to the associated MMC
IDC Rated current 1500 A
station. The breaking capability of Converter Breakers CDCCBs
SMMC Rated power (per pole) 500 MVA
is thus limited to the maximum short-circuit current
LARM Arm inductance 16 mH contribution of one MMC converter which is assumed to be
/ Model[14] Switching function arm 20kA. A Protective relays CRelay at each CBM will proceed to
/ Number of sub-modules/arm 400 DC fault detection and open-close operations management of
l13 Length of cable C13 150 km enclosed CDCCB and CFS. No communication is required with
DC grid

l12 Length of cable C12 120 km others protection modules of the grid thus, the inputs of
side

l23 Length of cable C23 100 km algorithms are exclusively local data (measurements, status,
/ Cable model[15] Wideband tripping orders …). In case of operation dysfunction during
/ Fault type Core-screen-ground the process, CBMs could exchange fault status with the
Table 1: MTDC test grid parameters adjacent Busbar Relay.

3 Breaking Modules presentation 3.2 Line Breaking Modules

In order to protect the MTDC grid against DC short-circuit Each DC transmission line of the system is associated to two
faults, two types of breaking modules (BMs) are considered: Line Breaking Modules (LBMs), located at each end as
the Converter Breaking Module CBM and the Line Breaking depicted on Figure 1. The role of the LBMs is to isolate the
Module LBM. Their locations on the MTDC grid are faulty transmission line in case of DC short-circuit fault. The
illustrated on Figure 1 and their composition and role will be current breaking capability of the breaker LDCCB is required to
developed in this chapter. Each breaking module, as depicted be equivalent to the highest maximum short-circuit current
on Figure 2, includes: contribution of the MMC converters of the grid, which is here
equal to 20kA. This characteristic will be later explained and

2
justified. At each LBM, protective relays (LRelay) will manage openings of CDCCB-1, CDCCB-2 and CDCCB-3 between t2 and t4. In
open-close operations of LDCCB after detecting a fault and case all CDCCB operate with no failure, AC sources
discriminating the faulty transmission line. The fault detection contributions are suppressed within 15-20 ms.
START
algorithm is based on local data in the same manner as
CBMs LBMs
algorithms on CRelays. However, in order to discriminate the
faulty line, communication between LRelays of the opposite
1. FAULT DETECTION
side of the line could be necessary. In case of operation
Measure ii and vi Measure ijk and vjk
dysfunction during the process, LBMs could exchange fault
status with the adjacent Busbar Relay.
Detection Detection
algorithm algorithm

4 Primary protection sequence Fault detected?


Fault detected? No
No
Yes
The primary protection sequence of the proposed strategy Yes

includes the following main steps of: Start reclosing 3.- 4. FAULTY LINE
timer Discrimination
1. Fault detection algorithm
DISCRIMINATION
AND ISOLATION
2. AC sources contributions suppression 2. AC SOURCES
CONTRIBUTION Open CDCCB-i No
Fault on the
3. Faulty transmission line discrimination SUPPRESSION
associated line?
4. Faulty transmission line isolation CDCCB-i Yes
opening verification
5. Grid voltage and power flow restoration algorithm
Line current level
reduction verification
The overall flowchart and the timeline of the proposed
No No
primary protection sequence are depicted on Figure 3 and CDCCB-i opened?
Current below
breaking
Figure 4. In this section, the proposed strategy is presented Yes
capability?
and time sequences are illustrated in case a fault F occurs on Reclosing timer
checking Yes
the end of cable C13 connected to node N3 (see Figure 1). Open LDCCB-jk

Reclosing timer
out?
4.1 Fault detection No

Yes
When a DC short-circuit fault occurs in the MTDC grid at
t=t0, the fault starts propagating along the transmission lines CDCCB failure Close CDCCB-i 5. GRID VOLTAGE AND POWER
before arriving to MMC stations. Once the fault is locally back-up FLOW RESTORATION

detected on each MMC station, the MMC converters are Fault isolation
verification algorithm
autonomously blocked by their internal protection system and
start behaving like an uncontrolled diode Rectifier Bridges No
Fault cleared?
[16]. At each Converter or Line breaking module, the
Yes
detection of the fault is locally carried out by protective relays
Voltage and power
between t1 and t2 of the timeline on Figure 4. The detection Fault isolation
failure back-up
flow restoration

algorithm is assumed to be based on local current and voltage N-1


measurements in order to ensure rapid fault detection. It could operation

be performed by applying overcurrent, undervoltage or Figure 3: Overall flowchart of the proposed protection
current/voltage derivatives principles or a combination of strategy.
them. Once the fault is detected at a breaking module at t2, Fault propagation [0 – 2 ms] Converter Breaking modules
Fault detection [0.2 – 2 ms] Line breaking modules
each CBM will participate to the AC sources contributions Fault detection and discrimination [1 – 10 ms]
suppression and each LBM will initiate faulty line Line current reduction verification [0 – 15 ms]
AC sources contributions supression [15 – 20 ms]
discrimination. Depending on the locations of the BMs, the Faulty line isolation [15 – 20 ms]
Delay before reclosing [60 ms]
fault could be detected within 2ms. Grid voltage restoration [10 – 20 ms]
Power flow restoration [50 – 100 ms]
t0 t1 t2 t3 t3’ t4 t5 t6 t7 t8 time
4.2 AC sources contributions suppression Total duration [120-180 ms]

Figure 4: Timeline and expected time duration of the primary


When the fault is detected at LBMs level, line currents flowing
protection sequence.
through LDCCBs could significantly exceed the current
breaking capability of the line breakers because of the
superimposition of current contributions (current from 4.3 Faulty transmission line discrimination
adjacent cable discharge and AC sources contributions). At The faulty transmission line discrimination starts at t=t2 by
each CBM, once the fault is detected at t=t2, the protective protectives relays at each LBM once the presence of a fault is
relay sends tripping signal to the Converter breaker CDCCB in detected. The discrimination process on LBMs is thus
order to disconnect the connected AC/DC converter station performed between t2 and t3 during the AC sources
from the DC grid and thus suppressing the contribution to the contributions suppression by CBMs as depicted on the timeline
fault current of the corresponding AC source. Therefore, on Figure 4. The fault discrimination algorithm will enable to
considering the study case, the AC sources contributions discriminate whether the LBM is connected or not to the faulty
suppression is performed by independent and asynchronous

3
line. Depending on the method implemented on protective source2 have been isolated by CDCCB-1 and CDCCB-2, the AC
relays, decisions are based on local current and voltage source3 associated to the MMC station3 will still feed the
measurements and/or data provided by the opposite LBM. For fault. Nevertheless, because of disconnection of N-1 MMC
example, the fault discrimination algorithm could be based on stations, where N is the number of MMC stations on the
current direction comparison principle. When the two current MTDC grid, the line currents flowing through LDCCB-13 and
directions are both positive, the fault is inside the line, LDCCB-31 will fall below the current breaking capability of the
otherwise, the line is not faulty. The discrimination process Line breakers allowing their tripping and thus the isolation of
could last between 1 to 10 ms, thus algorithms implemented the faulty line C13. This will result in the interruption of the
on LRelays could be based on data exchanged through fiber fault current flowing from converter station3. That station can
optic links. therefore be isolated aided by the isolation switch CFS-3
included in CBM-3. After the reclosing time has been elapsed,
4.4 Faulty transmission line isolation the CDCCB-1 and CDCCB-2 will reclose to proceed to grid voltage
and power flow restoration described on 4.5. As shown in
Assuming the fault discrimination process has well identified Figure 4 the proposed back-up is able to act without any delay
the faulty cable C13 at t=t3, the protective relays Lrelay-13 and in addition to the expected duration of primary protection
Lrelay-31 verify that the line currents i13 and i31 have been sequence.
reduced below the current breaking capability of the LDCCBs Converter Breaking modules
before sending tripping signals. Thereby, the faulty line can Fault propagation [0 – 2 ms] Line breaking modules
Fault detection [0.2 – 2 ms] Back-up actions
be isolated even if the fault current is not totally suppressed. Fault detection and discrimination [1 – 10 ms]
Line current reduction verification [0 – 15 ms]
In other words, in the proposed protection strategy, the dc CDCCB opening checking [20 ms]
fault current only need to be reduced up to the fault breaking AC sources contributions supression [20 – 35 ms]
Faulty line isolation [15 – 20 ms]
capability of the LDCCB. Once LDCCB-13 and LDCCB-31 are CFS opening [30 ms]
opened at t5 the faulty cable C13 is isolated and grid voltage Delay before reclosing [60 ms]
Grid voltage restoration [10 – 20 ms]
and power flow restoration process can start. Power flow restoration [50 – 100 ms]
t0 t1 t2 t3 t2’ t3’ t4=t5 t4’ t6 t7 t8 time
Total duration [120-180 ms]
4.5 Grid voltage and power flow restorations Figure 5: Timeline and expected time duration of back-up
After each MMC station has been isolated by associated C BM, protection sequence.
MMC converter control is resumed. The converter DC
voltage is controlled to 1pu of the nominal voltage and power 6 Off-line simulation results
references are set to Pref=0. During this time, the MMC
Off-line simulation studies of the proposed protection strategy
converter could act as a STATCOM in order to supply
were performed in EMTP-RV® based on the MTDC test grid
reactive power to the AC system.
presented on Figure 1. The simulation time step considered is
After the fault detection, because CDCCBs are not
10µs. The simulation results of the primary and the back-up
communicating, a reclosing timer is started and lasts a fixed
protection sequences are respectively shown in Figure 7 and
time duration taking into account the time necessary for AC
Figure 9. For better understanding of the results, grid voltages
sources contribution suppression and faulty line isolation
and currents are measured following the convention given in
even in case of breaker failure. The chosen delay before
Figure 1.
reclosing is 60ms. Once the delay before reclosing at CBMs
has elapsed at t=t6 at each CBM, the CDCCB is reclosed. Pre-
insertion resistances mentioned in chapter 3 will aim to limit 6.1 Primary protection sequence simulation results
inrush currents during cable capacitance charging. During the At t=0, a fault F occurs and propagates along the DC grid
first instance of the reclosing process, the effective isolation according to a cable propagation velocity of around
of the faulty line is verified to detect eventual fault isolation 200km/ms. The fault arrives at CBMs and LBMs at different t=t1
failure. The back-up sequence to face this latter failure will be depending on their location. At t=t2, the fault is detected, thus
treated in further works. Once the grid voltage has been tripping signals are sent to CDCCB-1, CDCCB-2 and CDCCB-3
resumed, at t=t7, the power flow can finally be restored by the respectively at t2=0.04ms, t2=0.57ms and t2=0.85ms. At each
coordinated control of the MMC stations. The grid voltage LBM, line current directions are determined after a fixed time
restoration could be performed in 10 to 20 ms. of 8ms from t2. Note that this fixed time could be optimized.
The total protection sequence is thus assumed to last 120 to In Figure 6, line current directions are compared for each
180 ms. cable. Assuming a communication between two LBMs
performed through fiber optic links with a propagation speed
5 A breaker failure back-up sequence of 200km/ms, LBM-31 and LBM-13 discriminate the faulty cable
C13 at t3=9.58ms and t3=8.86ms. After fault discrimination at
The proposed protection strategy and its back-up have been LBM, a line current verification algorithm will check if the
designed to withstand a contingency that could happen during current is already below the current breaking capability of the
the protection sequence, i.e. a breaker failure or a faulty line LDCCB. In this case, tripping signal is sent to LDCCB-13 at
isolation failure. This chapter explains the back-up sequence t3’=8.86ms. However, at LBM-31, the line current exceeds the
in case of a CDCCB failure. Assuming that after tripping signal breaking capability (see Figure 7.b), thus tripping signal is
is sent CDCCB-3 fails to open, even if AC source1 and AC

4
sent to LDCCB-31 at t3’=12.79ms when line current is reduced failure is tracked after the expected breaker opening time
during AC sources contribution suppression as illustrated on when breaker current and voltage waveforms differs from
Figure 7.a and Figure 7.b. Finally, 30ms after the fault expected waveforms associated to DC breakers operation as
occurrence, all MMC stations are disconnected and the faulty illustrated in Figure 8. At LBM-31, the faulty cable C13 is
cable C13 is isolated. In Figure 7.c, after the delay before discriminated and line current reduction is being verified.
reclosing has elapsed at t=t6, CBMs proceed to grid voltage Figure 9.b shows that, at t3’ of LDCCB-31, even with a failure on
restoration by CDCCB-1, CDCCB-2 and CDCCB-3 reclosing through CDCCB-3 opening, because CDCCB-1 and CDCCB-2 have been
pre-insertion resistances PIRs. As shown in Figure 7.a, PIR effectively opened, the line current i31 has been reduced
has limited the inrush current below the fault detection below the breaking capability. Once the faulty line is isolated,
threshold as expected. At t7=75ms the grid voltage is restored MMC station 3 is still connected to the DC grid and charges
and the power flow can be resumed. Note that the power flow the capacitors of the remaining DC grid to the diode rectifier
restoration has not been simulated. bridge voltage, which corresponds to around 0.8pu of the
t3- LBM-13 t3- LBM-31 nominal grid voltage as shown in Figure 9.c. In the same way
as in primary sequence, at t6=60ms, CDCCBs are reclosed and
grid voltage restored at t7=75ms.
Cable C12 Cable C23

Cable C13

VDCCB-3 i3
Figure 6: Current direction comparisons for each cable of the
grid.
t3’-LBM-13 t3’-LBM-31
t5 t6 t7 - without failure - with failure
Figure 8: CDCCB-3 current and voltage waveforms in case of
- i1 opening failure.
Current threshold
for fault detection - i2 t3’-LBM-13 t3’-LBM-31
- i3 a t4=t5 t6 t7

- i1
- i2
- i3 a
LCB Breaking
capability

Prospective - i13
line currents
- i31 b
LCB Breaking
capability

- i13 b
- i31

- v1
- v2
- v3 c

- v1 c
- v2
Figure 7: Current and Voltage waveforms during primary
protection sequence. - v3

6.2 Back-up protection sequence simulation results


In case CDCCB-3 opening fails, AC source3 will continue to Figure 9: Current and Voltage waveforms during CDCCB-3
feed the fault as shown on i3 waveform in Figure 9.a. CDCCB opening failure back-up sequence.

5
7 Conclusion [2] T. Eriksson, M. Backman, and S. Halen, “A low loss
mechanical hvdc breaker for hvdc grid applications,” Cigré
A protection strategy for Multi-terminal HVDC grids based 2014, 2014.
on low-speed mechanical DC Breakers has been proposed. [3] K. Tahata, S. E. Oukaili, K. Kamei, D. Yoshida,
Main advantages and features of the proposed strategy are Y. Kono, R. Yamamoto, and H. Ito, “HVDC circuit breakers
discussed hereunder. for HVDC grid applications,” in AC and DC Power
 The breaking capability requirement of the low-speed Transmission, 11th IET International Conference on, Feb
mechanical converter DC breakers is limited to the 2015, pp. 1–9.
maximum fault current contribution of its associated [4] W. Leterme and D. V. Hertem, “Classification of
MMC stations. fault clearing strategies for HVDC grids,” Across borders-
 Line DC breakers are based on the same technology as HVDC systems and markets integration: CIGRE Lund, 2015.
the converter DC breakers but with breaking capability [5] J. Descloux, “Protection contre les courts-circuits
equal to the highest maximum fault current of MMC des réseaux à courant continu de forte puissance,” PhD Thesis
stations. from Université de Grenoble, pp. 99 – 139, September 2013.
 No limiting inductances are required to perform fault [6] J. Sneath and A. D. Rajapakse, “Fault detection and
clearing operation thus their impact is reduced on cost, interruption in an earthed hvdc grid using rocov and hybrid dc
footprint and DC grid control dynamics. breakers,” IEEE Transactions on Power Delivery, vol. 31,
 Discrimination algorithms are not required to be ultra- no. 3, pp. 973–981, 2016.
fast and could be based on data exchanged between [7] W. Leterme, J. Beerten, and D. V. Hertem, “Nonunit
relays located at line ends. protection of HVDC grids with inductive DC cable
 In the framework of a multi-vendor DC grid combining termination,” IEEE Transactions on Power Delivery, vol. 31,
converters with and without fault handling capability, no. 2, pp. 820–828, April 2016.
the proposed strategy is still suitable. [8] R. Li, L. Xu, D. Holliday, F. Page, S. J. Finney, and
 This non-selective strategy is claimed to be effective for B. W. Williams, “Continuous operation of radial
cable systems due to the low probability of short-circuit multiterminal HVDC systems under DC fault,” IEEE
occurrence. Transactions on Power Delivery, vol. 31, no. 1, pp. 351–361,
 In extended MTDC grids divided into protection zones, Feb 2016.
this strategy can also be implemented in one zone of the [9] M. Hajian, L. Zhang, and D. Jovcic, “Dc
grid. transmission grid with low-speed protection using mechanical
 Line DC breakers could also be used for interrupting dc circuit breakers,” IEEE Transactions on Power Delivery,
nominal line current during normal operations. vol. 30, no. 3, pp. 1383–1391, 2015.
[10] C. D. Barker and R. S. Whitehouse, “An alternative
The study results show that the total protection sequence approach to HVDC grid protection,” in AC and DC Power
including back-up can be performed in 120-180ms, which is Transmission (ACDC 2012), 10th IET International
the time from the fault inception to power flow recovered. Conference on, Dec 2012, pp. 1–6.
This temporary stop of less than 200ms could be acceptable [11] C. Karawita, D. Suriyaarachchi, and M. Mohaddes,
depending on the characteristic of the interconnected AC grid. “A controlled dc fault clearance mechanism for full-bridge
In future work, AC grid stability requirement during this mmc vsc converters,” Cigré symposium, Lund., 2015.
period will be analyzed. Further studies are being held on line [12] L. Tang and B.-T. Ooi, “Locating and isolating dc
breaker failure and fault discrimination back-up sequences. faults in multi-terminal dc systems,” Power Delivery, IEEE
Protection algorithms including primary and back-up Transactions on, vol. 22, no. 3, pp. 1877–1884, July 2007.
protection will be developed. Thereafter, the complete [13] L. Tang, “Control and protection of multi-terminal
protection strategy including algorithms will be applied and dc transmission systems based on voltage-source converters,”
tested on RTS platform. The management of MMC stations Ph.D. dissertation, McGill University,Montreal,Canada, 2003.
during the fault clearance and the grid reclosing process are [14] H. Saad, S. Dennetière, J. Mahseredjian, P. Delarue,
key parts of the process and will be described in further X. Guillaud, J. Peralta, and S. Nguefeu, “Modular multilevel
studies. converter models for electromagnetic transients,” IEEE
Transactions on Power Delivery, vol. 29, no. 3, pp. 1481–
1489, June 2014.
Acknowledgements [15] A. Morched, B. Gustavsen, and M. Tartibi, “A
This research work was held at the SuperGrid Institute funded universal model for accurate calculation of electromagnetic
by the French National Research Agency. transients on overhead lines and underground cables,” IEEE
Transactions on Power Delivery, vol. 14, no. 3, pp. 1032–
1038, Jul 1999.
References [16] M. K. Bucher and C. M. Franck, “Analytic
[1] B. Jacobson and J. Hafner, “Proactive hybrid hvdc approximation of fault current contribution from AC
breakers - a key innovation for reliable hvdc grids,” CIGRE networks to MTDC networks during pole-to-ground faults,”
Bologna symposium, 2011. IEEE Transactions on Power Delivery, vol. 31, no. 1, pp. 20–
27, Feb 2016.

You might also like