SPECIAL CONDITIONS OF CONTRACT

GCC
Clause
1.20 The Intended Completion Date is: 185 CD from receipt of NTP.
1.28 The Procuring Entity is DPWH, Sorsogon 2nd DEO, Brgy. Payawin, Gubat, Sorsogon.
1.29 The Procuring Entity’s Representative is:
FELIX M. DIMAANO, JR.
OIC - District Engineer
DPWH, Sorsogon 2nd DEO, Payawin, Gubat, Sorsogon
procurementsor2@gmail.com

1.31 The Site is located along: Prieto Diaz, Sorsogon and is defined in Drawings No. 21FL0027 – Plans
1.35 The Start Date is seven (7) calendar days from the issuance of the Notice to Proceed. – Target Start Date is on May 08, 2021.
1.39 The Works consist of the following: Construction of road including shoulder paving and lined canal
2.2 N/A
5.1 The Procuring Entity shall give possession of any or all parts of the Site to the Contractor upon issuance of the Notice To Proceed :
6.5 The Contractor shall employ the following Key Personnel:
No. of Total Experience Same Position in
Position
Personnel (Minimum) (Years) Similar Works (Years)
I. For DED

II. For Construction :


Project Manager 1 5 5
Project Engineer 1 5 5
Materials Engineer 1 3 3
General Construction Foreman 1 3 3
Skilled Laborer Sufficient
Safety Health Officer 1 1 1
Common Laborers Sufficient

8.4 c “No further instructions”.


8.7 “No further instructions”.
9.1 “No further instructions”.
10.1 The applicable liquidated damages is at least one tenth (1/10) of one percent of the cost of the unperformed portion for every day of delay.

The maximum deduction shall be ten percent (10%) of the amount of the contract, the Procuring Entity shall rescind the contract, without
prejudice to other courses of action and remedies open to it.
11. List all available Site Investigation Reports to be provided by the Procuring Entity :
13.3 No further instructions.
13.5 Refer to Section 62.2 of the Revised IRR R.A. 9184 for the warranty periods applicable for the proposed infrastructure project.
14 No further instructions.
19.3(h)(i) No further instructions.
22.2 The Arbiter is: CONSTRUCTION INDUSTRY ARBITRATION COMMISSION (CIAC)
4F Jupiter Building, 56 Jupiter Street, Bel Air, Makati City
26.1 No further instructions.
28.1 Indicate if applicable.
30.1 The Contractor shall submit the Detailed Program of Work to the Procuring Entity’s Representative within 14 calendar days from the issuance
of Notice to Proceed.
30.3 The period between Program of Work updates is 30 calendar days.
The amount to be withheld for late submission of an updated Program of Work is [insert amount]. N / A
33.3 The Funding Source is the Government of the Philippines. GAA FY 2021
38.1 The amount and schedule of the advance payment is 15% of the Contract Price.
39.1 No further instructions.
39.3 No further instructions.
46.6 The Predetermined unworkable days are given: twenty-three (23) C.D.
50.1 The date by which the As-Built Drawings and/or Operating and Maintenance Manuals are required is: before issuance of Certificate of
Completion.
50.2 The amount to be withheld for failing to supply the As-Built Drawings and/or Operating and Maintenance Manuals by the date required is equal
to 10% of the Contract Price].