Posted by Mastercut Concrete | 11 September 2019 | Concrete Cutting
If your new to laying concrete or it’s been a while since you’ve laid your last slab you might
need a refresher on what control, contraction and a concrete expansion joint are. You also
will need to know if they are needed, where they are needed and when and how to make
them. Getting familiar with these joints will ensure the integrity of your slab and protect
the surrounding structures along with ensuring any unsightly cracks occur where you want
them.
An expansion joint in a roadway to isolate two concrete slabs from each other.
A concrete expansion joint is used to prevent a concrete slab from impacting surrounding
structures when it expands or contracts. These are also known as isolation joints as they
completely separate a section of concrete from other slabs of concrete or surrounding structures
such as walls and posts.
You often see noticeable expansion joints on pathways where some rubber or tar is placed in
between longer sections of path. Expansion joints can also be seen on bridges where metal teeth
are used to fill the gap between the bridge and the road slabs.
A contraction joint is a cut made part way through a slab of freshly poured concrete at regular
intervals. This cut is designed to control where cracks occur during both the setting of the
concrete and as the concrete contracts when gets cold. These are also known as control joints.
The purpose of making the cut partially through is to create a point of weakness so that the
concrete will crack in a specified area rather than a jagged unsightly creak in a prominent
position.
Contraction joints can be seen as smaller lines on pathways in between the expansion joints.
The remainder of this article will focus on the cutting of control joints.
Control joints are needed at regular intervals to ensure cracks will not appear in between control
joints. The distance between joints need to be made no more than 25 times the thickness of the
slab. So if the slab is 10cm thick the control joints need to be made every 2.5 metres.
On any sections with inside corners (also known as re-entrant corners) control joints should be
added on these known stress points. See below:
The internal corners require control joints to be made extending out each direction of the corner
as these are particularly prone to cracking.
Depth
The depth of a control joint is usually a quarter of the slabs thickness. So the same 10cm slab
should have a control joint cut which is 2.5cm deep.
Cuts should be within 12 hours of the concrete being poured otherwise it risks cracking.
The quarter thickness cuts in the slab can be made in freshly poured concrete using a grooving
tool. However, a concrete saw can be used when the concrete is hard enough that is won’t disturb
the concrete surface, usually after 6 hours.
Mastercut Concrete have been cutting concrete in Sydney for over 20 years and have a fleet of
skilled and mobile concrete cutters to cut the necessary contraction control joints in your
concrete slab soon after pouring. Our staff are equipped with a range of top quality machinery
and hardware perfect for the job. Contact 02 9755 5505 for a free consultation and quote or
complete an online quote request.