You are on page 1of 13

JOINT FREE SLABS ON GRADE

Warwick Colefax1 BE(Hons) MIEAust CPEng RPEQ


SUMMARY

Joint Free Slabs™ is an innovative method for the construction of vast areas of slab on
grade without the traditional formed and sawn shrinkage control joints. A crack inducer grid
is used to induce a closely spaced network of fine cracks throughout the entire area of the
slab that do not need to be reflected through applied floor finishes.

The joint free slab system is a very appropriate system for retail centres and supermarkets
where the installation and maintenance of control joint cover strips is both costly and
troublesome. They can be readily constructed at the rate of 1,500 to 2,000 square metres
per day per crew, delivering substantial savings in construction time as well as cost.

INTRODUCTION once it opens up. Also, all too often slabs are
thickened at the key thereby providing restraint
Traditional slabs on grade are typically detailed against shrinkage and rending the joint ineffective.
with a regular grid of shrinkage control joints at 6
to 10 metres centres in both directions. The most The joint free slab system provides an alternative
commonly used shrinkage control joints are keyed approach to the detailing of many large area slabs
joints, sawn joints, dowelled joints, and on grade that does away with all traditional
combinations of these. shrinkage control joints. In joint free slabs a crack
inducer grid is used in lieu of traditional control
One of the most popular control joints is the sawn joints, and this induces a closely spaced network
joint because of its simplicity and lower cost, of fine cracks throughout the entire slab area that
however all too often in the field sawn joints are do not need to be reflected through the applied
ineffective. If the saw cut is installed too long floor finishes. This contrasts with traditionally
after the slab has been placed, thermal shrinkage detailed slabs on grade in which significant
cracks may have already occurred [9] and in such movement is designed to occur at the control
cases the cracks do not coincide with the straight joints, and hence the joints must be reflected
line of the saw cut. The saw cut must be installed through finishes if damage is to be avoided.
within about four hours of placing the concrete if it
is to have a high prospect of success, and in Joint free slabs can be readily substituted for most
building projects this rarely occurs. traditional slabs on grade where there is a desire
to reap the many potential benefits. The system is
Dowelled joints in the past have rarely worked particularly suited to slab on grade floors that are
effectively as it was commonplace for the dowels to have finishes applied. It is these applications
to be not firmly and accurately secured in position that have the greatest potential savings in
and to be not correctly aligned. In such construction time, construction cost and ongoing
circumstances the concrete on both sides of the maintenance cost.
control joint becomes effectively locked. When
this happens a shrinkage crack usually appears
along a wandering line at one end of the dowels. HISTORY
In recent times pre-fabricated dowel cages have
become readily available, and these have greatly The joint free slab on grade system was first
improved the situation, however the cages are launched in October 2000. The concept
expensive and there are still many aspects of germinated from a client’s request to eliminate all
dowelled joints that can result in failure if they are of the traditional shrinkage control joints in a roller
not properly addressed. blade skating rink measuring some 50m x 30m in
which the joints were perceived to be a hazard to
One of the most effective joints in controlling the skaters. The outcome of this trial slab was so
shrinkage is the keyed joint, however this type of successful that it was quickly recognised there
joint is very susceptible to damage of the concrete was a huge potential for use of the system in a
slab edge over the female section of the key, and wide variety of commercial projects, and the first
it has questionable load transfer characteristics commercial project soon followed.
_________________________________
1
Director, Colefax Consulting Engineers Pty Ltd
In the early days there was much talk about the with segment lengths of 250mm. A hinge is
need for the passage of time so that all of the introduced at 1m centres (every fourth node) to
claims could be substantiated and the long term simulate an induced crack, and this is really the
performance of the system could be properly only difference between a joint free slab and a
evaluated. This is a difficulty faced with most new traditional slab on grade when it comes to
product and system launches, and it can make it modelling for analysis. It should be noted that this
very difficult for innovators in the building industry. is considered a conservative approach as not
every crack inducer will always induce a crack,
It was most fortunate that there were a number of and as the induced cracks will not behave as
builders and developers in the early days that perfect hinges because the reinforcement is
were quick to recognise the potential of the the continuous through them.
joint free slab system, understood the principles
on which it was based, and were prepared to give As always, the designer needs to complete a
it a go. Almost all of those that tried the system in sufficient number of analyses with different load
its early days have gone on to use it again, and case combinations to satisfy himself/herself that
again. Hutchinson Builders for example have now the worst case for stress and deflection has been
used the system on five Officeworks projects in identified. It is only then that the designer can
Queensland and NSW over the last two years and proceed to determine the minimum slab thickness
and are planning on using the system in further and concrete strength with a satisfactory level of
projects in the second half of 2004. confidence.

In 2001 the joint free slab system also received A sample output of a beam on elastic foundation
substantial recognition when it was awarded an analysis for a joint free slab is attached in
Excellence Certificate at the CIA biennial Annexure A.
conference in Perth. This provided a great boost
to the industry acceptance of the system in the Designers should be aware that in recent years
early days. there has been a drift away from the use of beam
on elastic foundation analysis to the use of finite
The system is now being used on many projects, element analysis (FEA) wherein soil layering is
and notably it is being used on projects for large modelled. FEA was used to generate the design
national retail chains in Australia such as charts in the latest edition of the C&CA Guidelines
Woolworths, Officeworks, Bi-Lo, Big W, Super [2]. The earlier editions of the Guidelines [1] used
Cheap Auto and Coles. The list of both projects beam on elastic foundation analysis, but in a case
and users is continuing to grow. Joint free slabs study of a pavement failure on a project in
have also been installed on projects for Qantas, Australia it was concluded that using a Modulus of
BP Australia, NSW Department of Education, Subgrade Reaction approach to the design
Project Services Queeensland, and other private contributed to the pavement failure.
school groups.
In his paper [11] on the new C&CA Guidelines [2]
presented at a recent seminar in Sydney on
STRUCTURAL ANALYSIS industrial pavement design, Professor Harry
Poulos explained that the shortcoming in using
Analysis is not necessary for lightly loaded slabs. subgrade reaction theory is that the subgrade
This is no different to normal practice with modulus is dimension dependent. He showed that
traditional slabs on grade where to a great extent an increase in the area of loading should coincide
most slabs under 150 thick are specified and with a decrease in the subgrade modulus used in
detailed on an empirical basis. the analysis.

For more heavily loaded slabs however, and slabs Hence while it is satisfactory to use beam on
with known heavy point loads, stacking loads and elastic foundation analysis for slabs with small
repetitive wheel loads, analysis and design is loaded areas (such as wheel loads), it can lead to
often required to satisfy the engineer that the slab problems where heavy loads are applied over
will perform satisfactorily to the client’s large areas unless a lower value is used for the
requirements in the long term. subgrade modulus. Poulos made the point that
soil layering also affects the subgrade modulus,
In these circumstances we use and recommend and that it is difficult to take layering into account
beam on elastic foundation analysis software to in other than FEA.
analyse joint free slabs. A 1m wide slab strip in
two orthogonal directions is modelled for analysis
_________________________________
1
Director, Colefax Consulting Engineers Pty Ltd
It is the author’s belief and experience that very control damage to the super structure that could
few engineers in practice would complete a finite be caused by differential movement of the
element analysis for a slab on grade because of foundation material. ‘Flexible’ and articulated
the complexity and hence the expertise, the time slabs will not achieve this outcome.
and the expense involved. It is therefore
suggested that taking steps such as using a
conservative value of the subgrade modulus can Industrial Floors and Pavements - Guidelines
compensate for the effects of large loads over for design construction and specification [2] is
large areas. a primary reference used by engineers when
designing floors that are to be subjected to heavy
The important thing is to be aware of potential point loads and stacking loads. As with the earlier
shortcomings and take them into consideration publications, it is the design charts and the
when preparing the analysis and the design. detailed technical content that makes this
publication particularly popular.

STRUCTURAL DESIGN
a) Concrete Strength
This section has been written around the SAA
Codes and it is will be necessary for delegates at One of the first tasks faced by the design engineer
Queenstown to substitute the NZ equivalents. is to select a characteristic compressive strength
for the concrete that will be adequate for the
AS 3600 – Concrete Structures [5] is the application. This is no different for joint free slabs
principal reference in Australia for reinforced than it is for traditional slabs on grade.
concrete structures, and for the uninitiated
reference should be made to the following The main factors affecting the choice of an
Sections/Clauses to begin with: adequate concrete strength are serviceability,
durability, and the anticipated flexural tensile
Clause 1.3: Use Of Alternative Materials Or strength requirement in the case of more heavily
Methods loaded slabs.

SECTION 2: Design Requirements And Rarely these days is a slab on grade specified
Procedures with a concrete compressive less than 25Mpa,
however 20Mpa is adequate for lightly loaded
SECTION 4: Design For Durability slabs that are to experience negligible wear or
abrasion, or that are to be covered with ceramic
Clause 9.4.3: Crack control for shrinkage and tiles, vinyl tiles, toppings or the like.
temperature effects
Section 4 in AS 3600 [5] stipulates the minimum
SECTION 16: Concrete Pavements, Floors And concrete strengths for various exposure
Residential Footings classifications, and the minimum strength is
20Mpa for the mildest exposure classification.
The relevance of each of these Clauses and This section addresses the need to provide
Sections is elaborated on below. adequate protection to embedded reinforcement in
aggressive environments.
AS 2870 - Residential slabs and footings –
Construction [6] is the main reference in Table 4.7 in AS 3600 [5] nominates the minimum
Australia for stiffened raft slabs used for characteristic strengths for various applications to
residential footings and it generally applies to ensure the concrete has adequate resistance to
single dwellings of limited area. This code is cross the anticipated wear and abrasion (see over).
referenced to AS 3600 [5] and it contains details of Table 1.3 in the C&CA Guidelines [2] is totally
standard designs for ‘deemed to comply’ raft slabs consistent with AS 3600 Table 4.7 [5].
on sites with differing site classification.
There are further requirements in AS 3600 Clause
There is limited scope for the standard designs 4.8 [5] for slabs that may be affected by freezing
however and in Clause 3.1.1 it is stated that they and thawing.
do not apply to slabs that are greater than 25m in
length, or slabs that contain contraction or control
joints. This is simply because the rafts are
intended to behave as stiff footings and thereby
_________________________________
1
Director, Colefax Consulting Engineers Pty Ltd
AS 3600 Table 4.7 AS 3600 Clause 16.2.2 [5] states that:
STRENGTH REQUIREMENTS FOR ABRASION
The thickness of the slab shall be proportioned to
Minimum adequately distribute concentrated loads to the
Member and/or traffic characteristic foundation.
strength (f′c)
and in Clause 16.3 it requires residential floors
Footpaths and residential and footing to be designed and constructed in
driveways 20MPa accordance with AS 2870 [6].

Commercial and Industrial AS 2870 [6] stipulates a minimum slab


floors not subject to vehicular 25MPa thicknesses of 100mm for stiffened raft slabs but
traffic allows for this to be reduced to 85mm in Western
Australia subject to it being “specified by an
Pavements or floors subject to: appropriate qualified engineer”.

(a) Light pneumatic tyred The C&CA Guidelines [2] in Clause 3.3 provides
traffic (vehicles up to 3t 25MPa for a simplified thickness design based on
gross mass) previous satisfactory performance, i.e. selected on
an empirical basis. The minimum recommended
(b) Medium or heavy thicknesses are as tabulated below:
pneumatic tyred traffic
(vehicles heavier than 3t 32MPa C&CA Guidelines Table 1.14
gross mass) Minimum pavement thicknesses for lightly-loaded
industrial pavements
(c) Non-pneumatic tyred traffic 40MPa

(d) Steel-wheeled traffic To be Typical application Rating of Minimum


assessed but subgrade thickness
not less than of
40MPa pavement
(mm)

If it is anticipated that flexural tensile stresses will


govern the determination of slab thickness, then Shops, garages
there may be a need to select a greater than mainly for private Poor 150
minimum concrete strength as this will reduce the cars, light industrial
slab thickness. premises with live Medium
loading up to 5kPa to Good 130
In summing up, concrete strength should not be
over-specified as stronger concrete will contain
more cement and hence will generally have Garages mainly for
greater shrinkage and higher cost. An increase in commercial vehicles, Poor 200
shrinkage will generally result in more cracking industrial premises
and/or larger cracks. with live loading Medium
between 5 and 20kPa to Good 180

b) Slab Thickness

The thickness of a slab on grade is either In the main references used by engineers the
empirical or calculated, however for the vast above is the only guidance to nominal slab
majority of light to medium duty slabs on grade up thicknesses, and it must be remembered that
to 150mm thick, the thickness is empirical. In these are minimum thicknesses, not mandatory
these cases it is left to the design engineer to thicknesses. Engineers may always specify
choose or nominate the slab thickness. greater thicknesses without fear of retribution, but
as always responsibility ultimately rests with the
Written guidance is available as follows: engineer just as it would if a thinner slab was
specified.

_________________________________
1
Director, Colefax Consulting Engineers Pty Ltd
Many engineers do specify the minimum or It is advised in the C&CA Guidelines [2] that no
nominal thickness in accordance with the above, research has been carried out to determine
however some specify thinner or thicker slabs due appropriate values for k1, hence it is suggested
for example to personal experience, inexperience, that values be chosen from Table 1.17 for various
personal preference, or traditional practice of the loading types:
firm he or she happens to be working for.
C&CA Guidelines Table 1.17
As can be seen above there is a large number of k1 for various loading types
slab on grade applications that are not covered by
the minimum Code or Guideline recommendations
or the tabulated empirical slab thicknesses, and Loading type Range of k1
for these applications it is left to the engineer to
decide on the slab thickness.
Wheel 0.85 – 0.95
Where such selection is not based on calculation
but simply on tradition or personal
Post 0.75 – 0.85
preference/experience, there is often a great
contrast between what different engineers will
Distributed 0.75 – 0.85
specify for a similar or identical application on
similar sites. For example the author has seen
designs for supermarket slabs that vary from
100mm to more than 150mm for no other reason When adopting a value for k1 circumstances in
than they were specified by different engineers. which the higher end of the range may be
This is most unfortunate as there are significant appropriate include:
cost implications for builders and developers.
‰ concrete and geotechnical parameters are
When the design brief includes specific stacking assessed conservatively
loads, racking loads and/or wheel loads it might be ‰ site-specific correlations are used for design
necessary (even for relatively lightly loaded slabs) parameters
for the design engineer to analyse and calculate ‰ careful construction control will be applied
the slab thickness if he/she hasn’t done so for a
similar project before. In the absence of specific test data, the
characteristic flexural tensile strength can be
Just as with traditional slabs on grade, traditional calculated as follows:
design methods are used for calculating the
minimum slab thickness of a joint free slabs. Once f′cf = 0.7√f′c
the analyses have been completed for the various
load combinations, the slab thickness can be This is the relationship recommended in the
calculated based on allowable flexural tensile C&CA Guidelines [2], and it should be noted that it
stresses and punching shear stresses. The is less conservative than the relationship given in
designer must also give due consideration to AS 3600 Clause 6.1.1.2 [5]
calculated deflections of the slab.

The following equation for design tensile stress c) Restraint


(MPa) is given in the C&CA Guidelines [2] Clause
3.4.9: Restraint to shrinkage is a real problem with
traditional slabs on grade and it is the reason that
f allowable = k1 k2 f′cf reinforcement is installed, therefore every effort is
made to eliminate restraint. Such measures
where include the installation of sand blinding, and the
k1 = a material factor that varies from 0.75 to 0.95 installation of compressible isolation wherever the
k2 = a load repetition factor that varies from 0.50 slab interfaces with rigid elements such as walls
to 0.73 and columns.
f′cf = the characteristic flexural tensile strength of
The unfortunate thing with compressible isolation
the concrete (MPa)
strips is that more often than not in practice, they
are not installed such that they penetrate the full
It should be noted that the design tensile stress so
thickness of the slab and hence do not effectively
calculated is for use with permissible stress limit
isolate the slab from the rigid member.
state design
_________________________________
1
Director, Colefax Consulting Engineers Pty Ltd
The other unfortunate thing with traditional slabs AS 3600 Section 2 [5] outlines the general design
on grade is that in a practical sense it is requirements for strength, serviceability, durability,
impossible to eliminate the restraint caused by fire resistance, fatigue etc. For most applications
edge and internal thickenings unless the these requirements are clearly met with joint free
thickenings themselves are eliminated. slabs, hence it is postulated that joint free slabs
comply with AS 3600 through the provisions of
In contrast, joint free slabs are designed to be Clause 1.3.1.
regularly cracked and hence many of the
difficulties encountered in trying to eliminate But despite the fact that Joint free slabs comply
cracks in traditional slabs on grade simply don’t with AS 3600 [5] for the reasons outlined above,
exist. The use of sand blinding with joint free the reinforcement provisions of AS 3600 obviously
slabs is discouraged as it is advantageous to do not entirely apply to joint free slabs.
increase the frictional resistance between the slab
and the subgrade, and generally all compressible Reinforcement is installed in joint free slabs for
isolation is deleted for a similar reason. two main reasons:

Every effort is made to maximise the restraint with ‰ to tie the slab through all induced cracks
joint free slabs to the extent that internal and hence keep the crack widths minimal
thickenings are introduced in most jobs for the and under control
sole purpose of increasing the level of restraint.
‰ to adequately trim all re-entrant corners and
penetrations to minimise the occurrence of
d) Reinforcement unintended cracks, and again to keep the
widths of such cracks minimal.
For traditional slabs on grade the design engineer
must determine the reinforcement requirements The reinforcement mesh used in joint free slabs is
based on the geometry of the slab. The proportioned such that the area of steel in both
reinforcement is not used to achieve flexural directions is in the order of 0.175% of the cross
capacity; it is simply installed to control cracking section of concrete above the crack inducer tubes.
due to restrained shrinkage and other non-flexural RF62 is the lightest mesh used in Australia (665 in
effects. As mentioned above sand blinding is New Zealand) as it is not practical to walk on
normally installed on the building platform to level mesh lighter than this when it is chaired at 1m
the site and to reduce the friction effect, however it centres.
must be appreciated that the larger a slab panel
is, the greater the build up of internal stresses due In the four years that joint free slabs have been in
to frictional restraint and other effects and hence the market place, this level of reinforcement has
the greater the reinforcement requirement. been found to be satisfactory. Arguably, it also
complies with the provisions of AS 3600 Clause
AS 3600 Clause 16.2.3 [5] is written for traditional 9.4.3.4(a)(i) [5] in which the minimum
jointed slabs on grade. It states that: reinforcement for a restrained slab in an interior
environment “where a minor degree of control
The reinforcement and the spacing, over cracking is required” is nominated. This
pattern and type of joints, shall be would have to be a fitting description of what is
designed to minimise cracking due to expected for typical joint free slabs.
shrinkage and warping
If a Joint Free Slab is to have no applied finishes,
At first glance therefore it could be argued that the area of reinforcement is increased to 0.225%
joint free slabs by their very nature do not comply minimum, but note again that this percentage is
with AS 3600 [5]. This is overcome however with applied to the net area of concrete above the
Clause 1.3.1 which states: crack inducer tubes. The area of reinforcement is
increased purely for aesthetic purposes.
Provided that the requirements of Section
2 are met, this Standard shall not be Trimmer bars are treated very seriously in joint
interpreted so as to prevent the use of free slabs. The typical requirement is for 2N12
materials or methods of design or bars (2D12 in New Zealand) around the full
construction not specifically referred to perimeter of each pour and on the four sides of all
herein. penetrations. At re-entrant corners the perimeter
trimmer bars are crossed and fully anchored, and
additional diagonal trimmers are also installed to
_________________________________
1
Director, Colefax Consulting Engineers Pty Ltd
suit. The minimum number of N12 (D12) diagonal plastic junctions. The junctions double as bar
bars at re-entrant corners is two. chairs and the conduits are supplied cut to length
for a 1m square grid. As such every fifth bar in a
At construction joints the perimeter trimmers are standard reinforcement mesh (in Australia) is
extended into any subsequent pour sufficiently for supported on a junction.
a full tension lap or full anchorage.
In consideration of the different standard mesh
configuration in New Zealand, it is intended to
STRUCTURAL DETAILING ultimately manufacture a 1050x1050 grid for the
New Zealand market.
The structural detailing of joint free slabs is a
simple and relatively quick activity when compared The crack inducer grid is assembled in position on
with traditional slabs on grade. Once the outline site and is placed directly on the ground or on the
of the Joint Free Slab has been agreed/decided, a vapour barrier as applicable. The grid is set out
1m square grid is overlayed and positioned for such that on site cutting of the conduits around the
‘best fit’ between all sides. The excess grid is perimeter is minimised, and on most projects no
then cropped off and all internal ground restraints cutting is required.
positioned to suit the grid. The perimeter
restraints are marked on the plan and the utilised Reinforcement:
details are dragged in from the standard suite of
details supplied. Any additional sections are Reinforcement mesh is supported on the junctions
drawn and the standard notes adjusted as and the sheets of mesh are lapped at the sides
necessary to complete the job. and ends such that the 200mm grid of bars is
maintained throughout. Nominal 200mm side and
end laps are adjusted marginally as necessary to
CONSTRUCTION cater for minor discrepancies in the fabrication of
the mesh sheets or the accurate alignment of the
Joint free slabs utilise a crack inducer grid to crack inducer grid.
induce a closely spaced network of shrinkage
cracks throughout the entire area of the slab. This Similar applies in New Zealand except that the
is the main difference between joint free slabs and spacing of bars in New Zealand mesh is 150
traditional slabs on grade however there are other instead of 200mm.
smaller differences that make construction
simpler, quicker and generally less expensive. Each alternate run of mesh is staggered by half a
sheet length to avoid four sheet corner laps.
Site preparation:
All slab perimeters, penetrations and re-entrant
Proper preparation and compaction of the building corners are trimmed, typically with 2N12 bars
platform is as important for joint free slabs as it is (2D12 in New Zealand).
for traditional slabs on grade, however sand
blinding is not required and its use is discouraged. Traditional bar chairs are only required around the
slab perimeter and where reinforcement is cut
With joint free slabs full perimeter restraint is locally around penetrations. More bar chairs are
required and this can be achieved by a perimeter required in New Zealand for general support but
thickening or by fixing the slab edge to tilt-up this will change when the grid dimension is
panels or the like. In contrast to traditional slabs increased to 1050mm x 1050mm.
on grade every effort is also made to restrain the
slab throughout its length and breadth. Internal Concrete:
ground restraints are used for this purpose and
these are typically located at about 14m centres in The perfect concrete for a Joint Free Slab floor is
both directions. Internal ground restraints are one with minimum long term shrinkage but with
typically continuous trenches measuring 200mm in high early shrinkage. Concrete with a maximum
depth and 300mm in width, however other forms 80 slump and a 56 day shrinkage of 600
of restraint can also be utilised. microstrain is specified for most projects, and the
use of super plasticiser can be an advantage
Grid Installation: provided it does not adversely affect the short
term strength or long term shrinkage.
The crack inducer grid comprises extruded plastic
conduits that are pushed onto moulded four way
_________________________________
1
Director, Colefax Consulting Engineers Pty Ltd
Best practice placing and compaction is very The methodology of joint free slabs and the plastic
important and the addition of water is not junctions are protected by an Australian patent
permitted after the concrete has left the batching and a New Zealand patent. Applications have
plant. also been filed for international patents in a
substantial number of countries, and it is
Other Details: anticipated these will all be granted over the next
couple of years.
In contrast to traditional slabs on grade
compressible separation between slab edges and
walls, columns etc is not generally required. ADVANTAGES OF THE JOINT FREE SLAB ON
Where construction joints are required, they are GRADE
positioned adjacent to a ground restraint such that
the restraint is included in the edge of the first The advantages of joint free slabs are numerous,
pour. The edges of the slabs on both sides of the generally amounting to simplicity of construction,
construction joint are trimmed with 2N12 bars reduced construction time, reduced construction
(2D12 in New Zealand), and the mesh cost, reduced maintenance cost and superior
reinforcement is continued through the aesthetics of the finished floor. The following is a
construction joint to lap with the mesh in the more detailed list of the individual advantages:
subsequent pour.
‰ Deletion of sand blinding
The preferred formwork at a construction joint is
quick and simple, and can be installed at short ‰ Generally lighter reinforcement
notice. A run of stock length timber boards of
suitable thickness is placed across the crack ‰ Deletion of all slab edge compressible
inducer tubes and the mesh is laid on the boards. isolation strips
A second run of stock length timber boards is laid
on top of the mesh in vertical alignment with the ‰ Deletion of all traditional formed and sawn
first run of timber, and the two lines of timber control joints
boards are tied together using reinforcement tie
wire to clamp the boards to the reinforcement. ‰ Simpler and faster reinforcement placing

The formwork is very simply removed within hours ‰ Elimination of most conventional bar chairs
of the first pour in readiness for the subsequent
pour. ‰ Larger concrete pours possible

Curing: ‰ Reduced concrete pump usage

Curing should be adequate to achieve a concrete ‰ Superior surface finish on slab


strength and surface quality suitable for the
application, but if the curing method can be ‰ Deletion of cover strips and fillers needed for
tailored to achieve the desired high early traditional control joints
shrinkage with low early strength it is an
advantage. ‰ Reduced construction cost

‰ Reduced construction time


AVAILABLE PRODUCT RANGE
‰ Superior termite resistance
Two sizes of crack inducer grid are currently
available and these are suitable for slab ‰ Superior aesthetics of the finished floor
thicknesses in the range of 90mm to 140mm. The
small grid is 30mm high and the large grid is ‰ Increased versatility
38mm high. These dimensions represent 30% of
a 100mm and 125mm slab respectively. ‰ Reduced on-going maintenance costs in many
projects
On certain jobs bar chairs might be required for
slab thicknesses at the upper end of the range for
each of the two grids to reduce top cover to the
reinforcement.

_________________________________
1
Director, Colefax Consulting Engineers Pty Ltd
SUITABLE PROJECTS Schools:

There is a wide range of projects in which the use The system has been installed in one public
of joint free slabs is both appropriate and school project in QLD and has been installed in an
beneficial. Whilst selection of the system is most indoor sports hall at Blaxland High School in
often driven by cost savings alone, aesthetics, NSW. It has also been used in several private
versatility and reduced construction time are also school projects in NSW and Victoria.
important considerations.
Indoor & Outdoor Sports Facilities:
The system is obviously suitable for all large area
floors that are to have applied finishes such as This is an area where there is a huge potential for
vinyl tiles, sheet vinyl, carpet, ceramic tiles etc, but joint free slabs, and it is an area that overlaps
it is increasingly being used in car parks and considerably with school projects.
industrial floors as well.
Many indoor basketball courts and similar facilities
Retail: have sprung timber floors install directly on a
concrete slab on battens. Once the timber floor is
The time and cost advantages offered by the installed the sub floor space is inaccessible. Any
system are maximised in retail developments open control joints or large cracks in the base slab
where there is usually extensive use of applied provide ready access for termites in a perfect
finishes of all types, and where the control joint environment to inflict extreme damage virtually
cover strips normally installed are expensive and unnoticed until it is too late. This may not be a
often ineffective. problem in New Zealand but it is a huge problem
in mainland Australia.
The system is not considered appropriate for retail
floors that have a burnished or polished concrete Joint free slabs are quicker to construct, and
finish. provide a more uniform surface for installing the
sprung floor or resilient rubber overlay.
Commercial:
Residential:
The system is suited to a wide range of
commercial developments that have applied floor The system has been used in a number of
finishes such as carpet, vinyl and ceramics. residential projects including an award winning
sprawling residence in north Queensland which
The system has also been specified into large car had extensive use of natural stone floor finishes
park areas, both under croft and on grade, where throughout. Many residences are not of sufficient
the primary objective was to save time. In multi floor area to justify use of the system, however
storey construction some builders prefer to form there is a proliferation of medium density housing
off slabs in under croft car parks thus bringing the projects in which the system could be of great
slab on grade construction onto critical path, and benefit to developers.
hence any time saved in placing the slabs has
direct impact on delivery of the project. Hospitals:

Industrial: An obvious application is in hospital wards,


however to date the system has not been used in
Industrial applications require special any hospital project. Most modern hospitals and
consideration as most often there are no applied nursing homes have either vinyl or carpet floor
floor finishes. It must be remembered that it is a finishes throughout, and apart from saving
joint free slab system, not a crack free slab construction time and cost, the system provides
system. for an uninterrupted surface finish which is far
more clinical than a floor with cover strips and the
The system has been installed in selected like.
industrial applications, including floors with epoxy
paint finishes and floors with no applied finishes.
As an indication of market approval, there are
repeat clients in this area as well.

_________________________________
1
Director, Colefax Consulting Engineers Pty Ltd
TECHNICAL SUPPORT & ADDITIONAL 10. O’Moore, Dr Liza and Dr Peter Dux, 2003
INFORMATION Seminar - Developments in Slab and
Pavement Construction, Crack Control - are
The joint free slab system is the brainchild of two we getting it right?, Concrete Institute of
consulting structural engineers in Australia. They Australia (NSW Branch) & Institution of
make themselves available to answer questions Engineers Australia, Sydney Division.
and help other engineers incorporate the system
into their projects. They also make available CAD 11. Poulos, Prof. Harry, Industrial Floors &
files, standard details and specifications. Pavements Seminar 2004, Development of
New Design Charts for Concrete Industrial
A lot of information is also available on the Slabs, Cement & Concrete Services.
following websites:
12. Schafer, Barry and Samia Guirguis, Biennial
www.jointfreeslabs.com Conference July 2003, Concrete Slabs and
www.canzac.com Subterranean Termites, Concrete Institute of
Australia.

REFERENCES

1 Cement and Concrete Association of


Australia, July 1995, Concrete Industrial Floor
& Pavement Design

2. Cement and Concrete Association of


Australia, May 1999 (second edition),
Industrial Floors and Pavements -
Guildelines for design construction and
specification.

3. The Concrete Society, Technical Report No


34 Third Edition, Concrete Industrial Ground
Floors - A guide to design and construction.

4. Portland Cement Association, Second Edition


1983, Concrete Floors on Ground.

5. Standards Australia, 2001, AS 3600 Concrete


Structures, Standards Australia International
Ltd.

6. Standards Australia, 1996, AS 2870 Reidential


slabs and footings - Construction, Standards
Australia International Ltd.

7. Colefax, Warwick, 2001, Inducing Small


Cracks to Create the Joint-Free Slab,
Concrete in Australia Vol22 No3.

8. Colefax, Warwick & Colefax, Robert, Biennial


Conference July 2003, Joint Free Slabs on
Grade - An innovative approach to the
construction of large area floor slabs,
Concrete Institute of Australia.

9. Cockerell, Allan BE(Hons) MIEAust RPEQ,


Industrial Floors & Pavements Seminar 2000,
Sawn Joints in Concrete Pavements for Crack
Control, Cement and Concrete Services Pty
Ltd.
_________________________________
1
Director, Colefax Consulting Engineers Pty Ltd
ANNEXURE A:

Beam on elastic foundation analysis completed for


a 20m long x 1m wide slab strip comprising 80 x
250mm long segments with a hinge inserted at
every fourth node to represent a crack induced by
the crack inducer grid.

Input details:

I000 wide slab strip x 125 thick


Modulus of subgrade reaction = 35kPa/mm

Primary load cases:

Load Case 1 - slab self weight


Load Case 2 - skip pattern 7.5kPa live load
Load Case 3 - 20kN/m wall input as 80kN/m UDL
Load Case 4 - Fork Lift axle load 40kN
Load Case 5 - Fork Lift axle load 40kN

Combined Load Cases:

Load Case 6 - LC1 + LC2 + LC3 + LC4


Load Case 7 - LC1 + LC2 + LC3 + LC4 + LC5
Load Case 8 - As for LC6 but with fork lift axle
increased to 60kN
Load Case 9 - As for LC7 but with both fork lift
axles increased to 60kN

Plotted Diagrams:

‰ Bending Moment Envelope - all load cases


‰ Part BM Envelope enlarged
‰ Part Loading Diagram enlarged
‰ Part Slab Deflection Diagram enlarged

_________________________________
1
Director, Colefax Consulting Engineers Pty Ltd
_________________________________
1
Director, Colefax Consulting Engineers Pty Ltd
_________________________________
1
Director, Colefax Consulting Engineers Pty Ltd

You might also like