Restoration Dolly Project

Restoration
Item D - 660
S - 011 S - 048 S - 069 S - 098
Part No. Description
Hour Prices Hour Prices Hour Prices Hour Prices
Material 340.000 340.000 340.000 340.000
Remove 1:00 1:00 1:00 1:00
Painting Masking 0:30 0:30 0:30 0:30
Primer 0:30 0:30 0:30 0:30
Top Coat 1:00 1:00 1:00 1:00
Material 240.000 240.000 240.000 240.000
Install Rubber, Spon, & Hose Cut 0:45 0:35 0:45 1:00
Bond 0:30 0:30 1:15 0:50
Change Castor PU 5 " Part 465.000 465.000 465.000
Swevel Hour 0:30 0:30 0:30
Part
Change Floor Lock
Hour
Frame Repair, pin Lock, Pin Material 135.000
Castor Hour 1:45 0:45 2:00

Frame Strength Up
Total Hours 6:30 455.000 4:35 320.833 5:45 402.500 7:20 513.333
Total Material 1.045.000 1.045.000 580.000 1.045.000
Total 1.500.000 1.365.833 982.500 1.558.333
Expenses 15% 225.000 204.875 147.375 233.750
Transportasi 200.000 200.000 200.000 200.000
Grand Total 1.925.000 1.770.000 1.329.000 1.992.000
Picture :

S-011 S - 048 S - 069 S - 098