Restoration Dolly Project

Restoration Date : 02 Nopember 2017


Item 650 660
S - 031 S - 052 S - 085 S - 040
Part No. Description
Hour Prices Hour Prices Hour Prices Hour Prices
Material 340.000 340.000 340.000 340.000
Remove 1:00 1:00 1:00 1:00
Painting Masking 0:30 0:30 0:30 0:30
Primer 0:30 0:30 0:30 0:30
Top Coat 1:00 1:00 1:00 1:00
Material 240.000 240.000 240.000 240.000
Install Rubber, Spon, & Hose Cut 0:45 0:25 0:45 1:25
Bond 1:30 0:45 1:15 1:00
Part 165.000 220.000
Rolloer Conveyor
Hour 1:00 1:30
Part
Change Castor PU 5 " Swevel
Hour
Part 300.000
Change Floor Lock
Hour 0:30
Material 135.000 100.000 202.500 100.000
Frame Repair, pin Lock, Pin Castor
Hour 2:45 1:45 3:45 2:00

Total Hours 9:30 665.000 7:25 519.167 8:45 612.500 7:25 519.167
Total Material 1.180.000 900.000 782.500 680.000
Total 1.845.000 1.419.167 1.395.000 1.199.167
Expenses 0.15 276.750 212.875 209.250 179.875
Transportasi 200.000 200.000 200.000 200.000
Grand Total 2.321.000 1.832.000 1.804.000 1.579.000