Mine Development 2018

Ferrari Tunnel Bridge


Tender Pre-bid Meeting
Scope Overview
• Concrete spun pile driving.
• Construction of reinforced concrete pilecap foundation for CMP base
support.
• Installation of Multi Plate CMP High Profile Arch material according to
manufacturer’s recommendation.
• Engineered backfill to retain CMP’s shape and structural integrity.
• Installation of gabion wall.
• Construction & Installation of tunnel walkway and road guard rail.
• Construction and installation of concrete protection bollard at Haul Road
above Tunnel.
• Installation of lighting, road sign and all other accessories.
Location Map
Topographical Drawings
Construction Method

Excavation on existing Preloading Material followed with Piling


works, concrete pilecap foundation and CMP Installation
Design Drawings
Project Reference

Existing PTVI’s Sumassang Tunnel Bridge (2003)


Project Progress (June 2018)

Temporary diverted public road under construction


Resources – Main Equipment/Tools required

• Pile Driving Rig (2 set) suitable for 400mm dia concrete spun pile.
• Welding Machine for pile joint splicing.
• Mobile Crane to support material lifting and CMP installation.
• Tools for CMP assembly, refer to manufacturer’s instruction.
• Compaction Equipment : Hand Tampers, Mechanical Tampers, Tamping
Rollers or Vibrating Compactors.
• Scaffolding and man-cage.
Resources – material required / supplied

• Main materials supplied by PTVI for this project are :


• CMP Material
• Spun Piles
• Road guard rail
• Concrete and rebars
• Road bollard
• Electrical fixtures material (cable, Lighting, Conduit)

• All other consumable materials to be supplied by CONTRACTOR.


Check the BOM in this EWP for contractor supply.
Safety Considerations

• Piling Works, some possible hazard including Noise, vibration, hazard of


buried or overhead services, stability of the surrounding backfilling.
• Working at height to install and assembly CMP material. Need to state
methodology for material installation using man-cage or scaffolding.
• Soil compaction hazard including vibration, stability of existing ground,
heavy equipment handling.
• All other safety issues related to the contractor's work method.
List of critical activities
• Piling Works
• Installation and removal of structures by crane.
• Assembly and fabrication of Corrugated Metal Pipe
• Slope stability
Schedule:
Contractor to supply a detailed project schedule that meet the following
deadlines:

• Concrete spun piles driving start on W40, 1 October 2018 after preloading
completed.
• All works including concrete foundation, CMP assembly & installation,
backfilling and all other supporting works to be completed by March 2018.